EX-99.1 · Permitting Path

Permitting Path

This milestone follows a defined sequence of steps in the process:

  • December 22, 2025 — DRMS issued an initial completeness determination on Highbury’s JD-8 restart application package, allowing the matter to advance through substantive review.

  • April 29, 2026 — The 112d application under File No. M-2025-056 was filed with DRMS (as reflected in the Division’s September 10, 2026 hearing notice).

  • August 24, 2026 — DRMS issued its rationale recommending that the Board approve the application.

  • September 10, 2026 — DRMS announced a Formal Board Hearing during the Board’s October 14–15, 2026 meeting in Denver.

ContentsView on SEC.gov

The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.