TERAWULF INC.

For the period ended Dec 31, 2025. Filed Feb 27, 2026.

View on SEC.gov

About this filing

A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.

FY2025 · Filed Feb 27, 2026

WULF$11.37+12.8%Stored close · as of Nov 6, 2026

What changed in Management’s Discussion and Analysis?

Read the current filing

Previous report: 10-K

Period ended 2024-12-31; filed 2025-03-03.

0001083301-25-000018

ITEM 7. Management’s Discussion and Analysis of Financial Condition and Results of Operations

Current report: 10-K

Period ended 2025-12-31; filed 2026-02-27.

0001083301-26-000031

ITEM 7. Management’s Discussion and Analysis of Financial Condition and Results of Operations

The baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.

Compared 113 previous paragraphs and 142 current paragraphs.

37 unchanged; 39 reworded; 66 added; 37 removed; 0 previous and 0 current paragraphs rearranged.

Tables are not compared: 9 previous and 10 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.

A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.

Added paragraphs (66)

Current report

We are a vertically integrated owner, developer, and operator of digital infrastructure assets in the United States, purpose-built to support HPC workloads, including AI, machine learning, and advanced cloud applications.

Current report

The Company has undergone a deliberate strategic transition toward HPC hosting as its primary business. While TeraWulf historically operated bitcoin mining facilities and leveraged flexible compute loads to support early infrastructure development, going forward the Company’s capital allocation, development activities, and operating focus are centered on HPC data center development, long-term hosting arrangements, and infrastructure supporting AI-driven compute workloads.

Current report

Our strategy is grounded in controlling infrastructure at utility scale and pairing compute-optimized facilities with reliable, long-duration power resources. By controlling land use through ownership or long-term ground leases, together with interconnection rights, electrical and cooling infrastructure, and, where appropriate, on-site generation, the Company delivers resilient, cost-efficient capacity to hyperscale and enterprise customers under multi-year hosting arrangements.

Current report

The Company’s platform is differentiated by long-term control of utility-scale infrastructure, deep in-house power and grid expertise, and a scalable development model supported by long-term, credit-enhanced customer contracts.

Current report

Management’s execution of the Company’s strategy is focused on converting advantaged infrastructure positions into long-dated, contracted HPC capacity. This execution model emphasizes vertical integration, long-duration customer contracts supported by credit enhancement, and phased development aligned with customer deployment schedules and power availability.

Current report

A core element of this approach is infrastructure control. By retaining control over land use, interconnection rights, electrical and cooling systems, and on-site generation where appropriate, the Company is able to manage development risk, optimize capital deployment, and maintain operational oversight throughout the lifecycle of its facilities. Management believes this approach reduces execution risk relative to third-party development models and supports infrastructure-style returns.

Current report

The Company’s contracting strategy prioritizes multi-year hosting arrangements with credit-supported counterparties. These arrangements provide long-dated revenue visibility, support project-level financing, and reduce cash flow volatility as the platform scales. Credit enhancement associated with certain customer contracts has been a key factor in accelerating development timelines and enabling third-party financing.

Current report

Each campus is designed for modular, multi-phase expansion. Initial phases deliver near-term contracted capacity, while subsequent phases are developed in line with customer demand and power availability. Management believes this phased approach allows the Company to scale efficiently while maintaining capital discipline.

Current report

Consistent with this strategy, the Company has deliberately shifted capital allocation away from new bitcoin mining investments and toward HPC data center development. While legacy mining operations continue to utilize existing infrastructure, management does not intend to deploy incremental growth capital to mining activities.

Current report

On May 21, 2025 (the “Acquisition Date”), the Company acquired 100% of the membership interests in Beowulf Electricity & Data LLC, Beowulf E&D (NY) LLC and Beowulf E&D (MD) LLC (collectively, “Beowulf E&D”). Additional detail regarding the consideration paid and contingent consideration associated with the Beowulf E&D acquisition is included in Note 3 to the consolidated financial statements.

Current report

The acquisition materially expanded the Company’s internal capabilities across power infrastructure development, site operations, engineering, and project execution. Approximately 94 employees transitioned to the Company as part of the transaction. Management believes this acquisition strengthened operational integration and execution capability as the Company scales its HPC platform.

Current report

On August 12, 2025, the Company entered into a long-term ground lease for approximately 183 acres in Lansing, New York. Upon completion of permitting and site development, the Cayuga Site has the potential for up to 400 MW of gross capacity, supporting approximately 320 MW of critical IT load. The Cayuga Site provides an additional anchor location with existing interconnection and supporting infrastructure and represents a key component of the Company’s forward development pipeline.

Current report

On October 27, 2025, the Company entered into an amended and restated limited liability company agreement governing the Abernathy Joint Venture. The Company holds a 50.1% equity interest in the joint venture. The Abernathy HPC Campus represents the extension of the Company’s commercial relationship with Fluidstack, supported by the same credit enhancement framework, to an additional site.

Current report

The Abernathy HPC Campus is designed for 168 MW of critical IT load, representing the full build-out of the site. The campus is 100% pre-leased to Fluidstack under a 25-year data center sublease with contractual rent escalators and options for term contraction. Lease obligations are supported by investment-grade credit enhancement provided by Google, materially strengthening the credit profile of the contracted revenues and facilitating third-party debt financing.

Current report

Management believes the Abernathy Joint Venture reflects the extension of the Company’s commercial relationship with Fluidstack, supported by continued credit enhancement from Google, to an additional site.

Current report

The Company’s primary operating campus is the Lake Mariner Data Campus, located in Barker, New York on the site of a former coal-fired power plant that was retired and repurposed into a modern digital infrastructure campus. The site benefits from substantial existing transmission infrastructure and is designed for scalable expansion.

Current report

As of December 31, 2025 the Lake Mariner Data Campus operated 245 MW of legacy bitcoin mining capacity and had 18 critical IT MW of HPC capacity. The Company commenced HPC leasing operations at the Lake Mariner Data Campus in July 2025 and is executing a phased expansion to support additional contracted HPC deployments.

Current report

The campus is capable of scaling to approximately 500 MW of gross capacity in the near term, with potential expansion to approximately 750 MW subject to additional approvals from the NYISO. Power for the Lake Mariner Data Campus is sourced from the NYISO Zone A grid, with 90 MW allocated under a long-term arrangement with the New York Power Authority.

Current report

The Company operates the Lake Mariner Data Campus through La Lupa and Akela. Together, the Company’s contracted HPC platform represents 522 MW of critical IT load, including the Company’s 50.1% attributable share of the Abernathy HPC Campus. As of December 31, 2025, the Company had energized 18 critical IT MW of HPC capacity and remains on track to deliver additional contracted capacity in phases aligned with customer deployment schedules.

Current report

The development of the Abernathy HPC Campus through the Abernathy Joint Venture provides the Company with meaningful regional diversification. By expanding its HPC platform beyond New York into the Southwest Power Pool region, the Company reduces concentration risk related to power markets, regulatory frameworks, weather events, construction timelines, and operational disruptions.

Current report

Geographic diversification also helps mitigate the potential impact of localized physical security incidents, natural disasters, and certain cyber events by distributing infrastructure across multiple regions and operating environments. Management believes this diversification enhances overall platform resilience, supports customer deployment flexibility, and strengthens the Company’s ability to maintain continuity of operations across its portfolio.

Current report

The Company’s power strategy emphasizes reliability, efficiency, and responsible integration with regional electric grids. The Company’s development and operations team brings deep experience in power generation, transmission, interconnection, and large-scale energy infrastructure, which informs site selection, facility design, and operational execution.

Current report

This power and infrastructure expertise enables the Company to evaluate complex, power-intensive sites efficiently and provides meaningful differentiation relative to data center developers without comparable in-house energy capabilities. The Company expects certain sites to include on-site generation, battery storage and other dispatchable resources to enhance reliability for mission-critical compute and to support grid operations where appropriate.

Current report

The Company’s primary sources of liquidity include cash on hand, cash generated from operations, sale proceeds from bitcoin, equity issuances, debt financing, and project-level financing arrangements. Capital requirements are driven primarily by HPC data center development, construction activities, and associated infrastructure investments.

