WESTWATER RESOURCES, INC.
For the period ended Dec 31, 2025. Filed Mar 19, 2026.
View on SEC.govAbout this filing
A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.
FY2025 · Filed Mar 19, 2026
Contents
SUMMARY OF RECENT DEVELOPMENTS
Customer Engagement Update
The global landscape for the U.S. supply of critical minerals, including natural graphite, continues to evolve. On November 3, 2025, FCA, which is part of the Stellantis group of companies, unexpectedly terminated its Offtake Agreement with the Company. FCA was one of three companies, including SK On and Hiller Carbon, with offtake agreements with Westwater.
The offtake agreements with SK On and Hiller Carbon remain in effect. While FCA has indicated it may be open to considering a new arrangement with the Company, any future agreement would be subject to current market conditions and other terms to be negotiated. The Company continues to explore additional offtake opportunities with other prospective customers and, as part of these efforts, has provided and expects to continue providing product samples to support customer evaluation and qualification processes.
Westwater continues to respond to inquiries from prospective customers as they evaluate the impact of announced and potential changes to global trade and industrial policy, including tariffs, export restrictions, domestic content requirements, countervailing and antidumping duties, the Section 45X advanced manufacturing production tax credit, and related policy measures that may affect demand for domestic battery-grade natural graphite. Many of these prospective customers include large, global lithium-ion battery manufacturers and original equipment manufacturers (“OEMs”).
Issuance of Patent for Graphite Purification
On September 17, 2025, the Company announced that it had received its U.S. Patent related to its graphite purification method. The Company believes its purification process provides a more environmentally sustainable alternative to certain conventional purification techniques used in China and other countries. In particular, the purification process is designed to avoid the use of hydrofluoric acid, a hazardous substance that is commonly used in certain traditional purification methods. The Company believes its patented approach supports the production of high-purity graphite and provides a competitive advantage as customers increasingly consider tariff restrictions, ESG, permitting and domestic supply chain requirements.
Kellyton Graphite Plant – Construction and Estimated Cost Update
During the year, construction activities at the Kellyton Graphite Plant included equipment installation and electrical work to establish the power distribution center, transition off temporary power generation, and connection of the facility to the Alabama power grid. The Company has installed micronization (sizing) and spheroidization (shaping) mills in the SG building and has commissioned and started one micronization and one spheroidization mill.
Westwater has constructed and continues to operate its R&D Lab. The R&D Lab supports ongoing product development and optimization with potential customers and provides in-house quality control testing capabilities. The Company believes the R&D Lab increases flexibility to refine and produce future samples in accordance with customer specifications.
Since inception of the Kellyton Graphite Plant, and inclusive of liabilities as of December 31, 2025, the Company has incurred costs of approximately $128.2 million. Refer to Note 5 of the consolidated financial statements in Item 8 of this Annual Report on Form 10-K for further details. The Company continued Phase I construction activities at a measured pace during 2025. With additional financing raised during 2025, the Company has ordered certain long-lead equipment items to further advance Phase I in 2026; however, the Company currently intends to maintain a measured approach to capital deployment.
In light of the Company’s customer engagement and commercial discussions, the Company completed an evaluation to optimize the Phase I capital plan for of the Kellyton Graphite Plant in December of 2025. Management notes that the original budget for Phase I was approximately $271 million and, through prior optimization and debottlenecking efforts, was reduced to approximately $245 million. While the Company’s additional optimization review in December 2025 resulted in additional potential cost reductions, the Company is also experiencing certain cost pressures related to tariffs and energy costs as a result of the current geopolitical climate and related uncertainties. As such, the Company is maintaining its current cost estimate of $245 million, of which approximately $117 million has not yet been incurred, including approximately $19 million related to contingency and potential cost escalations.
Qualification Line Development at Kellyton Graphite Plant
During 2025, the Company operated its qualification line at the Kellyton Graphite Plant and produced multiple customer samples, including aggregate production in excess of one metric ton of CSPG, for use in pre-production evaluations and testing. Throughout the year, the Company made incremental improvements to the qualification line to improve cycle times, yield, and graphite flow rates and to enhance overall operating performance.
