PERPETUA RESOURCES CORP.

For the period ended Jun 30, 2026. Filed Aug 14, 2026.

View on SEC.gov

About this filing

A company's report for each of its first three quarters. The financial statements are not audited. It shows how the business has moved since the last annual report, and what management says changed.

Jun 30, 2026 · Filed Aug 14, 2026

PPTA$19.53+16.6%Stored close · as of Nov 6, 2026

What changed in Management’s Discussion and Analysis?

Read the current filing

Previous report: 10-Q

Period ended 2026-03-31; filed 2026-05-11.

0001104659-26-058253

Item 2. Management’s Discussion and Analysis of Financial Condition and Results of Operations

Current report: 10-Q

Period ended 2026-06-30; filed 2026-08-14.

0001104659-26-097134

Item 2. Management’s Discussion and Analysis of Financial Condition and Results of Operations

The baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.

Compared 80 previous paragraphs and 91 current paragraphs.

44 unchanged; 32 reworded; 12 added; 3 removed; 1 previous and 3 current paragraphs rearranged.

Tables are not compared: 30 previous and 24 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.

A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.

Added paragraphs (12)

Current report

On August 6, 2026, the Company reported new high-grade gold and antimony discoveries and a new gold-tungsten zone at the Stibnite Mining District and provided an update on its 2026 exploration program in Valley County, Idaho. The Company’s 2026 drilling program contemplates a minimum of 10,000-meters of core drilling utilizing four drill rigs and may be expanded if warranted based on the results. Approximately 5,800 meters of the 2026 core drilling program have been completed to date and are being prepared for assay. The drill plan includes testing targets in the Yellow Pine and Hangar Flats deposits along strike and at depth to support potential pit extensions, upgrading inferred resources to measured and indicated categories within existing approved footprints, and testing high-grade targets near existing pits and planned milling infrastructure. Any future development outside the scope of the currently approved mine plan would require additional environmental review and permitting. Recent drilling between the permitted Yellow Pine and West End pits has identified multiple new high-grade gold intervals and a new gold-tungsten discovery, supporting tungsten, alongside historic exploration results and past tungsten production in the Stibnite Mining District, as an additional exploration focus and potential second critical mineral alongside antimony at the Stibnite site.

Current report

During the first half of 2026, the Company identified U.S. government-sponsored initiatives focused on tungsten and submitted grant funding proposals to support tungsten drilling, sampling, metallurgical analysis, and resource evaluation. There can be no assurance the Company will obtain such funding or identify recoverable quantities of tungsten will be identified. Any tungsten development would require separate environmental review and permitting outside the scope of the currently permitted Project.

Current report

Appeals for the Ninth Circuit and also requested an emergency stay of the District Court’s order pending the appeal. The Ninth Circuit on June 17, 2026 issued an order denying the plaintiffs’ request for a stay. Under the Ninth Circuit’s order, all briefs on the appeal are required to be filed by all parties by an outside date of August 20, 2026. While the appeal proceedings progressed, on June 24, 2026, the District Court heard oral argument on cross-motions for summary judgment on the merits of all the plaintiffs’ claims. All briefing relating to those motions is now complete, and the District Court is considering the summary judgment motions. No deadline for a ruling by the District Court’s on these motions on the merits has been set.

Current report

As part of the proceedings on the plaintiffs’ preliminary injunction motion in the Federal Environmental Case, the Company advised the plaintiffs and the U.S. District Court hearing the motion that additional critical path construction activities beyond the stipulated early works activities would commence in phases as of May 30, 2026. After the District Court denied the plaintiffs’ motion for preliminary injunction on May 29, 2026 the Company initiated the critical path construction activities in accordance with its submittals to the Court, and is continuing those activities along with the early works activities identified in the stipulations as described above.

Current report

Net loss for the six months ended June 30, 2026 was $146.2 million compared with a net loss of $14.2 million for the six months ended June 30, 2025. This $132.0 million increase compared to the prior year period was primarily attributable to a $133.0 million increase in exploration and pre-development expense and a $8.9 million decrease in grant income, partially offset by a $13.4 million increase in interest income.

Current report

On May 21, 2026, the board of U.S. EXIM unanimously approved a $2.9 billion senior secured long-term loan (“U.S. EXIM Loan”) under the Make More in America Initiative (“MMIA”) to support the development of the Company’s Stibnite Gold Project. U.S. EXIM’s approval came after extensive technical, financial, environmental and social due diligence and a 25-day notice period to Congress. The U.S. EXIM Loan will be available upon completion of definitive documentation and satisfaction of customary conditions precedent, which is expected to occur in the second half of 2026. The U.S. EXIM Loan is to be structured as a 13-year senior secured credit facility of $2.9 billion, consisting of an upfront facility of $2.4 billion with the remainder to cover capitalized interest during construction and U.S. EXIM’s exposure fee. Interest on the U.S. EXIM Loan is to be set at the applicable long-dated U.S. Treasury

Current report

bond rate plus 100 basis points and will be fixed at the time of the first drawdown. Scheduled repayments are anticipated to commence in 2030. There can be no assurance the terms or amount of such loan will be the same as those approved by the board of U.S. EXIM or that the proposed financing plan will be sufficient for us to construct the Project. Perpetua continues to work with U.S. EXIM to advance through completion of U.S. EXIM’s due diligence and documentation processes. The final amount and timing of such funding from U.S. EXIM, if any, is uncertain and subject to conditions outside the Company’s control.