Current report

Management expects future capital deployment to be focused on contracted HPC projects and disciplined expansion of the Company’s development pipeline. The Company continues to evaluate financing alternatives to support growth while managing balance sheet risk.

Current report

The Company expects future results to be increasingly influenced by the development and operation of its HPC data center platform. As contracted HPC capacity is delivered and energized under existing hosting arrangements, management expects the Company’s revenue mix to continue shifting toward HPC leasing and away from legacy bitcoin mining operations.

Current report

Future performance will depend on the timing of construction, commissioning, customer deployment schedules, access to power and interconnection, and the availability of project-level financing. Management expects capital deployment in future periods to be focused primarily on contracted HPC projects and disciplined expansion of the Company’s development pipeline.

Current report

The table below presents the lease and nonlease components of HPC lease revenue for the years ended December 31, 2025, 2024, and 2023.

Current report

(1)Certain of the Core42 Leases commenced in 2025 which comprised 18 critical IT MW HPC lease capacity as of December 31, 2025. The remainder of the HPC Leases are expected to commence in 2026.

Current report

(2)Cost of revenue (exclusive of depreciation) represents power costs which are passed through to the customer without markup and are included on a gross basis in HPC lease revenue as well as includes costs incurred by the Company in connection with its fit-out services under the HPC Leases.

Showing the first 40 of 66 passages. Open the source sections for the rest.

Removed paragraphs (37)

Previous report

We are a vertically integrated owner and operator of next-generation digital infrastructure, purpose-built to support bitcoin mining and HPC workloads. With a strong commitment to sustainability, our operations are powered predominantly by zero-carbon energy, reinforcing our focus on environmentally responsible data center operations in the United States. By leveraging clean, cost-effective, and reliable energy sources, we aim to drive long-term efficiency and resilience within the digital infrastructure sector.

Previous report

Our primary operations are centered at the Lake Mariner Facility, strategically located on the shores of Lake Ontario. Developed on the site of a decommissioned coal-fired power plant, this expansive facility is designed for scalable growth, with the ability to expand up to 500 MW in the near term and up to 750 MW with targeted transmission upgrades. Purpose-built to support both bitcoin mining and GPU-driven HPC workloads, the Lake Mariner Facility is well-positioned to meet the rising demand for compute-intensive applications. This dual-purpose strategy enhances operational efficiency, diversifies revenue streams, and strengthens our position in the evolving digital economy.

Previous report

Bitcoin, introduced in 2008, revolutionized digital finance by enabling a decentralized system for exchanging and storing value without reliance on traditional financial institutions. It operates on a public ledger known as the “blockchain,” which records every transaction transparently and securely. This decentralized structure eliminates the need for intermediaries, enhancing transaction efficiency while making the network resilient to censorship and fraud. Unlike fiat currencies, bitcoin is not controlled by any government or central bank, reinforcing its role as a scarce, independent store of value.

Previous report

Bitcoin mining is the process of validating transactions and securing the network through proof-of-work consensus, where miners solve complex cryptographic puzzles to add new blocks to the blockchain. The network is maintained by a global pool of distributed nodes, ensuring transaction integrity and preventing double-spending. Key factors influencing mining economics include computing power, energy costs, and network difficulty, with miners competing to maximize their share of the total computational power (hashrate) deployed on the bitcoin network. As more miners participate, the network difficulty adjusts dynamically every 2,016 blocks (approximately every two weeks) to maintain a consistent block creation rate.

Previous report

Bitcoin’s supply issuance follows a predefined halving schedule, reducing the block reward by 50% approximately every four years. This mechanism enforces a controlled supply of bitcoin, contributing to its scarcity and long-term value proposition. The total bitcoin supply is capped at 21 million coins, and halvings will continue until this limit is reached.

Previous report

The most recent halving occurred on April 19, 2024, reducing the block reward from 6.25 to 3.125 bitcoin per block. While the halving decreases the direct mining subsidy, transaction fees remain an additional source of miner revenue. This built-in supply constraint influences mining economics and often plays a role in bitcoin’s long-term price dynamics.

Previous report

Our strategy is centered on leveraging our owned and scalable digital infrastructure to drive revenue and profitability through both bitcoin mining and HPC hosting. As a vertically integrated operator, we own and control our infrastructure, allowing us to optimize efficiency, reduce costs, and maintain a highly competitive cost structure.

Previous report

While bitcoin mining remains a core focus, we are strategically transitioning an increasing portion of the Lake Mariner Facility to support HPC hosting and colocation. This shift allows us to capitalize on the growing demand for AI, machine learning, and cloud computing workloads while further optimizing our power utilization and digital infrastructure.

Previous report

A key milestone in this transition occurred on December 22, 2024, when we signed a multi-year data center lease agreement with Core42, securing 72.5 MW of HPC hosting capacity at the Lake Mariner Facility for GPU compute workloads. This agreement includes an option to expand by an additional 135 MW through March 31, 2025, enabling total deployments to Core42 of up to 72.5 MW in 2025 and 135 MW in 2026. This development accelerates our HPC hosting expansion, positioning us at the intersection of energy and digital compute infrastructure. To support this expansion, we have expanded our digital infrastructure at the site, featuring advanced liquid cooling systems and Tier 3 redundancy. This infrastructure will be optimized for high-density compute workloads, reinforcing our ability to attract hyperscale and enterprise customers.

Previous report

By prioritizing cost-efficient power utilization, sustainability, and scalable infrastructure, our strategy positions TeraWulf to maximize value creation while adapting to the evolving landscape of digital asset mining and AI-driven computing. Looking ahead, we remain focused on expanding our infrastructure, optimizing operations, and strengthening our competitive advantage in both bitcoin mining and HPC hosting.

Previous report

During the year ended December 31, 2024, we operated bitcoin mining activities at two data centers: the Lake Mariner Facility and the Nautilus Cryptomine Facility in central Pennsylvania. In October 2024, we sold our entire equity interest in Nautilus, allowing us to consolidate operations and reinvest in future infrastructure growth.

Previous report

Strategically located in Barker, New York, on the site of a former coal-fired power plant, the Lake Mariner Facility began operations in March 2022, designed to support sustainable bitcoin mining. As of December 31, 2024, the facility was operating 195 MW of bitcoin mining capacity, with an additional 50 MW under construction and expected to come online in the first half of 2025. Additionally, the Company is developing HPC data centers at the Lake Mariner Facility to provide HPC hosting services for Core42, supporting up to 72.5 MW of data center infrastructure dedicated to GPU compute workloads. This capacity is expected to come online throughout 2025. Core42 also has an option, exercisable through March 31, 2025, to secure an additional 135 MW of data center infrastructure at the Lake Mariner Facility.

Previous report

The Company has a PPA with NYPA, securing 90 MW of high-load factor power to support its bitcoin mining operations. The PPA, executed in February 2022, has a ten-year term from the commencement of NYPA’s power delivery. The Lake Mariner Facility is built for scalable expansion, with the ability to grow up to 500 MW in the near term and potentially 750 MW with targeted transmission upgrades. Its strategic location and access to low-cost, predominantly zero-carbon energy make it a highly attractive site for both bitcoin mining and HPC workloads.

Previous report

The Nautilus Cryptomine Facility, located in Berwick, Pennsylvania, was a joint venture between TeraWulf and Talen Member. The Nautilus Cryptomine Facility was a 200 MW bitcoin mining operation, situated adjacent to the 2.5-gigawatt nuclear-powered Susquehanna Station and was the first bitcoin mining site powered entirely by behind-the-meter, zero-carbon nuclear energy, operating under a fixed-rate power contract of 2.0 cents per kilowatt-hour for a five-year term, with options for two three-year renewals.

