EX-99.1 · Mining

Mining

The mining operation is a conventional shovel and truck open pit mine feeding a 60,000 tpd (permitted throughput on an annualised basis) processing plant. The planned mine life is currently just over 11 years (2025 – 2036). The pit has been planned as a series of seven discrete pushbacks and scheduled to maximize the production of ore. This plan has an overall LOM waste:ore ratio of 0.9:1.0. The mining sequence has been developed to allow for provision of suitable waste material for annual TSF construction requirements.

The mine fleet comprises four blast hole drills, one pre-shear drill, two rope shovels, one hydraulic excavator, two rubber-tired front-end loaders, fifteen haul trucks and various other dozers, loaders, graders, and excavators. A fleet of articulated trucks are used in dam construction and project activities.

Centerra Gold Inc.
2024 Annual Information FormPage 36

Mount Milligan Mill – Water Management

On December 27, 2017, we announced that due to a lack of sufficient water resources, mill processing operations at the Mount Milligan Mine in British Columbia, Canada had been temporarily suspended. Since that time, the Company has worked with B.C. regulators, its Indigenous partners and other stakeholders to amend Mount Milligan’s permits and environmental assessment certificates to ensure sufficient water access for the mine.

In January 2022, the Company obtained an amendment to its provincial environmental assessment certificate that has authorized a long-term water supply for the Mount Milligan Mine.

As at December 31, 2024, the Mount Milligan Mine had sufficient water inventory to maintain operations and does not expect a curtailment in production in 2025 as there is expected to be sufficient water in the tailings storage facility to run at full capacity throughout the year. However, during years of persistent dry conditions, there is a risk that Mount Milligan’s operations may need to be curtailed in future for lack of sufficient water.