FIRSTENERGY CORP
For the period ended Dec 31, 2024. Filed Feb 27, 2025.
View on SEC.govAbout this filing
A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.
FY2024 · Filed Feb 27, 2025
What changed in Risk Factors?
Read the current filingPrevious report: 10-K
Period ended 2023-12-31; filed 2024-02-13.
0001031296-24-000008
Item 1A. RISK FACTORSCurrent report: 10-K
Period ended 2024-12-31; filed 2025-02-27.
0001031296-25-000006
Item 1A. RISK FACTORSThe baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.
Compared 154 previous paragraphs and 156 current paragraphs.
79 unchanged; 61 reworded; 14 added; 14 removed; 0 previous and 2 current paragraphs rearranged.
Tables are not compared: 0 previous and 0 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.
A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.
Added paragraphs (14)
Current report
HB 6-related investigations and litigation could have a material adverse effect on our reputation, business, financial condition, results of operations, our ability to access capital, liquidity or cash flows.
Current report
As of July 22, 2024, we successfully completed the obligations required within the three-year term of the DPA. Under the DPA, and until the conclusion of any related investigation, criminal prosecution and civil proceeding brought by the U.S. Attorney’s Office, we have an obligation to continue (i) publishing quarterly a list of all payments to 501(c)(4) entities and all payments to entities known by us to be operating for the benefit of a public official, either directly or indirectly; (ii) not making any statements that contradict the DPA; (iii) notifying the U.S. Attorney’s Office for the S.D. Ohio of any changes in FirstEnergy’s corporate form; and (iv) cooperating with the U.S. Attorney’s Office for the S.D. Ohio. In accordance with the DPA, these obligations will continue until the completion of any related investigation, criminal prosecution, and civil proceeding brought by the U.S. Attorney’s Office related to the conduct set forth in the DPA’s statement of facts, including the January 17, 2025 indictment against two former FirstEnergy senior officers, described below in “Outlook—Other Legal Proceeding –United States v. Larry Householder, et al.” Within 30 days of those matters concluding, and FirstEnergy’s successful completion of its remaining obligations, the U. S. Attorney’s Office will dismiss the criminal information.
Current report
There are several ongoing HB 6 related state regulatory matters including, but not limited to, the below HB 6-related matters, each of which was stayed for a third time by the PUCO on August 23, 2023, at the request of the U.S. Attorney for the Southern District of Ohio, for a period of an additional six months. The stay on the following matters was lifted on February 26, 2024:
Current report
•On September 8, 2020, the OCC filed motions in the Ohio Companies’ corporate separation audit and DMR audit dockets, requesting the PUCO to open an investigation and management audit, hire an independent auditor, and require FirstEnergy to show it did not improperly use money collected from consumers or violate any utility regulatory laws, rules or orders in its activities regarding HB 6. On February 26, 2024, this proceeding was consolidated with the expanded DCR rider audit proceeding described below and on November 22, 2024, the administrative law judge ordered that the bifurcated portion of the corporate separation audit, discussed further below, be consolidated with the already-consolidated DMR audit and expanded DCR rider audit proceeding. Evidentiary hearings are scheduled to begin May 13, 2025;
Current report
See Note 14, "Regulatory Matters" of the Notes to Consolidated Financial Statements and “Management’s Discussion and Analysis of Financial Condition and Results of Operations—Critical Accounting Policies and Estimates” for additional details on the state regulatory investigations surrounding HB 6.
Current report
Demand for electricity within our service territory could exceed supply capacity, resulting in negative impacts to FirstEnergy’s reputation, results and financial condition, particularly if our systems are not performing as anticipated.
Current report
Recent industry projections reflect the potential for significant growth in energy demand over the next decade. This could be exacerbated if additional generation resources are not available to meet increased demand in the future. For example, data centers have substantially larger load requirements than typical residential or commercial users. New data centers or increase in demand for existing data centers located in our service territories could increase load requirements substantially over the next several years, thereby increasing the aggregate load obligations of the Electric Companies. A need to serve the load obligations of these data centers, which could be up to 5,575 MWs through 2029, has the potential to adversely impact our business, results of operations, financial condition, or cash flows.
Current report
We continue to evaluate the potential impacts of the development, construction, and operation of new data centers in our service territories and will continue to evaluate potential mitigants to these risks. FirstEnergy cannot predict whether the data centers under consideration will ever commence operations or the size of the load obligations of those that do become operational.
Current report
Competitive market forces or adverse regulatory actions may require FirstEnergy to purchase capacity and energy from the market or build additional resources to meet customers’ energy needs in an expedited manner. If that occurs, we may see opposition to recovery of these additional costs and could experience a lag between when costs are incurred and when regulators permit recovery in rates. These situations could have negative impacts on results of operations and cash flows.
Current report
Furthermore, in the event of electricity shortages, our ability to maintain service reliability may be compromised, which could adversely affect our financial performance, customer satisfaction, and compliance with regulatory requirements.
Current report
Our insurance coverage may not provide protection against all significant losses and our ability to obtain insurance coverage, as well as the terms of any available insurance coverage could be materially adversely affected by international, national, state or local events and company-specific events, as well as the financial condition of insurers.
Current report
If we cannot or do not obtain adequate insurance coverage, we may be required to pay costs associated with adverse future events. Through a combination of third-party and self-insurance, we have a comprehensive insurance program in place to provide coverage for various types of risks, including severe weather or other natural disasters, war, terrorism, cyber incidents, liability claims against us, or a combination of other significant unforeseen events that could impact our operations. However, insurance coverage may not continue to be available or may not be available at rates or on terms similar to those presently available to us. Our ability to obtain insurance and the terms of any available insurance coverage could be materially adversely affected by the financial condition of insurers, the impacts of actual or perceived climate-related events, as well as international, national, state, local or company-specific events.
Current report
There may be some instances in which we are not fully insured against all significant losses. A loss for which we are not fully insured could have a material adverse effect on our business, financial condition, results of operations and prospects.
Current report
Furthermore, change or uncertainty in U.S. policies or the policies of other countries and regions in which our suppliers do business, including any changes or uncertainty with respect to U.S. or international trade policies or tariffs, could also disrupt our key suppliers’ operations. The presidential administration has taken action in 2025 to impose substantial new or increased tariffs. Any widespread imposition of new or increased tariffs could have an adverse effect on our results of operations, cash flow and financial condition. New or increased tariffs could also negatively affect U.S. national or regional economies, which also could negatively impact our business and results of operations.
Removed paragraphs (14)
Previous report
If we violate our DPA that we entered into on July 20, 2021, it could have a material adverse effect on our reputation, consolidated financial statements, and our ability to access capital and our liquidity.
Previous report
The SEC investigation and HB 6 related litigation could have a material adverse effect on our reputation, business, financial condition, results of operations, liquidity or cash flows.