Previous report

Under the terms of the joint venture agreement, TeraWulf held a 25% equity interest in Nautilus, while Talen Member held a 75% equity interest, with ownership subject to adjustments based on capital contributions. TeraWulf began mining bitcoin at the Nautilus Cryptomine Facility in the first quarter of 2023, with an allotted 50 MW of operational capacity prior to divesting its interest in Nautilus in October 2024. While holding a 25% equity stake, TeraWulf’s share of mined bitcoin was determined by relative hashrate contributions. The Company had contributed approximately 1.9 EH/s of the facility’s total 5.2 EH/s capacity, representing approximately 35.7% of the total hashrate attributed to the Company. At the time of TeraWulf’s ownership, the Nautilus Cryptomine Facility deployed approximately 48,000 miners, of which 15,800 miners were attributed to TeraWulf’s contributions to utilize its 50 MW allotment.

Previous report

In October 2024, TeraWulf sold its entire equity interest in Nautilus, allowing the Company to reallocate capital toward expanding its digital infrastructure at the Lake Mariner Facility and advancing its HPC hosting strategy. As part of the transaction, Nautilus distributed to TeraWulf all of its right, title, and interest in its miners, as well as certain other related equipment. Following the sale, TeraWulf deployed 12,300 S19 XP miners and sold or otherwise disposed of 35,700 miners as of December 31, 2024.

Previous report

In October 2024, the Company’s board of directors approved a share repurchase program authorizing the Company to repurchase up to $200.0 million of the Company’s outstanding shares of Common Stock through December 31, 2025. Subsequent to December 31, 2024 and through February 28, 2025, the Company repurchased 5,900,000 shares of its Common Stock for $33.3 million.

Previous report

In December 2024, the Company entered into certain long-term data center lease agreements with Core42, a G42 company specializing in sovereign cloud, AI infrastructure, and digital services, to lease specified data center infrastructure comprising 72.5 MW of HPC hosting capacity at the Lake Mariner Facility to the customer to support the customer’s HPC operations (the “HPC Leases”). As of the date of this Annual Report, none of the HPC Leases had commenced and all are expected to commence at various dates in 2025, each having an initial term of ten years and granting the customer two five-year renewal options. Additionally, the HPC Leases provide Core 42 an option to expand near-term HPC hosting capacity by an additional 135 MW gross, which is equivalent to 108 MW of critical IT load, by March 31, 2025.

Previous report

The HPC Leases provide for certain prepaid rent amounts (“Prepaid Rent”) representing the first 12 months base rent under each lease for a total of $90.0 million and shall be applied towards each month’s base rent for 24 months commencing on the respective commencement date of each lease until the Prepaid Rent is exhausted. As of the date of this Annual Report, the Company has received all $90.0 million of Prepaid Rent.

Previous report

On December 13, 2021, TeraWulf completed its business combination (the “Merger”) with IKONICS Corporation (“IKONICS”), through which the Company effectively acquired IKONICS and became a publicly traded entity on Nasdaq, which was the primary objective of the business combination.

Previous report

As part of the Merger consideration, IKONICS shareholders received contractual contingent value rights (“CVR”) under a Contingent Value Rights Agreement (the “CVR Agreement”). Each IKONICS shareholder as of immediately prior to the Merger received one non-transferable CVR for each share of IKONICS common stock held at that time. The CVR holders were entitled to receive 95% of the Net Proceeds (as defined in the CVR Agreement) from any sale, transfer, disposition, spin-off, or licensing of IKONICS’ pre-merger business assets.

Previous report

During the year ended December 31, 2023, the Company fulfilled its CVR obligations, making $11.0 million in payments related to proceeds from the sale of net assets held for sale. As of December 31, 2023, the Company had completed all required distributions to CVR holders, and the CVR Agreement was deemed terminated.

Previous report

Gain on fair value of digital currency, net during the year ended December 31, 2024 was $2.2 million as a result of the Company adopting Financial Accounting Standards Board (“FASB”) Accounting Standards Update (“ASU”) No. 2023-08, Intangible – Goodwill and Other – Crypto Assets (Subtopic 350-60): Accounting for and Disclosure of Crypto Assets (“ASU 2023-08”), on January 1, 2024 which requires entities with certain crypto assets to subsequently measure such assets at fair value, with changes in fair value recorded in net income in each reporting period. Prior to the adoption of ASU 2023-08, the Company recorded impairment of digital currency of $3.0 million during the year ended December 31, 2023 representing the decline in bitcoin prices during the Company’s holding period of its bitcoin, which was not reversed during its holding period, and realized gain on sale of digital currency of $3.2 million during the year ended December 31, 2023 upon subsequent liquidation of bitcoin held. The Company elected to early adopt ASU 2023-08 effective January 1, 2024, resulting in a cumulative-effect change of $37,000 to increase the balance of digital currency with a corresponding decrease in the opening balance of accumulated deficit in the consolidated balance sheet as of January 1, 2024.

Previous report

During the years ended December 31, 2024 and December 31, 2023, the Company recorded a loss on disposal of property, plant and equipment of $17.8 million and $1.2 million, respectively, related to disposals of miners and write-off of deposits on miners.

Previous report

Equity in net income (loss) of investee, net of tax for the years ended December 31, 2024 and 2023 was $3.4 million and $(9.3) million, respectively, which represents TeraWulf’s proportional share of income or loss of Nautilus, which commenced operations in February 2023. The amount includes an impairment loss of $13.6 million for the year ended December 31, 2023 related to the distribution of miners from Nautilus to the Company whereby the miners were marked to fair value from book value on the date distributed. The impairment loss was the result of decreasing prices for miners between initial purchase and distribution.

Previous report

Cash provided by financing activities was $335.2 million and $119.9 million for the years ended December 31, 2024 and 2023, respectively. During the year ended December 31, 2024, the Company received proceeds from (i) issuance of convertible notes, net of issuance costs paid, of $487.1 million, (ii) issuances of Common Stock, net of issuance costs, of $188.7 million and (iii) warrant exercises of $4.8 million. The cash provided by financing activities during the year ended December 31, 2024 was partially offset by principal payments on long-term debt of $139.4 million, repurchases of treasury stock of $118.2 million, purchases of capped call instruments of $60.0 million and payments related to tax withholdings related to net share settlements of stock-based compensation awards of $23.7 million. During the year ended December 31, 2023, the Company received proceeds from (i) issuances of Common Stock, net of issuance costs, of $135.9 million (ii) proceeds from warrant exercises of $2.5 million, and (iii) issuance of convertible promissory notes of $1.3 million. The cash provided by financing activities during the year ended December 31, 2023 was partially offset by payments of contingent value rights liability related to the proceeds from sales of net assets held for sale of RM 101 of $11.0 million, principal payments on long-term debt of $6.6 million, and payments related to tax withholdings related to net share settlements of stock-based compensation awards of $2.0 million.
Reworded paragraphs (39)

Previous wording

The following Management’s Discussion and Analysis of Financial Condition and Results of Operations should be read in conjunction with the other Items included in this Annual Report on Form 10-K (the “Annual Report”) and with the accompanying consolidated financial statements and notes thereto included elsewhere in this report. All figures presented below represent results from continuing operations, unless otherwise specified. Capitalized terms used but not otherwise defined herein shall have the meanings ascribed to such terms in the Consolidated Financial Statements. Unless the context otherwise requires, references in this Annual Report to the “Company,” “TeraWulf,” “we,” “us” or “our” refers to TeraWulf Inc. and its consolidated subsidiaries. Certain statements contained in this Management’s Discussion and Analysis of Financial Condition and Results of Operations may be deemed forward-looking statements. See “Forward-Looking Statements.”

Current wording

The following Management’s Discussion and Analysis of Financial Condition and Results of Operations should be read in conjunction with the other Items included in this Annual Report and with the accompanying consolidated financial statements and notes thereto included elsewhere in this report. All figures presented below represent results from continuing operations, unless otherwise specified. Certain statements contained in this Management’s Discussion and Analysis of Financial Condition and Results of Operations may be deemed forward-looking statements. See “Forward-Looking Statements.”

