What changed in Management’s Discussion and Analysis?
Read the current filingPrevious report: 10-K
Period ended 2025-01-03; filed 2025-03-20.
0000950170-25-042721
Item 7. Management’s Discussion and Analysis of Financial Condition and Results of OperationsCurrent report: 10-K
Period ended 2026-01-02; filed 2026-03-13.
0001193125-26-105064
Item 7. Management’s Discussion and Analysis of Financial Condition and Results of OperationsThe baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.
Compared 178 previous paragraphs and 170 current paragraphs.
108 unchanged; 38 reworded; 21 added; 30 removed; 2 previous and 3 current paragraphs rearranged.
Tables are not compared: 9 previous and 9 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.
A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.
Added paragraphs (21)
Current report
Our History and the AECOM Sale Transaction
Current report
Equity in Earnings (Loss) of Unconsolidated Joint Ventures
Current report
Gross margin recognized on Shimmick Projects was $40 million and $12 million for the fiscal years ended January 2, 2026 and January 3, 2025, respectively. The $28 million increase in the gross margin was primarily the result of $21 million in gross margin from new projects ramping up and $7 million in gross margin from a California Palisades fire clean-up project.
Current report
Non-Core Projects
Current report
As part of the AECOM Sale Transaction, we acquired projects and backlog that were started under prior ownership (formerly referred to as "Legacy and Foundations Projects"). Separately, the Company entered into an agreement to sell the assets of our foundation drilling Non-Core Projects in the second quarter of 2024 and continued to wind down the remaining work which is substantially completed.
Current report
Non-Core Projects revenue was $96 million and $125 million for the fiscal year ended January 2, 2026 and January 3, 2025, respectively. The $29 million decrease was primarily the result of the favorable GGB Project settlement which included a $31 million increase to revenue during the third quarter of 2024, which did not reoccur during the fiscal year ended January 2, 2026 as well as a result of projects winding down to completion. These impacts were partially offset by the settlement on a federal lock and dam Non-Core Project which included a $23 million reduction to revenue during the second quarter of 2024, which also did not reoccur during the fiscal year ended January 2, 2026.
Current report
Gross margin was $(7) million for the fiscal year ended January 2, 2026 as compared to $(68) million for the fiscal year ended January 3, 2025. The $61 million increase was primarily the result of the settlement on a federal lock and dam Non-Core Project discussed above which included a $30 million reduction to gross margin during the second quarter of 2024 as well as $19 million of cost increases for time and design-related schedule extensions identified during the fiscal year ended January 3, 2025 which did not reoccur during the fiscal year ended January 2, 2026. These improvements in margin from prior period were partially offset by the favorable GGB Project settlement, which contributed $11 million to gross margin during the third quarter of 2024 and did not reoccur during the fiscal year ended January 2, 2026.
Current report
Selling, general and administrative expenses decreased by $9 million during the fiscal year ended January 2, 2026 primarily as a result of the continued implementation of our transformation plan.
Current report
Equity in earnings (loss) of unconsolidated joint ventures
Current report
Other (income) expense, net
Current report
Other income, net was $1 million for the fiscal year ended January 2, 2026 compared to other expense, net of $1 million for the fiscal year ended January 3, 2025 primarily as the result of a $1 million loss recognized on the settlement of certain claims with AECOM as well as expenses recognized associated with the change in fair value of contingent consideration and other costs incurred during the fiscal year ended January 3, 2025 which did not reoccur during the fiscal year ended January 2, 2026.
Current report
Adjusted net loss
Current report
Ansley Loan Agreement
Current report
On March 31, 2025, we entered into a loan and security agreement (the “Ansley Loan Agreement”) with Ansley Park Capital LLC which provides for a borrowing capacity of $15.0 million as evidenced by two promissory notes (each, a “Promissory Note,” and together, the “Promissory Notes”).
Current report
Each Promissory Note has a maturity date of April 1, 2031, and accrues interest at a rate of 12.50% per annum. Pursuant to the terms of the Ansley Loan Agreement, we granted a security interest in (a) certain items of equipment described therein, (b) all leases, rental contracts, chattel paper, accounts, security deposits and general intangibles relating thereto and (c) and any and all proceeds thereof as collateral for the payments under the Ansley Loan Agreement. The Ansley Loan Agreement contains customary affirmative and negative covenants for a transaction of this type. In connection with the Ansley Loan Agreement, we entered into a separate guaranty agreement (each, a “Guaranty Agreement,” and together, the “Guaranty Agreements”) in favor of the Ansley Park Capital LLC unconditionally guaranteeing our liabilities and the liabilities of one of our wholly-owned subsidiaries under the
Current report
ATM Agreement
Current report
On September 8, 2025, the Company entered into an At The Market Offering Agreement (the “Sales Agreement”) with Roth Capital Partners, LLC (the “Sales Agent”). Under the Sales Agreement, the Sales Agent may, at the Company’s discretion, sell up to $7.8 million of shares of the Company’s common stock, in “at the market offerings” as defined in Rule 415 under the Securities Act of 1933, as amended. The shares will be sold pursuant to the Company’s Registration Statement on Form S-3 (File No. 333-288513), declared effective by the SEC on July 10, 2025, and the related prospectus supplement (the “Prospectus Supplement”) dated September 8, 2025 filed with the SEC in connection with the offer and sale of the shares.
Current report
The Company is not obligated to make any sales of shares under the Sales Agreement, and no assurance can be given that the Company will sell any shares under the Sales Agreement, or, if the Company does, as to the price or amount of shares that the Company will sell, or the dates on which any such sales will take place. The Company or the Sales Agent, under certain circumstances and upon notice to the other, may suspend the offering of the shares under the Sales Agreement. The offering of the Shares pursuant to the Sales Agreement will terminate upon the sale of shares in an aggregate offering amount equal to $7.8 million, or sooner if either the Company or the Sales Agent terminates the Sales Agreement. The Company will pay the Sales Agent a cash commission in an amount up to 3% of the gross proceeds from each sale of Shares sold pursuant to the Sales Agreement and will reimburse the Sales Agent for the documented fees and costs of its legal counsel reasonably incurred in connection with entering into the transactions contemplated by the Sales Agreement in an amount not to exceed $50,000 in the aggregate.