Current report

The Company recently applied for additional grant funding to undertake drilling, sampling, metallurgical analysis, and resource evaluation with respect to tungsten at the Project. There is no assurance that the application will be successful and, if successful, whether any funding awarded will be sufficient to conduct the proposed exploration and evaluation activities or that such exploration and evaluation will produce positive results. Any tungsten development project would require separate environmental review and permitting from the currently approved mine plan for the Project.

Current report

On July 2, 2026 and August 5, 2026, the Company purchased various put option contracts from major national banks chartered under U.S. federal law and paid total premiums of $28.9 million for the right, but not an obligation, to sell a total of up to 158,016 ounces of gold during 2031 at an established put strike price of $3,000 per ounce. The put contracts were purchased to mitigate the Company’s exposure to fluctuations in metal prices.
Removed paragraphs (3)

Previous report

The U.S. District Court on October 2, 2025 issued a general order staying all civil cases listed in the order due to the partial shutdown of the federal government over appropriations for the government. The list included Federal Environmental Case and Federal NPT Case. This stay did not affect the validity of the USFS ROD or any of the other approvals challenged in either of these lawsuits in

Previous report

connection with the Stibnite Gold Project, and all such approvals remain in effect. After the partial federal government shutdown ended, the District Court lifted the stay and new scheduling orders were entered in both of these lawsuits challenging the ROD and other approvals of the Project issued by federal agencies. The scheduling order in the Federal Environmental Case required all procedural and dispositive motions to be filed before the end of January 2026. As of January 20, 2026, all briefs had been submitted. The scheduling order in the Federal NPT Casee required to be filed before the end of June 2026. These two lawsuits remain pending.

Previous report

In July 2025, the same petitioners filed a petition for judicial review in Idaho state court challenging the decisions of the IDEQ to issue the PTC and of the IBEQ in upholding the permit. IDEQ and IBEQ thereafter moved to dismiss the complaint on procedural grounds, and the court denied that motion and allowed the petitioners to amend their petition. The petitioners’ amended petition, which names the Company as well as IDEQ and the Board as defendants was served on the Company on or about September 23, 2025. The court subsequently entered an order dismissing the Board as a party and requiring all briefs of the parties to be filed by an outside date of January 16, 2026. All briefs were filed by all parties as of that date. The court has not ruled on the parties’ pending dispositive motions.
Reworded paragraphs (32)

Previous wording

You should read the following discussion and analysis of our financial condition and results of operations for the three months endedMarch 31, 2026 and 2025 with our unaudited condensed consolidated financial statements and related notes and other financial information appearing in this Quarterly Report. Some of the information contained in this discussion and analysis or set forth elsewhere in this Quarterly Report, including information with respect to our plans and strategy for our business, operations, and product candidates, includes forward-looking statements that involve risks and uncertainties. You should review the sections of this Quarterly Report captioned “Risk Factors” and “Cautionary Note Regarding Forward-Looking Statements” for a discussion of important factors that could cause our actual results to differ materially from the results described in or implied by the forward-looking statements contained in the following discussion and analysis.

Current wording

You should read the following discussion and analysis of our financial condition and results of operations for the three and six months ended June30, 2026 and 2025 with our unaudited condensed consolidated financial statements and related notes and other financial information appearing in this Quarterly Report. Some of the information contained in this discussion and analysis or set forth elsewhere in this Quarterly Report, including information with respect to our plans and strategy for our business and operations, includes forward-looking statements that involve risks and uncertainties. You should review the sections of this Quarterly Report captioned “Risk Factors” and “Cautionary Note Regarding Forward-Looking Statements” for a discussion of important factors that could cause our actual results to differ materially from the results described in or implied by the forward-looking statements contained in the following discussion and analysis.

Previous wording

Perpetua Resources Corp. (formerly Midas Gold Corp.) was incorporated on February 22, 2011 under the Business Corporations Act (British Columbia). The Corporation was organized to hold shares in wholly owned subsidiaries that locate, acquire, develop and restore mineral properties located principally in the Stibnite – Yellow Pine mining district in Valley County, Idaho, USA. The Corporation’s principal asset is 100% ownership in subsidiaries that control the Stibnite Gold Project. The Corporation currently operates in one segment: mineral exploration and development in the United States. The registered and records office of Perpetua Resources is located at Suite 2501-550 Burrard St, Vancouver, BC, V6C 2B5, Canada and the corporate head office is located at Suite 201-405 S 8th St, Boise, ID 83702, USA.

Current wording

Perpetua Resources Corp. (formerly Midas Gold Corp.) (the “Corporation”) was incorporated on February 22, 2011 under the Business Corporations Act (British Columbia). The Corporation was organized to hold shares in wholly owned subsidiaries that locate, acquire, develop and restore mineral properties located principally in the Stibnite – Yellow Pine mining district in Valley County, Idaho, USA (the “Stibnite Mining District”). The Corporation’s principal asset is 100% ownership in subsidiaries that control the Stibnite Gold Project. The Corporation currently operates in one segment: mineral exploration and development in the United States. The registered and records office of Perpetua Resources is located at Suite 2501-550 Burrard St, Vancouver, BC, V6C 2B5, Canada and the corporate head office is located at Suite 200-702 W Idaho St, Boise, ID 83702, USA.

