Enlight Renewable Energy Ltd.

For the period ended Nov 3, 2026. Filed Nov 3, 2026.

View on SEC.gov

About this filing

What a company based outside the US has published at home or sent to its shareholders. It is how many foreign companies share results and news between annual reports.

Nov 3, 2026 · Filed Nov 3, 2026

Use the contents to explore the available documents and sections.

ENLT$68.32+5.7%Stored close · as of Nov 6, 2026
See the whole filing, with its images and exhibits

EX-99.1 · Appendix

Appendix 5

a) Segment information: Operational projects

($ thousands) · 9 Months ended September 30 · 3 Months ended September 30
Operational Project Segments · Installed Capacity (MW) · Installed Storage (MWh) · Generation (GWh) · Revenues and income · Segment Adjusted EBITDA1 · Generation (GWh) · Reported Revenue · Segment Adjusted EBITDA1
2026 · 2025 · 2026 · 2025 · 2026 · 2025 · 2026 · 2025 · 2026 · 2025 · 2026 · 2025
MENA6768991,1611,158239,928173,180149,651115,51439546398,55777,54457,21251,127
Europe1,351752,0851,912165,541144,502123,170117,42860255952,22045,31837,68635,202
USA8962,5401,536790233,667110,948211,76798,17152327180,16841,96873,68838,258
Total Consolidated2,9233,5144,7823,860639,136428,630484,588331,1131,5201,293230,945164,830168,586124,587
Unconsolidated at Share3280
Total2,9553,594

b) Operational Projects Further Detail

($ thousands) · 9 Months ended September 30, 2026 · 3 Months ended September 30, 2026
Operational ProjectSegmentInstalled Capacity (MW)Installed Storage (MWh)Revenues and incomeSegment Adjusted EBITDA1Reported RevenueSegment Adjusted EBITDA1Debt balance as of September 30, 2026Ownership %2
MENA WindMENA316-82,21725,472604,85649%
MENA PVMENA360899157,71173,085619,66684%
Total MENA676899239,928149,65198,55757,2121,224,522
Europe WindEurope1,184-149,20745,213807,85365%
Europe PVEurope1677516,3347,00769,12174%
Total Europe1,35175165,541123,17052,22037,686876,974
USA PVUSA8962,540233,66780,168678,261100%
Total USA8962,540233,667211,76780,16873,688678,261
Total Consolidated Projects2,9233,514639,136484,588230,945168,5862,779,757
Uncons. Projects at share328050%
Total2,9553,594639,136484,588230,945168,5862,779,757
  1. For the 9 month ended September 2026, EBITDA included $1.9m of compensation recognized from Bjorenberget and excluded $30m from Sunlight sale and $3m of compensation from Emek; For the 9 month ended September 2025 EBITDA excluded $42m from Sunlight sale

  2. Ownership % is calculated based on the project's share of total revenues

c) Projects under construction

($ millions) Consolidated ProjectsCountryGeneration and energy storage Capacity (MW/MWh)Est. CODEst. Total Project CostTax credit benefit- Qualifying categoryTax credit benefit- Adders3Discounted Value of Tax Benefit2Est. Total Project Cost net of tax benefitCapital Invested as of September 30, 2026Est. Equity Required (%)Equity Invested as of September 30, 2026Est. First Full Year Revenue4Est. First Full Year EBITDA4,5Ownership %1
Country AcresUSA403/688Q4 2026814-855ITCDC (10%)399-419415-4367800%-10%69462-6548-50100%
Co Bar ComplexUSA1,211/4,000Q4 2027-H1 20282,938-3,089ITC, PTCEC (10%) + DC (10% BESS only)1,434-1,5081,504-1,5818340%-10%6348244-257195-205100%
Crimson OrchardUSA120/400Q2 2027298-313ITCEC (10%)11138-145160-1681930%-10%63427-2820-21100%
Snowflake AUSA594/1,900Q4 20271,353-1,422ITCEC (10%)11605-636748-7861,0210%-10%6159124-130104-109100%
Finland BESS10Finland0/902H1 2028144-151---144-1511425%-35%1443-4529-3151%
BertikowGermany0/881H1 2028176-185---176-1852020%-30%2036-3831-3250%
Gecama SolarSpain227/220Q4 2026196-206---196-20615923%-28%715036-3829-3172%
Tapolca BessHungary0/140Q4 2624-25---24-251640%-50%1676-7100%
Bjornberget – BESSSweden0/100Q1 202724-25---24-2519100%194355%
Ohad HV storage9Israel0/675H2 2028118-124---118-1241410%-20%1495100%
Israel ConstructionIsrael37/326H1 27- H2 2885-90---85-902215%-25%2215-167-885%
Total Consolidated Projects2,592/ 10,2326,170-6,4852,576-2,7083,594-3,7773,093890607-637477-502
Unconsolidated Projects at share10Israel7/137Q4 2026- H2 202727-28---27-282215%-20%225-6453%
Total2,599/ 10,3696,197-6,5132,576-2,7083,621-3,8053,115912612-643481-506

d) Pre-Construction Projects (due to commence construction within 12 months of the Approval Date)