Current report
The Company made certain customary representations, warranties and covenants in the Sales Agreement concerning the Company and its subsidiaries and the Registration Statement, Prospectus, Prospectus Supplement and other documents and filings relating to the offering of the shares. In addition, the Company has agreed to indemnify the Sales Agent against certain liabilities, including liabilities under the Securities Act. The shares to be sold under the Sales Agreement, if any, will be issued and sold pursuant to the Company’s Registration Statement, and its Prospectus Supplement related thereto.
Current report
For the fiscal year ended January 2, 2026, net cash provided by financing activities was $50 million, which primarily consisted of borrowings on credit and loan agreements of $129 million, partially offset by repayments on credit and loan agreements of $75 million, $2 million of debt issuance costs incurred for the ACF Credit Agreement and
Current report
Ansley Loan Agreement entered into during the first quarter of 2025 and $2 million of payments associated with tax withholdings related to the vesting of restricted stock units.
Removed paragraphs (30)
Previous report
Our History, the AECOM Sale Transaction and 2024 Financing Transactions
Previous report
AECOM Sale Transaction
Previous report
Shared Tax Benefits. Pursuant to the internal reorganization of its business in early 2020, AECOM agreed to make an election under Treasury Regulations Section 1.1502-36(d)(6) that could result in certain tax benefits to us (in the form of cash or a reduction in liability for taxes). We are obligated to share with AECOM actual tax benefits realized (i.e., in cash or through an actual reduction in liability for tax).
Previous report
Other Items. We have agreed to indemnify the Seller Entities for any costs or expenses incurred under any outstanding letters of credit, surety bonds, guarantees, advance payment guarantees and other contractual obligations arising from or relating to the assets purchased or the liabilities assumed under the Purchase Agreement, including bonds relating to the Legacy Projects. Further, the Seller Entities have provided a conditional guaranty required by any surety bonds and/or a bonding program relating to certain guaranteed obligations and payment obligations with respect to the certain other assets related to our business and our subsidiaries to the extent owned by Seller Entities or their affiliates.
Previous report
2024 Financing Transactions
Previous report
Credit Agreement. On May 20, 2024, we entered into a revolving credit facility (the “Credit Agreement”). See "Management's Discussion and Analysis of Financial Condition and Results of Operations — Liquidity and Capital Resources — Credit Agreement" for further discussion.
Previous report
Amendment to MidCap Credit Facility. On May 20, 2024, we entered into Amendment No. 3 to our existing Revolving Credit Facility, dated March 27, 2023, with MidCap Financial Services, LLC. See “— Liquidity and Capital Resources — Revolving Credit Facility” for further discussion.
Previous report
Side Letter. We and AECOM entered into a side letter to the Credit Agreement, dated as of May 20, 2024 (the “Side Letter”). Pursuant to the Side Letter, the Company (i) established a special committee of independent directors (the “Special Committee”), (ii) appointed a chief transformation officer, (iii) executed the Settlement Agreement and Mutual Release (as described below), and (iv) agreed to certain terms relating to AECOM’s registration rights under the Share Issuance Agreement (as described below).
Previous report
Settlement Agreement and Share Issuance. We entered into a Settlement Agreement and Mutual Release with AECOM pursuant to which, among other things, we and our subsidiaries released AECOM from all claims available to us under the Purchase Agreement. In return, AECOM released the Company and its subsidiaries from certain claims under the Purchase Agreement, specifically certain claims related to the Golden Gate Bridge Project, the Gerald Desmond Bridge Project and Chickamauga Lock Project and claims relating to certain earn-out payments. As consideration, we also entered into a Share Issuance Agreement (the “Share Issuance Agreement”) with AECOM, pursuant to which we issued an aggregate 7,745,000 shares of common stock.
Previous report
For additional information regarding AECOM, see “Risk Factors — Risks Related to Our Business and Industry — We may be required to make additional payments to AECOM pursuant to contractual arrangements” and “— If AECOM defaults on its contractual obligations under agreements in which we are a beneficiary, our business could be materially and adversely impacted.”
Previous report
Ural Yal Appointed CEO of Shimmick
Previous report
On November 12, 2024, Shimmick announced that it appointed Ural Yal as its new CEO and member of the Board of Directors effective December 2, 2024 and succeeded Steven Richards upon his retirement. We believe Mr. Yal brings deep expertise in both the California market and national infrastructure construction along with a proven track record of operational growth to lead the Company in capitalizing on market opportunities through operational excellence, safety and client satisfaction.
Previous report
Equity in (Loss) Earnings of Unconsolidated Joint Ventures
Previous report
Gross margin recognized on Shimmick Projects was $12 million and $38 million for the fiscal years ended January 3, 2025 and December 29, 2023, respectively. The $26 million decrease in gross margin was primarily the result of a $37 million decrease from increased cost of revenue, schedule extensions and a decrease in revenue from existing projects that are winding down, partially offset by an aggregate of $11 million of gross margin from a new water infrastructure project and ramp up of a transportation project.
Previous report
Legacy Projects
Previous report
As part of the AECOM Sale Transaction, we acquired the Legacy Projects and backlog that were started under prior ownership. Legacy Projects revenue was $93 million for the fiscal year ended January 3, 2025, a decline of $105 million as compared to the fiscal year ended December 29, 2023, as the Company works to complete these projects. The decline in revenue was primarily driven by continued impacts of Legacy Projects winding down during fiscal 2024, the sale of non-core business contracts in the third quarter of 2023 as well as a non-cash adjustment to revenue on a Legacy Loss Project (as defined below) settlement recognized during the second quarter of 2024, partially offset by a settlement agreement in the Company's Golden Gate Bridge Project (the “GGB Project”) during the third quarter of 2024.
Previous report
Gross margin was $(49) million for the fiscal year ended January 3, 2025 as compared to $(7) million for the fiscal year ended December 29, 2023, primarily as a result of the Legacy Loss Project settlement during the second quarter of 2024, projects winding down and additional cost overruns on Legacy Loss Projects that have experienced additional increases in the cost to complete as well as additional legal fees to pursue contract modifications and recoveries, partially offset by the GGB Project settlement.