Previous report
On August 10, 2020, the SEC, through its Division of Enforcement, issued an order directing an investigation of possible securities laws violations by FirstEnergy, and on September 1, 2020, issued subpoenas to FirstEnergy and certain of its officers. We continue to cooperate with the SEC in their ongoing investigation. We believe that it is probable that FE will incur a loss in connection with the resolution of the SEC’s investigation. Given the ongoing nature and complexity of such investigation, we cannot yet reasonably estimate a loss or range of loss that may arise from the resolution of the SEC investigation, but such resolution could have a material adverse effect on our reputation, business, financial condition, results of operations, liquidity or cash flows.
Previous report
There are several state regulatory matters associated with the ongoing governmental investigations including, but not limited to, the following:
Previous report
•On August 10, 2023, the U.S. Attorney for the Southern District of Ohio requested for the third time that the PUCO stay the below pending HB 6-related matters for a period of six additional months, which was approved by the PUCO on August 23, 2023. On September 22, 2023, OCC filed an application for rehearing challenging the PUCO’s August 23, 2023, order, which the PUCO denied on October 18, 2023. On November 17, 2023, OCC filed an application for rehearing, and on November 27, 2023, the Ohio Companies filed a memorandum contra OCC’s application for rehearing:
Previous report
▪On November 4, 2020, the PUCO initiated an additional corporate separation audit as a result of the FirstEnergy leadership transition announcement made on October 29, 2020.
Previous report
The inability to close the FET minority equity interest sale to Brookfield announced in February 2023 may have material adverse effects on our cash flows, liquidity and financial condition.
Previous report
On February 2, 2023, FE, along with FET, entered into the FET P&SA II with Brookfield and the Brookfield Guarantors, pursuant to which FE agreed to sell to Brookfield at the closing, and Brookfield agreed to purchase from FE, an incremental 30% equity interest in FET for a purchase price of $3.5 billion. The majority of the purchase price is expected to be paid in cash upon closing, and the remainder will be payable by the issuance of secured promissory notes, which is expected to be repaid by the end of 2024. As a result of the consummation of the transaction, Brookfield’s interest in FET will increase from 19.9% to 49.9%, while FE will retain the remaining 50.1% ownership interests of FET. The transaction is subject to customary closing conditions, including approval from the PPUC The FET Minority Equity Interest Sale is expected to close by the end of the first quarter of 2024. Upon closing, FET will continue to be consolidated in FirstEnergy’s financial statements.
Previous report
This transaction involves various inherent risks, such as our ability to obtain the necessary regulatory and other approvals; the timing of and conditions imposed upon us by regulators in connection with such approvals; and our ability to realize the benefits expected from the transaction. In addition, various factors, including prevailing market conditions, could negatively impact the benefits we receive from this transaction. Our failure to consummate this transaction in a timely manner, including satisfying all closing conditions, could have material adverse effects on our cash flows, liquidity and financial condition.
Previous report
Our efforts also could be adversely impacted by any impediments to our ability to finance the proposed expansion projects while maintaining adequate liquidity. There can be no assurance that our investment strategy in our distribution and transmission businesses will deliver the desired result, which could adversely affect our results of operations and financial condition.
Previous report
Particularly, our Utilities and Transmission Companies provide service at rates approved by one or more regulatory commissions. Thus, the rates the Utilities and Transmission Companies are allowed to charge may be decreased as a result of actions taken by FERC or by a state regulatory commission in the states in which our Utilities operate. Also, these rates may not be set to recover such applicable utility's expenses at any given time. Additionally, there may also be a delay between the timing of when costs are incurred and when costs are recovered, if at all. While rate regulation is premised on providing an opportunity to earn a reasonable return on investments and recovery of operating expenses, there can be no assurance that the applicable regulatory commission will determine that all of our costs have been prudently incurred or that the regulatory process in which rates are determined will always result in rates that will produce full recovery of our costs in a timely manner.
Previous report
Signal Peak is currently a party to litigation that is challenging the validity of its permit to expand its mine into adjacent leased federal coal reserves. After receiving initial approval in 2015 from the OSMRE to expand the mine, environmental non-governmental organizations filed suit in the United States District Court for the District of Montana the same year challenging OSMRE’s environmental assessment, which was a finding of no significant impact, and the expansion approval. The District Court affirmed OSMRE’s conclusions. In April 2022, the Ninth Circuit Court reversed the District Court’s ruling affirming the expansion approval and remanded the case back to the District Court. On February 10, 2023, the District Court vacated the permit issued by OSMRE, which restricts Signal Peak’s ability to mine federal coal until OSMRE completes an environmental impact statement and reissues the permit. While the District Court’s ruling is not expected to materially impede Signal Peak’s ability to conduct its mining operations over the next 12-24 months, the inability to successfully obtain the permit from OSMRE would prohibit Signal Peak from mining those adjacent leased federal coal reserves and could further adversely impact Signal Peak from efficiently and economically conducting its mining operations thus reducing its production, cash flow and profitability.
Previous report
Where federal or state legislation mandates the use of renewable fuel sources, such as wind and solar and such legislation does not also provide for adequate cost recovery of our revenue requirements, it could result in significant changes in our business, including material increases in renewable energy credit purchase costs, purchased power costs and capital investments, as such costs are spread over reduced sales volumes. Such mandatory renewable portfolio requirements may have an adverse effect on our financial condition and results of operations.
Previous report
In June 2023, the U.S. Treasury issued additional guidance that eliminated the requirement of corporations to include AMT in quarterly estimated tax payments, pending further guidance on the application and administration of AMT. Therefore, as a result of guidance issued to date, the current forecast of AMT obligation, and the amount of AMT already paid in April 2023, FirstEnergy did not make any additional AMT payments for the 2023 tax year. Until final U.S. Treasury regulations are issued, the amount of AMT FirstEnergy pays could be significantly different than current estimates or it may not be a payer at all. The regulatory treatment of the impacts of this legislation may also be subject to regulation by FERC and/or applicable state regulatory authorities. Any adverse development in this legislation, including guidance from the U.S. Treasury and/or the IRS or unfavorable regulatory treatment, could negatively impact FirstEnergy’s cash flows, results of operations and financial condition.
