Skip to main content

Goldgroup Mining Inc.

For the period ended Sep 11, 2026. Filed Sep 11, 2026.

View on SEC.gov

About this filing

What a company based outside the US has published at home or sent to its shareholders. It is how many foreign companies share results and news between annual reports.

Sep 11, 2026 · Filed Sep 11, 2026

Use the contents to explore the available documents and sections.

GORO$3.15+0.3%Stored close · as of Nov 6, 2026
See the whole filing, with its images and exhibits

EX-99.2 · EXISTING PROCESSING INFRASTRUCTURE

EXISTING PROCESSING INFRASTRUCTURE

A significant advantage of Don David is its established processing infrastructure.

The El Aguila mill has two processing circuits:

●A differential flotation circuit designed primarily to process sulphide ore from the Arista operation; and
●An agitated-leach circuit designed to process oxide material, including material from Mirador.

The flotation circuit has a nominal capacity of approximately 1,800 tonnes per day, while the agitated-leach circuit has a nominal capacity of approximately 300 tonnes per day. The flotation circuit produces separate copper, lead and zinc concentrates containing gold and silver.

This existing infrastructure provides an important foundation for future growth and means that exploration success has the potential to be developed within an established operating environment rather than requiring an entirely new greenfield processing facility.