Previous report
Foundations Projects
Previous report
Projects that focus on foundation drilling are referred to as "Foundations Projects". The Company entered into an agreement to sell the assets of our non-core Foundations Projects in the second quarter of 2024 and continued to wind down work during the 2024 fiscal year. As a result, revenue recognized on Foundations Projects declined during the 2024 fiscal year. Revenue recognized on Foundations Projects was $31 million and $48 million for the fiscal years ended January 3, 2025 and December 29, 2023, respectively. The $17 million decline in revenue was the result of timing of multiple projects winding down following the asset sale.
Previous report
Gross margin recognized on Foundations Projects was $(18) million and $(9) million for the fiscal years ended January 3, 2025 and December 29, 2023, respectively. The decline in gross margin was the result of cost overruns and projects winding down.
Previous report
Selling, general and administrative expenses remained approximately flat period over period.
Previous report
Equity in (loss) earnings of unconsolidated joint ventures
Previous report
Other expense, net
Previous report
Other expense, net remained approximately flat period over period.
Previous report
Adjusted net (loss) income
Previous report
During the fiscal year ended January 3, 2025, we repaid $30 million of the amount outstanding under the Revolving Credit Facility and paid $2 million in cash interest.
Previous report
The transactions with AECOM also included a mutual release and settlement of certain claims with AECOM and a corresponding agreement to issue 7,745,000 shares of our common shares to AECOM. 5,144,622 of the common shares were issued on May 20, 2024 and issuance of the remaining 2,600,378 shares was completed following stockholder approval on June 26, 2024. Of the total common shares issued, 1,036,949 were held in escrow which resulted in an AECOM voting interest of 19.6% as of January 3, 2025. The Company recognized a loss of $1 million in other expense, net within the consolidated statements of operations as a result of the share issuance which represented the excess of the $13 million fair market value of the common shares at the time of issuance over the $12 million carrying value of the contingent consideration liabilities settled with AECOM.
Previous report
The impact on net cash flows from operations in the fiscal years ended January 3, 2025 and December 29, 2023 from Legacy Loss Projects was cash proceeds of approximately $42 million in part due to settlements on claims during the year and cash used of $65 million, respectively.
Previous report
For the fiscal year ended December 29, 2023, net cash provided by financing activities was $48 million, which primarily consisted of net proceeds from the Revolving Credit Facility borrowings of $30 million and IPO proceeds of $25 million, partially offset by payments of IPO costs of $6 million.
Previous report
As of January 3, 2025, we had a backlog of projects of approximately $822 million, with over half of that amount comprised of water projects. We believe we have the ability to self-perform many of these projects, enabling us to compete for complex projects and differentiating us from many of our competitors. Self-performance also enables us to better control the critical aspects of our projects, reducing the risk of cost and schedule overruns.
Reworded paragraphs (38)
Previous wording
We have a long history of successfully completing complex water projects, ranging from the world’s largest wastewater recycling and purification system in California to the iconic Hoover Dam. According to Engineering News Record, in 2024, we are nationally ranked as a top ten builder of water supply (#8), dams and reservoirs (#6), and water treatment and desalination plants (#7). Our business includes construction operations from Morrison Knudsen and Washington Group International which were consolidated in 2017 by AECOM. In 2021, we were sold by AECOM and became an independent company under new private ownership ("AECOM Sale Transaction"). In November 2023, we completed our initial public offering (the “IPO”) and currently our stock is listed for trading on the Nasdaq Capital Market under the symbol "SHIM".
Current wording
We have a long history of successfully completing complex water projects, ranging from the world’s largest wastewater recycling and purification system in California to the iconic Hoover Dam. According to Engineering News Record, in 2025, we are nationally ranked as a top fifteen builder of water supply (#12), dams and reservoirs (#8), and water treatment and desalination plants (#11). Our business includes construction operations from Morrison Knudsen and Washington Group International which were consolidated in 2017 by AECOM. In 2021, we were sold by AECOM and became an independent company under new private ownership (the "AECOM Sale Transaction"). In November 2023, we completed our initial public offering (the “IPO”) and currently our stock is listed for trading on the Nasdaq Capital Market under the symbol "SHIM".
Previous wording
Transportation and Mobility. We construct mass transit systems (light passenger rail and bus rapid transit), autonomous transportation solutions (personal rapid transit, autonomous fixed guideway people movers, and implement intelligent transportation technologies.
Current wording
Transportation and Mobility. We construct mass transit systems (light passenger rail and bus rapid transit), autonomous transportation solutions (personal rapid transit, autonomous fixed guideway people movers, etc.) and implement intelligent transportation technologies.
Previous wording
As of January 3, 2025, we had a backlog of projects of approximately $822 million, mostly located in California, with ongoing projects in six other states. We self-perform many of these projects, which we believe allows us to better control critical aspects of construction, reduce cost and schedule risks, and deliver greater value to clients.
Current wording
As of January 2, 2026, we had a backlog of projects of approximately $793 million, mostly located in California, with ongoing projects in five other states. We self-perform many of these projects, which we believe allows us to better control critical aspects of construction, reduce cost and schedule risks, and deliver greater value to clients.
Previous wording
In January 2021, we were sold by AECOM and began operating as an independent company under new private ownership ("AECOM Sale Transaction") under a December 2020 Purchase Agreement with SCC Group, a special purpose entity formed for the purpose of entering into and consummating the sale transaction including acquiring 100% of the stock of the Company and certain other assets related to our business and our subsidiaries to the extent owned by Seller Entities or their affiliates. After the transaction, we began a transformation to shift our strategy to meet the nation’s growing need for water and other critical infrastructure and grow our business. We are also focusing more on smaller complex projects that we can largely self-perform and which we believe will have lower risk and higher margin.
Current wording
In January 2021, we were sold by AECOM and began operating as an independent company under new private ownership ("AECOM Sale Transaction") under a December 2020 Purchase Agreement with SCC Group, a special purpose entity formed for the purpose of entering into and consummating the sale transaction including acquiring 100% of the stock of the Company and certain other assets related to our business and our subsidiaries to the extent owned by Seller Entities or their affiliates. After the transaction, we began a transformation to shift our strategy to meet the nation’s growing need for water and other critical infrastructure and grow our business.