Reworded paragraphs (61)
Previous wording
On July 21, 2021, we entered into a three-year DPA with the U.S. Attorney’s Office that, subject to court proceedings, resolves the previously disclosed U.S. Attorney’s Office investigation into us relating to our lobbying and governmental affairs activities concerning HB 6. Under the DPA, the U.S. Attorney’s Office filed a single charge alleging that we conspired to commit honest services wire fraud. The DPA provides that the U.S. Attorney’s Office will defer any prosecution of such conspiracy charge and any other criminal or civil case against us in connection with the matters identified therein for a three-year period subject to certain obligations of ours, including, but not limited to, the following: (i) continued cooperation with the U.S. Attorney’s Office in all matters relating to the conduct described in the DPA and other conduct under investigation by the U.S. government; (ii) payment of a criminal monetary penalty totaling $230 million; (iii) publication a list of all payments made in 2021 to either 501(c)(4) entities or to entities known by FirstEnergy to be operating for the benefit of a public official, either directly or indirectly, and updating of the same on a quarterly basis during the term of the DPA; (iv) publication of a public acknowledgement of our conduct, including a statement, as dictated in the DPA, regarding our use of 501(c)(4) entities; and (v) continued implementation and review of our compliance and ethics program, internal controls, policies and procedures designed, implemented and enforced to prevent and detect violations of the U.S. laws throughout its operations, and to take certain related remedial measures. If we are found to have breached the terms of the DPA, the U.S. Attorney’s Office may elect to prosecute, or bring a civil action against, us for conduct alleged in the DPA or known to the government, which could result in fines or penalties and could have a material adverse impact on our reputation or relationships with regulatory and legislative authorities, customers and other stakeholders, as well as our consolidated financial statements. Failure to comply with the DPA, including alleged failures to comply with anti-corruption and anti-bribery laws, may also result in a breach of certain covenants contained in our credit agreements and could result in an event of default under such agreements, and we would not be able to access our credit facilities for additional borrowings and letters of credit during the existence of any such default.
Current wording
On July 21, 2021, we entered into a three-year DPA with the U.S. Attorney’s Office that, subject to court proceedings, resolves the previously disclosed U.S. Attorney’s Office investigation into us relating to our lobbying and governmental affairs activities concerning HB 6. Under the DPA, we paid a $230 million monetary penalty in 2021 and agreed to the filing of a criminal information charging FirstEnergy with one count of conspiracy to commit honest services wire fraud.
Previous wording
We also believe that it is probable that FE will incur a loss in connection with the resolution of In re FirstEnergy Corp. Securities Litigation. Given the ongoing nature and complexity of such litigation, we cannot yet reasonably estimate a loss or range of loss that may arise from its resolution. However, if it is resolved against us substantial monetary damages could result and our reputation, business, financial condition, results of operations, liquidity or cash flows may be materially adversely affected.
Current wording
Following the announcement by the U.S. Attorney’s Office for the S.D. Ohio of the investigation surrounding HB 6 in July 2020, certain of our stockholders and customers filed several lawsuits against us and certain current and former directors, officers and other employees, including the federal securities class action litigation In re FirstEnergy Corp. Securities Litigation (Federal District Court, S.D. Ohio). We believe that it is probable that FE will incur a loss in connection with the resolution of In re FirstEnergy Corp. Securities Litigation. Given the ongoing nature and complexity of such litigation, we cannot yet reasonably estimate a loss or range of loss that may arise from its resolution. However, if it is resolved against us substantial monetary damages could result and our reputation, business, financial condition, results of operations, liquidity or cash flows may be materially adversely affected.
Previous wording
Following the announcement by the U.S. Attorney’s Office for the S.D. Ohio of the investigation surrounding HB 6 in July 2020, certain of our stockholders and customers filed several lawsuits against us and certain current and former directors, officers and other employees, including the federal securities class action litigation In re FirstEnergy Corp. Securities Litigation (Federal District Court, S.D. Ohio). The investigations and litigation related to HB 6 could divert management’s focus and have resulted in, and could continue to result in substantial investigation expenses, and the commitment of substantial corporate resources. The outcome, duration, scope, result or related costs of the investigations and related litigation of the government investigations, particularly the SEC investigation and the securities class action lawsuit discussed below, are inherently uncertain. Therefore, any of these risks could impact us significantly beyond expectations. See Note 14, "Commitments, Guarantees and Contingencies" of the Notes to Consolidated Financial Statements and “Management’s Discussion and Analysis of Financial Condition and Results of Operations—Critical Accounting Policies and Estimates.” Moreover, we are unable to predict the potential for any additional investigations or litigation, any of which could exacerbate these risks or expose us to potential criminal or civil liabilities, sanctions or other remedial measures, and could have a material adverse effect on our reputation, business, financial condition, results of operations, liquidity or cash flows.
Current wording
The litigation related to HB 6 could divert management’s focus and have resulted in, and could continue to result in, substantial expenses, and the commitment of substantial corporate resources. The outcome, duration, scope, result or related costs of the in securities class action litigation In re: FirstEnergy Corp. Securities Litigation discussed above, are inherently uncertain. Therefore, any of these risks could impact us significantly beyond expectations. See Note 15, "Commitments, Guarantees and Contingencies" of the Notes to Consolidated Financial Statements and “Management’s Discussion and Analysis of Financial Condition and Results of Operations—Critical Accounting Policies and Estimates.”
Previous wording
▪On September 15, 2020, the PUCO opened a new proceeding to review the political and charitable spending by the Ohio Companies in support of HB 6 and the subsequent referendum effort.
Current wording
•On September 15, 2020, the PUCO opened a new proceeding to review the political and charitable spending by the Ohio Companies in support of HB 6 and the subsequent referendum effort. On September 30, 2024, the third-party auditor’s report was filed. See ”Outlook - State Regulation - Ohio” below for additional information regarding the auditor’s findings. Comments have been filed on the audit report and remain pending with the PUCO;
Previous wording
▪On December 30, 2020, the PUCO directed PUCO staff to solicit a third-party auditor and conduct a full review of the DMR to ensure funds collected from customers through the DMR were only used for the purposes established in ESP IV. The auditor’s report was filed on January 14, 2022, and the parties submitted final comments and responses in the second quarter 2022. See ”Outlook – Ohio” below for additional information regarding the auditor’s findings.
Current wording
•On December 30, 2020, the PUCO directed PUCO staff to solicit a third-party auditor and conduct a full review of the DMR to ensure funds collected from customers through the DMR were only used for the purposes established in ESP IV. The auditor’s report was filed on January 14, 2022, and the parties submitted final comments and responses in the second quarter 2022. See ”Outlook - State Regulation - Ohio” below for additional information regarding the auditor’s findings. On February 26, 2024, this proceeding was consolidated with the expanded DCR rider audit proceeding described below and on November 22, 2024, the administrative law judge ordered that the bifurcated portion of the corporate separation audit, discussed further below, be consolidated with the already-consolidated DMR audit and expanded DCR rider audit proceeding. Evidentiary hearings are scheduled to begin May 13, 2025; and
Previous wording
•On March 10, 2021, the PUCO expanded the scope of an ongoing annual audit of the Ohio Companies’ Rider DCR for 2020 to include a review of certain transactions that were either improperly classified, misallocated, or lacked supporting documentation, and to determine whether funds collected from customers were used to pay the vendors, and if so, whether or not the funds associated with those payments should be returned to customers through Rider DCR or through an alternative proceeding.