Previous wording

The Company has continued to execute its comprehensive plan to finance construction of the Project since it was announced in June 2025. On March 30, 2026, the board of U.S. EXIM initiated the last formal step before a vote for final approval of an approximately $2.7 billion senior secured loan for the construction and development of the Project by unanimously agreeing to publish a notification to Congress with respect to the proposed loan. The 25-day notice period expired on April 24, 2026. The loan, if approved, is expected to be comprised of a direct loan of approximately $2.2 billion for construction of the Project, financial assurance and certain discretionary corporation and exploration costs, and the remainder representing capitalized interest and fees. If approved by the board of U.S. EXIM in the amount indicated, the Company would have sufficient capital, together with $669.5 million of cash on hand as of March 31, 2026, to finance the estimated direct capital costs of $2,576 million to construct the Project, (based on the capital expenditures estimate as of December 31, 2025 in the TRS), as well as financial assurance and discretionary corporation and exploration costs. This action by the board of U.S. EXIM does not represent a financing commitment from U.S. EXIM. A final funding commitment, if any, is conditional upon the satisfaction of certain conditions, including final approval by the U.S. EXIM board and execution of definition loan documentation. The Company anticipates a final vote on the loan by the board of U.S. EXIM in the second quarter of 2026. The board of U.S. EXIM has included the Company’s loan on the agenda for the May 21, 2026, meeting of the board of U.S. EXIM. The agenda is subject to change by the board of U.S. EXIM at any time, and there can be no assurance that the board will vote to approve the loan at the May 21 meeting, at a different meeting, or at all. Funding under the loan (if approved) would be subject to the negotiation and execution of definitive loan documentation, satisfaction of conditions precedent and other customary closing requirements. There can be no assurance that definitive loan documentation will be executed on acceptable terms, or at all, or that the conditions to closing or funding will be satisfied in a timely manner, or at all, or that the final terms of the proposed financing will be consistent or that the amount will be sufficient for us to construct the Project. Perpetua continues to work with U.S. EXIM to advance the remaining due diligence, documentation and closing process. The amount and timing of any funding from U.S. EXIM remains uncertain and subject to conditions outside the Company’s control. See “Item 1A. Risk Factors.”

Current wording

The Company continues to execute its comprehensive plan to finance construction of the Project since it was announced in June 2025.

Previous wording

On March 30, 2026, the board of U.S. EXIM initiated the last formal step before a vote for final approval of an approximately $2.7 billion senior secured loan for the construction and development of the Project by unanimously agreeing to publish a notification to Congress with respect to the proposed loan. The 25-day notice period expired on April 24, 2026. The loan, if approved, is expected to be comprised of a direct loan of approximately $2.2 billion for construction of the Project, financial assurance and certain discretionary corporation and exploration costs, and the remainder representing capitalized interest and fees. If approved by the board of U.S. EXIM in the amount indicated, the Company would have sufficient capital, together with $669.5 million of cash on hand as of March 31, 2026, to finance the estimated direct capital costs of $2,576 million to construct the Project, (based on the capital expenditures estimate as of December 31, 2025 in the TRS), as well as financial assurance and discretionary corporation and exploration costs. This action by the board of U.S. EXIM does not represent a financing commitment from U.S. EXIM. A final funding commitment, if any, is conditional upon the satisfaction of certain conditions, including final approval by the U.S. EXIM board and execution of definition loan documentation. The Company anticipates a final vote on the loan by the board of U.S. EXIM in the second quarter of 2026. The board of U.S. EXIM has included the Company’s loan on the agenda for the May 21, 2026, meeting of the board of U.S. EXIM. The agenda is subject to change by the board of U.S. EXIM at any time, and there can be no assurance that the board will vote to approve the loan at the May 21 meeting, at a different meeting, or at all. Funding under the loan (if approved) would be subject to the negotiation and execution of definitive loan documentation, satisfaction of conditions precedent and other customary closing requirements. There can be no assurance that definitive loan documentation will be executed on acceptable terms, or at all, or that the conditions to closing or funding will be satisfied in a timely manner, or at all, or that the final terms of the proposed financing will be consistent or that the amount will be sufficient for us to construct the Project. Perpetua continues to work with U.S. EXIM to advance the remaining due diligence, documentation and closing process. The amount and timing of any funding from U.S. EXIM remains uncertain and subject to conditions outside the Company’s control.

Current wording

On May 21, 2026, the board of U.S. EXIM unanimously approved a $2.9 billion senior secured long-term loan (“U.S. EXIM Loan”) under the Make More in America Initiative (“MMIA”) to support the development of the Company’s Stibnite Gold Project. U.S. EXIM’s approval came after extensive technical, financial, environmental and social due diligence and a 25-day notice period to Congress. The U.S. EXIM Loan will be available upon completion of definitive documentation and satisfaction of customary conditions precedent, which is expected to occur in the second half of 2026. The U.S. EXIM Loan is to be structured as a 13-year senior secured credit facility of $2.9 billion, consisting of an upfront facility of $2.4 billion with the remainder to cover capitalized interest during construction and U.S. EXIM’s exposure fee. Interest on the U.S. EXIM Loan is to be set at the applicable long-dated U.S. Treasury bond rate plus 100 basis points and will be fixed at the time of the first drawdown. Scheduled repayments are anticipated to commence in 2030. If the U.S. EXIM Loan is finalized in the amount indicated, the Company would have sufficient capital, together with $574.2 million of unrestricted cash on hand as of June 30, 2026, to finance the estimated direct capital costs of $2,576 million to construct the Project (based on the capital expenditures estimate as of December 31, 2025 in the TRS), as well as financial assurance and certain discretionary corporation and exploration costs. There can be no assurance the terms or amount of such loan will be the same as those approved by the board of U.S. EXIM or that the proposed financing plan will be sufficient for us to construct the Project. Perpetua continues to work with U.S. EXIM to advance through completion of U.S. EXIM’s due diligence and documentation processes. The final amount and timing of such funding from U.S. EXIM, if any, is uncertain and subject to conditions outside the Company’s control. See “Item 1A. Risk Factors.”