Previous wording
Our Ability to Successfully Expand our Footprint. We review our bidding opportunities to attempt to minimize concentration of work with any one customer, in any one industry, or in tight labor markets. We believe that by carefully positioning ourselves in markets that have meaningful barriers to entry, like those with highly technical or specialized scopes of work, we can continue to be competitive. For example, we target projects with significant, highly-technical work that we can self-perform. We believe this provides us with a distinct pricing advantage, as well as better risk management. In addition, as a result of federal and state-level infrastructure initiatives, we believe that funding for technical construction projects may exceed capacity, enabling us to opportunistically target smaller specialized projects with less risk at higher margins. We may be limited in our ability to expand our footprint by barriers to entry to new markets, competition, and availability of capital and skilled labor.
Current wording
Our Ability to Successfully Expand our Footprint. We review our bidding opportunities to attempt to minimize concentration of work with any one customer, in any one industry, or in tight labor markets. We believe that by carefully positioning ourselves in markets that have meaningful barriers to entry, like those with highly technical or specialized scopes of work, we can continue to be competitive. For example, we target projects with significant, highly-technical work that we can self-perform. We believe this provides us with a distinct pricing advantage, as well as better risk management. In addition, as a result of federal and state-level infrastructure initiatives, we believe that funding for technical construction projects may exceed capacity, enabling us to opportunistically target smaller specialized projects with less risk at higher margins. Furthermore, on June 23, 2025 we announced the launch of Axia Electric, a dedicated electrical subsidiary designed to meet growing market demand for specialized, high-performance electrical and power distribution solutions, which represents an expansion of our electrical capabilities and positions us to expand to additional geographies such as Texas, Georgia and Tennessee. We may be limited in our ability to expand our footprint into these new project types and geographies by barriers to entry to new markets, competition, and availability of capital and skilled labor.
Previous wording
In addition, as is customary in the construction business, we are required to provide surety bonds to our customers to secure our performance under construction contracts. Our ability to obtain surety bonds primarily depends upon our capitalization, working capital, past performance, management expertise and reputation, as well as certain external factors, including the overall capacity of the surety market. Surety companies consider such factors in relationship to the amount of our backlog and their underwriting standards, which may change from time to time. Events that adversely affect the insurance and bonding markets generally may result in bonding becoming more difficult to obtain in the future, or being available only at a significantly greater cost. If are unable to obtain adequate bonding or if the cost of bonding materially increased, it would limit the amount that we can bid on new contracts, limit the competitiveness of our bids, and could have a material adverse effect on our future revenue and business prospects.
Current wording
In addition, as is customary in the construction business, we are required to provide surety bonds to our customers to secure our performance under construction contracts. Our ability to obtain surety bonds primarily depends upon our capitalization, working capital, past performance, management expertise and reputation, as well as certain external factors, including the overall capacity of the surety market. Surety companies consider such factors in relationship to the amount of our backlog and their underwriting standards, which may change from time to time. Events that adversely affect the insurance and bonding markets generally may result in bonding becoming more difficult to obtain in the future, or being available only at a significantly greater cost. If we are unable to obtain adequate bonding or if the cost of bonding materially increases, it would limit the amount that we can bid on new contracts, limit the competitiveness of our bids, and could have a material adverse effect on our future revenue and business prospects.
Previous wording
Gross margin represents revenue less contract costs. Contract costs consist of all direct and indirect costs on contracts, including raw materials, labor, equipment costs, and subcontractor costs. If the estimates of costs to complete fixed-price contracts indicate a further loss, the entire amount of the additional loss expected over the life of the project is recognized in the current period in the cost of revenue.
Current wording
Gross margin represents revenue less contract costs. Contract costs consist of all direct and indirect costs on contracts, including raw materials, labor, equipment costs, and subcontractor costs. If the estimates of costs to complete fixed-price contracts indicate a further loss, the entire amount of the additional loss expected over the life of the project is recognized in the current period in cost of revenue.
Previous wording
Equity in (loss) earnings of unconsolidated joint ventures includes our return on investment in unconsolidated joint ventures.
Current wording
Equity in earnings (loss) of unconsolidated joint ventures includes our return on investment in unconsolidated joint ventures.
Previous wording
Projects started after the AECOM Sale Transaction ("Shimmick Projects") have focused on water infrastructure and other critical infrastructure. Revenue recognized on Shimmick Projects was $356 million and $386 million for the fiscal years ended January 3, 2025 and December 29, 2023, respectively. The $30 million decrease in revenue was primarily the result of a $82 million decrease from lower activity on existing projects and projects winding down partially offset by an aggregate of $52 million of revenue from a new water infrastructure project and ramp up of a transportation project.
Current wording
Projects started after the AECOM Sale Transaction ("Shimmick Projects") have focused on critical infrastructure aligned with our strategy, including water, climate resilience, energy transition and sustainable transportation. Revenue recognized on Shimmick Projects was $397 million and $356 million for the fiscal years ended January 2, 2026 and January 3, 2025, respectively. The $42 million increase in revenue was primarily the result of $87 million of revenue from new higher margin projects ramping up and $31 million of revenue from a California Palisades fire clean-up project, partially offset by $77 million of decreases in revenue from lower activity on existing projects and projects winding down.
Previous wording
A subset of Legacy Projects ("Legacy Loss Projects") have experienced significant cost overruns due to the COVID pandemic, design issues, legal costs and other factors. In the Legacy Loss Projects, we have recognized the estimated costs to complete and the loss expected from these projects. If the estimates of costs to complete fixed-price contracts indicate a further loss, the entire amount of the additional loss expected over the life of the project is recognized as a period cost in the cost of revenue. As these Legacy Loss Projects continue to wind down to completion, no further gross margin will be recognized and in some cases, there may be additional costs associated with these projects. Revenue recognized on these Legacy Loss Projects was $68 million and $99 million for the fiscal years ended January 3, 2025 and December 29, 2023, respectively. Gross margin recognized on these Legacy Loss Projects was $(45) million and $(14) million for the fiscal years ended January 3, 2025 and December 29, 2023, respectively. The change in gross margin was primarily the result of a Legacy Loss Project settlement during the second quarter of 2024, additional increases in the cost to complete as well as additional legal fees to pursue contract modifications and recoveries, partially offset by the GGB Project settlement.