Current wording
•On March 10, 2021, the PUCO expanded the scope of an ongoing annual audit of the Ohio Companies’ Rider DCR for 2020 to include a review of certain transactions that were either improperly classified, misallocated, or lacked supporting documentation, and to determine whether funds collected from customers were used to pay the vendors, and if so, whether or not the funds associated with those payments should be returned to customers through Rider DCR or through an alternative proceeding. On February 26, 2024, this proceeding was consolidated with the Rider DMR audit proceeding described above, and further lifted the stay of the portion of the investigation relating to an apparent nondisclosure of a side agreement. On November 22, 2024, the administrative law judge ordered that the bifurcated portion of the corporate separation audit be consolidated with the already-consolidated DMR audit and the expanded DCR rider audit proceeding. Evidentiary hearings are scheduled to begin May 13, 2025.
Previous wording
While FirstEnergy is committed to pursuing an open dialogue with stakeholders in an appropriate manner with respect to the numerous regulatory proceedings currently underway, FirstEnergy shareholders in particular are at risk of being adversely impacted because the rates our Utilities and Transmission Companies are allowed to charge may be decreased as a result of actions taken by a regulator to which our Utilities and Transmission Companies are subject to jurisdiction, whether as a result of the DPA, any failure to have complied with anti-corruption laws, or otherwise.
Current wording
While FirstEnergy is committed to pursuing an open dialogue with stakeholders in an appropriate manner with respect to the numerous regulatory proceedings currently underway, FirstEnergy shareholders in particular are at risk of being adversely impacted because the rates our Electric Companies and Transmission Companies are allowed to charge may be decreased as a result of actions taken by a regulator to which our Electric Companies and Transmission Companies are subject to jurisdiction, whether as a result of the DPA, any failure to have complied with anti-corruption laws, or otherwise.
Previous wording
Our reputation is important. Damage to our reputation could materially adversely affect our business, results of operations, and financial condition and may arise from numerous sources further discussed below, including a breach of the DPA, negative outcomes associated with the SEC investigation or other HB 6 litigation or investigations, a significant cyber-attack, data security or physical security breach, failure to provide safe and reliable service, and negative perceptions regarding the operation of coal-fired generation, particularly GHG emissions. Any damage to our reputation may lead to negative customer perception, which may make it difficult for us to compete successfully for new opportunities, or could adversely impact our ability to launch new sophisticated technology-driven solutions to meet our customer expectations. A damaged reputation could further result in FERC, the PUCO, and other regulatory and legislative authorities being less likely to view us in a favorable light, and could negatively impact the rates we charge customers or otherwise cause us to be susceptible to unfavorable legislative and regulatory outcomes, as well as increased regulatory oversight and more stringent legislative or regulatory requirements. See "Risks Associated with Climate Change, GHG Emission and Other Environmental Matters" below.
Current wording
Our reputation is important. Damage to our reputation could materially adversely affect our business, results of operations and financial condition. Such damage may arise from numerous sources further discussed generally within these risk factors. Any damage to our reputation, either generally or as a result of the foregoing, may lead to negative customer perception, which may make it difficult for us to compete successfully for new opportunities, or could adversely impact our ability to launch new sophisticated technology-driven solutions to meet our customer expectations. A damaged reputation could further result in FERC, the state public utility commissions, and other regulatory and legislative authorities being less likely to view us in a favorable light and could negatively impact the rates we charge customers or otherwise cause us to be susceptible to unfavorable legislative and regulatory outcomes, as well as increased regulatory oversight and more stringent legislative or regulatory requirements.
Previous wording
FirstEnergy is engaged in an ongoing effort to create a culture of continuous improvement to strategically reduce our operating expenditures and continually reinvest in a more diverse capital program in support of our long-term strategy. FirstEnergy leverages opportunities to reduce costs – such as filling only critical positions, implementing our facility optimization plans, as well as exploring other additional, sustainable opportunities, such as reducing contractor spend. There can be no assurance that implementation of our continuous improvement culture will allow us to realize the anticipated benefits to our business, results of operations and financial condition in a timely manner, if at all.
Current wording
FirstEnergy is engaged in an ongoing effort to create a culture of continuous improvement to strategically reduce our operating expenditures and continually reinvest in a more diverse capital program in support of our long-term strategy. FirstEnergy leverages opportunities to reduce costs – such as filling only critical positions, implementing our facility optimization plans, and exploring other additional, sustainable opportunities, such as reducing contractor spend. There can be no assurance that implementation of our continuous improvement culture will allow us to realize the anticipated benefits to our business, results of operations and financial condition in a timely manner, if at all.
Previous wording
Our ability to capitalize on investment opportunities available to our distribution business depends, in part, on any future distribution rate cases or other filings seeking cost recovery for distribution system enhancements in the states where our Utilities operate and transmission rate filings at FERC, including maintaining the affordability of the rates charged to customers. Any denial of, or delay in, the approval of any future distribution or transmission rate requests could restrict us from fully recovering our cost of service, may impose risks on the distribution and transmission operations, and could have a material adverse effect on our regulatory strategy, results of operations and financial condition.
Current wording
Our ability to capitalize on investment opportunities available to our distribution business depends, in part, on any future distribution rate cases or other filings seeking cost recovery for distribution system enhancements in the states where our Electric Companies operate, including maintaining the affordability of the rates charged to customers. Any denial of, or delay in, the approval of any future distribution or transmission rate requests could restrict us from fully recovering our cost of service, may impose risks on the distribution and transmission operations, and could have a material adverse effect on our regulatory strategy, results of operations and financial condition.
Previous wording
Each of the Utilities' retail rates are set by its respective regulatory agency for utilities in the state in which it operates - in Maryland by the MDPSC, in New Jersey by the NJBPU, in Ohio by the PUCO, in Pennsylvania by the PPUC, in West Virginia by the WVPSC and in New York by the NYPSC – through traditional, cost-based regulated utility ratemaking. As a result, any of the Utilities may not be permitted to recover its costs and, even if it is able to do so, there may be a significant delay between the time it incurs such costs and the time it is allowed to recover them. Factors that may affect outcomes in the distribution rate cases include, but are not limited to: (i) the value of plant in service; (ii) authorized rate of return; (iii) capital structure (including hypothetical capital structures); (iv) depreciation rates; (v) the allocation of shared costs, including consolidated deferred income taxes and income taxes payable across the Utilities; (vi) regulatory approval of rate recovery mechanisms for capital investment spending programs; and (vii) the accuracy of forecasts used for ratemaking purposes in "future test year" cases.