Previous wording

The capital costs presented in the initial capital estimate in the TRS do not include financial assurance, debt service, cost overrun accounts and certain discretionary corporate and exploration costs. As a condition to the closing of the U.S. EXIM loan, the Company expects that it will be required to put in place one or more secured accounts or facilities to fund cost overruns during the construction phase of the Project. The Company is exploring various options for such facilities, which may include cash on hand, subordinated debt, letters of credit or other financial instruments or may require the Company to raise additional capital through debt or equity offerings, or enter into strategic or commercial agreements with third parties.

Current wording

The capital costs presented in the initial capital estimate in the TRS do not include financial assurance, debt service, cost overrun accounts and certain discretionary corporate and exploration costs. As a condition to the closing of the U.S. EXIM loan, the Company expects that it will be required to put in place one or more secured accounts or facilities to fund potential cost overruns during the construction phase of the Project. The Company is exploring various options for such facilities, which may include cash on hand, subordinated debt, letters of credit or other financial instruments or may require the Company to raise additional capital through debt or equity offerings, or enter into strategic or commercial agreements with third parties.

Previous wording

After posting required construction phase financial assurance with the USFS, IDL and USACE and receiving confirmation from those agencies of approval of this construction phase financial assurance on September 20 and 21, 2025, the Company commenced early works construction on certain activities for the Project as authorized by the USFS, IDL and USACE. Early works construction activities are limited to those activities permitted under the authorizations issued by the USFS, IDL and USACE, the terms of the financial assurance agreements, and the voluntary stipulations entered into by PRII and the plaintiffs in the two pending cases in federal district court challenging the USFS ROD and other federal agency approvals referenced above, which stipulations are further described under “NEPA Permitting Activities” below. The Company intends to continue progressing these early works construction activities during the pendency of the recently filed preliminary injunction motion in the Federal Environmental Case described under “NEPA Permitting Activities” below.

Current wording

After posting required construction phase financial assurance with the USFS, IDL and USACE and receiving confirmation from those agencies of approval of this construction phase financial assurance on September 20 and 21, 2025, the Company in October 2025 commenced early works construction on certain activities for the Project as authorized by the USFS, IDL and USACE. Early works construction activities initially were limited to the voluntary stipulations entered into by PRII and the plaintiffs in the two pending cases in federal district court challenging the USFS ROD and other federal agency approvals referenced above, which stipulations are further described under “NEPA Permitting Activities” below. The Company continued progressing these early works construction activities during the pendency of the legal proceedings with respect to the preliminary injunction motion in the Federal Environmental Case described under “NEPA Permitting Activities” below. As part of those proceedings, the Company advised the plaintiffs and the U.S. District Court hearing the motion that additional critical path construction activities beyond the stipulated early works activities would commence in phases beginning on May 30, 2026. After the District Court denied the plaintiffs’ motion on May 29, 2026, the Company initiated these additional critical path construction activities in accordance with its submittals to the District Court, and is now continuing those activities along with the early works activities subject to the stipulations as described above.

Previous wording

The Company is currently focused on advancing the Project towards a final investment and construction decision for the Project in the second half of 2026.

Current wording

The Company is currently focused on advancing the Project towards a final investment and construction decision in the second half of 2026.

Previous wording

Perpetua subsequently posted the agreed upon joint construction phase financial assurance for the Project, and the USFS on October 20, 2025, issued notice that the requirements necessary to start construction had been satisfied, the Plan of Operations had been approved and signed by USFS, and the Project could enter construction subject to terms and conditions specified in the notice. IDL and USACE on October 21, 2025, also issued notices confirming that the requirements necessary to begin construction under their respective approvals for the Project, including posting the agreed upon joint financial assurance, had been met and that the Company could begin construction subject to the terms and conditions identified by those agencies.

Current wording

Perpetua subsequently posted the agreed upon joint construction phase financial assurance for the Project, and the USFS on October 20, 2025, issued notice that the requirements necessary to start construction had been satisfied, the Plan of Operations had been approved and signed by USFS, and the Project could enter construction subject to terms and conditions specified in the notice. IDL and

Previous wording

Following the USFS’ publication of the ROD and FEIS approving the Modified Mine Plan for the Project, a lawsuit was filed against the USFS, USDA and other federal agencies on February 18, 2025, in the United States District Court for the District of Idaho by a number of environmental advocacy groups, including Save the South Fork Salmon, the Idaho Conservation League and other non-governmental organizations, alleging violations of NEPA and other federal laws in the regulatory process (“Federal Environmental Case”). Among other remedies, the claimants seek to vacate the ROD issued by the USFS, the Final Biological Opinions issued by the U.S. Fish and Wildlife Service and the National Marine Fisheries Service on September 6, 2024, and October 7, 2024, respectively (together, the “Final Biological Opinions”) and other Project approvals and to enjoin any further implementation of the Project. PRII filed a motion to intervene in this lawsuit, which was granted by the District Court on April 2, 2025.

