EX-99.1 · Fiscal 2024 Developments
PLATINUM GROUP METALS LTD.
| Engagement of BIC | |
| On June 21, 2023, the Company reported the engagement of BIC by Lion Battery to help drive commercialization of its next generation platinum and palladium based battery chemistries. Under an agreed scope of work, BIC is to conduct independent small scale and large scale trials to validate Lion Battery's proprietary platinum and palladium based electrode composition, slurry, and films in both lithium-sulfur and lithium-ion (NMC811) coin and pouch cells. Collaboration with BIC will also include additional research and development focused on improving performance and scale-up with the goal of creating prototypes for commercialization consideration in 2024. | |
| July 2023 | Africa Wide Applies for Reconsideration |
|---|---|
| On July 10, 2023, the Company received notice that Africa Wide had applied to the President of the Supreme Court of Appeal seeking reconsideration of the November 10, 2022, ruling by the South Africa Supreme Court of Appeal dismissing Africa Wide's earlier application seeking leave to appeal the High Court Ruling. The Company and RBPlat opposed the application. (See October 2023 below). |
Fiscal 2024 Developments
| September 2023 | Non-Brokered Private Placement Announced |
|---|---|
| On September 18, 2023, the Company closed a non-brokered private placement of 2,118,645 Common Shares at a price of $1.18 per Common Share with HCI, through its subsidiary Deepkloof, resulting in proceeds to the Company of approximately $2.5 million. The private placement allowed HCI to return to a near 27% interest in the Company. | |
| October 2023 | Supreme Court of Appeal of South Africa dismisses Africa Wide's Application for Reconsideration |
| On October 6, 2023, the Supreme Court of Appeal of South Africa dismissed with costs the application by Africa Wide for the reconsideration of the November 10, 2022, ruling by the South Africa Supreme Court of Appeal dismissing Africa Wide's earlier application seeking leave to appeal the High Court Ruling. The court found that no exceptional circumstances warranting reconsideration or variation of the decision refusing the application for leave to appeal had been established. Africa Wide was again ordered to pay costs. On November 23, 2023, the High Court determined that Africa Wide owed the Company a total of R2.99 million in costs. On November 29, 2023, the Company served Africa Wide by sheriff a demand for payment. | |
| December 2023 | Waterberg JV Co. Approves Stage Three Budget |
| On December 11, 2023, the board of directors of Waterberg JV Co. unanimously approved a work program in the amount of R29.8 million (approximately $1.65 million) for a third stage of work (the "Stage Three Budget") covering a six-month period from September 2023 to February 2024. The shareholders of Waterberg JV Co. also approved the Stage Three Budget, with Implats abstaining. On December 12, 2023, Implats advised that in the current operating environment and following their own restrictions to capital allocation across their portfolio, Implats could not fund their pro rata share of currently approved Waterberg budgets. As a result, Implats' interest in Waterberg JV Co. was diluted. Platinum Group alone elected to fund all of Implats' funding shortfall for the Stage Four Budget. The Stage Three Budget funded continued work activities, including the Waterberg DFS Update, and normal project maintenance. |
| Annual Information Form for the year ended August 31, 2024 | 29 |
|---|
| Platinum Group Announces Cooperation Agreement With Ajlan & Bros Mining & Metals On December 20, 2023, the Company announced a Cooperation Agreement with Ajlan & Bros Mining and Metals Co. ("Ajlan") to study the establishment of a stand-alone platinum group metals smelter and BMR in Saudi Arabia. The Cooperation Agreement encompasses three phases; a global PGE concentrate market study, a definitive feasibility study for the construction and operation of a PGE smelter and BMR in Saudi Arabia ("Smelter DFS"), and an option to form an incorporated 50:50 joint venture following the completion of the Smelter DFS. The Smelter DFS will assume the export of PGE concentrate from the Waterberg Project in South Africa to a port facility in Saudi Arabia. A key requirement would be to secure a long-term permit for the export of unrefined precious metals in concentrate. | |
| January 2024 | Africa Wide pays the High Court determined legal fees and administration expenses to Platinum Group On January 30, 2024, at the offices of Africa Wide's parent company Wesizwe, the Company attempted to serve Africa Wide with a writ of execution. Wesizwe refused to accept delivery. On February 4, 2024, Africa Wide paid the Company R2.99 million (approximately US $159 on that date), which was credited against legal fees in general and administration expenses for the period. |
|---|---|