Current wording
The retail rates for each of the Electric Companies are set by each of its respective regulatory agency for utilities in the state in which it operates - in Maryland by the MDPSC, in New Jersey by the NJBPU, in Ohio by the PUCO, in Pennsylvania by the PPUC, in West Virginia by the WVPSC and in New York by the NYPSC – through traditional, cost-based regulated utility ratemaking. As a result, any of the Electric Companies may not be permitted to recover its costs and, even if it is able to do so, there may be a significant delay between the time it incurs such costs and the time it is allowed to recover them. Factors that may affect outcomes in the distribution rate cases include, but are not limited to: (i) the value of plant in service; (ii) authorized rate of return; (iii) capital structure (including hypothetical capital structures); (iv) depreciation rates; (v) the allocation of shared costs, including consolidated deferred income taxes and income taxes payable across the Electric Companies; (vi) regulatory approval of rate recovery mechanisms for capital investment spending programs; and (vii) the accuracy of forecasts used for ratemaking purposes in "future test year" cases.
Previous wording
FirstEnergy can provide no assurance that any base rate request filed by any of the Utilities will be granted in whole or in part. Any denial of, or delay in, any base rate request could restrict the applicable utility from fully recovering its costs of service, may impose risks on its operations, and may negatively impact such Utility’s results of operations, cash flows and financial condition. In addition, to the extent that any of the Utilities seeks an increase in rates, pressure may be exerted on the applicable legislators and regulators to take steps to control rate increases, including through some form of rate increase moderation, reduction or freeze. Any related public discourse and debate, including with respect to the HB 6 investigation or litigation, can increase uncertainty associated with the regulatory process, the level of rates and revenues that are ultimately obtained, and the ability of the Utility to recover costs. Such uncertainty may restrict operational flexibility and resources, reduce liquidity and increase financing costs.
Current wording
FirstEnergy can provide no assurance that any base rate request filed by any of the Electric Companies will be granted in whole or in part. Any denial of, or delay in, any base rate request could restrict the applicable utility from fully recovering its costs of service, may impose risks on its operations, and may negatively impact such Electric Company’s results of operations, cash flows and financial condition. In addition, to the extent that any of the Electric Companies seek an increase in rates, third-party pressure may be exerted on the applicable legislators and regulators to take steps to control rate increases, including through some form of rate increase moderation, reduction or freeze. Any related public discourse and debate, including with respect to the HB 6 litigation, can increase uncertainty associated with the regulatory process, the level of rates and revenues that are ultimately obtained, and the ability of the Electric Company to recover costs. Such uncertainty may restrict operational flexibility and resources, reduce liquidity and increase financing costs.
Previous wording
Complex and changing government regulations and actions, including those associated with rates, could have a negative impact on our business, financial condition, results of operations and cash flows.
Current wording
Complex and changing federal, state and local government regulations and actions, including those associated with rates, could have a negative impact on our business, financial condition, results of operations and cash flows.
Previous wording
We are subject to comprehensive regulation by various federal, state and local regulatory agencies that significantly influence our operating environment. Changes in, or reinterpretations of, existing laws or regulations, or the imposition of new laws or regulations, have in the past and could in the future require us to incur additional costs, which could be substantial, or change the way we conduct our business, and therefore could have a material adverse impact on our results of operations and financial condition.
Current wording
We are subject to comprehensive regulation by various federal, state and local regulatory agencies that significantly influence our operating environment. Changes in, or reinterpretations of, existing laws or regulations, or the imposition of new laws or regulations, by federal executive orders or otherwise, have in the past and could in the future require us to incur additional costs, which could be substantial, or change the way we conduct our business, and therefore could have a material adverse impact on our results of operations and financial condition.
Previous wording
As a member of PJM, which is an RTO, we are subject to certain additional risks, including those associated with the allocation among members of losses caused by unreimbursed defaults of other participants in PJM’s market and those associated with complaint cases filed against PJM that may seek refunds of revenues previously earned by its members.
Current wording
As a member of PJM, which is an RTO, we are subject to certain additional risks, including those associated with the allocation among members of losses caused by unreimbursed defaults of other participants in PJM’s market, as well as those associated with complaint cases filed against PJM that may seek refunds of revenues previously earned by its members.
Previous wording
Power generation involves hazardous activities, including acquiring, transporting and unloading fuel, operating large pieces of rotating equipment and delivering electricity to transmission and distribution systems. In addition to natural risks, such as earthquakes, floods, lightning, hurricanes and wind, hazards, such as fire, explosion, collapse and machinery failure, are inherent risks in our operations which may occur as a result of inadequate internal processes, technological flaws, human error or actions of third parties or other external events. The control and management of these risks depend upon adequate development and training of personnel and on operational procedures, preventative maintenance plans, and specific programs supported by quality control systems, which may not prevent the occurrence and impact of these risks.
Current wording
Power generation involves hazardous activities, including acquiring, transporting and unloading fuel, operating large pieces of rotating equipment and delivering electricity to transmission and distribution systems. In addition to naturally occurring risks, such as earthquakes, floods, lightning, wildfire, hurricanes and wind, other hazards, such as fire, explosion, electrocution, collapse and machinery failure, are inherent risks in our operations which may occur as a result of inadequate internal processes, technological flaws, human error or actions of third parties or other external events. The identification, control and management of these risks depend upon adequate development and training of personnel and on operational procedures, preventative maintenance plans, and specific programs supported by quality control systems, which may not prevent the occurrence and impact of these risks.
Previous wording
Weather conditions directly influence the demand for electric power. Demand for power generally peaks during the summer and winter months, with market prices also typically peaking at that time. Overall operating results may fluctuate based on weather conditions. In addition, we have historically sold less power, and consequently received less revenue, when seasonal weather conditions are milder. For example, in 2023, residential and commercial distribution deliveries were impacted by lower customer usage as a result of the weather. Heating degree days in 2023 were 14% below 2022 and 15% below normal. Cooling degree days in 2023 were 23% below 2022 and 15% below normal.
Current wording
Weather conditions directly influence the demand for electric power. Demand for power generally peaks during the summer and winter months, with market prices also typically peaking at that time. Overall operating results may fluctuate based on weather conditions. In addition, we have historically sold less power, and consequently received less revenue, when seasonal weather conditions are milder. For example, in 2024, heating degree days in 2024 were 1% below 2023 and 15% below normal.
Previous wording
In the ordinary course of our business, we depend on information technology systems that utilize sophisticated operational systems and network infrastructure to run all facets of our regulated generation, transmission and distribution services. Additionally, we store sensitive data, intellectual property and proprietary or personally identifiable information regarding our business, employees, shareholders, customers, suppliers, business partners and other individuals in our data centers and on our networks. We may also need to provide sensitive data to vendors and service providers who require access to this information. The secure maintenance of information and information technology systems is critical to our operations.
Current wording
In the ordinary course of our business, we depend on information technology systems that utilize sophisticated operational systems and network infrastructure to run all facets of our generation, transmission and distribution services. Additionally, we store sensitive data, intellectual property and proprietary or personally identifiable information regarding our business, employees, shareholders, customers, suppliers, business partners and other individuals in our data centers and on our networks. We may also need to provide sensitive data to vendors and service providers who require access to this information. The secure maintenance of information and information technology systems is critical to our operations.