Current wording

Following the USFS’ publication of the ROD and FEIS approving the Modified Mine Plan for the Project, a lawsuit was filed against the USFS, USDA and other federal agencies on February 18, 2025, in the United States District Court for the District of Idaho by a number of environmental advocacy groups, including Save the South Fork Salmon, the Idaho Conservation League and other non-governmental organizations, alleging violations of NEPA and other federal laws in the regulatory process (“Federal Environmental Case”). Among other remedies, the claimants seek to vacate the ROD issued by the USFS, the Final Biological Opinions issued by the U.S. Fish and Wildlife Service and the National Marine Fisheries Service on September 6, 2024, and October 7, 2024, respectively (together, the “Final Biological Opinions”) and other Project approvals and to enjoin any further implementation of the Project. PRII filed a motion to intervene in this lawsuit, which was granted by the District Court on April 2, 2025. The scheduling order for the Federal Environmental Case required all dispositive motions and briefs to be submitted by the end of January 2026. All pleadings were timely filed and the matter remains pending as further described below in this section.

Previous wording

On August 29, 2025, the Nez Perce Tribe filed a lawsuit against the USFS, United States Department of Agriculture and other federal agencies in the U.S. District Court for the District of Idaho challenging the USFS ROD and other approvals by the USFS and other federal agencies in connection with the Stibnite Gold Project and alleging violations of NEPA and other federal statutes, regulations, and requirements in the regulatory review and approval process for the Project. Among other remedies, the Tribe seeks to vacate the USFS ROD and other regulatory approvals and to enjoin any further implementation of the Project (“Federal NPT Case”). PRII filed a motion to intervene in this lawsuit, which was granted by the District Court on September 4, 2025.

Current wording

On August 29, 2025, the Nez Perce Tribe filed a lawsuit against the USFS, United States Department of Agriculture and other federal agencies in the U.S. District Court for the District of Idaho challenging the USFS ROD and other approvals by the USFS and other federal agencies in connection with the Stibnite Gold Project and alleging violations of NEPA and other federal statutes, regulations, and requirements in the regulatory review and approval process for the Project. Among other remedies, the Tribe seeks to vacate the USFS ROD and other regulatory approvals and to enjoin any further implementation of the Project (“Federal NPT Case”). PRII filed a motion to intervene in this lawsuit, which was granted by the District Court on September 4, 2025. The scheduling order in the Federal NPT Case required all dispositive motions and briefs to be filed by all parties before the end of June 2026. All pleadings were timely filed and the matter remains pending.

Previous wording

As to the merits of the Federal Environmental Case and the Federal NPT Case, the Company believes the USFS ROD and other federal regulatory processes in these lawsuits, were conducted thoroughly and completely by the relevant federal regulatory agencies. However, the District Court has not yet ruled on these lawsuits and the Company cannot predict the outcome or timing of the Court’s ultimate decision on the merits, or in any interim proceedings, in the Federal Environmental Case or the Federal NPT Case. There can be no assurance that the Project approvals challenged in those two cases will be upheld upon judicial review or that the Company will be successful in defending against the challenges raised in the two lawsuits, including the pending motion for a preliminary injunction in the Federal Environmental Case.

Current wording

These two federal lawsuits challenging the USFS ROD and other approvals of the Project remain pending. As to the merits of the Federal Environmental Case and the Federal NPT Case, the Company believes the USFS ROD and other federal regulatory processes in these lawsuits, were conducted thoroughly and completely by the relevant federal regulatory agencies. However, the District Court has not yet ruled on these lawsuits and the Company cannot predict the outcome or timing of the Court’s ultimate decision on the merits, or in any interim proceedings, in the Federal Environmental Case or the Federal NPT Case. There can be no assurance that the Project approvals challenged in those two cases will be upheld upon judicial review or that the Company will be successful in defending against the challenges raised in the two lawsuits, including the preliminary injunction proceedings further described below in the Federal Environmental Case.

Previous wording

Before early works construction commenced as described in the “Engineering, Contracting and Construction Activities” section above, the Company entered into voluntary stipulations with the plaintiffs in the two above-mentioned federal lawsuits. Those stipulations provided for certain restrictions on the early works construction activities for the Project until February 1, 2026, after which the stipulations would terminate on 30-days’ notice by the Company to the plaintiffs. In exchange for the Company’s commitments to these restrictions, the plaintiffs in each case agreed not to seek a preliminary injunction against development of the Project in conformance with the stipulations during the restriction period that will end when the stipulations terminate. These stipulations were filed with the U.S. District Court for the District of Idaho in the two federal lawsuits. On March 16, 2026, the Company provided notice to the plaintiffs that the above-referenced stipulation restriction period will end 30 days from such notice. Accordingly, as of April 16, 2026, the construction restrictions provided in these stipulations in the two federal lawsuits no longer were in effect.

Current wording

Before early works construction commenced as described in the “Engineering, Contracting and Construction Activities” section above, the Company entered into voluntary stipulations with the plaintiffs in the two above-mentioned federal lawsuits. Those stipulations provided for certain restrictions on the early works construction activities for the Project until February 1, 2026, after which the stipulations would terminate on 30-days’ notice by the Company to the plaintiffs. In exchange for the Company’s commitments to these restrictions, the plaintiffs in each case agreed not to seek a preliminary injunction against development of the Project in conformance with the stipulations during the restriction period. These stipulations were filed with the U.S. District Court for the District of Idaho in the two federal lawsuits. On March 16, 2026, the Company provided notice to the plaintiffs that the above-referenced stipulation restriction period would end 30 days from such notice.

