Skip to main content

Nouveau Monde Graphite Inc.

For the period ended Dec 31, 2025. Filed Mar 26, 2026.

View on SEC.gov

About this filing

The yearly report of certain Canadian companies, filed under a joint US and Canadian system. It is the main yearly account these companies give US investors, largely as filed in Canada.

FY2025 · Filed Mar 26, 2026

Use the contents to explore the available documents and sections.

NMG$0.84+3.9%Stored close · as of Nov 6, 2026
See the whole filing, with its images and exhibits
Contents

EX-99.3 · Project Financing

Project Financing

The project financing process for the Phase-2 Matawinie Mine is nearing completion withdue diligence processes, credit and/or investment committee presentations, advancement of legal documentation, and finalization of adefinitive offtake agreement with the Government of Canada.

NMG has secured a senior secured project financing debt commitment letter with Export Development Canada (“EDC”) and Canada Infrastructure Bank (“CIB”). The facilities account for a majority of the project’s capital structure and offer competitive terms supportive of long-term project economics. Facilities will be available upon completion of the definitive documentation, final legal, insurance and regulatory due diligence, and satisfaction of customary conditions precedents.

»Total senior project-level debt facilities of US$335 million, including:
-US$290 million senior secured term loan facility
-US$45 million senior secured cost overrun debt facility
»Competitive interest rate and repayment structure to support commercial launch
»First-ranking security over the Matawinie Mine project and all material assets
​​
Management Discussion and Analysis25
»NMG credentials aligned with international best practices for environmental, social and governance standards, including Equator Principles and IFC Performance Standards

The senior debt facilities will be used to fund eligible project construction costs, working capital requirements prior to completion, and transaction costs associated with the financing. The cost overrun facility provides additional protection against construction cost overruns, subject to defined conditions.

In light of this, NMG is actively progressing its negotiations with targeted strategic investors for the equity component of the financing with a view to completing the Matawinie financing structure in a timely manner.

The Company is advancing a sequenced FID for the Phase-2 First-Stage Bécancour Battery Material Plant. Upon the completion of the AACE Class 3 estimate, NMG intends to refine and crystallize the financing structure with contemplated lenders and investors that have already been identified and confirmed their interest. The Company is targeting a FID in H2-2026 for this project.

ContentsView on SEC.gov

The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.