Previous wording
Over the last several years, there has been an increase in the frequency of cyber-attacks by terrorists, hackers, international activist organizations, foreign governments and individuals. These and other unauthorized parties may attempt to gain access to our network systems or facilities, or those of third parties with whom we do business in many ways, including directly through our network infrastructure or through fraud, trickery, or other forms of deception against our employees, contractors and temporary staff. Additionally, our information and information technology systems and those of our vendors and service providers may be increasingly vulnerable to data security breaches, damage and/or interruption due to viruses, ransomware, unauthorized physical access, theft of access devices, human error, malfeasance, faulty password management or other malfunctions and disruptions. Further, hardware, software, or applications we develop or procure from third parties may contain defects in design or manufacture or other problems that could unexpectedly compromise information and/or security.
Current wording
Over the last several years, there has been an increase in the frequency of cyber-attacks by terrorists, hackers, international activist organizations, foreign governments and individuals. These and other unauthorized parties may attempt to gain access to our network systems or facilities, or those of third parties with whom we do business, including directly through our network infrastructure or through fraud, trickery, or other forms of deception against our employees, contractors and temporary staff. Additionally, our information and information technology systems and those of our vendors and service providers may be increasingly vulnerable to data security breaches, damage and/or interruption due to viruses, ransomware, unauthorized physical access, theft of access devices, human error, malfeasance, faulty password management or other malfunctions and disruptions. Further, hardware, software, or applications we develop or procure from third parties may contain defects in design or manufacture or other problems that could unexpectedly compromise information and/or security.
Previous wording
As a source of critical infrastructure, the energy industry is at heightened threat of cyber-attacks, which are becoming increasingly more difficult to anticipate and prevent due to their rapidly evolving nature. We cannot anticipate, detect, or implement fully preventive measures against all cyber security threats because the techniques used are increasingly sophisticated and constantly evolving. For example, as artificial intelligence continues to evolve, cyber-attackers could use artificial intelligence to develop malicious code, denial-of-service attacks, sophisticated phishing attempts and other attacks leading to data loss, loss of operational control, or exploitation of inherent vulnerabilities.
Current wording
As a source of critical infrastructure, the energy industry is at heightened threat of cyber-attacks, which are becoming increasingly more difficult to anticipate and prevent due to their rapidly evolving nature. We cannot anticipate, detect, or implement fully preventive measures against all cybersecurity threats because the techniques used are increasingly sophisticated and constantly evolving and in some cases, assisted by artificial intelligence.
Previous wording
In addition, the increased use of smartphones, tablets, and other wireless devices, as well as ongoing remote work-from-home arrangements for a substantial portion of our corporate employees, may also heighten these and other operational risks. Furthermore, economic sanctions issued by one country against another, such as those issued by the U.S. and other countries against Russia in response to its war with Ukraine, or other increasing global geopolitical tensions, such as the war between Israel and Hamas, could increase the risk of state-sponsored cyber-attacks.
Current wording
In addition, the increased use of smartphones, tablets, and other wireless devices, as well as ongoing remote work-from-home arrangements, may also heighten these and other operational risks.
Previous wording
Despite security measures and safeguards we have employed, including certain measures implemented pursuant to mandatory NERC Critical Infrastructure Protection standards, our infrastructure, as well as the transmission facilities of third parties with whom we are interconnected, may be increasingly vulnerable to such attacks as a result of the rapidly evolving and increasingly sophisticated means by which attempts to defeat security measures and gain access to our information technology systems may be made. Because our transmission facilities are interconnected with those of third parties, the operation of our facilities could be adversely affected by cyber-attacks or other unexpected or uncontrollable events occurring on the systems of such third parties. Given the rapidly evolving nature, sophistication, and complexity of cyber-attacks, despite our reasonable efforts to mitigate and prevent such attacks, it is possible that we may not be able to anticipate, prevent, detect, or implement effective preventive measures to protect against all cyber-attack incidents.
Current wording
Our generation, transmission and distribution infrastructure, as well as the transmission facilities of third parties with whom we are interconnected, may be increasingly vulnerable to such attacks as a result of the rapidly evolving and increasingly sophisticated means by which attempts to defeat security measures and gain access to our information technology systems may be made. As our transmission facilities are interconnected with those of third parties, the operation of our facilities could be adversely affected by cyber-attacks or other unexpected or uncontrollable events occurring on the systems of such third parties.
Previous wording
Any actual or perceived cyber-attack, data security breach, damage, interruption and/or defect could: (i) disable our generation, transmission (including our interconnected regional transmission grid) and/or distribution services for a significant period of time; (ii) delay development and construction of new facilities or capital improvement projects; (iii) adversely affect our customer operations; (iv) expose us to increased risk of lawsuits; (v) expose us to increased risk of regulatory penalties; (vi) expose us to increased risk of loss of potential or existing customers; (vii) expose us to increased risk of damage relating to loss of proprietary information; (viii) corrupt data; and/or (ix) result in unauthorized access to the information stored in our data centers and on our networks and those of our vendors and service providers, including, company proprietary information, supplier information, employee data, and personal customer data, causing the information to be publicly disclosed, lost or stolen or result in incidents that could result in economic loss and liability and harmful effects on the environment and human health, including loss of life. Additionally, because our regulated generation, transmission and distribution services are part of an interconnected system, disruption caused by a cyber security incident at another utility, electric generator, RTO, or commodity supplier could also adversely affect our operations.
Current wording
Any actual or perceived cyber-attack, data security breach, damage, interruption and/or defect could: (i) disable our generation, transmission and/or distribution services for a significant period of time; (ii) delay development and construction of new facilities or capital improvement projects; (iii) adversely affect our customer operations; (iv) expose us to increased risk of lawsuits; (v) expose us to increased risk of regulatory penalties; (vi) expose us to increased risk of loss of potential or existing customers; (vii) expose us to increased risk of damage relating to loss of proprietary information; (viii) corrupt data; and/or (ix) result in unauthorized access to the information stored in our data centers and on our networks and those of our vendors and service providers, including company proprietary information, supplier information, employee data and personal customer data, causing the information to be publicly disclosed, lost or stolen or result in incidents that could result in economic loss and liability and harmful effects on the environment and human health, including loss of life.
Previous wording
Although we maintain cyber insurance and property and casualty insurance, there can be no assurance that liabilities or losses we may incur, including as a result of cyber security-related litigation, will be covered under such policies or that the amount of insurance will be adequate. Further, as cyber threats continually evolve and become more difficult to detect and successfully defend against, there can be no assurance that we can implement or maintain adequate preventive measures, accurately assess the likelihood of a cyber-incident or quantify potential liabilities or losses. Also, we may not discover any data security breach and loss of information for a significant period of time after the data security breach occurs particularly those of our vendors and service providers.
