Tartan Mine Project
The Tartan Mine Project is located in Flin Flon, Manitoba and was acquired as part of our Canadian Gold acquisition completed on January 5, 2026.
During Q1/26, a total of $1.0 million was incurred at the Tartan Mine Project to advance drilling, permitting, metallurgical testing to optimize both process plant designs and underground mine plans, and engineering studies.