Item 1. Business
MGE Energy operates in the following business segments:
Regulated electric utility operations – generating, purchasing, and distributing electricity through MGE.
Regulated gas utility operations – purchasing and distributing natural gas through MGE.
Nonregulated energy operations – owning and leasing electric generating capacity that assists MGE through MGE Energy's wholly owned subsidiaries MGE Power Elm Road and MGE Power West Campus.
Transmission investments – representing our investment in American Transmission Company LLC, a company engaged in the business of providing electric transmission services primarily in Wisconsin, and our investment in ATC Holdco LLC, a company created to facilitate out-of-state electric transmission development and investments.
All other – investing in companies and property that relate to the regulated operations and financing the regulated operations, through its wholly owned subsidiaries CWDC, MAGAEL, and North Mendota, and Corporate functions.
See Footnote 22 to the Notes to Consolidated Financial Statements in Part II, Item 8 of this Report for more information regarding MGE Energy's business segments.
MGE's utility operations represent a majority of the assets, liabilities, revenues, expenses, and operations of MGE Energy. MGE Energy's nonregulated energy operations currently include an undivided interest in two coal-fired generating units located in Oak Creek, Wisconsin, which we refer to as the Elm Road Units, and an undivided interest in a cogeneration facility located on the Madison campus of the University of Wisconsin, which we refer to as the West Campus Cogeneration Facility or WCCF.
As a public utility, MGE is subject to regulation by the PSCW and the FERC. The PSCW has authority to regulate most aspects of MGE's business including rates, accounts, the issuance of securities, and plant siting. The PSCW also has authority over certain aspects of MGE Energy as a holding company of a public utility. FERC has jurisdiction, under the Federal Power Act, over certain accounting practices and certain other aspects of MGE's business.
MGE Energy's subsidiaries are also subject to regulation under local, state, and federal laws regarding air and water quality and solid waste disposal. See "Environmental Regulation" below for additional information regarding the environmental regulations to which MGE Energy and its subsidiaries are subject.
MGE Energy was organized as a Wisconsin corporation in 2001. MGE was organized as a Wisconsin corporation in 1896. Our principal offices are located at 133 South Blair Street, Madison, Wisconsin 53788, and our telephone number is (608) 252-7000.
Electric Utility Operations
MGE distributes electricity in a service area covering a 264 square-mile area of Dane County, Wisconsin. The service area includes the city of Madison, Wisconsin. It owns or leases ownership interests in electric generation facilities located in Wisconsin and Iowa.
As of December 31, 2025, MGE supplied electric service to approximately 170,000 customers, with approximately 91% located in the cities of Fitchburg, Madison, Middleton, and Monona, Wisconsin and 9% in adjacent areas.
Electric sales, customers, and revenues for 2025 were comprised of the following:
Electric operations accounted for approximately 72%, 74%, and 71% of MGE's total 2025, 2024, and 2023 regulated revenues, respectively.
See Part I, Item 2. Properties, of this Report for a description of MGE's electric utility plant.
MGE is registered with North American Electric Reliability Corporation (NERC) and one regional entity, the Midwest Reliability Organization. The essential purposes of these entities are to develop and implement regional and NERC reliability standards and determine compliance with those standards, including enforcement mechanisms.
Transmission
In 2001, American Transmission Company LLC (ATC) was collectively formed by Wisconsin-based utilities which were required by Wisconsin law to contribute their transmission facilities to an independent system operator. ATC continues to be owned by those utilities and their affiliates. ATC's purpose is to provide reliable, economic transmission service to all customers in a fair and equitable manner. ATC plans, constructs, operates, maintains, and expands transmission facilities that it owns to provide adequate and reliable transmission of power. ATC is regulated by FERC for all rate terms and conditions of service. ATC is also regulated by the PSCW for some aspects of its governance and is a transmission-owning member of the MISO.
Regional Transmission Organizations (RTO)
MISO
MGE is a nontransmission owning member of MISO. MISO, a FERC-approved RTO, is responsible for monitoring the electric transmission system that delivers power from generating plants to wholesale power customers. MISO's role is to ensure equal access to the transmission system and to maintain or improve electric system reliability across 15 U.S. states and the Canadian province of Manitoba.
