Item 1A. Risk FactorsCurrent report: 10-K
Period ended 2025-12-31; filed 2026-03-09.
0001104659-26-024827
Item 1A. Risk FactorsThe baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.
Compared 266 previous paragraphs and 279 current paragraphs.
151 unchanged; 100 reworded; 11 added; 1 removed; 14 previous and 17 current paragraphs rearranged.
Tables are not compared: 96 previous and 94 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.
A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.
Added paragraphs (11)
Current report
Our business and growth prospects have and continue to benefit, in part, from federal, state and local policies, as well as incentives and regulatory frameworks that support the adoption of EVs and the deployment of EV charging infrastructure, which are subject to change and uncertainty outside of our control.
Current report
We may need to raise additional funds, and they may not be available when needed or may only be available on unfavorable terms, which could impact our ability to fund our operations, our growth and the build-out of our network.
Current report
Our business has generally been financed through a combination of our corporate funds and non-recourse project finance debt. If our project subsidiaries default on their obligations under such limited or non-recourse debt, we may be required to make certain payments to the relevant debt holders, and if the collateral supporting such project financing structures is foreclosed upon, we may lose certain of our assets.
Current report
Our business has generally been financed using a combination of our corporate funds and limited or non-recourse project finance debt. If our project subsidiaries default on their obligations under the relevant debt documents and the creditors foreclose on the relevant collateral, we may lose our ownership interest in the relevant project subsidiary or our project subsidiary owning the assets would only retain an interest in the physical assets, if any, remaining after all debts and obligations were paid in full.
Current report
Our use of artificial intelligence technologies, including generative AI, may expose us to operational, regulatory, and competitive risks.
Current report
We use AI technologies, including generative AI, in connection with various business activities such as network planning and operational analysis. Our use of these technologies is subject to evolving regulatory frameworks at the federal and state level, and compliance with emerging requirements may impose additional costs, require modifications to our practices, or restrict certain uses of AI. Generative AI and other related emerging technologies present inherent risks, including unintended biases, accuracy issues, and the potential for discriminatory outcomes that could lead to errors in decision-making and negatively affect our operations, reputation, and financial performance. The use of AI by our employees, vendors, or third-party providers also presents data privacy and security risks, including the potential for sensitive Company or customer information to be exposed to unauthorized recipients, and could result in claims related to confidential information, intellectual property, or failure to comply with applicable legal requirements. We also rely on third-party platforms and providers for certain AI capabilities, and changes to those providers' terms of service, pricing, availability, or functionality could disrupt our operations or require us to identify alternative solutions on short notice. Information technology systems, including AI capabilities, are a component of our long-term competitive strategy for optimizing our charging network and enhancing customer experience. Other participants in the EV charging industry are investing in AI technologies for network optimization, predictive maintenance, dynamic pricing, and customer experience, and our failure to keep pace with these technological developments could place us at a competitive disadvantage, particularly if regulatory developments also limit our ability to deploy these tools. If we fail to maintain appropriate governance and oversight over AI systems, we could face customer complaints, reputational harm, or regulatory scrutiny that could adversely affect our business and results of operations.
Current report
Our business is concentrated in certain markets, exposing us to region‑specific risks.
Current report
For the years ended December 31, 2025 and 2024, 49.7% and 46.7%, respectively, of our charging revenues were generated in California. This concentration of our operational infrastructure makes our business and results of operations particularly susceptible to adverse economic, regulatory, political, weather, utility, and other conditions affecting this market. Changes in state or local incentive programs, utility rate structures, permitting and zoning requirements, grid reliability, or the occurrence of extreme weather events or natural disasters could disproportionately impact our operations, growth prospects, and results of operations.
Current report
During the industry’s transition to NACS, we will need to significantly increase our deployment of NACS‑equipped chargers to serve future EV demand while still supporting customers who rely on CCS charging. This may require integrating both connector types on our chargers and retooling, retrofitting, or replacing portions of our existing CCS‑based hardware. If we cannot transition as quickly as OEMs adopt NACS, or if NACS equipment shortages, certification delays, or interoperability issues occur, our network may become less attractive than competing networks that adapt more rapidly, reducing utilization, customer satisfaction, and revenue. Simultaneously, we must ensure this transition does not adversely impact customer demand, throughput, and revenue from non‑NACS customers, who may still represent a significant share of the EV fleet.
Current report
The following material weaknesses in internal control over financial reporting were identified as of December 31, 2025: We did not effectively design, implement or operate sufficient and appropriate process level control activities related to our financial reporting processes. Additionally, we had ineffective general information technology controls (“GITCs”) for certain IT systems related to charging revenue, which results in a corresponding failure of automated process level controls and manual controls dependent on the accuracy and completeness of information derived from those IT systems.
Current report
Following the CRIS Business Combination, we utilized these exemptions, with the exception that we have performed an annual performance evaluation of the compensation and nominating and corporate governance committees. As a
Removed paragraphs (1)
Previous report
The following material weakness in internal control over financial reporting was identified as of December 31, 2024: due to an ineffective information and communication process to ensure the completeness and accuracy of underlying data
Reworded paragraphs (100)
Previous wording
We have a history of operating losses and negative operating cash flows. As of December 31, 2024, we had $120.5 million of cash, cash equivalents, and restricted cash and working capital of $94.0 million. Our net cash outflow for the year ended December 31, 2024 was $88.6 million. While we believe that our cash on hand as of December 31, 2024 and the DOE Loan are sufficient to meet our current working capital and capital expenditure requirements, there can be no assurance that we will be able to successfully draw on the DOE Loan in full and achieve and maintain profitability in the future. Our potential profitability is particularly dependent upon the continued adoption of EVs by consumers, fleet operators and other electric transportation modalities, continued support from regulatory programs and, in each case, the use of our chargers, any of which may not occur at the levels we currently anticipate or at all. We may need to raise additional financing through loans, securities offerings or additional investments in order to fund our ongoing operations. There is no assurance that we will be able to obtain such additional financing or that we will be able to obtain such additional financing on favorable terms.
Current wording
We have a history of operating losses and negative operating cash flows. As of December 31, 2025, we had $210.7 million of cash, cash equivalents, and restricted cash, and $161.2 million of working capital. While we believe that our cash, cash equivalents, and restricted cash on hand as of December 31, 2025, together with the DOE Loan, and the Credit Agreement are sufficient to meet our current working capital and capital expenditure requirements, there can be no assurance that we will be able to successfully draw on our loans in full and achieve and maintain profitability in the future. Any future profitability is particularly dependent upon the continued adoption of EVs by consumers, fleet operators and other electric transportation modalities, continued support from regulatory programs and, in each case, the use of our chargers, any of which may not occur at the levels we currently anticipate or at all. We may need to raise additional financing through loans, securities offerings or additional investments in order to fund our ongoing operations. There is no assurance that we will be able to obtain such additional financing or that we will be able to obtain such additional financing on favorable terms.
Previous wording
Our growth and success are highly correlated with and thus dependent upon the continuing rapid adoption of and demand for EVs and OEMs’ ability to supply such EVs to the market.
Current wording
Our growth and success are highly correlated with and thus dependent upon the continuing adoption of and demand for EVs and OEMs’ ability to supply such EVs to the market.