Current wording
As cyber threats continually evolve and become more difficult to detect and successfully defend against, there can be no assurance that we can implement or maintain adequate preventive measures, accurately assess the likelihood of a cyber-incident or quantify potential liabilities or losses. Also, we may not discover any data security breach and loss of information for a significant period of time after the data security breach occurs, particularly when the breach has occurred on the systems of our vendors and service providers.
Previous wording
For all of these reasons, any such cyber incident could result in significant lost revenue, the inability to conduct critical business functions and serve customers for a significant period of time, the loss of confidential, sensitive, and proprietary information, including but not limited to personal information of our customers, employees, suppliers, vendors and other third parties, the use of significant management resources, legal claims or proceedings, regulatory penalties, significant remediation costs, increased regulation, increased capital costs, increased insurance costs, increased protection costs for enhanced cyber security systems or personnel, damage to our reputation and/or the rendering of our internal controls ineffective, all of which could materially adversely affect our business, results of operations, financial condition and reputation.
Current wording
For all of these reasons, any such cyber incident could result in significant lost revenue, the inability to conduct critical business functions and serve customers for a significant period of time, the loss of confidential, sensitive and proprietary information, including but not limited to personal information of our customers, employees, suppliers, vendors and other third parties, the use of significant management resources, legal claims or proceedings, regulatory penalties, significant remediation costs, increased regulation, increased capital costs, increased insurance costs, increased protection costs for enhanced cyber security systems or personnel, and/or damage to our reputation, all of which could materially adversely affect our business, results of operations, financial condition and reputation.
Previous wording
Inflation and interest rate pressures may negatively impact our financial condition, results of operations, liquidity, and cash flows.
Current wording
Macroeconomic conditions that are beyond our control, such as government fiscal policy, tariffs, recessions, inflation and interest rate pressures, may negatively impact our financial condition, results of operations, liquidity, and cash flows.
Previous wording
Prices for equipment, materials, supplies, employee labor contractor services, together with the cost of variable-rate debt have increased during 2023, and could continue to increase in 2024 and beyond. Long-term inflationary pressures may result in such prices continuing to increase more quickly than expected. Inflation increases costs for labor, materials and services, and we may be unable to secure these resources on economically acceptable terms or offset such costs with increased revenues, operating efficiencies, or cost savings, which may adversely impact our financial condition, results of operations, liquidity, and cash flows.
Current wording
Economic conditions, including those that may arise from government fiscal policy, tariffs, recessions, inflationary and interest rate pressures, may impact the demand for electricity and, therefore, any decline in economic conditions could lead to declines in the demand for electricity, which would reduce our revenues. Prices for equipment, materials, supplies, employee labor contractor services, together with the cost of variable-rate debt, have increased in recent years and could continue to increase in 2025 and beyond. Long-term inflationary pressures may result in such prices continuing to increase more quickly than expected. Inflation increases costs for labor, materials and services, and we may be unable to secure these resources on economically acceptable terms or offset such costs with increased revenues, operating efficiencies, or cost savings, which may adversely impact our financial condition, results of operations, liquidity, and cash flows.
Previous wording
We have near-term exposure to interest rates from outstanding short-term indebtedness indexed to variable interest rates, and we have exposure to future interest rates to the extent we seek to raise long-term debt in the capital markets to meet maturing debt obligations and fund construction or other investment opportunities. Past disruptions in capital and credit markets, as well as the U.S. Federal Reserve's interest rate policies, have resulted in volatile interest rates on new publicly issued debt securities and increased costs for variable interest rate debt securities. Disruptions in capital and credit markets, or the Federal Reserve Board's interest rate policies, could result in volatile interest rates on new publicly issued debt securities and increase our financing costs and adversely affect our results of operations, cash flows and liquidity. Also, interest rates could change as a result of economic or other events that are beyond our risk management processes. As a result, we cannot always predict the impact that our risk management decisions may have if actual events lead to greater losses or costs than our risk management positions were intended to hedge. Although we employ risk management techniques to hedge against interest rate volatility, significant and sustained increases in market interest rates could materially increase our financing costs and negatively impact our reported results of operations, cash flows and liquidity.
Current wording
We have near-term exposure to interest rates from outstanding short-term indebtedness indexed to variable interest rates, and we have exposure to future interest rates to the extent we seek to raise long-term debt in the capital markets to meet maturing debt obligations and fund construction or other investment opportunities. Past disruptions in capital and credit markets, as well as the U.S. Federal Reserve's interest rate policies, have resulted in volatile interest rates on new publicly issued debt securities and increased costs for variable interest rate debt securities. Disruptions in capital and credit markets, or the Federal Reserve Board's interest rate policies, could result in volatile interest rates on new publicly issued debt securities and increase our financing costs and adversely affect our results of operations, cash flows and liquidity. Also, interest rates could change as a result of economic or other events that are beyond the control of our risk management processes. As a result, we cannot always predict the impact that our risk management decisions may have if actual events lead to greater losses or costs than our risk management positions were intended to hedge. Significant and sustained increases in market interest rates could materially increase our financing costs and negatively impact our reported results of operations, cash flows and liquidity.
Previous wording
We have continued to experience supply chain challenges due to economic conditions that developed during the COVID-19 pandemic, with order lead times increasing across numerous material categories and with some as much as tripling from pre-pandemic lead times. Several key suppliers have struggled with labor shortages and raw material availability, which along with increasing inflationary pressure, have increased the costs and decreased the availability of certain materials, equipment and contractors. FirstEnergy has taken steps to mitigate these risks and does not currently expect service disruptions or any material impact on its capital spending plan. However, the situation is subject to change and a prolonged continuation or further increase in supply chain disruptions could have an adverse effect on FirstEnergy’s results of operations, cash flow and financial condition.
Current wording
We continue to experience supply chain challenges due to economic conditions that developed during the COVID-19 pandemic and have continued in the years since, with order lead times increasing across numerous material categories, some of which remained elevated through 2024 and into 2025. The situation is fluid and a prolonged continuation or further increase in supply chain disruptions could have an adverse effect on FirstEnergy’s results of operations, cash flow and financial condition. Such disruptions could be exacerbated by unstable or uncertain macroeconomic conditions, including inflationary pressures. Any significant disruption or increased costs arising from these pressures on our suppliers may inhibit our access to, or require us to spend more money to source, certain products or that we use in our operations.
Previous wording
Our business follows economic cycles. Economic conditions, including inflationary and interest rate pressures, impact the demand for electricity and therefore declines in the demand for electricity will reduce our revenues. The regional economy in which our Utilities operate is influenced by conditions in industries in our business territories, e.g., data centers, shale gas, automotive, chemical, steel and other heavy industries, and as these conditions and resultant demand of those industries for electricity generation changes, our revenues will be impacted.
Current wording
Our business follows economic cycles. The regional economy in which our Electric Companies operate is influenced by conditions in industries in our business territories, e.g., data centers, shale gas, automotive, chemical, steel and other heavy industries, and as these conditions and resultant demand of those industries for electricity generation changes, our revenues will be impacted.