Previous wording

Following the Company’s notice on March 16, 2026 relating to expiration of the above-referenced stipulations, on May 8, 2026 the plaintiffs in the Federal Environmental Case filed a motion for a preliminary injunction seeking to delay certain planned construction activities for the Project. The plaintiffs’ motion expressly excluded early works construction activities that were contemplated under the previously agreed stipulations that have now expired as described above. These early works activities remain ongoing. A decision from the Court on the motion is expected swiftly as plaintiffs in their motion requested a decision by May 30, 2026, and the Court has set a hearing on the motion for May 28, 2026. The Company believes that this motion and the underlying lawsuit are without merit and intends to vigorously oppose the motion. The Company, however, cannot predict the outcome of the Court’s decision. If the requested relief is granted, it could delay or restrict further implementation of the Project.

Current wording

Following the Company’s notice on March 16, 2026 relating to expiration of the above-referenced stipulation period, on May 8, 2026 the plaintiffs in the Federal Environmental Case filed a motion for a preliminary injunction seeking to delay certain planned construction activities for the Project. The plaintiffs’ motion expressly excluded early works construction activities that were contemplated under the previously agreed stipulations. The plaintiffs, however, sought to delay certain critical path construction activities (beyond the early works activities subject to the stipulations) that the Company had indicated would commence on May 30, 2026. On May 29, 2026, the District Court issued an order denying the plaintiffs’ motion for a preliminary injunction. The plaintiffs subsequently filed a notice of appeal of the District Court’s order denying the preliminary injunction motion with the U.S. Court of

Previous wording

Previously submitted applications for certain regulatory approvals are continuing through the administrative review process. These include the Company’s application to IDEQ for an IPDES sanitary wastewater discharge permit and the IDEQ’s modification of the Clean Water Act Section 401 Certification described above. The Company anticipates an IDEQ decision on the IPDES sanitary permit in Q2 2026. The status of IDEQ’s process on the modification of the Section 401 Certification is described above in this section. Applications to IDEQ for approval of certain drinking water systems also are pending. The IDEQ approvals are anticipated in 2027 after Project construction has advanced to the stage where the final designs for the systems will be prepared.

Current wording

Previously submitted applications for certain regulatory approvals are continuing through the applicable administrative review processes. These include the Company’s application to IDEQ for an IPDES sanitary wastewater discharge permit and the IDEQ’s modification of the Clean Water Act Section 401 Certification described above. Applications to IDEQ for approval of certain drinking water systems also are pending. The IDEQ approvals of these systems are anticipated in 2027 after Project construction has advanced to the stage where the final designs for the systems will be prepared.

Previous wording

Three months ended March 31, 2026 compared to three months ended March 31, 2025

Current wording

Three and six months ended June 30, 2026 compared to three and six months ended June 30, 2025

Previous wording

Net loss for the three months ended March 31, 2026 was $48.6 million compared with a net loss of $8.2 million for the three months ended March 31, 2025. The increase compared to the prior year period was primarily attributable to a $40.0 million increase in

Current wording

Net loss for the three months ended June 30, 2026 was $97.5 million compared with a net loss of $6.0 million for the three months ended June 30, 2025. The increase compared to the prior year period was primarily attributable to a $93.0 million increase in exploration and pre-development expense and a $3.5 million decrease in grant income, partially offset by a $6.8 million increase in interest income.

Previous wording

This expense relates to all exploration and evaluation expenditures related to the Stibnite Gold Project, including labor, drilling, field operations, engineering, permitting, environmental, legal and sustainability costs. Exploration and pre-development expenses during the three months ended March 31, 2026 were $53.1 million, which was $40.0 million higher than the 2025 comparative period, primarily due to an increase in spend following financings, financial assurance posting and commencement of early works. See additional details in the table below:

Current wording

This expense relates to all exploration and evaluation expenditures related to the Project, including labor, drilling, field operations, engineering, permitting, environmental, legal and sustainability costs. Exploration and pre-development expenses during the three and six months ended June 30, 2026 were $103.9 million and $157.0 million, respectively, which was higher than both 2025 comparative periods, primarily due to an increase in spend following financings, financial assurance posting and commencement of early works construction. See additional details in the table below:

Previous wording

These expenses include corporate salaries and benefits, director fees, professional fees, shareholder and regulatory, and other operating expenses. General and administrative expensesfor the three months ended March 31, 2026 were $3.4 million, which was $1.5 million more than the 2025 comparative period, primarily due to higher short term incentive payments approved by the Board of Directors to recognize milestones achieved and increased legal review and filing fees for the TRS, S-3 and S-8.

Current wording

These expenses include corporate salaries and benefits, director fees, professional fees, shareholder and regulatory, and other operating expenses. General and administrative expenses for the three and six months ended June 30, 2026 were $2.5 million and $5.8 million, respectively, which was more than both 2025 comparative periods, primarily due to higher short term incentive payments

Previous wording

This income is from funding grants awarded to the Company from the DOW to study the domestic production of military-grade antimony trisulfide and to complete environmental and engineering studies necessary to obtain a FEIS, a ROD and other ancillary permits to sustain the domestic production of antimony trisulfide capability for defense energetic materials. Grant income for the three months ended March 31, 2026 was $1.0 million, which was $5.4 million less than the comparable period in 2025 due to the DPA funding being exhausted in May 2025.

Current wording

This income is from funding grants awarded to the Company from the DOW to study the domestic production of military-grade antimony trisulfide and to complete environmental and engineering studies necessary to obtain a FEIS, a ROD and other ancillary permits to sustain the domestic production of antimony trisulfide capability for defense energetic materials. Grant income for the three and six months ended June 30, 2026 was $1.4 million and $2.4 million, respectively, which was lower than both 2025 comparable periods due to the DPA funding being exhausted in May 2025.

