Liquidity and Capital Resources
We continually evaluate the availability of adequate financing to fund our ongoing business operations, working capital and core safety and infrastructure investment programs. Our financing is sourced through cash flow from operations, the issuance of debt and/or equity, and minority interest investments. Equity issuances are primarily conducted through our ATM program. Additionally, we received proceeds from tax credit transfers related to previously and currently monetized credits, which are returned to customers over a ten‑year period for investment tax credits and a one-year period for production tax credits. External debt financing is provided primarily through the issuance of long-term debt, accounts receivable securitization programs and our commercial paper program, which is backstopped by our committed revolving credit facility. We believe these sources provide adequate capital to fund operating activities and capital expenditures for our base business (i.e., excluding operations and capital expenditures related to serving data center customers) in 2026 and beyond.
The aggregate cost of Contract Assets and Pool Resource Assets supporting our existing data center customers is currently estimated to be between $9.25 to $9.75 billion. We expect to finance the construction and development of these assets and purchases of market capacity through a number of sources including, but not limited to, funds received under our data center contracts, debt, and equity financing raised by NiSource and capital contributions from affiliates of Blackstone to NIPSCO Holdings II and Generation Holdings II in connection with such Blackstone affiliates’ minority interest investments in those entities. For additional information on these minority interest investments, refer to Note 4, "Noncontrolling Interests," and Note 19, "Other Commitments and Contingencies - E. Other Matters," in our Annual Report on Form 10-K for the year ended December 31, 2025. If we enter into additional data center contracts, we expect that we would need to develop additional generation assets to serve our new data center customers, which may be significant. In order to fund the development of these assets required to serve our data center customers we will be required to obtain significant additional financing, for which we may consider other funding sources, structures, or partnerships, which may include JVs, off-balance sheet arrangements in the form of BTAs, or other arrangements to support maintenance of our investment grade credit ratings.
Sources of financing activities for the current year are as follows:
Details of our ATM program activity are summarized below:
In February 2026, we executed a forward sale agreement, which allows us to issue a fixed number of shares at a price to be settled in the future. The forward purchaser under our forward sale agreement borrowed 2,200,000 shares from third parties, which the forward purchaser sold, through its affiliated agent, at a weighted average price of $45.63 per share. We may settle the forward sale agreement in shares, cash or net shares by December 2026.
In June 2026, we executed a forward sale agreement, which allows us to issue a fixed number of shares at a price to be settled in the future. The forward purchaser under our forward sale agreement borrowed 2,151,874 shares from third parties, which the forward purchaser sold, through its affiliated agent, at a weighted average price of $46.47 per share. We may settle the forward sale agreement in shares, cash or net shares by December 2026.
As of June 30, 2026, the ATM program inclusive of the outstanding forward sale agreements had approximately $1.15 billion of equity capacity available. The ATM program expires in December 2028.
Details of our long-term debt activity are summarized below:
In May 2026, we completed the issuance and sale of $500.0 million of 4.75% senior unsecured notes maturing in 2031, and $750.0 million of 5.30% senior unsecured notes maturing in 2036. The issuances resulted in approximately $1.236 billion of total net proceeds after discount and debt issuance costs.
See Note 6, "Equity," Note 7, "Short-Term Borrowings," and Note 8, "Long-Term Debt," in the Notes to the Condensed Consolidated Financial Statements (unaudited) for more information on our financing activities.
Cash Flow Activities
The following table summarizes our cash flow activities:
| Six Months Ended June 30, | |||
|---|---|---|---|
| (in millions) | 2026 | 2025 | Change in 2026 vs 2025 |
| Cash from (used for): | |||
| Operating Activities | $1,122.7 | $1,181.8 | $(59.1) |
| Investing Activities | (2,106.8) | (2,566.3) | 459.5 |
| Financing Activities | $943.8 | $1,551.5 | $(607.7) |
Operating Activities
The year over year decrease in cash from operating activities was primarily attributable to changes in exchange gas receivables, partially offset by increases in accounts receivable and depreciation.
Investing Activities
The year over year decrease in investing activities was primarily driven by prior year milestone payments to renewable generation asset developers for certain of our BTA projects and prior year advanced deposits offset by current year capital expenditures.
We expect to make capital investments of approximately $600 million in connection with Pool Resource Assets initially being developed in connection with contracted demand from data center customers. These capital expenditures are incremental to the estimates of capital investments relating to data center contracts described in our Annual Report on Form 10-K for the year ended December 31, 2025. For an overview of our forecasted capital investments in the period from 2026 through 2030, refer to Part I, Item 2, "Management’s Discussion and Analysis of Financial Condition and Results of Operations—Liquidity and Capital Resources—Cash Flow Activities—Investing Activities" in our Quarterly Report on Form 10-Q for the quarter ended March 31, 2026.