Previous wording

As of December 31, 2024, we owned approximately 62,000 miners, of which approximately 58,800 are operational at the Lake Mariner Facility with the remainder undergoing maintenance, awaiting disposal or on standby to replace miners under repair. These miners were comprised as follows:

Current wording

As of December 31, 2025, we owned approximately 54,100 miners, with approximately 49,400 operational at our bitcoin mining facilities on the Lake Mariner Data Campus (the “LMD Bitcoin Mining Facilities”) and the remainder undergoing maintenance, awaiting disposal or on standby to replace miners under repair. These miners were comprised as follows:

Previous wording

As of December 31, 2024, our fleet of miners ranged in age from 0.1 to 2.6 years and have an average age of approximately 0.7 years. We do not have scheduled downtime for our miners; however, while we periodically perform unscheduled maintenance on our miners, such downtime has not been significant historically. When performing unscheduled maintenance, depending on the length of estimated repair time, we may replace a miner with a substitute miner to limit overall downtime. As of December 31, 2024, our fleet of miners at the Lake Mariner Facility had a range of energy efficiency from 15 to 23 joules per terahash (“j/th”) and has an average energy efficiency of 19.8 j/th.

Current wording

As of December 31, 2025, our fleet of miners ranged in age from 0.7 years to 3.6 years and have an average age of approximately 1.2 years. We do not have scheduled downtime for our miners and while we periodically perform unscheduled maintenance on our miners, such downtime has not been significant historically. When performing unscheduled maintenance, depending on the length of estimated repair time, we may replace a miner with a substitute miner to limit overall downtime. As of December 31, 2025, our fleet of miners at the LMD Bitcoin Mining Facilities had a range of energy efficiency from 15 to 23 joules per terahash (“j/th”) and has an average energy efficiency of 17.2 j/th.

Previous wording

As outlined above, several factors influence our ability to mine bitcoin profitably, including bitcoin’s USD value, mining difficulty, global hashrate, power costs, fleet energy efficiency, and overall data center efficiency. Among these, energy efficiency is a critical driver of profitability, as power costs represent the most significant direct expense in bitcoin mining. We believe we operate a highly efficient mining fleet, optimized to maximize output while minimizing energy consumption. To assess operational performance and effectiveness, the Company tracks key metrics, which we believe are also valuable to investors for evaluating our progress and benchmarking against industry peers.

Current wording

Several factors influence our ability to mine bitcoin profitably, including bitcoin’s USD value, mining difficulty, global hashrate, power costs, fleet energy efficiency, and overall data center efficiency. Among these, energy efficiency is a critical driver of profitability, as power costs represent the most significant direct expense in bitcoin mining. We believe we operate a highly efficient mining fleet, optimized to maximize output while minimizing energy consumption. To assess operational performance and effectiveness, the Company tracks key metrics, which we believe are also valuable to investors for evaluating our progress and benchmarking against industry peers.

Previous wording

(1) Results as of December 31, 2023 reflect hashrate of mining operations at the Lake Mariner Facility and TeraWulf’s net share of hashrate produced at the Nautilus Cryptomine Facility.

Current wording

(1) Results as of December 31, 2024 reflect hashrate of mining operations at the LMD Bitcoin Mining Facilities and TeraWulf’s net share of hashrate produced at the Nautilus Cryptomine Facility.

Previous wording

(4) While nameplate inventory at the Lake Mariner Facility was 9.7 EH/s as of December 31, 2024 and was 5.5 EH/s for TeraWulf’s two facilities as of December 31, 2023, inclusive of gross total hosted miners, actual monthly hashrate performance depends on a variety of factors, including (but not limited to) performance tuning to increase efficiency and maximize margin, scheduled outages (scopes to improve reliability or performance), unscheduled outages, curtailment due to participation in various cash generating demand response programs, derate of ASICS due to adverse weather and ASIC maintenance and repair.

Current wording

(4) While nameplate at the LMD Bitcoin Mining Facilities was 10.9 EH/s and 9.7 EH/s as of December 31, 2025 and 2024, respectively, actual operational hashrate depends on a variety of factors, including (but not limited to) performance tuning to increase efficiency and maximize margin, scheduled outages (scopes to improve reliability or performance), unscheduled outages, curtailment due to participation in various cash generating demand response programs, derate of ASICS due to adverse weather and ASIC maintenance and repair.

Previous wording

As of December 31, 2024, our operating hashrate represented approximately 1.4% of the total global hashrate, aligning with our share of global blockchain rewards. As of that date, this translated to approximately 6 bitcoin mined per day. To maintain profitability, we focus on optimizing operational efficiency and cost management, ensuring that our mining rewards consistently cover direct operating expenses.

Current wording

As of December 31, 2025, our operating hashrate represented approximately 0.9% of the total global hashrate, aligning with our share of global blockchain rewards. As of that date, this translated to approximately 4 bitcoin mined per day. To maintain profitability, we focus on optimizing operational efficiency and cost management, ensuring that our mining rewards consistently cover direct operating expenses.

Previous wording

The table below presents the average cost of mining each bitcoin, including bitcoin mined at the Lake Mariner Facility and the Company’s net share of bitcoin mined at the Nautilus Cryptomine Facility, for the years ended December 31, 2024 and 2023 and the total energy cost per kWh utilized within the facilities.

Current wording

The table below presents the average cost of mining each bitcoin, including bitcoin mined at the LMD Bitcoin Mining Facilities and the Company’s net share of bitcoin mined at the Nautilus Cryptomine Facility, for the years ended December 31, 2025 and 2024 and the total energy cost per kWh utilized within the facilities.

Previous wording

(1)“Cost to mine one bitcoin” is a cash cost metric and does not include depreciation. Although the Company recognizes depreciation with respect to its mining assets, it does not consider depreciation in determining whether it is economical to operate its mining equipment. As a result, the Company does not consider the sunk costs or depreciation of past capital investments in its historical or forecasted breakeven analysis. If depreciation of our miner fleet were factored into the above cost of mining analysis, it would add $22,086 and $9,892 per bitcoin mined for the years ended December 31, 2024 and 2023, respectively, bringing the total “cost to mine one bitcoin” to $47,354 and $18,598 for the years ended December 31, 2024 and 2023, respectively.

Current wording

(1)“Cost to mine one bitcoin” is a cash cost metric and does not include depreciation. Although the Company recognizes depreciation with respect to its mining assets, it does not consider depreciation in determining whether it is economical to operate its mining equipment. As a result, the Company does not consider the sunk costs or depreciation of past capital investments in its historical or forecasted breakeven analysis. If depreciation of our miner fleet were factored into the above cost of mining analysis, it would add $41,930 and $22,086 per bitcoin mined for the years ended December 31, 2025 and 2024, respectively, bringing the total “cost to mine one bitcoin” to $95,611 and $47,354 for the years ended December 31, 2025 and 2024, respectively.

Previous wording

(2) Computed as the weighted-average opening price of bitcoin on each respective day the mined bitcoin is earned. Excludes bitcoin earned from profit sharing associated with a bitcoin miner hosting agreement that expired in February 2024 at the Lake Mariner Facility.

Current wording

(2) Computed as the weighted-average opening price of bitcoin on each respective day the mined bitcoin is earned. Excludes bitcoin earned from profit sharing associated with a bitcoin miner hosting agreement that expired in February 2024 at the LMD Bitcoin Mining Facilities.

Previous wording

(3)Excludes bitcoin earned from profit sharing associated with a bitcoin miner hosting agreement that expired in February 2024 at the Lake Mariner Facility of 6 and 64 bitcoin for the years ended December 31, 2024 and 2023, respectively, and includes TeraWulf’s net share of bitcoin mined at the Nautilus Cryptomine Facility, based on the hashrate share attributed to the Company.

Current wording

(3)Excludes bitcoin earned from profit sharing associated with a bitcoin miner hosting agreement that expired in February 2024 at the LMD Bitcoin Mining Facilities of 0 and 6 bitcoin for the years ended December 31, 2025 and 2024, respectively, and includes TeraWulf’s net share of bitcoin mined at the Nautilus Cryptomine Facility, based on the hashrate share attributed to the Company.

