EX-99.1 · 6.13 Mining Methods

6.13Mining Methods
6.13.1Geotechnical Considerations

Pit walls at Hammerdown and Orion will be comprised primarily of mafic volcanic and felsic to mafic schist units with dominant sub-vertical, northeast-southwest trending foliation. The Stog’er Tight pits will be developed in Gabbro and Mafic Volcanics with a well-developed, shallow to moderately north-northeast dipping foliation. Secondary, shallow to moderately dipping joint sets have also been identified and incorporated into the geotechnical design at Hammerdown and Stog’er Tight.

Rock mass quality at all three deposits generally classifies as “Good” geomechanical quality according to the Bieniawski (1989) rock mass rating (RMR) classification system. Intact rock strengths are typically “Strong” (50 to 100 MPa) to “Very Strong” (100 to 150 MPa) according to ISRM (1978) standards.

Based on rock mass, the quality and structural characteristics described above along with the relatively shallow pit depths, kinematic (structurally controlled) failures are anticipated to be the primary mechanism of instability. Interramp slope angles recommended for the final Hammerdown pit range from for 49 to 55°, depending on wall orientation. An interramp slope angle of 55° is recommended for the final Orion and Stog’er Tight pit designs. Good quality wall control blasting and scaling practices will be required to achieve 55° interramp slopes while maintaining adequate catch bench widths.

The Captain Nemo Fault parallels the south wall of the Hammerdown pit and is considered critical to overall stability of final pit south wall. Pit designs should mine out the fault to avoid potential for multi-bench or overall slope failures.

6.13.2Hydrogeological Considerations

The Hammerdown/Orion area lies near a groundwater divide intersecting three surface watersheds. Analytical estimates indicate pit inflows of approximately 3,426 m³/d at Hammerdown and 1,124 m³/d at Orion at full development. Historical underground workings may currently act as a groundwater sump and could be integrated into future dewatering. Faults and fractures within the pit area may contribute to groundwater inflow and require further investigation. Existing hydrogeologic testing has been limited to shallow depths (≤30 m), and deeper drilling and hydraulic testing are required to characterize full-pit conditions. Water-management design must account for stockpile toe-seepage and seasonal groundwater elevations, including occasional artesian conditions.

Groundwater flows northwest toward Camp Pond, with water levels varying from artesian to ~6 m depth, driven by local topography and past pit development. Further testing is required to delineate potential faults/fractures that may influence inflows to the proposed Gabbro Pit and Pit 278. Development near Fox Pond and Camp Pond will require careful management of pond water levels to avoid unintended drawdown. If pond-level reductions cannot be avoided, a Fisheries Act authorization may be required. A 3-D groundwater model is recommended to integrate pit development, lithology, hydraulic conductivity, and pond interactions.

Groundwater levels surrounding the Pine Cove pit are higher than pit water levels, indicating continued groundwater inflow of ~500 m³/d. Groundwater contributions will remain an important factor in the evolution of the pit lake and long-term water quality. The in-pit tailings facility requires a minimum 10 m water cover, and ongoing monitoring indicates water levels near elevation 23.5 masl. Water-cover thickness will vary as tailings deposition progresses, and groundwater inflow should be incorporated into closure planning and modeling.

6.13.3Mining

The PEA is preliminary in nature. It includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that the PEA would be realized.

Open pit optimization was conducted to determine the optimal economic shape of the open pit and guide the open pit design process, with cut-off grades ranging from 0.41 to 0.56 depending on the deposit. Revenue factor of 1.00 pit shells were selected to guide the pit designs for the Hammerdown, Orion and Stog’er Tight deposits. Mined physical quantities represent 4.3 Mt of mineralized material at an average grade of 2.19 g/t for 306.6 koz, 48.0 Mt of waste and 1.7 Mt of overburden. The pits’ mining sequence is planned as follows: Hammerdown, Orion and Stog’er Tight. The Hammerdown pit will be mined in three phases: a Hammerdown phase 1 pit, a Rumbullion area pit and a Hammerdown phase 2 pushback joining the pits together. The 13-year life of mine incorporates 12 years of direct mill feed from open pit operations and 1 years of stockpile rehandling at a processing rate of 700 tpd. The mining rate is expected to peak at 18,300 t/d and average 12,300 t/d over the 12 years of mining. The project is planned as a conventional truck-and-shovel open pit mining operation with mining executed by a contractor. Waste loading and haulage will be handled by 3 m 3 hydraulic excavators and 41-tonne payload articulated haul trucks. Mineralized material loading and hauling will be handled by a fleet of 2 m 3 hydraulic excavators with a 7 m 3 front end loader as backup and 38 tonne payload articulated haul trucks.