Regulatory Capital Programs. We continue to upgrade and modernize our electric system to enhance safety and reliability by addressing aged infrastructure and deploying advanced grid technologies. We are also upgrading and modernizing our gas infrastructure to enhance safety and reliability by reducing leaks. An ancillary benefit of these programs is the reduction of GHG emissions. In 2026, we continue to move forward on core infrastructure investment programs supported by complementary regulatory and customer initiatives across five states of our operating area.
The following table describes the most recent vintage of our regulatory programs to recover infrastructure replacement and other federally mandated compliance investments:
| (in millions) | |||||
|---|---|---|---|---|---|
| Company | Program | Capital Investment | Investment Period | Filing Date | Costs Covered(1) |
| Approved | |||||
| Columbia of Ohio | CEP - 2025 | $1,027.8 | 4/21-12/24 | 2/27/2025 | Assets not included in the IRP or PHMSA IRP. |
| Columbia of Virginia | SAVE - 2026 | $176.1 | 10/24-12/26 | 8/12/2025 | Replacement projects that (i) enhance system safety or reliability, or (ii) reduce, or potentially reduce, greenhouse gas emissions. Includes costs associated with Advanced Leak Detection and Repair. |
| Columbia of Kentucky | SMRP - 2026 | $181.4 | 1/23-12/26 | 10/15/2025 | Replacement of mains and inclusion of system safety investments. |
| NIPSCO - Electric(2) | TDSIC - 7 | $175.4 | 7/22-3/25 | 5/27/2025 | New or replacement projects undertaken for the purpose of safety, reliability, system modernization or economic development. |
| NIPSCO - Electric(3) | GCT - 3 | $385.6 | 9/23-10/26 | 12/16/2025 | New gas peaker generation project cost forecasted through October 2026. |
| NIPSCO - Gas | TDSIC - 10 | $90.3 | 4/25-9/25 | 11/25/2025 | New or replacement projects undertaken for the purpose of safety, reliability, system modernization, or economic development. |
| NIPSCO - Gas | FMCA - 1 | $52.5 | 7/25-12/25 | 2/24/2026 | Project costs to comply with federal mandates. |
| Columbia of Ohio | IRP - 2026 | $1,185.0 | 4/21-12/25 | 2/27/2026 | Replacement of hazardous service lines, cast iron, wrought iron, uncoated steel, and bare steel pipe. |
| Columbia of Ohio | PHMSA IRP - 2026 | $180.2 | 1/23-12/25 | 2/27/2026 | Investments necessary to comply with the PHMSA Mega Rule. |
| Pending Commission Approval | |||||
| Columbia of Ohio | CEP - 2026 | $1,292.0 | 4/21-12/25 | 2/20/2026 | Assets not included in the IRP or PHMSA IRP. |
| NIPSCO - Electric | TDSIC – 9 | $451.6 | 7/22 – 3/26 | 6/9/2026 | New or replacement projects undertaken for the purpose of safety, reliability, system modernization or economic development. |
| NIPSCO - Electric(3) | GCT – 4 | $521.2 | 9/23 - 4/27 | 6/23/2026 | New gas peaker generation project cost forecasted through April 2027. |
| NIPSCO - Gas | TDSIC – 11 | $113.2 | 10/25–12/25 | 5/26/2026 | New or replacement projects undertaken for the purpose of safety, reliability, system modernization, or economic development. |
(1)Programs do not include any costs already included in base rates.
(2)TDSIC – 7 was originally filed in May 2025. TDSIC - 7 was refiled in February 2026, due to the electric rate case Step 2 Compliance Filing. The refiling adjusted the capital in the tracker from $315.6 million to $175.4 million.
(3)Capital investment is based on a projected amount. The capital investment has not all been incurred to date and represents a forecasted average for the billing period.
Columbia of Ohio filed an application in December 2025 to seek continuation of its PHMSA IRP Rider for calendar year 2027. The request includes recovery of $404.3 million of capital to reconfirm maximum allowable operating pressure of transmission class pipe to meet federal rule requirements. Also, Columbia of Ohio filed an application in June 2026 to seek continuation of its Rider IRP and CEP Rider for calendar year 2027. The request includes recovery of $241.7 million of capital for Rider IRP and $345.6 million of capital for the CEP Rider.