Previous wording
Our growth is highly dependent upon the continued rapid adoption of EVs by governments, businesses and consumers. The market for EVs is still rapidly evolving, characterized by rapidly changing technologies, increasing consumer choice as it relates to available EV models, their pricing and performance, evolving government regulation and industry standards, changing consumer preferences and behaviors, intensifying levels of concern related to environmental issues and government initiatives related to climate change and the environment generally. Our revenues are driven in large part by EV drivers’ driving and charging behavior. Potential shifts in behavior may include but are not limited to changes in annual vehicle miles traveled, preferences for urban vs. suburban vs. rural and public vs. private, and DCFC vs. Level 2 charging, demand from rideshare or urban delivery fleets and the emergence of autonomous vehicles and/or new forms of mobility. Although demand for EVs has grown in recent years, there is no guarantee of continuing future demand. Public DC fast charging may not develop as expected and may fail to attract projected market share of total EV charging. If the market for EVs develops more slowly than expected, or if demand for EVs develops more slowly than expected or decreases, our growth would be reduced, and our business, prospects, financial conditions and results of operations would be harmed. The market for EVs, and ultimately EV charging, could be affected by numerous factors, such as:
Current wording
Our growth is highly dependent upon the continued adoption of EVs by governments, businesses and consumers. The market for EVs is still rapidly evolving, characterized by rapidly changing technologies, increasing consumer choice as it relates to available EV models, their pricing and performance, evolving government regulation and industry standards, changing consumer preferences and other related factors. Our revenues are driven in large part by EV drivers’ driving and charging behavior. Potential shifts in behavior may include but are not limited to changes in annual vehicle miles traveled, preferences for urban vs. suburban vs. rural and public vs. private, and DCFC vs. Level 2 charging, demand from rideshare or urban delivery fleets and the emergence of autonomous vehicles and/or new forms of mobility. Although demand for EVs grew over the past decade, there is no guarantee of continuing future demand. Public DC fast charging may not develop as expected and may fail to attract projected market share of total EV charging. If the market
Previous wording
While many global OEMs and several new market entrants have announced plans for new EV models, the lineup of EV models with increasing fast charging needs expected to come to market over the next several years may not materialize in that timeframe or may fail to attract sufficient customer demand. Demand for EVs may also be affected by factors directly impacting automobile prices or the cost of purchasing and operating automobiles, such as sales and financing incentives, prices of raw materials and parts and components, cost of fuel and governmental regulations, including tariffs, import regulations and other taxes. Volatility in demand may lead to lower vehicle unit sales, which may result in reduced demand for EV charging solutions and therefore materially and adversely affect our business, financial condition and results of operations.
Current wording
While many global OEMs and several new market entrants have announced plans for new EV models, the lineup of EV models with increasing fast charging needs expected to come to market over the next several years may not materialize in that timeframe, may fail to attract sufficient customer demand, or may be cancelled or delayed by manufacturers, beyond those cancellations in the past year. Demand for EVs may also be affected by factors directly impacting automobile prices or the cost of purchasing and operating automobiles, such as sales and financing incentives, prices of raw materials and parts and components, cost of fuel and governmental regulations, including tariffs, import regulations and other taxes. Volatility in demand may lead to lower vehicle unit sales, which may result in reduced demand for EV charging solutions and therefore materially and adversely affect our business, financial condition and results of operations.
Previous wording
With continued fast growth, we will be required to continue developing, implementing, and enhancing our information technology systems and internal control over financial reporting and related procedures. The implementation, maintenance, segregation, and improvement of these systems require significant management time, support and cost, and there are inherent risks associated with developing, implementing, improving, and expanding core systems as well as updating current systems, including disruptions to the related areas of business operations. These risks may affect our ability to manage our data and inventory, procure parts or supplies or manufacture, sell, deliver and service products, adequately
Current wording
With continued fast growth, we will be required to continue developing, implementing, and enhancing our information technology systems and internal control over financial reporting and related procedures. The implementation, maintenance, segregation, and improvement of these systems require significant management time, support and cost, and there are inherent risks associated with developing, implementing, improving, and expanding core systems as well as updating current systems, including disruptions to the related areas of business operations. These risks may affect our ability to manage our data and inventory, procure parts or supplies or manufacture, sell, deliver and service products, adequately protect our intellectual property or achieve and maintain compliance with, or realize available benefits under, tax laws and other applicable regulations. These risks may also result in data security incidents that may interrupt business operations and allow third parties to obtain unauthorized access to business information or misappropriate funds. We may also face risks to the extent such third parties infiltrate the information technology infrastructure of our contractors.
Previous wording
Current and future administrations at the federal and state level may create uncertainty for the EV sector, which may have a material and adverse effect on our business, prospects, financial condition and results of operations.
Current wording
Current and future administrations at the federal and state level may create uncertainty for the EV sector, which may have a material and adverse effect on our business, financial condition and results of operations.
Previous wording
As noted above, we are monitoring possible changes under the current administration and 119 th Congress which could impact the availability of federal incentives to encourage the adoption of EVs and investment in charging infrastructure. These include federal policies such as the IRA’s $7,500 EV tax credit and $4,000 used EV credit, the NEVI Program to provide funding to states to deploy EV charging, or emissions standards proposed by the EPA. See Part I, Item 1 “Business – Market Overview.” In addition to NEVI Program funding, a number of states also offer various rebates, grants and tax credits to incentivize both EV and EVSE purchases. Such federal policies relating to investment in charging infrastructure could also impact our ability to draw funds down under the DOE Loan, which could materially and adversely impact our business, financial condition and results of operations. See Part I, Item IA,“Risk Factors — Risks Related to the DOE Loan.” Additionally, in many states, utilities offer rebates or other incentive programs, typically called “make-ready” programs, to incentivize the development of EV charging infrastructure.
Current wording
On July 4, 2025, H.B. 1, 119th Congress (2025), also referred to as the OBBBA, was enacted in the U.S. OBBBA includes significant provisions, such as the permanent extension of certain expiring provisions of the TCJA, modifications to the international tax framework, and the restoration of favorable tax treatment for certain business provisions. The OBBBA led to the sunset of the IRA’s $7,500 EV tax credit and $4,000 used EV credit after September 30, 2025 and terminates the 30C income tax credits for any locations placed in service after June 30, 2026. The NEVI Program continues to provide funding to states to deploy EV charging, or emissions standards proposed by the EPA. See Part I, Item 1 “Business – Market Overview.” In addition to NEVI Program funding, a number of states also offer various rebates, grantsand tax credits to incentivize both EV and EVSE purchases. Such federal policies relating to investment in charging infrastructure could also impact our ability to draw funds down under the DOE Loan, which could materially and adversely impact our business, financial condition and results of operations. See Part I, Item IA,“Risk Factors — Risks Related to the DOE Loan.” Additionally, in many states, utilities offer rebates or other incentive programs, typically called “make-ready” programs, to incentivize the development of EV charging infrastructure.
Previous wording
However, incentives set by federal or state governments, as well as other government commitments and initiatives, may expire on a particular date, end when the allocated funding is exhausted, or may be reduced, modified or terminated as a matter of regulatory, executive or legislative policy. The impact of the IRA and other government EV initiatives, including regulatory requirements and restrictions that may impact the ability of us and our competitors to take advantage of such initiatives, cannot be known with any certainty at this time, and we may not reap any or all of the expected benefits of the IRA or the IIJA.
Current wording
However, federal and state incentives and other government commitments and initiatives may expire on a particular date, end when the allocated funding is exhausted, or may be reduced, modified or terminated as a matter of regulatory, executive or legislative policy. The impact of the government EV initiatives, including regulatory requirements and
Previous wording
Current and future administrations at the federal and state level may create further uncertainty for the EV sector. For example, the current administration may enact policies and change regulations that may adversely affect the growth of the EV market, including by eliminating the EV Tax Credits or the Tailpipe Rule, and may take additional steps to remove incentives for manufacturing and purchasing EVs. The current administration has also proposed further increases of tariffs on certain foreign imports into the U.S. New or increased tariffs on imports to the U.S. could also have a significant impact on us, particularly our ability to source components for our charging network and the cost of such components. New or increased tariffs may also result in a suppressed EV market, fewer EVs on the road and lower demand for EV chargers, which would have an adverse effect on our business, prospects, financial condition and results of operations.
Current wording
Current and future administrations at the federal and state level may create further uncertainty for the EV sector. For example, the current administration may enact policies and change regulations that may continue to adversely affect the growth of the EV market. See Part I, Item 1, “Business – Government Regulations.” The current administration has also proposed further increases of tariffs on certain foreign imports into the U.S. New or increased tariffs on imports to the U.S. could also have a significant impact on us, particularly our ability to source components for our charging network and the cost of such components. New or increased tariffs may also result in a suppressed EV market, fewer EVs on the road and lower demand for EV chargers, which would have an adverse effect on our business, prospects, financial condition and results of operations.
Previous wording
The EV charging market is relatively new, and we currently face competition from a number of companies. There are a number of established and emerging EV charging companies operating in the U.S. that pursue various business models that are constantly evolving, including Tesla, Electrify America, ChargePoint, and EV Connect.
Current wording
The EV charging market is relatively new, and we currently face competition from a number of companies. There are a number of established and emerging EV charging companies operating in the U.S. that pursue various business models that are constantly evolving, including Tesla, Electrify America, ChargePoint, Ionna, and Blink.