Current wording
A subset of Non-Core Projects ("Non-Core Loss Projects") have experienced significant cost overruns due to the COVID pandemic, design issues, legal costs and other factors. In the Non-Core Loss Projects, we have recognized the estimated costs to complete and the loss expected from these projects. If the estimates of costs to complete fixed-price contracts indicate a further loss, the entire amount of the additional loss expected over the life of the project is recognized as a period cost in the cost of revenue. As these Non-Core Loss Projects continue to wind down to completion, no further gross margin will be recognized absent external factors and in some cases, there may be additional costs associated with these projects that could lower gross margin. Revenue recognized on these Non-Core Loss Projects was $74 million and $68 million for the fiscal year ended January 2, 2026 and January 3, 2025, respectively. Gross margin recognized on these Non-Core Loss Projects was $(2) million and $(45) million for the fiscal year ended January 2, 2026 and January 3, 2025, respectively. The change in gross margin was primarily the result of the settlement of the claims discussed above as well as cost increases for time and design-related schedule extensions during the fiscal year ended January 3, 2025 which did not reoccur during the fiscal year ended January 2, 2026.
Previous wording
Equity in (loss) earnings of unconsolidated joint ventures was $(5) million, compared to earnings of $10 million in the prior year period, primarily due a favorable subcontractor settlement during the fiscal year ended December 29, 2023 that did not reoccur during the fiscal year ended January 3, 2025 and increased costs due to schedule extensions.
Current wording
Equity in earnings of unconsolidated joint ventures was $2 million for the fiscal year ended January 2, 2026 compared to equity in loss of unconsolidated joint ventures of $5 million for the fiscal year ended January 3, 2025 primarily as the result of increased costs due to schedule extensions experienced during the fiscal year ended January 3, 2025 which did not reoccur during the fiscal year ended January 2, 2026.
Previous wording
Gain on sale of assets decreased by $11 million primarily due to the gain recognized on the sale of non-core business contracts for $30 million during the fiscal year ended December 29, 2023, partially offset by the $17 million gain recognized on the transaction for the sale-leaseback of our equipment yard in Tracy, California and $2 million gain recognized on the sale of the assets of our non-core Foundations Projects during the fiscal year ended January 3, 2025.
Current wording
Gain on sale of assets, net decreased by $21 million during the fiscal year ended January 2, 2026 primarily due to the $17 million gain recognized on the transaction for the sale-leaseback of our equipment yard in Tracy, California and the $4 million gain recognized on the sale of the assets of our foundation drilling Non-Core Projects, each of which occurred during the fiscal year ended January 3, 2025 and did not reoccur during the fiscal year ended January 2, 2026.
Previous wording
Interest expense increased by $3 million primarily due to increased borrowings on the Credit Agreement, which was entered into on May 20, 2024 as well as interest charges on the Revolving Credit Facility which was not entered into until March 27, 2023.
Current wording
Interest expense increased by $1 million primarily due to increased average borrowings on the Credit Agreement during the fiscal year ended January 2, 2026 as well as interest expense incurred on the ACF Credit Agreement and Ansley Loan Agreement entered into during the fiscal year ended January 2, 2026.
Previous wording
Income tax benefit of $1 million was recognized for the fiscal year ended January 3, 2025, primarily as the result of a decrease in other taxes payable. No taxable income was recognized for the fiscal year ended December 29, 2023, thus no income tax expense or benefit was recorded.
Current wording
Due to a tax loss for the fiscal year ended 2025, no income tax expense was recorded for the fiscal year ended January 2, 2026. Income tax benefit of $1 million was recognized for the fiscal year ended January 3, 2025, primarily as the result of a decrease in other taxes payable.
Previous wording
Net loss increased by $122 million from $2 million to a net loss of $125 million for the fiscal year ended January 3, 2025, primarily due to a decrease in gross margin of $78 million of which $52 million was a result of gross margin declines in the legacy and foundations projects. In addition, the ERP pre-implementation asset impairment and associated costs of $16 million, a decrease of gain on the sale of assets of $11 million, an increase in equity in loss of unconsolidated joint ventures of $15 million as well as an increase in interest expense of $3 million added to the net loss increase, each as described above.
Current wording
Net loss decreased by $100 million to a net loss of $25 million for the fiscal year ended January 2, 2026, primarily due to an increase in gross margin of $89 million, a decrease in ERP pre-implementation asset impairment and associated costs of $16 million, a decrease in selling, general and administrative expenses of $9 million, an increase in equity in earnings (loss) of unconsolidated joint ventures of $6 million and an increase in other (income) expense, net of $2 million, partially offset by a decrease in gain on sale of assets of $21 million and an increase in interest expense of $1 million, all as described above.
Previous wording
We report our financial results in accordance with GAAP. However, management believes that certain non-GAAP financial measures provide investors with additional useful information in evaluating our performance. Therefore, to supplement our consolidated financial statements, we provide investors with certain non-GAAP financial measures, including Adjusted net (loss) income and Adjusted EBITDA.
Current wording
We report our financial results in accordance with GAAP. However, management believes that certain non-GAAP financial measures provide investors with additional useful information in evaluating our performance. Therefore, to supplement our consolidated financial statements, we provide investors with certain non-GAAP financial measures, including Adjusted net loss and Adjusted EBITDA.
Previous wording
Adjusted net (loss) income represents Net loss attributable to Shimmick Corporation adjusted to eliminate stock-based compensation, ERP pre-implementation asset impairment and associated costs, legal fees and other costs for Legacy Projects and transaction-related costs and changes in fair value of contingent consideration remaining after the impact of transactions with our prior owner. We have also made an adjustment for transformation costs we have incurred including advisory costs in connection with settling outstanding claims, exiting the Legacy Projects and transforming the Company to shift our strategy to meet the nation’s growing need for water and other critical infrastructure and grow our business.
Current wording
Adjusted net loss represents Net loss attributable to Shimmick Corporation adjusted to eliminate stock-based compensation, ERP pre-implementation asset impairment and associated costs, legal fees and other costs for Non-Core Projects and transaction-related costs and changes in fair value of contingent consideration remaining after the impact of transactions with our prior owner. We have also made an adjustment for transformation costs we have incurred including advisory costs in connection with settling outstanding claims, exiting the Non-Core Projects and transforming the Company to shift our strategy to meet the nation’s growing need for water and other critical infrastructure and grow our business.