NIPSCO filed a Gas TDSIC Plan (2026 - 2030) in December 2025. The petition is seeking recovery of new or replacement projects undertaken for the purpose of safety, reliability, system modernization, or economic development. The request includes $741.0 million of estimated capital, including indirect costs and AFUDC. There was a hearing in May 2026 with the final order expected in the third quarter of 2026.
Financing Activities
Common Stock. Refer to Note 6, "Equity," in the Notes to the Condensed Consolidated Financial Statements (unaudited) for information on common stock.
Short-Term Debt. Refer to Note 7, "Short-Term Borrowings," in the Notes to the Condensed Consolidated Financial Statements (unaudited) for information on short-term debt activity.
Noncontrolling Interest. Refer to Note 4, "Noncontrolling Interests," in the Notes to the Condensed Consolidated Financial Statements (unaudited) for information on contributions and distributions from noncontrolling interests.
Sources of Liquidity
The following table displays our liquidity position as of June 30, 2026 and December 31, 2025:
| (in millions) | June 30, 2026 | December 31, 2025 |
|---|---|---|
| Current Liquidity | ||
| Revolving Credit Facility | $2,500.0 | $2,500.0 |
| Accounts Receivable Programs(1) | 245.0 | 175.0 |
| Less: | ||
| Commercial Paper | 692.0 | 736.0 |
| Letters of Credit Outstanding Under Credit Facility | 25.0 | 25.0 |
| Add: | ||
| Cash and Cash Equivalents | 70.0 | 110.1 |
| Net Available Liquidity | $2,098.0 | $2,024.1 |
(1)Represents the lesser of the seasonal limit or maximum borrowings supportable by the underlying receivables.
Debt Covenants. We are subject to a financial covenant under our revolving credit facility, which requires us to maintain a debt to capitalization ratio that does not exceed 70.0%. As of June 30, 2026, the ratio was 52.6%.
Credit Ratings. The credit rating agencies periodically review our ratings, taking into account factors such as our capital structure and earnings profile. The following table includes our and NIPSCO's credit ratings and ratings outlook as of June 30, 2026.
A credit rating is not a recommendation to buy, sell, or hold securities, and may be subject to revision or withdrawal at any time by the assigning rating organization.
| S&P | Moody's | Fitch | ||||
| Rating | Outlook | Rating | Outlook | Rating | Outlook | |
| NiSource | BBB+ | Stable | Baa2 | Stable | BBB | Stable |
|---|---|---|---|---|---|---|
| NIPSCO | BBB+ | Stable | Baa1 | Stable | BBB | Stable |
| Commercial Paper | A-2 | Stable | P-2 | Stable | F2 | Stable |
Certain of our subsidiaries have agreements that contain ''ratings triggers'' that require increased collateral if our credit rating or the credit ratings of certain of our subsidiaries are below investment grade. These agreements are primarily for insurance purposes and for the physical purchase or sale of power. As of June 30, 2026, the collateral requirement of approximately $153.9 million would be required in the event of a downgrade below investment grade. In addition to agreements with ratings triggers, there are other agreements that contain ''adequate assurance'' or ''material adverse change'' provisions that could necessitate additional credit support such as letters of credit and cash collateral to transact business.
Equity. Our authorized capital stock consists of 770,000,000 shares, $0.01 par value, 750,000,000 are common stock and 20,000,000 are preferred stock. As of June 30, 2026, 479,498,053 shares of common stock were outstanding and no shares of preferred stock were outstanding.
Contractual Obligations. A summary of contractual obligations is included in the Company's Annual Report on Form 10-K for the year ended December 31, 2025. Since December 31, 2025, NIPSCO and GenCo have executed several capacity agreements and other agreements to support data center contracts. In addition, GenCo has exercised an option and intends to convert its ESA relating to the Tipton BESS Project to a BTA. Except for these items and our May 2026 debt issuances, there were no additional material changes from year-end during the six months ended June 30, 2026. Refer to Note 8, "Long-Term Debt," and Note 15, "Other Commitments and Contingencies," in the Notes to the Condensed Consolidated Financial Statements (unaudited) for additional information regarding the EPC Contracts and equipment supply contracts.
Guarantees, Indemnities and Other Off Balance Sheet Arrangements. We and certain of our subsidiaries enter into various agreements providing financial or performance assurance to third parties on behalf of certain subsidiaries as a part of normal business. Such agreements include guarantees and stand-by letters of credit. Refer to Note 15, "Other Commitments and Contingencies," in the Notes to the Condensed Consolidated Financial Statements (unaudited) for additional information about such arrangements.