Previous wording
We compete (or, in the future, may compete) with some or all of these companies and other competitors across a number of industry segments, including retail and fleet. The principal competitive factors in the industry include charger count, locations, accessibility and reliability; charger connectivity to EVs and ability to charge all standards; speed of charging relative to expected vehicle dwell times at the location; DCFC network reliability, scale and local density; the software-enabled services offered and overall customer experience; operator brand, track record and reputation; access to equipment vendors, and service providers; and policy incentives and pricing. Competitors may be able to respond more quickly and effectively than us to new or changing opportunities, technologies, standards or customer requirements and may be better equipped to initiate or withstand substantial price competition. Additionally, historically we have generated a significant portion of our revenue from agreements with OEM partners, and the loss of one or more of these OEM partners as a result of such partners investing in their own EV charging networks (or another EV charging network in which they participate) could materially and adversely affect our business, financial condition and results of operations.
Current wording
We compete (or, in the future, may compete) with some or all of these companies and other competitors across a number of industry segments, including retail and fleet. The principal competitive factors in the industry include charger count, locations, accessibility and reliability; charger connectivity to EVs and ability to charge widely adopted standards; speed of charging relative to expected vehicle dwell times at the location; adjacent amenities; DCFC network reliability, scale and local density; software-enabled services offerings and overall customer experience; operator brand, track record and reputation; access to equipment vendors and service providers; policy support incentives; and pricing. Competitors may be able to respond more quickly and effectively than we can to new or changing opportunities, technologies, standards or customer requirements and may be better equipped to initiate or withstand substantial price competition. Additionally, historically we have generated a significant portion of our revenue from agreements with OEM partners, and the loss of one or more of these OEM partners as a result of such partners investing in their own EV charging networks (or another EV charging network in which they participate) could materially and adversely affect our business, financial condition and results of operations.
Previous wording
In addition, there are other means for charging EVs, which could affect the level of demand for charging at our DCFCs. For example, Tesla continues to build out its supercharger network across the U.S. for Tesla vehicles and has opened up a portion of its supercharger network to non-Tesla EVs, which could reduce overall demand for EV charging at other sites, including our charging stalls. Also, other companies sell chargers designed for customers seeking to have on-premises EV charging capability as well as for home or workplace charging, which may reduce the demand for fast charging if EV owners find “slow” charging at a workplace, at home, or other parking locations to be sufficient. Municipalities may decide to convert street lighting poles and lampposts to public charging points for EV drivers who rent, have no access to home charging, or park their EVs on the street, potentially reducing our serviceable markets. Retailers, utilities or other Site Hosts or commercial, municipal and federal fleet businesses may opt to become owners and operators of public or private EV fast charging equipment and purchase that equipment and associated management software directly from vendors in the marketplace.
Current wording
In addition, there are other means for charging EVs, which could affect the level of demand for charging at our DCFCs. For example, Tesla continues to build out its supercharger network across the U.S. for Tesla vehicles and has opened up a portion of its supercharger network to non-Tesla EVs, which could reduce overall demand for EV charging at other sites, including our charging stalls. Also, other companies sell chargers designed for customers seeking to have on-premises EV charging capability as well as for home or workplace charging, which may reduce the demand for fast charging if EV owners find “slow” charging at a workplace, at home, or other parking locations to be sufficient. Municipalities may decide to convert street lighting poles and lampposts to public charging points for EV drivers who
Previous wording
We rely on a limited number of vendors for design, testing and manufacturing of charging equipment which at this stage of the industry is unique to each supplier and thus singularly sourced with respect to components as well as aftermarket maintenance and warranty services. For the year ended December 31, 2024, two vendors provided 87.9% of our total charging equipment. For the year ended December 31, 2023, one vendor provided 76.9% of our total charging equipment. This reliance on a limited number of vendors increases our risks, since we do not currently have proven reliable alternative or replacement vendors beyond these key parties. In the event of production interruptions or supply chain disruptions including but not limited to reduced availability of certain key components such as semiconductors, we may not be able to take advantage of increased production from other sources or develop alternate or secondary vendors without incurring material additional costs and substantial delays. See Part I, Item IA,“Risk Factors — Risks Related to Our
Current wording
We rely on a limited number of vendors for design, testing and manufacturing of charging equipment which at this stage of the industry is unique to each supplier and thus singularly sourced with respect to components as well as aftermarket maintenance and warranty services. For the years ended December 31, 2025 and 2024, two vendors provided 91.4% and 87.9%, respectively, of our total charging equipment. This reliance on a limited number of vendors increases our risks, since we do not currently have proven reliable alternative or replacement vendors beyond these key parties. In the event of production interruptions or supply chain disruptions including but not limited to reduced availability of certain key components such as semiconductors, we may not be able to take advantage of increased production from other sources or develop alternate or secondary vendors without incurring material additional costs and substantial delays. See Part I, Item IA,“Risk Factors — Risks Related to Our Business — Disruptions in our supply chain could materially and adversely affect our business, financial condition and results of operations.” Thus, our business, financial condition and results of operations could be materially and adversely affected if one or more of our current or future vendors is impacted by any interruption at a particular location or is acquired or impacted by liquidity issues.
Previous wording
We rely on our vendor partners to supply spare parts to repair damaged charging equipment. If any of our vendor partners are unable source and provide replacement parts or fulfill warranty and maintenance obligations pursuant to existing agreements, we may be unable to repair damaged charging equipment and may be required to either leave it inoperable or fully replace damaged charging stations. In addition, some vendors have stopped supporting our older generation charging equipment. If we are unable to source replacement parts for our older generation charging equipment, some of our charging stations may become obsolete and we may be required to incur additional costs to replace them. The occurrence of any of the foregoing may materially and adversely affect our business, financial condition and results of operations.
Current wording
We rely on our vendor partners to supply spare parts to repair damaged charging equipment. If any of our vendor partners are unable source and provide replacement parts or fulfill warranty and maintenance obligations pursuant to existing agreements, we may be unable to repair damaged charging equipment and may be required to either leave it inoperable or fully replace damaged charging stations. In addition, some vendors have stopped supporting our older generation charging equipment. If we are unable to source replacement parts for our older generation charging
Previous wording
Given the nascent stage of the industry, a limited number of contractual commercial customers and OEM partners currently account for a substantial portion of our income. For the years ended December 31, 2024 and 2023, one customer represented 33.5% and 45.2% of total revenue, respectively. Our operating projections are currently contingent on our performance under our commercial contracts. At least in the short term, we expect that a majority of our sales outside of the retail customer market will continue to come from a concentrated number of commercial customers and OEM partners. We expect a substantial portion of our cash receipts in the near future to be from a limited number of commercial customers and OEM partners and, as a result, will be subject to any risks specific to those entities and the jurisdictions and markets in which they operate, including OEMs’ ability to develop a portfolio of EV models and attract customers for those models and maintain or expand their investments in EVs and EV charging infrastructure. We may be unable to accomplish our business plan to diversify and expand our customer and OEM partner base by attracting a broad array of customers and OEM partners, which could materially and adversely affect our business, financial condition and results of operations.
Current wording
Given the nascent stage of the industry, a limited number of contractual commercial customers and OEM partners currently account for a substantial portion of our income. For the years ended December 31, 2025 and 2024, one customer represented 30.2% and 33.5% of total revenue, respectively. Our operating projections are currently contingent on our performance under our commercial contracts. At least in the short term, we expect that a majority of our sales outside of the retail customer market will continue to come from a concentrated number of commercial customers and OEM partners. We expect a substantial portion of our cash receipts in the near future to be from a limited number of commercial customers and OEM partners and, as a result, will be subject to any risks specific to those entities and the jurisdictions and markets in which they operate, including OEMs’ ability to develop a portfolio of EV models and attract customers for those models and maintain or expand their investments in EVs and EV charging infrastructure. We may be unable to accomplish our business plan to diversify and expand our customer and OEM partner base by attracting a broad array of customers and OEM partners, which could materially and adversely affect our business, financial condition and results of operations.
Previous wording
Our success and growth depend on our ability to develop and maintain relationships with automotive OEM and fleet partners.
Current wording
Our success and growth depend on our relationships with automotive OEM and fleet partners.