Previous wording

(4)Excludes energy expenses associated with a bitcoin miner hosting agreement that expired in February 2024 at the Lake Mariner Facility and includes TeraWulf’s net share of energy expense at the Nautilus Cryptomine Facility, based on aggregate nameplate power consumption of deployed miners attributed to TeraWulf’s contribution to Nautilus.

Current wording

(4)Excludes energy expenses associated with a bitcoin miner hosting agreement that expired in February 2024 at the LMD Bitcoin Mining Facilities and includes TeraWulf’s net share of energy expense at the Nautilus Cryptomine Facility, based on aggregate nameplate power consumption of deployed miners attributed to TeraWulf’s contribution to Nautilus.

Previous wording

Power costs are the most significant expense in our bitcoin mining operations, accounting for 40.1% and 29.4% of the total value of bitcoin mined for the years ended ended December 31, 2024 and 2023, respectively. The increase in power costs as a percentage of bitcoin mined in 2024 compared to 2023 was primarily driven by a near doubling of network difficulty and the bitcoin halving event in April 2024, which reduced block rewards. These impacts were partially offset by growth in our average operating hashrate and an increase in the average market value of each bitcoin mined.

Current wording

Power costs are the most significant expense in our bitcoin mining operations, accounting for 52.9% and 40.1% of the total value of bitcoin mined for the years ended December 31, 2025 and 2024, respectively. The increase in power costs as a percentage of bitcoin mined in 2025 compared to 2024 was primarily driven by an approximate 30% increase in the realized cost per kWh and a near doubling of network difficulty and the bitcoin halving event in April 2024, which reduced block rewards. These impacts were partially offset by growth in our average operating hashrate for a portion of 2025 and an increase in the average market value of each bitcoin mined.

Previous wording

Energy prices are highly volatile, influenced by global events that can drive nationwide fluctuations in power costs. At the Lake Mariner Facility, power costs are subject to variable market rates, which can change hourly based on wholesale electricity pricing. While this introduces some unpredictability, it also provides us with the flexibility to actively manage our energy consumption, optimizing for profitability and efficiency. Energy prices are also highly sensitive to weather conditions, such as winter storms and polar vortices, which can increase regional power demand and drive up costs. During such events, we may curtail operations to avoid consuming power at peak rates, or we may be curtailed under demand response programs in which we participate. For the years ended December 31, 2024, and 2023, the average aggregate realized power prices at the Lake Mariner Facility and Nautilus Cryptomine Facility were $0.043 and $0.032 per kilowatt hour, respectively.

Current wording

Energy prices are highly volatile, influenced by global events that can drive nationwide fluctuations in power costs. At the LMD Bitcoin Mining Facilities, power costs are subject to variable market rates, which can change hourly based on wholesale electricity pricing. While this introduces some unpredictability, it also provides us with the flexibility to actively manage our energy consumption, optimizing for profitability and efficiency. Energy prices are also highly sensitive to weather conditions, such as winter storms and polar vortices, which can increase regional power demand and drive up costs. During such events, we may curtail operations to avoid consuming power at peak rates, or we may be curtailed under demand response programs in which we participate. For the years ended December 31, 2025 and 2024, the average aggregate realized power prices at the LMD Bitcoin Mining Facilities and Nautilus Cryptomine Facility were $0.060 and $0.043 per kilowatt hour, respectively.

Previous wording

During the years ended December 31, 2024 and 2023, we curtailed operations at the Lake Mariner Facility in response to weather events, energy price spikes, and participation in demand response programs. The Company records expected payments to be received for demand response programs as a reduction in cost of revenue, which amounted to $8.6 million and $3.5 million for the years ended December 31, 2024 and 2023, respectively.

Current wording

During the years ended December 31, 2025 and 2024, we curtailed operations at the LMD Bitcoin Mining Facilities in response to weather events, energy price spikes, and participation in demand response programs. The Company records expected payments to be received for demand response programs as a reduction in cost of revenue, which amounted to $17.7 million and $8.6 million for the years ended December 31, 2025 and 2024, respectively.

Previous wording

The Company has purchased all miners with cash, without relying on limited recourse equipment financing for miner acquisitions. To support operations, invest in our joint venture, and purchase miners and other fixed assets, we have raised capital through both equity issuances and corporate-level debt. Costs related to these capital raises are not included in this analysis.

Current wording

The Company has purchased all miners with cash, without relying on limited recourse equipment financing for miner acquisitions. To support operations, invest in our previously owned Nautilus joint venture, and purchase miners and other fixed assets, we have raised capital through both equity issuances and corporate-level debt. Costs related to these capital raises are not included in this analysis.

Previous wording

During the year ended December 31, 2024, the Company recorded an accelerated depreciation expense of $5.1 million related to certain miners whose estimated useful lives were shortened due to planned replacement by April 2024. While our standard depreciation period for miners is four years, historically low power costs may allow for a longer actual useful life in certain cases. However, if depreciation were included in the cost of mining analysis, it would add $22,086 and $9,892 per bitcoin mined for the years ended December 31, 2024 and 2023, respectively.

Current wording

During the year ended December 31, 2025, the Company recorded accelerated depreciation expense of $19.6 million related to a certain miner building and related miners of which the Company shortened their useful lives based on expected shutdown of operations for purposes of supporting the HPC operations. During the year ended December 31, 2024, the Company recorded accelerated depreciation expense of $5.1 million related to certain miners of which the Company shortened their estimated useful lives based on replacement by April 30, 2024. While our standard depreciation period for miners is four years, historically low power costs may allow for a longer actual useful life in certain cases. However, if depreciation were included in the cost of mining analysis, it would add $41,930 and $22,086 per bitcoin mined for the years ended December 31, 2025 and 2024, respectively.

Previous wording

The Company generates revenue in the form of bitcoin by providing hash computation services to a mining pool operator to mine bitcoin and validate transactions on the global bitcoin network using miners owned by the Company. The earned bitcoin are routinely sold for U.S. dollars. The Company also earned revenue by providing bitcoin miner hosting services to third parties. While the Company may choose to mine other digital currencies, it has no plans to do so currently.

Current wording

The Company generates revenue in the form of bitcoin by providing hash computation services to a mining pool operator to mine bitcoin and validate transactions on the global bitcoin network using miners owned by the Company. The earned bitcoin are routinely sold for U.S. dollars. The Company also previously earned revenue by providing bitcoin miner hosting services to third parties.

Previous wording

The Company’s business strategy centers on growing revenue and profitability by enhancing the capacity and efficiency of our bitcoin mining fleet while expanding our data center infrastructure to support HPC hosting activities. We plan to strategically develop the infrastructure necessary for profitability of bitcoin mining while pursuing adjacent high-value HPC hosting opportunities that leverage our power utilization and digital infrastructure. We are confident that our expertise in power infrastructure and digital asset mining can be favorably applied to the design, development, and operation of large-scale data centers. These data centers are optimized for high-value applications such as cloud computing, machine learning, and artificial intelligence. We will actively seek opportunities to expand into these areas using our knowledge, expertise, and existing infrastructure wherever favorable market opportunities arise.

Current wording

The Company’s business strategy centers on maximizing revenue and profitability of our bitcoin mining fleet while expanding our datacenter infrastructure to support HPC leasing activities. We plan to operate infrastructure necessary for profitable bitcoin mining while pursuing high-value HPC leasing opportunities that leverage our power utilization and digital infrastructure. We are confident our expertise in power infrastructure and digital asset mining can be favorably applied to the design, development, and operation of large-scale datacenters. These datacenters are optimized for high-value applications such as cloud computing, machine learning, and artificial intelligence. We are actively seeking opportunities to expand into these areas using our knowledge, expertise, and existing infrastructure wherever favorable market opportunities arise.

Previous wording

Revenue for the years ended December 31, 2024 and 2023 was $140.1 million and $69.2 million, respectively, an increase of $70.9 million. The increase was primarily attributed to an increase in the average price of bitcoin during the year ended December 31, 2024 of $65,824 as compared to $28,788 during the same period in the prior year and an increase in mining capacity at the Lake Mariner Facility to approximately 195 MW as of December 31, 2024 as compared to 110 MW as of December 31, 2023, partially offset by decreases in the total bitcoin mined due to impacts of the halving in April 2024 and the increase in network hashrate, resulting in total bitcoin mined of 2,177 bitcoin during the year ended December 31, 2024 as compared to 2,168 bitcoin during the same period in the prior year.