MISO operates a bid-based energy market. MGE offers substantially all of its generation to the MISO market and purchases its electric supply, or load requirement from the MISO market in accordance with the MISO tariff. MGE also participates in the ancillary services market operated by MISO, which is an extension of the existing energy market. Through the operation of the ancillary services market, MISO provides the reserves for MGE's load, and MGE may offer to sell reserves from its generating units.
MGE participates in the MISO capacity auction, which provides a forum for buyers and sellers of planning resource credits to interact. Load serving entities such as MGE may participate in the capacity auction to obtain the necessary aggregate planning resource credits needed to meet their planning reserve margin requirement established by the PSCW. Generator owners may participate to sell any excess aggregate planning resource credits.
Fuel supply and generation
MGE satisfies its customers' electric demand with internal generation and purchased power. MGE's current fuel mix for generation fluctuates from year-to-year due to fuel pricing in the market, generating unit availability, weather, and customer demand. MGE has a responsibility to its customers to dispatch the lowest cost generation available pursuant to regulatory requirements.
MGE's electric energy delivery requirements were satisfied from the following fuel sources:
| (in MWh) | 2025 | 2024 | 2023 |
|---|---|---|---|
| Coal(a) | 1,750,273 | 1,452,156 | 1,359,691 |
| Natural gas | 756,966 | 654,406 | 566,972 |
| Renewable sources(b) | 913,612 | 840,060 | 715,369 |
| Fuel oil | 862 | 489 | 544 |
| Purchased power - other(c)(d) | 305,250 | 537,445 | 744,120 |
| Total fuel sources | 3,726,963 | 3,484,556 | 3,386,696 |
| Adjusted total fuel sources(d) | 4,033,161 | 3,814,229 | 3,643,267 |
(a)
MGE's coal generation for electric supply may fluctuate from year to year. Generation sources change based on lowest cost generation available. MGE continues to drive its commitment to achieve our emission reduction goals through the continuing addition of renewable generation and its transition plan to eliminate coal as a fuel source.
(b)
Includes both internal generation and purchased power.
(c)
Includes third-party purchased power and MISO market activity. A significant percentage of MGE's electric supply comes from internal generation sources. MGE supplements this internal generation with long-term purchase power agreements and spot purchases in the MISO market.
(d)
The MISO market consists of two energy markets, the Day-ahead market and the Real-time market. The table above nets purchases and sales within the same hour in the two MISO markets. For the years ended December 31, 2025, 2024, and 2023, the amount netted between Day-ahead and the Real-time MISO markets was 306,198 MWh, 329,672 MWh, and 256,571 MWh, respectively. These amounts are reflected in "Adjusted total fuel sources."
Environmental Initiatives – Electricity Generation
MGE continues to advance its long-term strategy to achieve a more sustainable future for the benefit of its investors, employees, customers and the communities it services. MGE has set a target of providing net-zero carbon electricity by 2050.
MGE's carbon reduction goals are generally aligned with leading scientific guidance, including recommendations from the Intergovernmental Panel on Climate Change (IPCC) to limit global temperature increases to 1.5 degrees Celsius above pre-industrial levels. In 2020, the University of Wisconsin-Madison's Nelson Institute for Environmental Studies released its analysis of MGE's net-zero by 2050 goal. The IPCC modeling available suggested that by 2050, emissions from electricity generation in industrialized countries should be 87% to 99% lower than the 2005 baseline. The analysis determined that our 2050 goal is in line with model benchmarks to limit global warming to 1.5 degrees Celsius above pre-industrial levels.
MGE's strategy focuses on adopting cost effective technologies as they become commercially available, while maintaining reliability and affordability. Significant investments in solar, wind, and battery storage support MGE's long term decarbonization goal.
Renewable generation and storage - Solar, wind, and battery storage projects play a critical role in MGE's strategy for reducing carbon emissions in pursuit of net-zero carbon electricity by 2050. Additionally, MGE plans to reduce its use of fossil fuels and work to help customers with energy efficiency and electrification, including the electrification of transportation.