Previous wording
some cases, our OEM partners have agreed to fund capital expenditures related to the build-out of our charger network. For example, GM is providing payments for performance obligations that will help fund the accelerated build-out of 2,850 charger stalls for our fast charger network through June 2028. If we fail to develop and maintain relationships with OEMs, or if OEMs opt to partner with competitors rather than us, our revenues may decline and our business may suffer.
Current wording
Thesuccess of our business depends on our ability to develop and maintain relationships with OEMs, such as GM, Honda, Toyota, and others. These relationships help us access new customers and build brand awareness through co-marketing. We may also benefit from promotional programs sponsored by OEMs, such as prepaid charging credits. In some cases, our OEM partners have agreed to fund capital expenditures related to the build-out of our charger network. For example, GM is providing payments for performance obligations that will help fund the accelerated build-out of 2,850 charger stalls for our fast charger network through June 2028. If we fail to develop and maintain relationships with OEMs, or if OEMs opt to partner or expand partnerships with competitors rather than us, our revenues may decline and our business may suffer.
Previous wording
There can be no certainty that we will be able to identify and contract with suitable additional OEM and fleet partners. To the extent we identify such partners, we will need to negotiate the terms of a commercial agreement with such partners. There can be no assurance that we will be able to negotiate commercially attractive terms with additional OEM and fleet partners, if at all. We may also be limited in negotiating future commercial agreements by the provisions of our existing contracts such as “most-favored nations” clauses. For example, our contracts with GM prohibit us from entering into agreements for similar programs on terms more favorable than the terms afforded to GM for a limited period of time. See Part I, Item 1, “Business — Customers, Partnerships and Strategic Relationships.”
Current wording
There can be no certainty that we will be able to identify and contract with suitable additional OEM and fleet partners. To the extent we identify such partners, we will need to negotiate the terms of a commercial agreement with such partners. There can be no assurance that we will be able to negotiate commercially attractive terms with additional OEM and fleet partners, if at all. We may also be limited in negotiating future commercial agreements by the provisions of our existing contracts such as “most-favored nations” clauses. For example, our contracts with GM prohibit us from
Previous wording
We are required to install a substantial number of chargers pursuant to the GM Agreement. If we do not meet our obligations under this agreement, we may not be entitled to payments from GM and may be required to pay liquidated damages, which may be significant.
Current wording
We are required to install a substantial number of chargers pursuant to the GM Agreement. If we do not meet our obligations under this agreement, we may not be entitled to payments from GM and may be required to pay liquidated damages.
Previous wording
Pursuant to the GM Agreement, we are required to meet certain quarterly milestones measured by the number of charger stalls installed and GM is required to make certain payments based on charger stalls installed. Under the GM Agreement, we are required to install a total of 2,850 charger stalls by June 30, 2028, 73.5% of which were required to be and were installed by December 31, 2024. Meeting the quarterly milestones will require additional funds beyond the amounts committed by GM, and we may face delays in construction, commissioning or aspects of installation of the charger stalls we are obligated to develop. We are also required to maintain network availability (i.e., the percentage of time a charger is operational and available on the network) of at least 97% across Flagship Stalls and 95% across the rest of the GM network.
Current wording
Pursuant to the GM Agreement, we are required to meet certain quarterly milestones measured by the number of charger stalls installed and GM is required to make certain payments based on charger stalls installed. Under the GM Agreement, we are required to install a total of 2,850 charger stalls by June 30, 2028, 81.4% of which were required to be and were installed by December 31, 2025. Meeting the quarterly milestones will require additional funds beyond the amounts committed by GM, and we may face delays in construction, commissioning or aspects of installation of the charger stalls we are obligated to develop. We are also required to maintain network availability (i.e., the percentage of time a charger is operational and available on the network) of at least 97% across Flagship Stalls and 95% across the rest of the GM network. In addition to the capital-build program, we are committed to providing GM EV customers with a certain aggregate amount of charging credits.
Previous wording
The GM Agreement is subject to early termination in certain circumstances, including in the event we fail to meet the quarterly charger stall-installation milestones or fail to maintain the specified level of network availability. In the event we fail to meet a charger stall-installation milestone or maintain the required network availability in a calendar quarter, GM has the right to provide us with notice of such deficiency within 30 days of the end of the quarter. If the same deficiency still exists at the end of the quarter immediately following the quarter for which a deficiency notification was delivered, GM may immediately terminate the agreement and seek pre-agreed liquidated damages of up to $15.0 million.
Current wording
The GM Agreement is subject to early termination in certain circumstances, including in the event we fail to meet the quarterly charger stall installation milestones or maintain the specified level of network availability. If GM opts to terminate the agreement, we may not be entitled to receive continued payments from GM and instead may be required to pay liquidated damages to GM. In the event we fail to meet a charger stall installation milestone or maintain the required network availability in a calendar quarter, GM has the right to provide us with notice of such deficiency within 30 days of the end of the quarter. If the same deficiency still exists at the end of the quarter immediately following the quarter for which a deficiency notification was delivered, GM may immediately terminate the agreement and seek pre-agreed liquidated damages.
Previous wording
15, 2025, there were approximately 326 charger stalls in the active engineering and construction development pipeline, of which approximately 310 charger stalls had been approved by GM. As of February 15, 2024, we had approximately 58 charger stalls left to install to meet our charger stall-installation milestone for the quarter ending March 31, 2025. If we do not meet our charger stall-installation milestone in any period, GM will have the right, if it so chooses, to send us a charger stall count breach notice, which would trigger a cure period. Under the terms of the GM Agreement, we and GM can agree to adjust quarterly charger stall installation milestones from time to time, provided the quarterly targets for an applicable calendar year must equal the annual target for such year. Going forward, it is uncertain whether these, or other potential issues in the procurement, installation, or energization of chargers, will be resolved in a timely fashion.
Current wording
We may not meet the charger stall installation milestones under the GM Agreement in the future, particularly as a consequence of delays in permitting, commissioning and utility interconnection, as well as delays related to industry and regulatory adaptation tothe requirements of high-powered charger installation including slower than expected third-party approvals of certain site acquisitions and site plans by utilities and land owners, and supply chain issues. As of February 15, 2026, there were approximately 429 charger stalls in the active engineering and construction development pipeline, all of which had been approved by GM. As of February 15, 2026, we had approximately 12 charger stalls left to install to meet our charger milestone for the quarter ending March 31, 2026. If we did not build any additional charger stalls after February 15, 2026, the liquidated damages would be up to $4.8 million. Under the terms of the GM Agreement, we and GM can agree to adjust quarterly charger stall installation milestones from time to time, provided that the quarterly targets for an applicable calendar year must equal the total annual target under the GM Agreement for such year. Going forward, it is uncertain whether the potential issues in the procurement, installation, or energization of chargers will continue to be resolved in a timely fashion.
Previous wording
Pursuant to the Pilot Infrastructure Agreement, we are required to meet certain milestones over two biennial periods measured by the number of chargers installed and charger sites serviced, and the Pilot Company is required to make certain payments each month based on the progress of construction at each charger site and for each charger procured. Under the Pilot Infrastructure Agreement, we are required to install approximately 500 chargers at 300 charger sites during the first two-year period and will be required to install approximately 500 chargers at approximately 200 to 250 additional charger sites during the second two-year period. We may not be able to meet the charger installation milestones and may be subject to liquidated damages, modifications to the Pilot Infrastructure Agreement or termination of the Pilot Infrastructure Agreement.
Current wording
Pursuant to the Pilot Infrastructure Agreement, we are required to meet certain milestones over two biennial periods measured by the number of chargers installed and charger sites serviced, and the Pilot Company is required to make certain payments each month based on the progress of construction at each charger site and for each charger procured. Under the Pilot Infrastructure Agreement, we were required to install approximately 500 chargers at 300 charger sites during the first two-year period and will be required to install approximately 500 chargers at approximately 200 to 250 additional charger sites during the second two-year period. Although we have met our charger installation milestones to date, we may not be able to meet the charger installation milestones in the future and may be subject to liquidated damages, modifications to the Pilot Infrastructure Agreement or termination of the Pilot Infrastructure Agreement.
