Skip to main content

EVOLUTION PETROLEUM CORP

For the period ended May 11, 2026. Filed May 12, 2026.

View on SEC.gov

About this filing

A notice of a major event between regular reports, such as results, a deal or a change of executives. It is often the first formal record of the news.

May 11, 2026 · Filed May 12, 2026

Use the contents to explore the available documents and sections.

EPM$3.48+0.6%Stored close · as of Nov 6, 2026
See the whole filing, with its images and exhibits

EX-99.1 · Operations Update

Operations Update

The Company continued to expand its mineral and royalty position, completing two mineral acreage acquisitions in the Haynesville and Bossier Shales in Louisiana during fiscal Q3, following two similar acquisitions completed in fiscal Q2. The Company’s mineral acquisitions prioritize placing value on wells that are either currently producing or are expected to be producing within one year of purchase. We expect 23 wells to be brought online and meaningfully contribute to revenue and cash flow in the fiscal fourth quarter.

At SCOOP/STACK, quarterly production was impacted by 64 BOEPD due to the winter storm in January. Additionally, there are 7 gross wells in progress and 12 gross wells on production that we are still waiting for first production data and revenue. Production from mineral and royalty interests acquired in August 2025 continued to contribute to overall volumes during the quarter, leading to a material increase of 27% in production and 24% decrease in LOE per BOE during the current fiscal quarter compared to the prior-year quarter.

At Chaveroo, the January winter storm and gas interference on an ESP affected production by 30 net BOEPD for the quarter. Subsequent to quarter-end, we converted that well from ESP to a rod pump, and all but one of our 7 wells have now been converted to rod pumps. The Company expects to secure permits for its next drilling block, comprising six gross wells, before the end of the 4 th fiscal quarter.

At TexMex, oil production increased quarter over quarter due to a successful workover program at the end of the prior quarter. However, January winter storms not only impacted production but also caused power outages and surface equipment damage that required repairs. This led to higher expenses in the quarter. We expect TexMex to continue to improve substantially. Subsequent to quarter-end, we began a new workover program, which we expect will increase production by an additional 100 net BOEPD by the end of fiscal Q4.

At the Williston Basin, production was down 32 BOEPD, due to downtime caused by the January winter storm and delays in crude oil trucking. Operations were quickly restored, and the field runtimes remain strong.

At Barnett, quarterly production was heavily impacted by the winter storm, resulting in a decline of approximately 160 BOEPD. The impacts carried into February and were restored by March.

At Delhi, the January winter storm outages impacted production for 6 days during the quarter. The CO₂ recycle compressor, which was down for most of the prior quarter, remained down for 40 days during fiscal Q3, negatively affecting production. These issues were resolved during the quarter, and we expect to see the benefits of a return to normal run times and restoring full CO₂ recycle capacity moving forward.