Electric Reliability Needs

CECONY monitors the adequacy of the electric capacity resources and related developments in its service area, and works with other parties on long-term resource adequacy within the framework of the NYISO reliability planning process.

In October 2025, the NYISO issued its 2025 Q3 Short-Term Assessment of Reliability (STAR) that identifies a bulk power system electric reliability need in New York City beginning in the summer of 2026 and continuing through 2030. See "Electric Supply" above. The need is primarily driven by forecasted increases in peak demand, deactivation notices of existing generation on the Gowanus and Narrows barges and the uncertainty as to whether certain planned projects will be completed and energized within the forecasted time period (the Gowanus-Greenwood 345-138 kV feeder and the Champlain Hudson Power Express transmission line in May 2026, Empire Wind 1 in July 2027 and Propel NY in May 2030). In its 2025 Q4 STAR report issued in January 2026, the NYISO observed that the scope, scale, and nature of the forecasted reliability need remains unchanged. NYISO previously solicited both market-based and regulated solutions which remain under evaluation by the NYISO.

In December 2025, CECONY issued its preliminary 2025 Local Transmission Plan (LTP), which projected reliability needs in New York driven by increasing load demand, cumulative generator retirements without incremental new generation resources, and reliability design criteria updates. Following CECONY’s preliminary 2025 LTP, the NYSPSC issued an order directing CECONY to develop a reliability contingency plan by June 2026 to address projected reliability needs in New York City.

In January 2026, pursuant to the NYSPSC order, CECONY filed its updated projection of reliability needs in New York City of 125 MW beginning in 2032 and increasing to 750 MW by 2036. Additionally, CECONY issued a Request for Information (RFI) to engage with stakeholders for the submission of feasible, effective, timely and cost-effective options to meet these needs. The RFI will be used to inform CECONY's New York City reliability contingency plan.