($ millions) Consolidated Projects · Country · Generation and energy storage Capacity (MW/MWh) · Est. COD · Est. Total Project Cost · Tax Credit Benefit · Discounted Value of Tax Benefit2 · Est. Total Project Cost net of tax benefit · Capital Invested as of September 30, 2026 · Est. Equity Required (%) · Equity Invested as of September 30, 2026 · Est. First Full Year Revenue4 · Est. First Full Year EBITDA4,5 · Ownership %1
Qualifying CategoryAdders3
NardoItaly104/8722029232-244---232-2441125%-35%1144-4636-38100%
JupiterGermany150/2,166H2 2028536-563---536-563830%-40%895-9978-8251%
KarpenRomania0/848H2 2028-H1 2029153-161---153-161725%-35%731-3326-27100%
Finland BESSFinland0/1,400H1 2028237-249---237-2492625%-35%2662-6542-44100%
MosciskaPoland0/216H2 202850-52---50-52530%-40%516-1713-14100%
Neot Smadar HV storage9Israel0/675H1 2029117-123---117-123010%-20%073100%
($ millions) Additional Pre-Construction Projects · MW Deployment MW/MWh · Est. Total Project Cost · Tax Credit Benefit · Discounted Value of Tax Benefit2 · Est. Total Project Cost net of tax benefit · Capital Invested as of September 30, 2026 · Est. Equity Required (%) · Equity Invested as of September 30 2026 · Est. First Full Year Revenue4 · Est. First Full Year EBITDA4,5 · Ownership %1
2027 · 2028 · 2029 · Qualifying Category · Adders3
United States128/0184/0255/01,008-1,059ITCDC (10%) & EC (10%)8488-513520-5466415%-35%6464-6849-51100%
Europe0/750/429-93-98---93-98530%-100%520-2115-1686%
MENA0/7574/945-284-298---284-2981320%-40%1359-6232-3493%
Total Consolidated Projects128/150258/1,374255/02,710-2,847488-5132,222-2,334139139398-419294-309
Unconsolidated Projects at share100/260/22-6---6115%-20%11-2154%
Total Pre-Construction895MW +7,749MWh2,716-2,853488-5132,228-2,340140140399-420295-310
  1. The legal ownership share for all U.S. projects is 90%, but Enlight invests 100% of the equity in the project and entitled to 100% of the project distributions until full repayment of Enlight's capital plus a preferred return

  2. Value of tax benefits under the IRA: The PTC value is estimated based on the project’s expected annual production and a yearly CPI indexation of 2%, discounted by 8% to COD. In assessing the value of the ITC, a step-up adjustment was made to reflect the full value of the tax credits, thus lowering net construction costs and enhancing the valuation and return of the project. The actual value attributed to tax benefits in a tax equity transaction may differ from the value presented, subject to the structure of the transaction and prevailing market conditions.

  3. The Energy Community (EC) Adder provides extra credits for renewable energy projects in areas impacted by fossil fuel reliance or economic transition. The Domestic Content (DC) Adder rewards projects using U.S.-manufactured components, promoting local job creation and supply chain growth

  4. Revenue and EBITDA for the first year of U.S. projects as presented above do not include income from tax benefits

  5. EBITDA is a non-IFRS financial measure. This figure represents consolidated EBITDA for the project and excludes the share of project distributions to tax equity partners, as well as ITC and PTC proceeds. These components of the tax equity transaction may differ from project to project, are subject to market conditions and commercial terms agreed upon reaching financial close

  6. The required equity during construction is estimated at 10% and is expected to decrease to 0% at COD

  7. The majority of Gecama Solar's equity is funded through debt held at Gecama Wind, amounting to $129m as of September 30, 2026. This debt is included in Gecama Wind's debt balance under the operational projects.

  8. Rustic hills 1+2 - DC (10%) + EC (10%); Coggon - DC (10%); Gemstone - DC (10%);

  9. Two high voltage projects with total capacity of 1,350MWh. Estimated revenue for the first 5 years is $16m million per year. From year 6, the projects will move to a deregulated market, with revenue expected to be $36 million per year

  10. All numbers, beside equity invested, reflects Enlight share only

  11. In the previous quarter, the Snowflake A BESS project was presented as expected to be eligible for the Domestic Content (“DC”) Adder. The project will not meet the applicable requirements for the DC adder. However, the removal of the DC adder is offset by significant savings capital expenditure of the new alternative equipment resulting in a negligible impact on the project’s economics

e) Additional information on tax equity investments

Tax equity investment · Tax equity partner's share of project tax credits, cash flows, and taxable income
($ millions) Projects*Est. Total Project CostUpfront tax equity investmentTax credit proceeds during the project's operation ("pay-go")Share of ITC/PTC tax credit allocated to tax equity partnerShare of taxable income initial periodDuration of initial period for share of taxable income (years)Share in project cash flow initial period (second period)Duration of initial period for share in project cash flow (years)
Atrisco PV36919855ConfidentialConfidentialConfidential17.5% (5%)10
Atrisco BESS458266-ConfidentialConfidentialConfidential23% (7%)5
Quail Ranch2741311899%99%1010% (5%)10
Roadrunner6213375599%99%5-1010%-12% (5%)10