Since 2015, MGE has added 253 MW of solar, 93 MW of wind generation, and 11 MW of battery storage to its electric renewable generation portfolio. See Item 2. Properties below for further information on these facilities. In addition, MGE expects to add approximately 252 MW of solar, 18 MW of wind, and 125 MW of battery storage, which include projects approved or pending PSCW approval, by the end of 2030.
MGE is partnering with Columbia's co-owners to construct a compressed carbon dioxide long-duration energy storage system, known as the Columbia Energy Storage project. MGE's 19% share will be 3 MW. The project was selected for a grant from the U.S Department of Energy. The Columbia Energy Storage project was approved by the PSCW in 2025. This project will be the first of its kind in the United States.
MGE is working to achieve a more sustainable energy future by investing in cost-effective renewable generation and innovative new technologies and services for customers. MGE has emphasized this innovation by developing customer programs to address climate change and encourage our customers to use clean energy. A portion of MGE's renewable generation is dedicated to customer programs such as the Renewable Energy Rider (RER) and Shared Solar Program. The RER and Shared Solar programs reduce MGE's carbon emissions while providing customers the ability to purchase renewable energy to meet their energy needs.
Renewable Energy Rider (RER) – Under this program, MGE partners with large energy users, primarily governmental entities, to provide customized renewable energy solutions. MGE owns the generation assets and RER customers are billed a PSCW-approved contractual renewable resource rate that covers all costs associated with the construction and ongoing operations of the renewable generation facility. MGE has developed approximately 42 MW of solar generation under the RER program.
Shared Solar Program – This program offers residential and small business customers to meet up to half of their annual energy needs with locally generated solar energy. The first solar array associated with this program, owned by MGE, became operational in 2017 for 500 KW capacity. The completion of a second solar facility (Morey Field) added 3.5 MW of capacity to the program, as well as 2 MW from Strix Solar, which was completed in 2025. In December 2025, the PSCW approved the implementation of a new community solar program, Shared Solar for Business, for large commercial customers.
Electrifying Transportation - The electrification of transportation is a key strategy for reducing carbon emissions. MGE has established a network of nearly 60 charging stations, powered by renewable energy, serving the growing number of electric vehicles (EV) in MGE's service area. The EV fast charging hubs feature some of the most powerful EV chargers in the Midwest. MGE has continued to add EVs to its fleet and is targeting 100% all-electric or plug-in hybrid light-duty vehicles by 2030. Additionally, we are working with the City of Madison to further the electrification of its vehicles and buses. MGE continues to provide technical assistance to the city in the development of an all-electric Bus Rapid Transit system.
Transitioning away from coal
o
Elm Road Units – In October 2025, MGE, along with the plant co-owners, filed a joint application with the PSCW to end the use of coal as a primary fuel at the Elm Road Units and transition the plant to natural gas. Transition plans and costs will be subject to PSCW approval. By the end of 2030, coal is expected to be used only as a backup fuel at the Elm Road Units. By the end of 2032, MGE expects that the Elm Road Units will be fully transitioned away from coal.
o
Columbia - Operational, regulatory, and environmental regulation considerations have impacted and continue to impact Columbia's generation planning. MGE, as a minority owner, and Columbia's other co-owners continue to evaluate transitioning away from coal and continue to evaluate replacing the generation from Columbia while maintaining electric service reliability. MGE and Columbia's co-owners are exploring converting Columbia to natural gas.
Natural gas as a fuel source - As part of MGE's continued energy transition plan, MGE plans to invest in additional natural gas-fired generation and storage facilities. Natural gas plants add needed reliability and balance to the electric system while MGE continues to transition away from coal-fired generation and add more renewable capacity to MGE's generation mix. MGE purchased 50 MW (25 MW in 2023 and 25 MW in 2024) in the West Riverside Energy Center (West Riverside), a highly efficient, state-of-the-art natural gas-fired plant in Beloit, Wisconsin. In February 2026, MGE executed an asset purchase agreement for 168 MW of existing gas-fired generation through an ownership share in the RockGen Energy Center near Cambridge, Wisconsin, subject to PSCW approval. If approved, the transaction is expected to close in late 2027.