Current wording

Digital asset revenue for the years ended December 31, 2025 and 2024 was $151.6 million and $140.1 million, respectively, an increase of $11.5 million. The increase was primarily attributed to an increase in the average price of bitcoin during the year ended December 31, 2025 of $101,658 as compared to $65,824 during 2024. This increase was partially offset by a decrease in the total bitcoin mined to 1,496 bitcoin during the year ended December 31, 2025 as compared to 2,177 bitcoin mined during the same period in the prior year. Although the Company expanded its mining infrastructure capacity at the LMD Bitcoin Mining Facilities to approximately 245 MW as of December 31, 2025 as compared to 195 MW as of December 31, 2024, total bitcoin mined decreased due to the halving in April 2024 and the increase in network hashrate.

Previous wording

During the years ended December 31, 2024 and 2023 revenue from bitcoin miner hosting was $0.8 million and $7.5 million, respectively, a decrease due to the expiration of the Company’s bitcoin miner hosting contract with a customer in February 2024.

Current wording

During the years ended December 31, 2025 and 2024, revenue from bitcoin miner hosting was $0 and $0.8 million, respectively, a decrease due to the expiration of the Company’s bitcoin miner hosting contract with a customer in February 2024.

Previous wording

Cost of revenue (exclusive of depreciation) for the years ended December 31, 2024 and 2023 was $62.6 million and $27.3 million, respectively, an increase of approximately $35.3 million. Cost of revenues is primarily comprised of power expense and the increase was primarily due to the increase in mining capacity due to infrastructure constructed and placed in service between December 31, 2023 and December 31, 2024 at the Lake Mariner Facility and, to a lesser extent, an increase in realized power prices during the year ended December 31, 2024 as compared to the same period in the prior year. The Company records proceeds related to participation in demand response programs as a reduction in cost of revenue in the period corresponding to the underlying demand response program period; the amount of aggregate proceeds received or expected to be received were $8.6 million and $3.5 million for the years ended December 31, 2024 and 2023, respectively. The Company is actively expanding its enrollment in such available programs in New York State.

Current wording

Proceeds from participation in demand response programs are recorded as a reduction in cost of revenue in the period in which the underlying program occurs. These proceeds totaled $17.7 million and $8.6 million for the years ended December 31, 2025 and 2024, respectively. The Company is actively expanding its enrollment in such available programs in New York State.

Previous wording

Operating expenses (including related party expenses) for the years ended December 31, 2024 and 2023 were approximately $7.6 million and $4.9 million, respectively, a net increase of $2.7 million. Operating expenses increased primarily due to higher engineering expenses of $0.4 million and property insurance of $0.7 million. Operating expense - related party increased primarily due to $0.4 million in rent expense and $1.1 million due to increased staffing at the Lake Mariner Facility. These increases related to infrastructure constructed and placed in service between December 31, 2023 and 2024.

Current wording

Operating expenses (including related party expenses) for the years ended December 31, 2025 and 2024 were approximately $19.7 million and $7.6 million, respectively, a net increase of $12.1 million. Operating expenses increased primarily due to higher miner repairs of $2.9 million and increased site labor of $2.6 million driven by the expansion of operations at the Lake Mariner Data Campus. Operating expense - related party increased primarily due higher rent subsequent to the New Ground Lease in October 2024 of $4.4 million, partially offset by $1.0 million of site labor at the Lake Mariner Data Campus which was previously reported in operating expenses-related party and since the acquisition of Beowulf E&D in May 2025 is included in operating expenses.

Previous wording

Selling, general and administrative expenses (including related party expenses) for the years ended December 31, 2024 and 2023 were $70.6 million and $37.0 million, respectively, a net increase of $33.6 million. Selling, general and administrative expenses increased primarily due to increased expense during the year ended December 31, 2024 as compared to the same period in the prior year of (i) stock-based compensation of $25.2 million, (ii) employee compensation and benefits of $5.7 million, (iii) travel expenses of $0.6 million, (iv) legal and other professional fees of $1.4 million, (v) charity, sponsorships and investor relations of $1.1 million and (vi) other public company costs of $1.1 million, partially offset by decreases in insurance expense of $0.9 million. Selling, general and administrative expenses – related party decreased a net $1.3 million in fees paid under the Services Agreement with Beowulf E&D primarily due to performance milestone expense incurred during the year ended December 31, 2023 that were not incurred during the year ended December 31, 2024, offset by an increase in the base fee as well as increased travel expense of $0.6 million.

Current wording

Selling, general and administrative expenses (including related party expenses) for the years ended December 31, 2025 and 2024 were $147.8 million and $70.6 million, respectively, a net increase of $77.2 million. Selling, general and administrative expenses increased primarily due to increased expense during the year ended December 31, 2025 as compared to the same period in the prior year of (i) employee compensation and benefits of $47.7 million, (ii) stock-based compensation of $20.0 million, (iii) travel expenses of $2.4 million, (iv) legal and other professional fees of $5.1 million, (v) and Beowulf E&D acquisition-related costs of $1.5 million.

Previous wording

Depreciation for the years ended December 31, 2024 and 2023 was $59.8 million and $28.4 million, respectively. The increase was primarily due to the increase in mining capacity due to infrastructure constructed and placed in service between December 31, 2023 and December 31, 2024 at the Lake Mariner Facility. Additionally, during the year ended December 31, 2024, the Company recorded accelerated depreciation expense of $5.1 million related to certain miners of which the Company shortened their estimated useful lives based on anticipated replacement by April 30, 2024.

Current wording

Depreciation for the years ended December 31, 2025 and 2024 was $88.6 million and $59.8 million, respectively. The increase was primarily due to mining and HPC infrastructure constructed and placed in service between December 31, 2024 and December 31, 2025 at the Lake Mariner Data Campus. Additionally, during the year ended December 31, 2025, the Company recorded accelerated depreciation expense of $19.6 million related to a certain miner building and related miners of which the Company shortened their useful life based on expected shutdown of operations for purposes of supporting the HPC operations. The increase was partially offset by (i) decrease in depreciation on certain electrical equipment and leasehold improvements related to a change in accounting estimate of useful lives in connection with the New Ground Lease in October 2024 and (ii) accelerated depreciation expense of $5.1 million during the year ended December 31, 2024 related to certain miners of which the Company shortened their estimated useful lives based on expected replacement by April 2024.

Previous wording

Interest expense for the years ended December 31, 2024 and 2023 was $19.8 million and $34.8 million, respectively, a decrease of $15.0 million. Interest expense through July 2024 related primarily to the borrowings under the Loan, Guaranty and Security Agreement (the “LGSA”) with Wilmington Trust (the “Term Loans”), which had an original maturity date of December 1, 2024 and was fully repaid in July 2024 ahead of maturity. In October 2024, the Company completed a private offering of convertible senior notes due 2030 (the “2030 Convertible Notes”) which accrue 2.75% interest annually. The decrease in interest expense during the year ended December 31, 2024 as compared to the prior year is primarily due to early repayments of the Term Loans principal balance resulting in a decrease of amortization of debt issuance costs and debt discount of $8.1 million. Additionally, interest expense related to the stated interest rate decreased $9.4 million for the same reason, partially offset by $2.6 million of interest accrued during the year ended December 31, 2024 under the 2030 Convertible Notes and payable in May 2025.

Current wording

Interest expense for the years ended December 31, 2025 and 2024 was $80.2 million and $19.8 million, respectively, an increase of $60.4 million. The increase is primarily attributed to stated interest expense of $58.0 million and amortization of debt issuance costs of $22.2 million related to the 2030 Secured Notes, 2031 Convertible Notes and 2032 Convertible Notes which were issued during the year ended December 31, 2025 as well as the 2030 Convertible Notes issued in October 2024. The $19.8 million of interest expense recognized in the year ended December 31, 2024, primarily related to the borrowings under the Loan, Guaranty and Security Agreement with Wilmington Trust (the “Term Loans”), which were fully repaid in July 2024 ahead of maturity.