Previous wording
The Pilot Infrastructure Agreement is subject to early termination for several reasons including: (a) at the Pilot Company’s election after 1,000 charging stalls have been completed, subject to the delivery of certain payments to us, (b) our inability to secure certain charger types in specified circumstances and (c) a material increase in the price of chargers due to a change in law.
Current wording
The Pilot Infrastructure Agreement is subject to early termination for several reasons including: (a) at the Pilot Company’s election after 1,000 charging stalls have been completed, subject to the delivery of certain payments to us, (b) our inability to secure certain charger types in specified circumstances and (c) a material increase in the price of chargers due to a change in law. In 2025, we surpassed the 1,000 completed stalls milestone.
Previous wording
Charger installation and construction is typically performed by third-party contractors managed by us. The installation and construction of charging stations at a particular site is generally subject to oversight and regulation in accordance with state and local laws and ordinances relating to building codes, safety, environmental protection and related matters and typically requires local utility cooperation in design and interconnection request approval and commissioning, as well as various local and other governmental approvals and permits that vary by jurisdiction. In addition, building codes, accessibility requirements, utility interconnect specifications, review, approval or study lead time or regulations may hinder EV charger installation and construction because they end up costing the developer or installer more in order to meet the code requirements. In addition, increased demand for the components necessary to install and construct charging stations could lead to higher installed costs. Meaningful delays or cost overruns caused by our vendor supply chains, contractors, utility upgrades scope and delays, or inability of local utilities and approving agencies to cope with heightened levels of activity, may impact our ability to satisfy the requirements under the Build Schedule and our other contractual commitments, and may impact revenue recognition in certain cases and/or impact our relationships, any of which could impact our business and profitability, pace of growth and prospects. For example, the installation of charger stalls under the GM Agreement has required significant utility upgrades to accommodate the higher capacity chargers. We have experienced significant delays in these upgrades, which have in turn caused delays in the construction of the chargers pursuant to the GM Agreement. We expect utility-related delays to continue as the industry continues to adapt to the requirements of high-powered charger installation. If these delays continue or worsen, we may not meet the charger-installation milestones under the GM Agreement or its other contractual commitments under agreements with other third parties. See Part I, Item IA,“Risk Factors — Risks Related to Our Business — We are* required to install a substantial number of chargers pursuant to theGM Agreement. Ifwedo not meet our obligations under this agreement,wemay not be entitled to payments fromGM and may be required to pay liquidated damages, which may be significant*” and Part I, Item IA,“Risk Factors — Risks Related to Our Business — We are required to install a substantial number of charger stalls pursuant to the Pilot Infrastructure Agreement. If we do not meet our obligations under this agreement, we may not be entitled to payments from the Pilot Company and may be required to pay liquidated damages, which may be significant.”
Current wording
related matters and typically requires local utility cooperation in design and interconnection request approval and commissioning, as well as various local and other governmental approvals and permits that vary by jurisdiction. In addition, building codes, accessibility requirements, utility interconnect specifications, review, approval or study lead time or regulations may hinder EV charger installation and construction because they end up costing the developer or installer more in order to meet thecode requirements. In addition, increased demand for the components necessary to install and construct charging stations could lead to higher installed costs. Meaningful delays or cost overruns caused by our vendor supply chains, contractors, utility upgrades scope and delays, or inability of local utilities and approving agencies to cope with heightened levels of activity, may impact ourability to satisfy the requirements under the Build Schedule and our other contractual commitments, and may impact revenue recognition in certain cases and/or impact our relationships, any of which could impact our business and profitability, pace of growth and prospects. For example, the installation of charger stalls under the GM Agreement has required significant utility upgrades to accommodate the higher capacity chargers. We have experienced significant delays in these upgrades, which have in turn caused delays in the construction of the chargers pursuant to the GM Agreement. We expect utility-related delays to continue as the industry continues to adapt to the requirements of high-powered charger installation. If these delays continue or worsen, we may not meet the charger-installation milestones under the GM Agreement or its other contractual commitments under agreements with other third parties. See Part I, Item IA,“Risk Factors — Risks Related to Our Business — We are required to install a substantial number of chargers pursuant to theGM Agreement. If we do not meet our obligations under this agreement, we may not be entitled to payments fromGM and may be required to pay liquidated damages” and Part I, Item IA,“Risk Factors — Risks Related to Our Business — We are required to install a substantial number of charger stalls pursuant to the Pilot Infrastructure Agreement. If we do not meet our obligations under this agreement, we may not be entitled to payments from the Pilot Company and may be required to pay liquidated damages, which may be significant.”
Previous wording
In addition, our network expansion plan relies on our site development efforts and our business is exposed to risks associated with receiving site control and access necessary for the construction of the charging station and operation of the charging equipment, electrical interconnection and power supply at identified locations sufficient to host chargers on a timely basis. We generally do not own the land at the charging sites and rely on site licenses with Site Hosts that convey the right to build, own and operate the charging equipment on the site. We may not be able to renew the site licenses or
Current wording
In addition, our network expansion plan relies on our site development efforts and our business is exposed to risks associated with receiving site control and access necessary for the construction of the charging station and operation of the charging equipment, electrical interconnection and power supply at identified locations sufficient tohost chargers on a timely basis. We do not own the land at the charging sites and rely on site licenses with Site Hosts that convey the right to build, own and operate the charging equipment on the site. We may not be able to renew the site licenses or retain site control. The process of establishing or extending site control and access could take longer or become more competitive. As the EV market grows, competition for premium sites may intensify, the power distribution grid may require upgrading, and electrical interconnection with local utilities may become more competitive, all of which may
Previous wording
retain site control. The process of establishing or extending site control and access could take longer or become more competitive. As the EV market grows, competition for premium sites may intensify, the power distribution grid may require upgrading, and electrical interconnection with local utilities may become more competitive, all of which may lead to delays in construction and/or commissioning or prevent us from completing construction. As a result, we have in the past experienced, and may in the future experience, Site Hosts terminating site development agreements for which we were unable to recover termination fees and construction costs incurred, and we may be exposed to increased interconnection costs and utility fees, as well as delays, which may slow the pace of our network expansion.
Current wording
lead to delays in construction and/or commissioning or prevent us from completing construction. As a result, we have in the past experienced, and may in the future experience, Site Hosts terminating site development agreements for which we were unable to recover termination fees and construction costs incurred, and we may be exposed to increased interconnection costs and utility fees, as well as delays, which may slow the pace of our network expansion.
Previous wording
The conflict between Russia and Ukraine and an escalation of tensions and conflict in Israel and the broader Middle East region could lead to disruption, instability and volatility in global markets and industries that could negatively impact our supply chain. The U.S. government and other governments have already imposed severe economic sanctions and export controls against Russia and Russian interests and may impose additional economic sanctions and trade controls. The impact of these measures, as well as potential responses to them by Russia, could adversely affect our supply chain, which, in turn, could materially and adversely affect our business, financial condition and results of operations.
Current wording
The conflict in Ukraine and tensions in the Middle East region continue to result in disruption, instability and volatility in global markets and industries that negatively impact our supply chain. The U.S. government and other governments have already imposed severe economic sanctions and export controls against Russia and Russian interests and may impose additional economic sanctions and trade controls. The impact of these measures, as well as potential responses to them by Russia, could adversely affect our supply chain, which, in turn, could materially and adversely affect our business, financial condition and results of operations.
Previous wording
We may need to raise additional capital in the future to fund our operations, further scale our business and expand our charging network. We may raise additional funds through the issuance of equity, equity-related or debt securities, through obtaining credit from government or financial institutions or through grant funding. We cannot be certain that additional funds or incentives will be available on favorable terms when required, or at all, or that we will be able to capture expected grant funding under various existing and new state and local programs in the future. Interest rates have been elevated in recent periods, and, while they have recently fallen, if that trend does not continue, the cost of capital could remain high or increase in future periods. Any future indebtedness we incur would be effectively subordinated to the DOE Loan to the extent of the collateral securing the DOE Loan and would be structurally subordinated to the existing and future indebtedness of our subsidiaries, including the DOE Loan. Additionally, the terms of the DOE Loan impose limitations on our ability to raise funds insofar as restrictive covenants relating to the Borrower’s ability to incur indebtedness and pledge assets. See Part I, Item IA,“Risk Factors — Risks Related to the DOE Loan — The restrictions imposed on the Borrower under the DOE Loan limit our flexibility in operating the business of the Borrower and could limit our flexibility in operating our business.”