Previous wording

This income results from interest received on the Company’s cash balances. Interest income for the three months ended March 31, 2026 was $6.9 million, which was higher than the comparable period in 2025 due to higher average cash balances.

Current wording

This income results from interest received on the Company’s cash balances. Interest income for the three and six months ended June 30, 2026 was $7.6 million and $14.5 million, respectively, which was higher than both 2025 comparable periods due to higher average cash balances.

Previous wording

Capital resources of Perpetua Resources consist primarily of cash and liquid short-term investments. As of March 31, 2026, Perpetua Resources had $669.5 million in cash and cash equivalents, $59.6 million in restricted cash equivalents, $3.0 million in receivables, $4.1 million in prepaid expenses, $22.0 million in current deposits, and $32.4 million in trade and other payables. See additional discussion in “Capital Resources” section below.

Current wording

Capital resources of Perpetua Resources consist primarily of cash and liquid short-term investments. As of June 30, 2026, Perpetua Resources had $574.2 million in cash and cash equivalents, $60.9 million in restricted cash equivalents, $3.3 million in receivables, $5.0 million in prepaid expenses, $14.9 million in current deposits, and $46.7 million in trade and other payables. See additional discussion in “Capital Resources” section below.

Previous wording

The Company’s short-term liquidity needs include costs related to ongoing permitting, financial assurance, engineering, project financing, general corporate and administrative costs as the Company prepares for a final investment and construction decision for the Project in the second half of 2026, as well as certain early works construction activities and down payments on long-lead items approved for early investment. Short-term liquidity needs also include financial obligations under the various contracts entered into for early works construction, including the IPCo contract, the ATCO contract and other vendor obligations described in the “Commitments” section below. The Company expects to finance these costs using cash on hand and, when available, funds available from the U.S. EXIM loan.

Current wording

The Company’s short-term liquidity needs include costs related to ongoing permitting, financial assurance, engineering, project financing, general corporate and administrative costs as the Company prepares for a final investment and construction decision for the Project in the second half of 2026, as well as certain early works and critical path construction activities and down payments on long-lead items approved for early investment. Short-term liquidity needs also include financial obligations under the various contracts entered into for construction work described above as early works and critical path construction activities, including the IPCo contracts, the ATCO contract and other vendor obligations described in the “Commitments” section below. The Company expects to finance these costs using cash on hand and, when available, funds available from the U.S. EXIM loan.

Previous wording

The Company has been awarded government grants by the DOW. Since December 2022, the Company has received $59.2 million in funding under the TIA under Title III of the DPA. The TIA expired on June 16, 2025, and no additional funds are available under the program. The Company also has an ongoing contract under an OTIA with the DOW through DOTC for up to $22.4 million. See Note 8 to the Condensed Interim Consolidated Financial Statements for additional information regarding these grants. The Company continues to evaluate other U.S. government funding opportunities, including programs available through the DOW.

Current wording

The Company has been awarded government grants by the DOW. Since December 2022, the Company has received $59.2 million in funding under the TIA under Title III of the DPA. The TIA expired on June 16, 2025, and no additional funds are available under the program. The Company also has an ongoing contract under an OTIA with the DOW through DOTC for up to $27.1 million. See Note 8 to the Condensed Interim Consolidated Financial Statements for additional information regarding these grants. The Company continues to evaluate other U.S. government funding opportunities, including programs available through the DOW.

Previous wording

See Note 9 – Commitments and Contingencies to the Consolidated Financial Statements contained in our Annual Report on Form 10-K for the year ended December 31, 2025, for additional details regarding the Company’s commitments. Expected commitment costs are included in the approved budget and capital costs discussed in the “Liquidity” section below.

Current wording

See Note 9 – Commitments and Contingencies to the Condensed Interim Consolidated Financial Statements above, for additional details regarding the Company’s commitments. Expected commitment costs are included in the approved budget and capital costs discussed in the “Liquidity” section below.

Previous wording

The Company is obligated to make option payments on mineral properties in order to maintain the option to purchase these properties. As of March 31, 2026, the option payments due on these properties during 2026 is $0.03 million. The agreements include options to extend.

Current wording

The Company is obligated to make option payments on mineral properties in order to maintain the option to purchase these properties. As of June 30, 2026, the option payments due on these properties during 2026 are $0.03 million. The agreements include options to extend.

Previous wording

In February 2026, the Board of Directors approved a budget for the first half of 2026 to continue the progress made during 2025 on permits, financing, and early works construction activities. This budget includes expenditures related to early works construction activities that commenced in the fall of 2025 following receipt of necessary permits and approvals. Our anticipated expenditures for the first half of 2026 are approximately $328 million which includes $224 million for detailed engineering, design work and down payments on long lead time equipment, $76 million for field operations and site early works, $4 million for exploration, $20 million for permit compliance, legal and other project costs, and $4 million for corporate costs. These costs are expected to be incurred prior to closing of the U.S. EXIM loan (if successful) and final investment and construction decision. Board approved costs are expected to be funded from cash on hand and are subject to change due to various factors such as cost over-runs, litigation, weather events, or other unbudgeted events. The Board expects to approve the full 2026 budget during the second half of 2026 in connection with completion of the project financing and final investment and construction decision in the second half of 2026. The Company believes it has sufficient cash on hand to cover expenses incurred and expected to be incurred until the final investment and construction decision and has flexibility to adjust planned activities through the next twelve months based on available funds if the project financing is delayed.