Previous wording

Loss on extinguishment of debt was $6.3 million for the year ended December 31, 2024 related to voluntary prepayments of the Term Loans in February and July 2024. The Company incurred prepayment fees of $1.3 million in connection with the voluntarily prepayments and derecognized unamortized debt discount of $5.0 million associated with the principal repaid. The Company made no prepayments on the principal balance of the Term Loans during the year ended December 31, 2023.

Current wording

Loss on extinguishment of debt during the year ended December 31, 2024 was $6.3 million related to voluntary prepayment of the Term Loans in February and July 2024, reflecting $1.3 million of prepayment fees and the derecognition of unamortized debt discount of $5.0 million associated with the principal repaid. No loss on extinguishment of debt was recorded during the year ended December 31, 2025.

Previous wording

Income tax benefit was $0 for the years ended December 31, 2024 and 2023. Based upon the level of historical U.S. losses and future projections over the period in which the net deferred tax assets are deductible, at this time, management believes it is more likely than not that the Company will not realize the benefits of the remaining deductible temporary differences, and as a result the Company has recorded a full valuation allowance against its gross deferred tax assets as of December 31, 2024 and 2023.

Current wording

Income tax provision was $76,000 and $0 for the years ended December 31, 2025 and 2024, respectively. Based upon the level of historical U.S. losses and future projections over the period in which the net deferred tax assets are deductible, at this time, management believes it is more likely than not that the Company will not realize the benefits of the remaining deductible temporary differences, and as a result the Company has recorded a full valuation allowance against its net deferred tax assets as of December 31, 2025 and 2024, except for a $76,000 deferred tax liability as of December 31, 2025 arising from indefinite-lived assets (e.g., tax-deductible goodwill related to the acquisition of Beowulf E&D) that cannot be used as a source of taxable income to support the realization of deferred tax assets when a full valuation allowance is in place.

Current wording

Equity in net loss of investee, net of tax for the year ended December 31, 2025 was $4.1 million which represents TeraWulf’s proportional share of net loss of the Abernathy Joint Venture which was formed in October 2025 and has not yet commenced operations. The $3.4 million equity in net income of investee, net of tax for the year ended December 31, 2024 represents TeraWulf’s proportional share of the net income of Nautilus prior to the Company’s divestiture of its entire 25% equity interest in Nautilus in October 2024.

Previous wording

Additionally the Company recorded a gain on sale of equity interest in investee of $22.6 million in the consolidated statement of operations for the year ended December 31, 2024 as a result of the sale of its entire 25% equity interest in Nautilus to the Talen Member in October 2024.

Current wording

Additionally the Company recorded a gain on sale of equity interest in investee of $22.6 million in the consolidated statement of operations for the year ended December 31, 2024 as a result of the sale of its interest in Nautilus in October 2024.

Previous wording

We define Adjusted EBITDA as net loss adjusted for (i) impacts of interest, taxes, depreciation and amortization; (ii) stock-based compensation expense, amortization of right-of-use asset and related party expense to be settled with respect to common stock, all of which are non-cash items that the Company believes are not reflective of its general business performance, and for which the accounting requires management judgment, and the resulting expenses could vary significantly in comparison to other companies; (iii) one-time, non-recurring transaction-based compensation expense related to the 2030 Convertible Notes (iv) equity in net income (loss) of investee, net of tax, related to Nautilus and the gain on sale of interest in Nautilus; (v) other income which is related to interest income or income for which management believes is not reflective of the Company’s ongoing operating activities; (vi) loss on extinguishment of debt and net losses on disposals of property, plant and equipment, net, which are not reflective of the Company’s general business performance and (vii) loss from discontinued operations, net of tax, which is not applicable to the Company’s future business activities. The Company’s Adjusted EBITDA also includes the impact of distributions from investee received in bitcoin related to a return on the Nautilus investment, which management believes, in conjunction with excluding the impact of equity in net income (loss) of investee, net of tax, is reflective of assets available for the Company’s use in its ongoing operations as a result of its investment in Nautilus.

Current wording

We define Adjusted EBITDA as net loss adjusted for (i) impacts of interest, taxes, depreciation and amortization; (ii) stock-based compensation expense, amortization of right-of-use asset and related party expense to be settled with respect to common stock, all of which are non-cash items that the Company believes are not reflective of its general business performance, and for which the accounting requires management judgment, and the resulting expenses could vary significantly in comparison to other companies; (iii) one-time, non-recurring transaction-based compensation expense related to the 2030 Convertible Notes (iv) equity in net (loss) income of investee, net of tax, related to the Abernathy Joint Venture and Nautilus and the gain on sale of interest in Nautilus; (v) other income which is related to interest income or income for which management believes is not reflective of the Company’s ongoing operating activities; (vi) change in fair value of contingent consideration, change in fair value of warrant and derivative liabilities, loss on extinguishment of debt and net losses on disposals of property, plant and equipment, net, which are not reflective of the Company’s general business performance; and (vii) acquisition-related transaction costs which management believes are not reflective of the Company’s ongoing operating activities. The Company’s Adjusted EBITDA also includes the impact of distributions from investee received in bitcoin related to a return on the Nautilus investment, which management believes, in conjunction with excluding the impact of equity in net (loss) income of investee, net of tax, is reflective of assets available for the Company’s use in its ongoing operations as a result of its investment in Nautilus.

Previous wording

Management believes that providing this non-GAAP financial measure allows for meaningful comparisons between the Company's core business operating results and those of other companies, and provides the Company with an important tool for financial and operational decision making and for evaluating its own core business operating results over different periods of time. In addition to management's internal use of non-GAAP Adjusted EBITDA, management believes that Adjusted EBITDA is also useful to investors and analysts in comparing the Company’s performance across reporting periods on a consistent basis. Management believes the foregoing to be the case even though some of the excluded items involve cash outlays and some of them recur on a regular basis (although management does not believe any of such items are normal operating expenses necessary to generate the Company’s bitcoin related revenues). For example, the Company expects that share-based compensation expense, which is excluded from Adjusted EBITDA, will continue to be a significant recurring expense over the coming years and is an important part of the compensation provided to certain employees, officers, directors and consultants. Additionally, management does not consider any of the excluded items to be expenses necessary to generate the Company’s bitcoin related revenue.

Current wording

Management believes that providing this non-GAAP financial measure allows for meaningful comparisons between the Company's core business operating results and those of other companies, and provides the Company with an important tool for financial and operational decision making and for evaluating its own core business operating results over different periods of time. In addition to management's internal use of non-GAAP Adjusted EBITDA, management believes that Adjusted EBITDA is also useful to investors and analysts in comparing the Company’s performance across reporting periods on a consistent basis. Management believes the foregoing to be the case even though some of the excluded items involve cash outlays and some of them recur on a regular basis (although management does not believe any of such items are normal operating expenses necessary to generate the Company’s revenues). For example, the Company expects that share-based compensation expense, which is excluded from Adjusted EBITDA, will continue to be a significant recurring expense over the coming years and is an important part of the compensation provided to certain employees, officers, directors and consultants.

Previous wording

As of December 31, 2024, the Company had balances of cash and cash equivalents of $274.1 million, working capital of $229.6 million, total stockholders’ equity of $244.4 million and an accumulated deficit of $332.3 million. The Company incurred a net loss of $72.4 million for the year ended December 31, 2024. The Company began mining bitcoin in March 2022 and had 9.7 EH/s of operating capacity as of December 31, 2024. To date, the Company has relied primarily on proceeds from the sale of bitcoin, both self-mined and distributed from the joint venture which owned the Nautilus Cryptomine Facility, and its issuances of debt and equity to fund its principal operations.