Current wording
We may need to raise additional capital in the future to fund our operations, further scale our business and expand our charging network. We may raise additional funds through the issuance of equity, equity-related or debt securities, through obtaining credit from government or financial institutions or through grant funding. We cannot be certain that additional funds or incentives will be available on favorable terms when required, or at all, or that we will be able to capture expected grant funding under various existing and new state and local programs in the future. Interest rates have been elevated in recent periods, and, while they have recently fallen, if that trend does not continue, the cost of capital could remain high or increase in future periods. Any future indebtedness we incur would be effectively subordinated to the DOE Loan and the Credit Agreement to the extent of the collateral securing the DOE Loan and the Credit Agreement, and would be structurally subordinated to the existing and future indebtedness of our subsidiaries, including the DOE Loan and the Credit Agreement. Additionally, the terms of the DOE Loan impose limitations on our ability to raise funds insofar as restrictive covenants relating to Swift Borrower’s ability to incur indebtedness and pledge assets. See Part I, Item IA,“Risk Factors — Risks Related to the DOE Loan — The restrictions imposed on Swift Borrower under the DOE Loan limit our flexibility in operating the business of Swift Borrower and could limit our flexibility in operating our business.”
Previous wording
For example, we are dependent on the interoperability of our mobile applications with popular mobile operating systems that we do not control, such as Google’s Android and Apple’s iOS, and any changes in such systems that degrade our products’ functionality or give preferential treatment to competitive products could adversely affect the usage of our applications on mobile devices. Additionally, in order to deliver high quality mobile products, it is important that our products work well with a range of mobile technologies, systems, networks and standards that we do not control. We may not be successful in developing or maintaining relationships with key participants in these industries or in developing products that operate effectively with these technologies, systems, networks or standards.
Current wording
For example, we are dependent on the interoperability of our mobile applications with popular mobile operating systems thatwe do not control, such as Google’s Android and Apple’s iOS, and any changes in such systems that degrade our products’ functionality or give preferential treatment to competitive products could adversely affect the usage of our applications on mobile devices. Additionally, in order to deliver high quality mobile products, it is important that our products work well with a range of mobile technologies, systems, networks and standards thatwe do not control. We may not be successful in developing or maintaining relationships with key participants in these industries or in developing products that operate effectively with these technologies, systems, networks or standards.
Previous wording
In addition, a significant portion of our software platform depends on our partnership with Driivz, an EV charging management platform. If for any reason Driivz is unable to effectively support our software platform, our business could be adversely impacted. For example, Driivz is headquartered in Israel, and any escalation of tensions or conflict in or involving Israel could lead to disruptions in the services provided by Driivz to us, which could adversely impact our business. Furthermore, if for any reason we are no longer able to maintain our partnership with Driivz, we may face a material challenge in efficiently transitioning our software offering.
Current wording
In addition, a significant portion of our software platform depends on our partnership with Driivz, an EV charging management platform. If for any reason Driivz is unable to effectively support our software platform, our business could be adversely impacted. For example, if for any reasonwe are no longer able to maintain our partnership with Driivz, we may face a material challenge in efficiently transitioning our software offering.
Previous wording
In addition, we currently serve customers from third-party data center facilities operated by Amazon Web Services and Google, as well as others. All of our services are housed in third-party data centers operated in the U.S., and we employ geographically distributed, redundant back-up data centers for all services. Any outage or failure of such data centers could negatively affect our product connectivity and performance. Our primary environments are operated by Google and Amazon, and any interruptions of these primary and backup data centers could negatively affect our product connectivity and performance. Furthermore, we depend on connectivity from our charging stations to our data centers through cellular service and virtual private networking providers, such as AT&T and Verizon. Any incident affecting a data center facility’s or cellular and/or virtual private networking services provider’s infrastructure or operations, whether caused by fire, flood, storm, earthquake, power loss, telecommunications failures, breach of security protocols, computer viruses and disabling devices, failure of access control mechanisms, natural disasters, war, criminal act, military actions, terrorist attacks and other similar events could negatively affect the use, functionality or availability of our services.
Current wording
In addition, we currently serve customers from third-party data center facilities operated by Amazon Web Services and Google, as well as others. All of our services are housed in third-party data centers operated in the U.S., andwe employ geographically distributed, redundant back-up data centers for all services. Any outage or failure of such data centers could negatively affect our product connectivity and performance. Our primary environments are operated by Google and Amazon, and any interruptions of these primary and backup data centers could negatively affect our product connectivity and performance. Furthermore, we depend on connectivity from our charging stations to our data centers through cellular service and virtual private networking providers, such as AT&T and Verizon. Any incident affecting a data center facility’s or cellular and/or virtual private networking services provider’s infrastructure or operations, whether caused by fire, flood, storm, earthquake, power loss, telecommunications failures, breach of security protocols, computer viruses and disabling devices, failure of access control mechanisms, natural disasters, war, criminal act, military actions, terrorist attacks and other similar events could negatively affect the use, functionality or availability of our services.
Previous wording
If we are unable to attract and retain key employees and hire qualified management, technical, engineering, financial, legal, sales, marketing and business development personnel, our ability to compete and successfully grow our business and customer base could be harmed.
Current wording
Ifwe are unable to attract and retain key employees and hire qualified management, technical, engineering, financial, legal, sales, marketing and business development personnel, our ability to compete and successfully grow our business and customer base could be harmed.
Previous wording
Many of our facilities are located in California, an active earthquake zone, and Florida and Texas, areas susceptible to hurricanes. Additionally, we have significant operations in a number of areas, including Los Angeles and San Francisco, that are projected to be vulnerable to future water scarcity and sea level rise due to climate change. The occurrence of natural disasters such as an earthquake, hurricane, drought, flood, fire, localized extended outages of critical utilities or transportation systems, or any critical resource shortages could cause a significant interruption in our business, damage or destroy our facilities or inventory and cause us to incur significant costs, any of which could harm our business, financial condition and results of operations. Climate change may also result in various physical risks, such as the increased frequency or intensity of extreme weather events or changes in meteorological and hydrological patterns that could adversely impact our business. Such physical risks may result in damage to our facilities or otherwise adversely impact operations. The insurance we maintain against fires, earthquakes, hurricanes and other disasters and damage may not be adequate to cover losses in any particular case.
Current wording
Many of our facilities are located in California, an active earthquake zone, and Florida and Texas, areas susceptible to hurricanes. Additionally, we have significant operations in a number of areas, including Los Angeles and San Francisco, that are projected to be vulnerable to future water scarcity and sea level rise due to climate change. The occurrence of natural disasters such as an earthquake, hurricane, drought, flood, fire, localized extended outages of critical utilities or transportation systems, or any critical resource shortages could cause a significant interruption in our business, damage or destroy our facilities or inventory and cause us to incur significant costs, any of which could harm our business, financial condition and results of operations. Climate change mayalso result in various physical risks, such as the increased frequency or intensity of extreme weather events or changes in meteorological and hydrological patterns that could adversely impact our business. Such physical risks may result in damage to our facilities or otherwise adversely impact operations. The insurancewe maintain against fires, earthquakes, hurricanes and other disasters and damage may not be adequate to cover losses in any particular case.
Previous wording
In addition, rolling public safety power shut offs in California or other states can affect throughput and/or user acceptance of EVs, as charging may be unavailable at the desired times, or at all during these events. These shut offs could also affect the ability of fleet operators to charge their EVs, which, for example, could adversely affect transportation schedules or any service level agreements to which either us or the fleet operator may be a party. Additionally, extended patterns of extreme cold weather have caused, and may in the future cause, owners of EVs to experience reduced charging speeds and driving ranges. If any of these events occur and/or persist, the demand for EVs could decline, which would result in reduced demand for charging.
Current wording
In addition, rolling public safety power shut offs in California or other states can affect throughput and/or user acceptance of EVs, as charging may be unavailable at the desired times, or at all during these events. These shut offs could also affect the ability of fleet operators to charge their EVs, which, for example, could adversely affect transportation schedules or any service level agreements to which eitherus or the fleet operator may be a party. Additionally, extended patterns of extreme cold weather have caused, and may in the future cause, owners of EVs to
Previous wording
Our charging stations are often located in areas that are publicly accessible and may be exposed to vandalism or misuse by customers or other individuals, which would increase our replacement and maintenance costs.