Previous wording
We have included Adjusted net (loss) income in this Annual Report on Form 10-K because it is a key measure used by our management and board of directors to understand and evaluate our core operating performance and trends, to prepare and approve our annual budget and to develop short and long-term operational plans. In particular, we believe that the exclusion of the income and expenses eliminated in calculating Adjusted net (loss) income can provide a useful measure for period-to-period comparisons of our core business. Accordingly, we believe that Adjusted net (loss) income provides useful information to investors and others in understanding and evaluating our results of operations.
Current wording
We have included Adjusted net loss in this Annual Report on Form 10-K because it is a key measure used by our management and board of directors to understand and evaluate our core operating performance and trends, to prepare and approve our annual budget and to develop short and long-term operational plans. In particular, we believe that the exclusion of the income and expenses eliminated in calculating Adjusted net loss can provide a useful measure for period-to-period comparisons of our core business. Accordingly, we believe that Adjusted net loss provides useful information to investors and others in understanding and evaluating our results of operations.
Previous wording
Our use of Adjusted net (loss) income as an analytical tool has limitations, and you should not consider it in isolation or as a substitute for analysis of our financial results as reported under GAAP. Some of these limitations are:
Current wording
Our use of Adjusted net loss as an analytical tool has limitations, and you should not consider it in isolation or as a substitute for analysis of our financial results as reported under GAAP. Some of these limitations are:
Previous wording
Adjusted net (loss) income does not reflect changes in, or cash requirements for, our working capital needs,
Current wording
Adjusted net loss does not reflect changes in, or cash requirements for, our working capital needs,
Previous wording
Adjusted net (loss) income does not reflect the potentially dilutive impact of stock-based compensation, and
Current wording
Adjusted net loss does not reflect the potentially dilutive impact of stock-based compensation, and
Previous wording
other companies, including companies in our industry, might calculate Adjusted net (loss) income or similarly titled measures differently, which reduces their usefulness as comparative measures.
Current wording
other companies, including companies in our industry, might calculate Adjusted net loss or similarly titled measures differently, which reduces their usefulness as comparative measures.
Previous wording
Because of these and other limitations, you should consider Adjusted net (loss) income alongside Net loss attributable to Shimmick Corporation, which is the most directly comparable GAAP measure.
Current wording
Because of these and other limitations, you should consider Adjusted net loss alongside Net loss attributable to Shimmick Corporation, which is the most directly comparable GAAP measure.
Previous wording
Adjusted EBITDA represents our net loss attributable to Shimmick Corporation before interest expense, income tax benefit and depreciation and amortization, adjusted to eliminate stock-based compensation, ERP pre-implementation asset impairment and associated costs, legal fees and other costs for Legacy Projects and transaction-related costs and changes in fair value of contingent consideration remaining after the impact of transactions with our prior owner. We have also made an adjustment for transformation costs we have incurred including advisory costs in connection with settling outstanding claims, exiting the Legacy Projects and transforming the Company to shift our strategy to meet the nation’s growing need for water and other critical infrastructure and grow our business.
Current wording
Adjusted EBITDA represents our Net loss attributable to Shimmick Corporation before interest expense, income tax benefit and depreciation and amortization, adjusted to eliminate stock-based compensation, ERP pre-implementation asset impairment and associated costs, legal fees and other costs for Non-Core Projects and transaction-related costs and changes in fair value of contingent consideration remaining after the impact of transactions with our prior owner. We have also made an adjustment for transformation costs we have incurred including advisory costs in connection with settling outstanding claims, exiting the Non-Core Projects and transforming the Company to shift our strategy to meet the nation’s growing need for water and other critical infrastructure and grow our business.
Previous wording
(1) Consists of transformation-related costs we have incurred including advisory costs in connection with settling outstanding claims in connection with exiting certain Legacy Projects as part of the Company’s growth strategy to address and capitalize on the nation’s growing need for water and other critical infrastructure.
Current wording
(1) Consists of transformation-related costs we have incurred including advisory costs in connection with settling outstanding claims in connection with exiting certain Non-Core Projects as part of the Company’s growth strategy to address and capitalize on the nation’s growing need for water and other critical infrastructure.
Previous wording
(2) Reflects a strategic decision to enhance the Company’s current ERP system rather than implementing a new platform which, due to prior capitalized costs and remaining contractual obligations, resulted in a charge of $16 million in the third quarter of fiscal 2024.
Current wording
(2) Reflects a strategic decision to enhance the Company’s current ERP system rather than implementing a new platform which, due to prior capitalized costs and remaining contractual obligations, resulted in a one-time charge of $16 million in the third quarter of fiscal 2024.
Previous wording
(3) Consists of legal fees and other costs incurred in connection with claims relating to Legacy Projects.
Current wording
(3) Consists of legal fees and other costs incurred in connection with claims relating to Non-Core Projects.
Previous wording
During the fiscal year ended January 3, 2025, our capital expenditures were approximately $10 million compared to $7 million for the fiscal year ended December 29, 2023. Historically, we have had significant cash requirements in order to organically expand our business to undertake new projects. Our cash requirements include costs related to increased expenditures for equipment, facilities and information systems, purchase of materials and production of materials and cash to fund our organic expansion into new markets, including through joint ventures. Our working capital needs are driven by the seasonality and growth of our business, with our cash requirements greater in periods of growth. Additional cash requirements resulting from our growth include the costs of additional personnel, enhancing our information systems, our compliance with laws and rules applicable to being a public company and, in the future, our integration of any acquisitions. Unrestricted cash and cash equivalents at January 3, 2025 totaled $34 million and availability under the Revolving Credit Facility and Credit Agreement totaled $15 million and $51 million, respectively, resulting in total liquidity of $100 million.
Current wording
During the fiscal year ended January 2, 2026, our capital expenditures were approximately $6 million compared to $10 million for the fiscal year ended January 3, 2025. Historically, we have had significant cash requirements in order to organically expand our business to undertake new projects. Our cash requirements include costs related to increased expenditures for equipment, facilities and information systems, purchase of materials and production of materials and cash to fund our organic expansion into new markets, including through joint ventures. Our working capital needs are driven by the seasonality and growth of our business, with our cash requirements greater in periods of growth. Additional cash requirements resulting from our growth include the costs of additional personnel, enhancing our information systems, our compliance with laws and rules applicable to being a public company and, in the future, our integration of any acquisitions. Unrestricted cash and cash equivalents at January 2, 2026 totaled $20 million and availability under the Credit Agreement and ACF Credit Agreement totaled $17 million and $7 million, respectively, resulting in total liquidity of $44 million.