Current wording

As of December 31, 2025, the Company had balances of cash and cash equivalents of $3,266.4 million, working capital of $1,742.4 million, total stockholders’ equity of $140.4 million and an accumulated deficit of $993.7 million. The Company incurred a net loss of $661.4 million for the year ended December 31, 2025. The Company began mining bitcoin in March 2022 and had 9.3 EH/s of operating capacity as of December 31, 2025. In 2025, the Company commenced its HPC operations. To date, the Company has relied primarily on proceeds from the sale of bitcoin, both self-mined and distributed from the joint venture which owned the Nautilus Cryptomine Facility, and its issuances of debt and equity to fund its principal operations.

Previous wording

The principal uses of cash are for the operation and buildout of data center facilities, debt service, and general corporate activities and, to a lesser extent in 2023, investments in the Nautilus joint venture related to mining facility buildout and general corporate activities. Cash flow information is as follows (in thousands):

Current wording

The principal uses of cash are for the operation and buildout of data center facilities, debt service, and general corporate activities and, to a lesser extent in 2024, investments in the Nautilus joint venture related to mining facility buildout and activities. Cash flow information is as follows (in thousands):

Previous wording

Cash (used in) provided by operating activities for continuing operations was $(24.4) million and $4.2 million for the years ended December 31, 2024 and 2023, respectively, reflecting a decrease of $28.6 million. During the year ended December 31, 2024, the Company completed significant expansion of its bitcoin mining operations resulting in an increase in mining capacity at the Lake Mariner Facility to approximately 195 MW as of December 31, 2024 as compared to 110 MW as of December 31, 2023 which resulted in stable bitcoin earned during the period despite the impacts of the halving in April 2024. In addition, the average price of bitcoin increased during the year ended December 31, 2024 to $65,824 as compared to $28,788 during the same period in the prior year, resulting in an increase in revenue of $70.9 million. Power prices increased during the year ended December 31, 2024 as compared to prior year and cost of revenue (exclusive of depreciation) increased approximately $35.3 million for the year ended December 31, 2024 as compared to the prior year primarily due to the increase in mining capacity and the halving in April 2024. Additionally, prior to the repayment of the Term Loans in July 2024, the Company converted its bitcoin holdings nearly immediately to cash and the related proceeds from sales of digital currency were included within cash flows from operating activities in the consolidated statements of cash flows. Subsequently, proceeds from sales of digital currency of $67.4 million are included within cash flows from investing activities in the consolidated statements of cash flows for the year ended December 31, 2024 as the Company no longer converts bitcoin into cash on a nearly immediate basis.

Current wording

Additionally, prior to the repayment of the Term Loans in July 2024, the Company converted its bitcoin holdings nearly immediately to cash and the related proceeds from sales of digital assets of $97.6 million were included within cash flows from operating activities in the consolidated statements of cash flows.

Previous wording

Cash used in investing activities was $91.2 million and $78.0 million for the years ended December 31, 2024 and 2023, respectively. The Company invested $267.9 million and $75.2 million in the buildout of its facilities at the Lake Mariner Facility for the years ended December 31, 2024 and 2023, respectively, which included $69.2 million during the year ended December 31, 2024 related to infrastructure intended to support expansion into HPC leasing operations in 2025. Additionally, during the year ended December 31, 2023, the Company invested $2.8 million in its joint venture. During the year ended December 31, 2024, the Company received proceeds from the sale of its equity interest in the joint venture of $86.1 million, proceeds from the sale of property, plant and equipment of $23.3 million, and proceeds from sales of digital currency not converted nearly immediately into cash of $67.4 million.

Current wording

Cash used in investing activities was $1,368.9 million and $91.2 million for the years ended December 31, 2025 and 2024, respectively, reflecting an increase of $1,277.8 million. The increase is primarily attributed to (i) an increase in purchases of plant and equipment of $792.2 million related to infrastructure intended to support expansion into HPC leasing operations, (ii) lower proceeds from sales of property, plant and equipment of $11.7 million, (iii) investments in joint venture of $450.0 million, and (iv) $21.7 million for the acquisition of Beowulf E&D. The increase in cash used in investing activities were partially offset by increases in cash provided by investing activities related to proceeds from sales of digital assets of $84.0 million during the year ended December 31, 2025 as compared to the prior year, as the Company began classifying proceeds from sales of digital assets in investing activities starting July 2024. Additionally, during the year ended December 31, 2024, the Company received proceeds from sale of equity interest in investee of $86.1 million related to the sale of Nautilus.

Previous wording

The Company incurred a net loss of $72.4 million and reported cash used in operating activities of $24.4 million for the year ended December 31, 2024. As of December 31, 2024, the Company had balances of cash and cash equivalents of $274.1 million, working capital of $229.6 million, total stockholders’ equity of $244.4 million and an accumulated deficit of $332.3 million. The Company had 9.7 EH/s of operating capacity at the Lake Mariner Facility as of December 31, 2024. To date, the Company has relied primarily on proceeds from sales of bitcoin, both self-mined and distributed from the joint venture which owned the Nautilus Cryptomine Facility, and its issuances of debt and equity to fund its principal operations. Subsequent to December 31, 2024, the Company received $90.0 million of Prepaid Rent under its HPC Leases which shall be applied towards each month’s base rent for 24 months commencing on the respective commencement date of each lease until the Prepaid Rent is exhausted.

Current wording

The Company incurred a net loss of $661.4 million and reported cash used in operating activities of $123.2 million for the year ended December 31, 2025. As of December 31, 2025, the Company had balances of cash and cash equivalents of $3,266.4 million, working capital of $1,742.4 million, total stockholders’ equity of $140.4 million and an accumulated deficit of $993.7 million. For the year ended December 31, 2025, the Company leveraged its strategic transition toward HPC leasing and execution of long-term lease agreements with Fluidstack, which benefit from substantial credit support provided by Google, to enable efficient financing and funding of the phased development of the La Lupa and Akela facilities. Prior to these developments, the Company historically relied primarily on proceeds from sales of digital assets, both self-mined and distributed from the joint venture which owned the Nautilus Cryptomine Facility, and its issuances of debt and equity to fund its principal operations.

Previous wording

Digital currency is comprised of bitcoin earned as noncash consideration in exchange for providing hash computation services to a mining pool as well as consideration for bitcoin miner hosting services. From time to time, the Company also receives bitcoin as distributions-in-kind from its joint venture.

Current wording

Digital assets is comprised of bitcoin earned as noncash consideration in exchange for providing hash computation services to a mining pool as well as consideration for bitcoin miner hosting services. From time to time, the Company also receives bitcoin as distributions-in-kind from its joint venture.

Previous wording

Bitcoin are accounted for as intangible assets with indefinite useful life and is included in current assets in the consolidated balance sheets due to the Company’s ability to sell it in a highly liquid marketplace and because the Company reasonably expects to liquidate its bitcoin to support operations within the next twelve months. The Company elected to early adopt ASU 2023-08 effective January 1, 2024, which requires digital currency to be valued at fair value each reporting period in accordance with ASC 820 with changes in fair value recorded in net income. Gains and losses from the remeasurement of digital currency are included within gain on fair value of digital currency, net in the consolidated statements of operations. The Company sells bitcoin and gains and losses from such transactions, measured as the difference between the cash proceeds and the cost basis of bitcoin as determined on a first-in-first-out basis, are also included within gain on fair value of digital currency, net in the consolidated statements of operations.

Current wording

Bitcoin are accounted for as intangible assets with indefinite useful life and is included in current assets in the consolidated balance sheets due to the Company’s ability to sell it in a highly liquid marketplace and because the Company reasonably expects to liquidate its bitcoin to support operations within the next twelve months. The Company elected to early adopt ASU 2023-08 effective January 1, 2024, which requires digital assets to be valued at fair value each reporting period in accordance with ASC 820 with changes in fair value recorded in net income. Gains and losses from the remeasurement of digital assets are included within gain on fair value of digital assets, net in the consolidated statements of operations. The Company sells bitcoin and gains and losses from such transactions, measured as the difference between the cash proceeds and the cost basis of bitcoin as determined on a first-in-first-out basis, are also included within gain on fair value of digital assets, net in the consolidated statements of operations.