Current wording
Our industry and business are subject to risks associated with consumer fraud and misuse, including at our charging stations that are often located in areas that are publicly accessible and may be exposed to vandalism or misuse by customers or other individuals, which would increase our replacement and maintenance costs.
Previous wording
Our public chargers may be exposed to vandalism or misuse by customers and other individuals, increasing wear and tear of the charging equipment. Such damage could shorten the usable lifespan of the chargers and require us to increase our spending on replacement, maintenance and insurance costs and could result in Site Hosts reconsidering the value of hosting our charging stations at their sites. Damaged charging stations may also not be able to be used while they await repair and any disruption to the availability of spare parts may extend maintenance windows, each of which may negatively impact our revenue. In addition, the cost of any such damage may not be covered by our insurance in full or at all and, in the event of repeated damage to our charging equipment, our insurance premiums and deductibles could continue to increase and we could be subject to additional insurance costs or may not be able to obtain insurance at all, any of which could have an adverse effect on our business.
Current wording
Our public chargers may be exposed to vandalism or misuse by customers and other individuals, increasing wear and tear of the charging equipment. Such damage could shorten the usable lifespan of the chargers and require us to increase our spending on replacement, maintenance and insurance costs and could result in Site Hosts reconsidering the value of hosting our charging stations at their sites. Damaged charging stations may also not be able to be used while they await repair and any disruption to the availability of spare parts may extend maintenance windows, each of which may negatively impact our revenue. In addition, the cost of any such damage may not be covered by our insurance in full or at all and, in the event of repeated damage to our charging equipment, our insurance premiums and deductibles could continue to increase and we could be subject to additional insurance costs or may not be able to obtain insurance at all, any of which could have an adverse effect on our business. As a consumer business, we are also subject to risks associated with credit or debit card fraud and other payment processing related issues.
Previous wording
As part of our business strategy, we market the electricity provided from our charging stations as 100% matched with purchases of RECs. We purchase various RECs in order to qualify the electricity that we distribute through our charging stations as renewable. Several states have passed renewable energy portfolio standards, which set a minimum percentage of energy that must be generated from renewable sources. These standards may require utilities or load serving entities to acquire RECs annually in order to demonstrate their compliance. Other regulations may also impact the supply of and demand for, such RECs. While higher renewable energy portfolio standards may also increase the amount of renewable energy available, we cannot predict the impact such regulations may have on the price or availability of RECs. If we are unable to purchase a sufficient number of RECs, we may be unable to achieve this objective, which may negatively impact our reputation in the marketplace. If the cost of RECs increases, we may be unable to fully pass the higher cost of RECs through to our customers and increases in the price of RECs may decrease our results of operations.
Current wording
As part of our business strategy, we market the electricity provided from our charging stations as either 100% matched with purchases of RECs or comprised of renewable energy procured from the grid. We purchase various RECs in order to qualify the electricity thatwe distribute through our charging stations as renewable. Several states have passed renewable energy portfolio standards, which set a minimum percentage of energy that must be generated from renewable sources. These standards may require utilities or load serving entities to acquire RECs annually in order to demonstrate their compliance. Other regulations may also impact the supply of and demand for, such RECs. While higher renewable energy portfolio standards may also increase the amount of renewable energy available, we cannot predict the impact such regulations may have on the price or availability of RECs. Ifwe are unable to purchase a sufficient number of RECs, we may be unable to achieve this objective, which may negatively impact our reputation in the marketplace. If the cost of RECs increases, it may negatively impact our results of operations.
Previous wording
Once our charging stations are installed, Site Hosts and drivers rely on us to provide maintenance services to resolve any issues that might arise in the future. Rapid and high-quality customer and equipment support is important so drivers can receive reliable charging for their EVs. The importance of high-quality customer and equipment support will increase as we seek to expand our business and pursue new customers and geographies. If we do not quickly resolve issues and provide effective support, our ability to retain customers or sell additional products and services to existing customers could suffer, and our brand and reputation could be harmed. We have limited experience with certain of our charging equipment. While we conduct extensive testing on all new equipment prior to deployment, our assumptions regarding the durability and reliability of our charging equipment could prove to be materially different from the actual performance of such equipment, causing us to incur substantial expense to repair or replace defective equipment in the future. Any widespread or persistent equipment failures could damage our market reputation, cause our sales and charging revenue to decline, require us to repair or replace the defective equipment, and increase our maintenance costs, any of which could have a material adverse effect on our business and results of operations.
Current wording
can receive reliable charging for their EVs. The importance of high-quality customer and equipment support will increase aswe seek to expand our business and pursue new customers and geographies. Ifwe do not quickly resolve issues and provide effective support, our ability to retain customers or sell additional products and services to existing customers could suffer, and our brand and reputation could be harmed. We have limited experience with certain of our charging equipment. While we conduct extensive testing on all new equipment prior to deployment, our assumptions regarding the durability and reliability of our charging equipment could prove to be materially different from the actual performance of such equipment, causing us to incur substantial expense to repair or replace defective equipment in the future. Any widespread or persistent equipment failures could damage our market reputation, cause our sales and charging revenue to decline, require us to repair or replace the defective equipment, and increase our maintenance costs, any of which could have a material adverse effect on our business and results of operations.
Previous wording
disclosure, alteration, destruction, misuse or theft of data, including confidential, proprietary or personal information. Computer malware, viruses, ransomware, hacking, phishing attacks and denial-of-service attacks against online networks have become more prevalent and may occur on our systems or the systems of our vendors, suppliers or service providers and other third parties. Our business may be subject to heightened risks of cyber intrusion as nation-state hackers and other hackers use ransomware attacks seeking to disable critical infrastructure and extort companies for ransom payments. Cybersecurity organizations in many countries have published warnings of increased cybersecurity threats to U.S. businesses, and external events, like the conflict between Russia and Ukraine or conflicts in the Middle East, may increase the likelihood of cybersecurity attacks, particularly directed at energy, fueling or infrastructure service providers.
Current wording
From time to time, we have experienced cyber-attacks on our information technology infrastructure and systems. While we believe such attacks have been unsuccessful against us to-date, computer malware, viruses, physical or electronic break-ins and similar disruptions could lead to interruptions and delays in our services and operations and loss, access, disclosure, alteration, destruction, misuse or theft of data, including confidential, proprietary or personal information. Computer malware, viruses, ransomware, hacking, phishing attacks and denial-of-service attacks against online networks have become more prevalent and may occur on our systems or the systems of our vendors, suppliers or service providers and other third parties. Our business may be subject to heightened risks of cyber intrusion as nation-state hackers and other hackers use ransomware attacks seeking to disable critical infrastructure and extort companies for ransom payments. Cybersecurity organizations in many countries have published warnings of increased cybersecurity threats to U.S. businesses, and external events, like the conflict in Ukraine or tensions in the Middle East, may increase the likelihood of cybersecurity attacks, particularly directed at energy, fueling or infrastructure service providers.
Showing the first 40 of 100 pairs. Open the source sections for the rest.
Rearranged current paragraphs (17)
Current report — wording carried from elsewhere
for EVs develops more slowly than expected, or if demand for EVs develops more slowly than expected or decreases, our growth would be reduced, and our business, prospects, financial conditions and results of operations would be harmed. The market for EVs, and ultimately EV charging, could be affected by numerous factors, such as:
Current report — wording carried from elsewhere
restrictions that may impact the ability of us and our competitors to take advantage of such initiatives, cannot be known with any certainty at this time, and we may not reap any or all of the expected benefits of such initiatives.
Current report — wording carried from elsewhere
rent, have no access to home charging, or park their EVs on the street, potentially reducing our serviceable markets. Retailers, utilities or other Site Hosts or commercial, municipal and federal fleet businesses may opt to become owners and operators of public or private EV fast charging equipment and purchase that equipment and associated management software directly from vendors in the marketplace.
Current report — wording carried from elsewhere
equipment, some of our charging stations may become obsolete and we may be required to incur additional costs to replace them. The occurrence of any of the foregoing may materially and adversely affect our business, financial condition and results of operations.
Current report — wording carried from elsewhere
entering into agreements for similar programs on terms more favorable than the terms afforded to GM for a limited period of time. See Part I, Item 1, “Business — Customers, Partnerships and Strategic Relationships.”
