Skip to main content

Versamet Royalties Corp

For the period ended Jun 30, 2026. Filed Aug 13, 2026.

View on SEC.gov

About this filing

What a company based outside the US has published at home or sent to its shareholders. It is how many foreign companies share results and news between annual reports.

Jun 30, 2026 · Filed Aug 13, 2026

Use the contents to explore the available documents and sections.

VMET$9.13+2.2%Stored close · as of Nov 6, 2026
See the whole filing, with its images and exhibits
Contents

EX-99.2 · Development assets

Development assets

Toega, Burkina Faso (2.7% NSR)

During Q2, construction of the mobile maintenance workshop, office and ancillary infrastructure continued to progress on schedule, with completion expected in Q3. Haul road construction has now been completed, and a preferred local contractor has been selected to undertake ore haulage to Sanbrado. Toega open pit mining activities continued during the quarter using West African’s owner mining equipment. Mining activities continued to focus on pre-production stripping of the stage 1 Toega open pit with some waste movement also undertaken within the stage 2 pit to utilize available free dig material while the explosives supply remains constrained. The stage 1 pit is currently behind schedule, and ore delivery to the Sanbrado mill is expected to be delayed. A 13,500 metre infill drilling program targeting the Toega underground resource is ongoing, with results expected to be reported in Q3.

For more information, please refer to Western African’s ASX announcement dated July 29, 2026.

Cuiú Cuiú, Brazil, 1.5% NSR

On August 13, 2026, Cabral Gold Inc. (“Cabral Gold”) provided an update on construction and commissioning activities at Cuiú Cuiú. Construction of the wet processing circuit is more than 90% complete. The ADR leach processing plant has arrived on site and electrical installation is over 90% complete with commissioning in progress. Cabral Gold received the operating license from the Para State environmental authority and the mining of gold-in-oxide ore and stacking on the first pad is in process. First gold production is now targeting September, an estimated six weeks ahead of schedule with ramp up to full production planned during Q4 2026.