| March 2024 | Application filed in the High Court against the grant of the Waterberg Mining Right On March 7, 2024, a group claiming to be the rightful leadership of two host communities filed an application in the High Court seeking to set aside the January 28, 2021, grant of the Waterberg Mining Right by the DMR. Many of the applicants participated in the earlier unsuccessful appeals and court actions described above. The applicants have requested condonation for the late filing of this appeal, claim informal rights to two farms overlaying a portion of the Waterberg Mining Right area, object to the grant of the Waterberg Mining Right, and object to the DMR dismissing their appeals on or about October 13, 2022. The two farms in question are not expected to host any significant mine infrastructure. Attorneys acting on behalf of Waterberg JV Co. have filed a notice of opposition and will prepare and file an answering affidavit in due course. |
| April 2024 | Waterberg JV Co. Approves Stage Four Budget On April 3, 2024, the directors, and shareholders of Waterberg JV Co. approved the Stage Four Budget consisting of $1.35 million for continued work on the Waterberg Project to allow the continuation of work programs underway while the Waterberg DFS Update was finalized. The Stage Four Budget covered the period from March 1, 2024, to August 31, 2024. On May 9, 2024, Implats advised that in the current operating environment and following their own approach to capital allocation across their portfolio, Implats could not fund their pro rata share of the Stage Four Budget. As a result, Implats' interest in Waterberg JV Co. was diluted. Platinum Group alone elected to fund all of Implats' funding shortfall for the Stage Four Budget. Implats stated that it would consider the funding of subsequent cash calls as future circumstances allowed. |
| Annual Information Form for the year ended August 31, 2024 | 30 |
|---|
PLATINUM GROUP METALS LTD.
Subsequent to Fiscal 2024 Developments
| September 2024 | Independent Definitive Feasibility Study Update for the Waterberg Mine Announced |
|---|---|
| On September 16, 2024, the Company announced positive results from the Waterberg DFS Update for the Waterberg Project completed by a team of independent specialists including international engineering firm Stantec Consulting International Ltd. ("Stantec") and South African engineering firm DRA Projects SA (Pty) Ltd. ("DRA"). Engineering oversight and project management for the Waterberg DFS Update was provided by South African engineering firm Fraser McGill (Pty) Ltd. ("Fraser McGill"). The Waterberg DFS Update is an update to the original Waterberg DFS published in September 2019. The Waterberg DFS and the Waterberg DFS Update were completed by the same authors and QPs. See "Item 5.3 Mineral Property Interests, Material Mineral Property Interest - Waterberg Project, Technical Report - Waterberg DFS Update, Waterberg Project Summary" for additional information on the Waterberg DFS Update. | |
| October 2024 | Independent Definitive Feasibility Study Update for the Waterberg Mine Filed |
| The Company announced the filing of the Waterberg DFS Update, which is incorporated herein by reference. The Waterberg DFS Update may be accessed on the Company's website at www.platinumgroupmetals.net, on SEDAR+ at www.sedarplus.ca or on EDGAR at www.sec.gov. | |
| November 2024 | 2024 Shelf Prospectus and 2024 Registration Statement Filed |
| On November 13, 2024, the Company filed the 2024 Shelf Prospectus with the securities regulatory authorities in each of the provinces and territories of Canada and the corresponding 2024 Registration Statement with the SEC under the Multijurisdictional Disclosure System established between Canada and the United States. Pursuant to the 2024 Shelf Prospectus and the 2024 Registration Statement, the Company may offer and sell Common Shares, debt securities, warrants, subscription receipts or a combination thereof up to an aggregate initial offering price of $250 million (or its equivalent in Canadian dollars) from time to time, separately or together, in amounts, at prices and on terms to be determined based on market conditions at the time of the offering and as set out in an accompanying prospectus supplement, during the 25-month period that the 2024 Shelf Prospectus and the 2024 Registration Statement remain effective. |
4.2 SIGNIFICANT ACQUISITIONS
The Company has not made any significant acquisitions during its most recently completed financial year for which disclosure is required under Part 8 of NI 51-102.
ITEM 5 DESCRIPTION OF THE COMPANY'S BUSINESS
5.1 OVERVIEW
The Company is a platinum and palladium focused exploration, development and operating company conducting work primarily on mineral properties it has staked or acquired by way of option agreements or applications in the Republic of South Africa.
The Company's sole material mineral property is the Waterberg Project, which is the subject of the Waterberg DFS Update as described in this AIF. The Company's key business objective is to advance the Waterberg Project to a development and construction decision. Before a construction decision can be undertaken, arrangements will be required for project financing and concentrate offtake or processing. The Company and Waterberg JV Co. are assessing commercial alternatives for mine development, concentrate offtake and financing. The Company continues to evaluate exploration opportunities both on currently owned properties and on new prospects.
| Annual Information Form for the year ended August 31, 2024 | 32 |
|---|