Current report — wording carried from elsewhere
Charger installation and construction is typically performed by third-party contractors managed by us. The installation and construction of charging stations at a particular site is generally subject to oversight and regulation in accordance with state and local laws and ordinances relating to building codes, safety, environmental protection and
Current report — wording carried from elsewhere
experience reduced charging speeds and driving ranges. If any of these events occur and/or persist, the demand for EVs could decline, which would result in reduced demand for charging.
Current report — wording carried from elsewhere
Once our charging stations are installed, Site Hosts and drivers rely on us to provide maintenance services to resolve any issues that might arise in the future. Rapid and high-quality customer and equipment support is important so drivers
Current report — wording carried from elsewhere
with respect to our third-party vendors. Though it is difficult to determine what, if any, harm may directly result from any specific interruption or attack, an inability to maintain performance, reliability, security and availability of systems and technical infrastructure may, in addition to other losses, harm our reputation, brand and ability to attract customers.
Current report — wording carried from elsewhere
We have in the past, and may in the future, acquire additional assets, products, technologies or businesses that are complementary to our existing business and strategic direction. The process of identifying and consummating
Current report — wording carried from elsewhere
Separate federal guidance on Buy America requirements applicable to the NEVI Program, which was established by the Infrastructure Investment and Jobs Act, requires immediate domestic assembly and U.S. steel requirements for chargers to qualify for funding under the NEVI Program, with higher domestic content percentages required in 2024. In February 2026, the current administration also proposed increasing domestic content percentages, but has not finalized
Current report — wording carried from elsewhere
We may be subject to claims that persons were injured or purported to be injured, or that personal property has been damaged, including due to latent defects, errors, bugs, malfunctions, or excessive wear in connection with the use of our charging stations. Any insurance that we carry may not be sufficient or it may not apply to all situations. Similarly,
Current report — wording carried from elsewhere
Additionally, we and EVgo OpCo may be subject to significant income, withholding and other tax obligations in the U.S. and may become subject to taxation in numerous additional state, local and non-U.S. jurisdictions with respect to income, operations and subsidiaries related to those jurisdictions. Our and EVgo OpCo’s after-tax profitability and financial results could be subject to volatility or be affected by numerous factors, including (a) the availability of tax deductions, credits, exemptions, refunds and other benefits to reduce tax liabilities, (b) changes in the valuation of deferred tax assets and liabilities, if any, (c) the expected timing and amount of the release of any tax valuation allowances, (d) the tax treatment of share-based compensation, (e) changes in the relative amount of earnings subject
Current report — wording carried from elsewhere
other stockholders. For additional information, see Part II, Item 8,* “Consolidated Financial Statements and Supplementary Data — Note 2 — Summary of Significant Accounting Policies — Tax Receivable Agreement Liability.”*
Current report — wording carried from elsewhere
in public sentiment, which has resulted in dynamics that increase the risk of reputational damage, boycotts and shifts in consumer behavior, and we may not be able to align our practices with such evolving expectations within the timeframes expected by stakeholders or without incurring significant costs to our business and reputation. If we do not successfully manage ESG-related expectations across stakeholders, it could erode stakeholder trust, impact our reputation, our ability to attract or retain employees, and our attractiveness as an investment, supplier or business partner, and materially and adversely affect our business, financial conditionand results of operations.
Current report — wording carried from elsewhere
of the holders of at least 75% of the then outstanding voting stock after LS Power owns less than 30% of our voting capital stock, (vi) providing forour Board of Directors to be divided into three classes of directors, (vii) providing that the amended and restated bylaws can be amended byour Board of Directors, (viii) limitations on the ability of stockholders to call special meetings, (ix) limitations on the ability of stockholders to act by written consent and (x) renouncing any reasonable expectancy interest that we have in, or right to be offered an opportunity to participate in, any corporate or business opportunities that are from time to time presented to LS Power, directors affiliated with LS Power, their respective affiliates and non-employee directors.
Current report — wording carried from elsewhere
As described in our consolidated financial statements included in this Annual Report, we are accounting for our issued and outstanding Warrants as a warrant liability and recording that liability at fair value upon issuance and
Rearranged previous paragraphs (14)
Previous report — wording carried elsewhere
protect our intellectual property or achieve and maintain compliance with, or realize available benefits under, tax laws and other applicable regulations. These risks may also result in data security incidents that may interrupt business operations and allow third parties to obtain unauthorized access to business information or misappropriate funds. We may also face risks to the extent such third parties infiltrate the information technology infrastructure of our contractors.
Previous report — wording carried elsewhere
*Business —*Disruptions in our supply chain could materially and adversely affect our business, financial condition and results of operations.” Thus, our business, financial condition and results of operations could be materially and adversely affected if one or more of our current or future vendors is impacted by any interruption at a particular location or is acquired or impacted by liquidity issues.
Previous report — wording carried elsewhere
The success of our business depends on our ability to develop and maintain relationships with OEMs, such as GM, Honda, Nissan, and others. These relationships help us access new customers and build brand awareness through co-marketing. We may also benefit from promotional programs sponsored by OEMs, such as prepaid charging credits. In
Previous report — wording carried elsewhere
We may not meet the charger stall-installation milestones under the GM Agreement in the future, particularly as a consequence of delays in permitting, commissioning and utility interconnection, as well as delays related to industry and regulatory adaptation to the requirements of high-powered charger installation including slower than expected third-party approvals of certain site acquisitions and site plans by utilities and land owners, and supply chain issues. As of February
Previous report — wording carried elsewhere
From time to time, we have experienced cyber-attacks on our information technology infrastructure and systems. While we believe such attacks have been unsuccessful against us to-date, computer malware, viruses, physical or electronic break-ins and similar disruptions could lead to interruptions and delays in our services and operations and loss, access,
Previous report — wording carried elsewhere
Our obligations under the DOE Loan are secured on a first priority basis (subject to customary exceptions and permitted liens) by, and among other things, certain assets of the Borrower, which include the DC Stalls contributed to the Borrower by us pursuant to the terms of the DOE Loan, and the equity interests of the Borrower. Because a substantial portion of our consolidated assets secure the DOE Loan, we may not have substantial remaining assets available to secure
Previous report — wording carried elsewhere
Regulatory initiatives that require an increase in the mileage capabilities of cars and consumption of renewable transportation fuels, such as ethanol and biodiesel, have helped increase consumer acceptance of EVs and other alternative vehicles. However, the EV fueling model is different from gasoline and other fuel models, requiring behavior changes and education of businesses, consumers, regulatory bodies, local utilities and other stakeholders. Further developments in and improvements in the affordability of, alternative technologies, such as renewable diesel, biodiesel, ethanol, hydrogen fuel
Previous report — wording carried elsewhere
federal and state level may create uncertainty for the EV sector, which may have a material and adverse effect on our business, financial condition and results of operations.”
Previous report — wording carried elsewhere
being subject to tax in multiple state, local or non-U.S. jurisdictions. Factors that could materially affect our and EVgo OpCo’s future effective tax rates include but are not limited to: (a) changes in tax laws or the regulatory environment, (b) changes in accounting and tax standards or practices, (c) changes in the composition of operating income by tax jurisdiction and (d) pre-tax operating results of our business.
Previous report — wording carried elsewhere
consumers and our business, financial condition and results of operations. Although we are closely monitoring these developments to adapt to changing trade policies, there can be no assurances that we will be successful in mitigating any negative impacts arising therefrom.
Previous report — wording carried elsewhere
of such EVgo OpCo Units that will be available to the Company Group as a result of its acquisition of such EVgo OpCo Units) and certain benefits attributable to imputed interest. The Company Group will retain the benefit of the remaining net cash savings, if any.
Previous report — wording carried elsewhere
Risks Related to Legal Matters and Regulations
Previous report — wording carried elsewhere
comply with new regulations, which could subject us to penalties and enforcement actions. Additionally, we could be regulated as a retail electric service provider in the future.
Previous report — wording carried elsewhere
them to be more expensive for us to pursue. As a result, our renunciation of our interest and expectancy in any business opportunity that may be from time to time presented to an Identified Person could adversely impact our business or prospects if attractive business opportunities are procured by such parties for their own benefit rather than for ours.