EX-99.1 · 23.3 MINING

23.3 MINING

In addition to the standard analysis and design elements essential for a FS Mine design, the following mining activities are recommended:

  • Mine Equipment Selection:

o Conventional equipment selection

  • Detailed quotes from vendors

  • Continuous Miner Evaluation:

o Examination of the use of Wirtgen to

  • reduce blasting needs

  • size material to potentially reduce crushing capital for sulfide material

  • potential increase in recovery with smaller material for ROM heap leach facilities

  • Blasting Analysis:

o Detailed blasting analysis for areas adjacent to existing infrastructure

  • Waste Rock Storage Facility Optimization:

o Optimizing the design of waste storage facilities.

  • Contract Mining Comparison:

o Conducting a comprehensive assessment of contract mining options suitable for each pit area

The cost of mining analysis and optimization is estimated to be $0.50 million during the FS.