Previous wording
We believe that our operating, investing and financing cash flows are sufficient to fund our operations for at least the next twelve months. However, future cash flows are subject to a number of variables, and significant additional expenditures will be required to conduct our operations. There can be no assurance that operations and other capital resources will provide cash in sufficient amounts to maintain planned or future levels of expenditures. In the event we make one or more acquisitions and the amount of capital required is greater than the amount we have available for acquisitions at that time, we could be required to reduce the expected level of expenditures and/or seek additional capital. If we seek additional capital, we may do so through joint ventures, asset sales, offerings of debt or equity securities or other means. We cannot guarantee that this additional capital will be available on acceptable terms or at all. If we are unable to obtain the funds we need, we may not be able to complete acquisitions that may be favorable to us or finance the expenditures necessary to conduct our operations.
Current wording
We believe that our operating, investing and financing cash flows are sufficient to fund our operations for at least the next twelve months and thereafter for the foreseeable future. However, future cash flows are subject to a number of variables, and significant additional expenditures will be required to conduct our operations. There can be no assurance that operations and other capital resources will provide cash in sufficient amounts to maintain planned or future levels of expenditures. In the event we make one or more acquisitions and the amount of capital required is greater than the amount we have available for acquisitions at that time, we could be required to reduce the expected level of expenditures and/or seek additional capital. If we seek additional capital, we may do so through joint ventures, asset sales, offerings of debt or equity securities or other means. We cannot guarantee that this additional capital will be available on acceptable terms or at all. If we are unable to obtain the funds we need, we may not be able to complete acquisitions that may be favorable to us or finance the expenditures necessary to conduct our operations.
Previous wording
On May 20, 2024, we, as guarantor, and our wholly-owned subsidiaries as borrowers (“Borrowers”), Alter Domus (US) LLC, as agent, and AECOM and Berkshire Hathaway Specialty Insurance Company (“BHSI”) as lenders, entered into a revolving credit facility (the “Credit Agreement”), which was subsequently amended on September 25, 2024, January 30, 2025 and March 12, 2025 to, among other things, permit the Company’s concurrent amendment to the Revolving Credit Facility and waive the specified noncompliance of the Material Project Documents covenant regarding entering into non-bonded contracts. As amended, the Credit Agreement provides borrowing capacity up to $60 million. The obligations under the Credit Agreement bear interest at a per annum rate equal to one month Term SOFR (as defined in the Credit Agreement), subject to a 1.00% floor, plus 3.50%. Interest on any outstanding amounts drawn under the Credit Agreement will be payable, in kind or in cash at our election, on the last day of each month and upon prepayment. Payment-in-kind interest accrued and capitalized shall not constitute loan outstanding amounts for the purposes of calculating loan availability. During the fiscal year ended January 3, 2025, the Company paid $0.3 million in cash interest and accrued $2 million in non-cash payment-in-kind interest.
Current wording
On May 20, 2024, the Company, as guarantor, and its wholly-owned subsidiaries as borrowers (“Borrowers”), Alter Domus (US) LLC, as agent, and AECOM and Berkshire Hathaway Specialty Insurance Company (“BHSI”) as lenders, entered into a revolving credit facility (the “Credit Agreement”), which was most recently amended on March 9, 2026 to, among other things, waive the specified noncompliance of the Material Project Documents covenant regarding entering into non-bonded contracts. As amended, the Credit Agreement provides borrowing capacity up to $60 million. The obligations under the Credit Agreement bear interest at a per annum rate equal to One Month Term SOFR (as defined in the Credit Agreement), subject to a 1.00% floor, plus 3.50%. Interest on any outstanding amounts drawn under the Credit Agreement will be payable, in kind or in cash at our election, on the last day of each month and upon prepayment. Payment-in-kind interest accrued and capitalized shall not constitute loan outstanding amounts for the purposes of calculating loan availability.
Previous wording
Obligations of the Borrowers under the Credit Agreement are guaranteed by us and secured by a lien on substantially all of our and the Borrowers' assets.
Current wording
Obligations of the Borrowers under the Credit Agreement are guaranteed by the Company and secured by a lien on substantially all assets of the Company and the Borrowers.
Previous wording
The Credit Agreement contains customary affirmative and negative covenants for a transaction of this type, including covenants that limit liens, asset sales and investments, in each case subject to negotiated exceptions and baskets. In addition, the Credit Agreement contains a maximum leverage ratio covenant as tested quarterly commencing with the close of the first quarter of 2026. The Credit Agreement also contains representations and warranties and event of default provisions customary for a transaction of this type. Subsequent to January 3, 2025, the Company was not in compliance with a non-financial covenant regarding entering into material non-bonded contracts as set forth in the Credit Agreement. As of January 3, 2025 and following the March 12, 2025 amendment, we are not aware of any instances of noncompliance with non-financial or financial covenants. As of January 3, 2025, $9 million was outstanding under the Credit Agreement.
Current wording
The Credit Agreement contains customary affirmative and negative covenants for a transaction of this type, including covenants that limit liens, asset sales and investments, in each case subject to negotiated exceptions and baskets. In addition, the Credit Agreement contains a maximum leverage ratio covenant as tested quarterly commencing with the close of the second quarter of 2027. The Credit Agreement also contains representations and warranties and event of default provisions customary for a transaction of this type. The Company is not aware of any instances of noncompliance with non-financial or financial covenants as of January 2, 2026.
Previous wording
On March 12, 2025, we entered into a Credit Agreement (“ACF Credit Agreement”) with ACF FINCO I LP, which provides a total commitment of $15 million and bears interest at an annual rate of adjusted term SOFR, subject to a 2.0% floor, plus 4.50%. Further, the ACF Credit Agreement is subject to an annual unused line fee of 0.50%. The ACF Credit Agreement includes certain financial operating covenants, including a minimum liquidity requirement of $5 million. The ACF Credit Agreement matures on the earlier of March 12, 2028 or 90 days prior to the maturity date of the Credit Agreement.