Generation sources
MGE receives electric generation supply from coal-fired, gas-fired, and renewable energy sources. These sources include owned facilities as well as facilities leased from affiliates and accounted for under our nonregulated energy operations. See Item 2. Properties for more information regarding these generation sources, including location, capacity, ownership or lease arrangement, and fuel source. See "Nonregulated Energy Operations" below for more information regarding generating capacity leased to MGE by MGE Energy's nonregulated subsidiaries.
Purchased power
MGE enters into short- and long-term purchase power commitments with third parties to meet a portion of its anticipated electric energy supply needs. As of December 31, 2025, MGE has 30 MW of a renewable purchase power commitment for each of the next two years.
Gas Utility Operations
MGE transports and distributes natural gas in a service area covering 1,722 square miles in seven south-central Wisconsin counties. The service area includes the city of Madison, Wisconsin and surrounding areas.
As of December 31, 2025, MGE supplied natural gas service to approximately 180,000 customers in the cities of Elroy, Fitchburg, Lodi, Madison, Middleton, Monona, Prairie du Chien, Verona, and Viroqua; 25 villages; and all or parts of 49 townships. Gas sales, customers, and revenues for 2025 were comprised of the following:
Gas operations accounted for approximately 28%, 26%, and 29% of MGE's total 2025, 2024, and 2023 regulated revenues, respectively.
MGE can curtail gas deliveries to interruptible customers. These are customers who agree to reduce their load in the case of an emergency interruption. In 2025, 2024, and 2023, approximately 2%, 2%, and 3%, respectively, of retail gas deliveries were to interruptible customers.
Environmental Initiatives - Natural gas distribution
Building upon our long-standing commitment to providing affordable, sustainable energy, MGE has set a goal to achieve net-zero methane emissions from its natural gas distribution system by 2035. If MGE can accelerate plans to achieve net-zero methane emissions from its natural gas system—through the evolution of new technologies, such as renewable natural gas—it will. MGE is working to reduce overall emissions from its natural gas distribution system in a quick and cost effective manner. MGE offers two voluntary renewable natural gas programs. The initial program, launched in May 2024, enables customers to offset emissions associated with their natural gas consumption through a mechanism in which MGE purchases renewable thermal credits and retires them on behalf of participating customers. The second program, launched in January 2026, enables customers to inject renewable natural gas produced on the customer's premise into MGE's distribution system; customers may sell the natural gas to MGE or another third party and may retain or sell to MGE or another third party the associated environmental attributes.
Gas supply
MGE has physical interconnections with ANR Pipeline Company (ANR) and Northern Natural Gas Company (NNG). MGE's primary service territory, which includes Madison and the surrounding area, receives deliveries at one NNG and four ANR gate stations. MGE's outlying territory receives deliveries at NNG gate stations located in Elroy, Prairie du Chien, Viroqua, and Crawford County. Interconnections with two major pipelines provide competition in interstate pipeline service and a more reliable and economical gas supply mix, which includes gas from Canada and the mid-continent and Gulf Coast regions of the United States.
During the winter months, when customer demand is typically higher, MGE is primarily concerned with meeting its obligation to customers. MGE meets customer demand by using firm supplies under contracts finalized before the heating season, supplies in storage (injected during the summer), and other firm supplies purchased during the winter period.
Annually, through our contracts with ANR, a total of approximately 6.5 million Dth of gas can be injected into ANR's storage fields in Michigan from April 1 through October 31. These gas supplies are then available for withdrawal during the subsequent heating season, November 1 through March 31. Using storage allows MGE to buy gas supplies during the summer season, when prices are normally lower, and withdraw these supplies during the winter season, when prices are typically higher. Storage also gives MGE more flexibility in meeting daily load fluctuations.
MGE's contracts for firm transportation service of gas include winter maximum daily quantities of:
185,650 Dth (including 116,078 Dth of storage withdrawals) on ANR.
81,453 Dth on NNG.
The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.