The CSPG produced on the qualification line is representative of CSPG material produced in a future commercial setting. The Company expects the continued operation of the qualification line will support the production of bulk CSPG samples in one to ten metric ton batches for customer qualification activities. The qualification line is also being used for operations training and process familiarization, which the Company believes may support a more efficient commissioning and start-up of the Kellyton Graphite Plant.
During 2025, the Company commissioned one micronization mill and one shaping mill. These commissioned mills are being used in conjunction with the qualification line to produce additional customer samples, and the Company expects these assets to transition to the mass production line when Phase I of the Kellyton Graphite Plant is completed and becomes operational.
Coosa Graphite Deposit
On October 27, 2025, Westwater announced plans to progress the permitting process for future mine development at its Coosa Graphite Deposit. The Company has retained a third-party permitting and engineering firm to support and manage permitting activities and expects to engage with the U.S. Army Corps of Engineers, the Alabama Department of Environmental Management, and other state and local authorities as the process progresses. The permitting effort is expected to include the preparation of environmental studies and the submission of applications under applicable federal and state frameworks, including, as relevant, water discharge, wetlands and air permits, and other approvals associated with the construction and operation of the Coosa Graphite Deposit. These results will inform ongoing mine planning and design efforts, as Westwater continues to evaluate and optimize the Coosa Graphite Deposit for efficient, responsible production of natural graphite.
Certain permitting activities commenced in the fourth quarter of 2025, and subsequent to year end, the Company filed an application for a NPDES permit with the ADEM and submitted its project application to the FAST-41 Federal Permitting Council dashboard. Established by the U.S. Congress in 2015, the FAST-41 program is intended to streamline the federal permitting process by improving timeliness and predictability through publicly posted permitting timelines and procedures. The program also provides formal issue‑resolution mechanisms, and its federal permitting dashboard allows project stakeholders and the general public to track a project’s progress, including opportunities for public comment.
Financing Update
During 2025, the Company entered into the Series Purchase Agreements pursuant to which the Company issued and sold in registered public offerings Convertible Notes in the aggregate principal amount of $10.0 million, which are convertible into shares of the Company’s Common Stock.
The Company continued to raise capital through its ATM Sales Agreement and 2024 Lincoln Park PA which resulted in net proceeds of $53.4 million and $3.2 million, respectively.
Refer toNote 5, Convertible Notes, andNote 9, Stockholders’ Equity, of the consolidated financial statements inItem 8 of this Annual Report on Form 10-K for further details.
Debt Financing Update
Following the unexpected termination of the FCA Offtake Agreement in the fourth quarter, which the Company had expected to be a key commercial underpinning for the debt syndication, the Company, together with its investment banker, paused efforts related to syndication of a secured debt facility. While the private debt syndication process has been paused, the Company continues to receive interest from lenders that may be interested in providing financing pending sufficient commercial offtake. No assurance can be given that the Company will ultimately enter into a lending arrangement, or that financing will be available in amounts sufficient to meet its needs, or on terms acceptable to the Company. Further, we continue to pursue other potential financing sources including, but not limited to, governmental financing and opportunity zones.
In April 2025, Westwater received a letter of interest from EXIM related to the Kellyton Graphite Plant, under EXIM’s “Make More in America Initiative” and “China and Transformational Exports Program.” The Company’s application remains pending. Progression from an EXIM letter of interest to a loan commitment is subject to, among other things, additional offtake to support loan repayment, submission and acceptance of a formal application, completion of EXIM due diligence and underwriting, and negotiation and finalization of definitive terms and conditions. No assurance can be given that the Company will enter into a loan transaction with EXIM.
In addition to the EXIM loan application, Westwater has engaged advisors to support ongoing efforts to evaluate and pursue other sources of government funding that may be available.
The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.