Current wording
On March 12, 2025, we entered into a credit agreement (“ACF Credit Agreement”) with ACF FINCO I LP, which provides a total commitment of $15 million and bears interest at an annual rate of adjusted term SOFR (as defined in the ACF Credit Agreement), subject to a 2.0% floor, plus 4.50%. Further, the ACF Credit Agreement is subject to an annual unused line fee of 0.50%. The ACF Credit Agreement includes certain financial operating covenants, including a minimum liquidity requirement of $5 million. The ACF Credit Agreement matures on the earlier of March 12, 2028 or 90 days prior to the maturity date of the Credit Agreement. As of January 2, 2026, we are not aware of any instances of noncompliance with non-financial or financial covenants.
Previous wording
On March 27, 2023, we entered into the Revolving Credit Facility with MidCap Financial Services, LLC, which originally provided a total commitment of $30 million. The Revolving Credit Facility has been subsequently amended, most recently on September 25, 2024. As amended, the Revolving Credit Facility provides for a total commitment of $15 million and bears interest at an annual rate of adjusted term SOFR, subject to a 1.0% floor, plus 5.50%. Further, the Revolving Credit Facility is subject to an annual collateral management fee of 0.50% and an annual unused line fee of 0.50%. The Revolving Credit Facility includes certain financial operating covenants, including a minimum liquidity requirement of $7.5 million. We are not aware of any instances of noncompliance with the key financial covenants as of January 3, 2025. The Revolving Credit Facility was terminated on March 13, 2025 upon the execution of the ACF Credit Agreement (as defined below).
Current wording
On March 27, 2023, we entered into the Revolving Credit Facility with MidCap Financial Services, LLC, which originally provided a total commitment of $30 million. The Revolving Credit Facility was terminated on March 12, 2025 upon execution of the ACF Credit Agreement.
Previous wording
During the fiscal year ended January 3, 2025, net cash used in operating activities was $21 million, compared to net cash used in operating activities of $88 million for the fiscal year ended December 29, 2023. Cash flows used in operating activities were driven by a net loss, adjusted for various non-cash items and changes in accounts receivable, contract assets, contract liabilities, accounts payable and accrued expenses balances, accrued salaries and wages and other assets and liabilities as discussed below.
Current wording
During the fiscal year ended January 2, 2026, net cash used in operating activities was $65 million, compared to net cash used in operating activities of $21 million for the fiscal year ended January 3, 2025. Cash flows used in operating activities were driven by a net loss, adjusted for various non-cash items and changes in accounts receivable, contract assets, contract liabilities, accounts payable and accrued expenses balances, accrued salaries and wages and other assets and liabilities as discussed below.
Previous wording
During the fiscal year ended January 3, 2025, the increase in operating assets and liabilities was $83 million, which was primarily driven by decreases in contract assets and increases in contract liabilities and accrued expenses. The Company’s operating assets and liabilities fluctuations are impacted by the mix of projects in backlog, seasonality, the timing of new awards and related payments for work performed and the contract billings to the customer as projects are completed. Operating assets and liabilities are also impacted at period end by the timing of accounts receivable collections and accounts payable payments for projects.
Current wording
During the fiscal year ended January 2, 2026, the decrease in operating assets and liabilities was $66 million, which was primarily driven by decreases in contract liabilities and increases in contract assets, partially offset by increases in accounts payable. The Company’s operating assets and liabilities fluctuations are impacted by the mix of projects in backlog, seasonality, the timing of new awards and related payments for work performed and the contract billings to the customer as projects are completed. Operating assets and liabilities are also impacted at period end by the timing of accounts receivable collections and accounts payable payments for projects.
Previous wording
For the fiscal year ended December 29, 2023, net cash provided by investing activities was $22 million, which primarily consisted of cash proceeds from the sale of non-core business contracts of $30 million, proceeds from sale of assets of $6 million ($4 million due to sale of an office building), and return of investment in unconsolidated joint ventures of $16 million, partially offset by unconsolidated joint venture equity contributions of $23 million and purchases of property, plant and equipment of $7 million.
Current wording
For the fiscal year ended January 2, 2026, net cash provided by investing activities was $1 million, which was primarily driven by proceeds from the sale of assets of $5 million and return of investment in unconsolidated joint ventures of $3 million, partially offset by purchases of property, plant and equipment of $7 million.
Previous wording
Contractual obligations of the Company consisted of liabilities associated with remaining lease payments through the fiscal years ending December 28, 2029 of approximately $7 million, $5 million, $4 million, $4 million and $3 million, respectively, and approximately $3 million in the aggregate thereafter based on balances outstanding as of January 3, 2025. See Note 10 - Leases, of the notes to the consolidated financial statements included in Item 8 of this Annual Report on Form 10-K.
Current wording
Contractual obligations of the Company consisted of liabilities associated with remaining lease payments through the fiscal years ending January 3, 2030 of approximately $6 million, $4 million, $4 million, $3 million and $2 million, respectively, and approximately $1 million in the aggregate thereafter based on balances outstanding as of January 2, 2026. See Note 10 - Leases, of the notes to the consolidated financial statements included in Item 8 of this Annual Report on Form 10-K.
Rearranged current paragraphs (3)
Current report — wording carried from elsewhere
Ansley Loan Agreement. As of January 2, 2026, we are not aware of any instances of noncompliance with non-financial or financial covenants.
Current report — wording carried from elsewhere
During the fiscal year ended January 2, 2026, the Company paid $2 million in cash interest, and accrued $3 million in non-cash payment-in-kind interest as of January 2, 2026.
Current report — wording carried from elsewhere
As of January 2, 2026, we had a backlog of projects of approximately $793 million.
Rearranged previous paragraphs (2)
Previous report — wording carried elsewhere
ERP pre-implementation asset impairment and associated costs
Previous report — wording carried elsewhere
ERP pre-implementation asset impairment and associated costs were $16 million due to the strategic decision to enhance the Company’s current ERP system rather than implementing a new platform which, due to prior capitalized costs and remaining contractual obligations, resulted in a charge of $16 million recorded in the fiscal year ended January 3, 2025.