Current wording

In June 2026, the Board of Directors approved a budget for the third quarter of 2026 to continue the progress made to date on permits, financing, and early works and critical path construction activities. This budget includes expenditures related to early works construction activities that commenced in the fall of 2025 following receipt of necessary permits and approvals as well as additional critical path construction activities that started on May 30, 2026. Our anticipated expenditures for the third quarter of 2026 are approximately $177 million which includes $131 million for detailed engineering, design work and down payments on long lead time equipment, $27 million for field operations and initial construction works, $7 million for exploration, $11 million for permit compliance, legal and other project costs, and $1 million for corporate costs. These costs are expected to be incurred prior to closing of the U.S. EXIM loan (if successful) and final investment and construction decision. Board approved costs are expected to be funded from cash on hand and are subject to change due to various factors such as cost overruns, litigation, weather events, or other unbudgeted events. The Board expects to approve the remaining 2026 budget during the second half of 2026 in connection with completion of the project financing and final investment and construction decision. The Company believes it has sufficient cash on hand to cover expenses incurred and expected to be incurred until the final investment and construction decision and has flexibility to adjust planned activities through the next twelve months based on available funds if the project financing is delayed.

Previous wording

Our long-term liquidity requirements will require project financing to fund the capital costs to develop the Project, which was estimated to be approximately $2,576 million as of the fourth quarter of 2025 according to the TRS, and to fund reclamation financial assurance, debt service, exploration and other corporate costs. As such, our capital expenditures may increase significantly during the next 12 months to reflect the commencement of full construction and any such expenditures would be subject to the timing and nature of project financing. The Company expects to finance the majority of these capital costs through cash on hand and project financing from U.S. EXIM or other sources and would not commence full construction activities until such full project financing is in place.

Current wording

Our long-term liquidity requirements will require project financing to fund the capital costs to develop the Project, which was estimated to be approximately $2,576 million as of the fourth quarter of 2025 according to the TRS, and to fund reclamation financial assurance, debt service, exploration and other corporate costs. As such, our capital expenditures may increase significantly during the next 12 months to reflect the commencement of full construction and any such expenditures would be subject to the timing and nature of project financing. The Company expects to finance the majority of these capital costs through cash on hand and project financing from U.S. EXIM or other sources and does not intend to commence full construction activities until such full project financing is in place.

Previous wording

We believe our Project financing plans will be successful, although there can be no assurance that the Company will successfully complete all of its contemplated plans because these plans are not entirely within our control as of the date hereof. As such, Perpetua remains open to strategic funding opportunities that support Perpetua’s overall financing and development goals for the Project, which may include the issuance of additional equity, new debt, or project specific debt; government funding; offtake, royalty or streaming arrangements; and/or other financing or strategic opportunities. The future receipt of potential funding from these and/or other means cannot be considered certain at this time. In the event Project funding is not available in the amounts or at the times anticipated, the Company may defer certain activities to ensure available cash resources are sufficient to satisfy the Company anticipated expenses until such full project financing is in place.

Current wording

We believe our Project financing plans will be successful, although there can be no assurance that the Company will successfully complete all of its contemplated plans because these plans are not entirely within our control as of the date hereof. As such, Perpetua remains open to strategic funding opportunities that support Perpetua’s overall financing and development goals for the Project, which may include the issuance of additional equity, new debt, or project specific debt; government funding; offtake, royalty or streaming arrangements; and/or other financing or strategic opportunities. The future receipt of potential funding from these and/or other means cannot be considered certain at this time. In the event funding for the Project is not available in the amounts or at the times

Previous wording

We have determined our current cash balance is sufficient to satisfy the Company’s ongoing obligations and to continue early works construction, engineering, permitting and other ongoing operations for at least 12 months from the date these financial statements are issued.

Current wording

We have determined our current cash balance is sufficient to satisfy the Company’s ongoing obligations and to continue early works and critical path construction, engineering, permitting and other ongoing operations for at least 12 months from the date these financial statements are issued.

Previous wording

There have been no material changes to our critical accounting estimates subsequent to December 31, 2025. For a discussion of the Company’s critical accounting estimates for the fiscal year ended December 31, 2025, please see our Annual Report on Form 10-K for the year ended December 31, 2025.

Current wording

There have been no material changes to our critical accounting estimates subsequent to December 31, 2025. For a discussion of the Company’s critical accounting estimates for the fiscal year ended December 31, 2025, please see our 2025 Annual Report.
Rearranged current paragraphs (3)

Current report — wording carried from elsewhere

USACE on October 21, 2025, also issued notices confirming that the requirements necessary to begin construction under their respective approvals for the Project, including posting the agreed upon joint financial assurance, had been met and that the Company could begin construction subject to the terms and conditions identified by those agencies.

Current report — wording carried from elsewhere

approved by the Board of Directors to recognize milestones achieved and increased legal review and filing fees for the TRS, S-3 and S-8 in the first quarter of 2026 and legal review of the updated equity incentive plan and other corporate governance matters in the second quarter of 2026.

Current report — wording carried from elsewhere

anticipated, the Company may defer certain activities to ensure available cash resources are sufficient to satisfy the Company anticipated expenses until such full project financing is in place.
Rearranged previous paragraphs (1)

Previous report — wording carried elsewhere

exploration and pre-development expense and a $5.4 million decrease in grant income, partially offset by a $6.5 million increase in interest income.