ANFIELD ENERGY INC.
For the period ended Sep 15, 2026. Filed Sep 15, 2026.
View on SEC.govAbout this filing
What a company based outside the US has published at home or sent to its shareholders. It is how many foreign companies share results and news between annual reports.
Sep 15, 2026 · Filed Sep 15, 2026
Use the contents to explore the available documents and sections.
Contents
EX-99.1 · Permitting Path
Permitting Path
This milestone follows a defined sequence of steps in the process:
December 22, 2025 — DRMS issued an initial completeness determination on Highbury’s JD-8 restart application package, allowing the matter to advance through substantive review.
April 29, 2026 — The 112d application under File No. M-2025-056 was filed with DRMS (as reflected in the Division’s September 10, 2026 hearing notice).
August 24, 2026 — DRMS issued its rationale recommending that the Board approve the application.
September 10, 2026 — DRMS announced a Formal Board Hearing during the Board’s October 14–15, 2026 meeting in Denver.
The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.