Previous wording
Our Energize365 business plan calls for extensive capital investments totaling approximately $26 billion from 2024 through 2028, including but not limited to our transmission expansion program and our distribution grid modernization, resiliency and reliability programs. We may be exposed to the risk of substantial price increases in, or the adequacy or availability of, the costs of labor and materials used in construction, nonperformance of equipment and increased costs due to inflation, delays, including delays relating to the procurement of permits or approvals, adverse weather or environmental matters. We engage numerous contractors and enter into a large number of construction agreements to acquire the necessary materials and/or obtain the required construction-related services. As a result, we are also exposed to the risk that these contractors and other counterparties could breach their obligations to us. Such risk could include our contractors’ inabilities to procure sufficient skilled labor as well as potential work stoppages by that labor force. Should the counterparties to these arrangements fail to perform, we may be forced to enter into alternative arrangements at then-current market prices that may exceed our contractual prices, with resulting delays in those and other projects. Although our agreements are designed to mitigate the consequences of a potential default by the counterparty, our actual exposure may be greater than these mitigation provisions. Also, because we enter into construction agreements for the necessary materials and to obtain the required construction related services, any cancellation by FirstEnergy of a construction agreement could result in significant termination payments or penalties. Any delays, increased costs or losses, or cancellation of a construction project could adversely affect our business and results of operations, particularly if we are not permitted to recover any such costs in rates.
Current wording
Our Energize365 business plan calls for extensive capital investments totaling approximately $28 billion from 2025 through 2029, including but not limited to our transmission expansion program and our distribution grid modernization, resiliency and reliability programs. We may be exposed to the risk of substantial price increases in, or the adequacy or availability of, the costs of labor and materials used in construction, nonperformance of equipment and increased costs due to inflation, interest rates or other macroeconomic forces, delays, including delays relating to the procurement of permits or approvals, adverse weather or environmental matters. We engage numerous contractors and enter into a large number of construction agreements to acquire the necessary materials and/or obtain the required construction-related services. As a result, we are also exposed to the risk that these contractors and other counterparties could breach their obligations to us. Such risk could include our contractors’ inabilities to procure sufficient skilled labor as well as potential work stoppages by that labor force. Should the counterparties to these arrangements fail to perform, we may be forced to enter into alternative arrangements at then-current market prices that may exceed our contractual prices, with resulting delays in those and other projects. Although our agreements are designed to mitigate the consequences of a potential default by the counterparty, our actual exposure may be greater than these mitigation provisions. Also, because we enter into construction agreements for the necessary materials and to obtain the required construction related services, any cancellation by FirstEnergy of a construction agreement could result in significant termination payments or penalties. Any delays, increased costs or losses, or cancellation of a construction project could adversely affect our business and results of operations, particularly if we are not permitted to recover any such costs in rates.
Previous wording
We are committed to providing safe and reliable service and equipment in our franchised service territories. Meeting this commitment requires the expenditure of significant capital resources. However, our employees, contractors and the general public may be exposed to dangerous environments due to the nature of our operations. Failure to provide safe and reliable service and equipment due to various factors, including cyber or physical attacks, equipment failure, accidents weather or natural disasters, could result in serious injury or loss of life that may harm our business reputation and adversely affect our operating results through reduced revenues, increased capital and operating costs, litigation or the imposition of penalties/fines or other adverse regulatory outcomes.
Current wording
We are committed to providing safe and reliable service and equipment in our franchised service territories. Meeting this commitment requires the expenditure of significant capital resources. However, our employees, contractors and the general public may be exposed to dangerous environments due to the nature of our operations. Failure to provide safe and reliable service and equipment due to various factors, including cyber or physical attacks, equipment failure, accidents, human error, weather or natural disasters, could result in serious injury or loss of life that may harm our business reputation and adversely affect our operating results through reduced revenues, increased capital and operating costs, litigation or the imposition of penalties/fines or other adverse regulatory outcomes.
Previous wording
We are involved in a number of litigation, arbitration, mediation, and similar proceedings, including with respect to asbestos claims. These and other matters may divert financial and management resources that would otherwise be used to benefit our operations. Further, no assurances can be given that the resolution of these matters will be favorable to us. If certain matters were ultimately resolved unfavorably to us, the results of operations and financial condition of FirstEnergy could be materially adversely impacted.
Current wording
We are involved in a number of litigation, arbitration, mediation, and similar proceedings, including with respect to asbestos claims. These and other matters may divert financial and management resources that would otherwise be used to benefit our operations. Further, no assurances can be given that the resolution of these matters will be favorable to us. If certain matters were ultimately resolved unfavorably to us, our results of operations and financial condition could be materially adversely impacted. See Note 15. “Commitments, Guaranties and Contingencies” of the Notes to Consolidated Financial Statements for a summary of such matters.
Previous wording
We are continually challenged to find ways to balance the retention of our aging skilled workforce while recruiting new talent to mitigate losses in critical knowledge and skills due to retirements. Workforce demographic issues challenge employers nationwide and are of particular concern to the electric utility industry. On May 9, 2023, FirstEnergy announced a voluntary retirement program for eligible non-bargaining employees, known as the PEER. More than 65% of eligible employees, totaling approximately 450 employees, accepted the PEER, which included lump sum compensation equivalent to severance benefits, healthcare continuation costs and a temporary pension enhancement. Most PEER participating employees departed in 2023. Our costs, including costs for contractors to replace employees and productivity costs, may rise. Failure to hire and adequately train replacement employees, including the transfer of significant internal historical knowledge and expertise to the new employees, may adversely affect our ability to manage and operate our business. If we are unable to successfully recruit and retain an appropriately qualified workforce, our results of operations could be negatively affected.
Current wording
We are continually challenged to find ways to balance the retention of our aging skilled workforce while recruiting new talent to mitigate losses in critical knowledge and skills due to retirements. Workforce demographic issues challenge employers nationwide and are of particular concern to the electric utility industry. Our costs, including costs for contractors to replace employees and productivity costs, may rise. Failure to hire and adequately train replacement employees, including the transfer of significant internal historical knowledge and expertise to the new employees, may adversely affect our ability to manage and operate our business. If we are unable to successfully recruit and retain an appropriately qualified workforce, our results of operations could be negatively affected.
Previous wording
Advances and widespread adoption in distributed generation and regulatory policies may make our facilities significantly less competitive and adversely affect our results of operations.
Current wording
Advances in and widespread adoption of distributed generation and regulatory policies may make our facilities significantly less competitive and adversely affect our results of operations.
Previous wording
Energy companies are subject to adverse publicity causing less favorable regulatory and legislative outcomes which could have an adverse impact on our business.
Current wording
Energy companies are subject to adverse publicity that makes them vulnerable to negative regulatory and legislative outcomes, which could have an adverse impact on our business.
Previous wording
Energy companies, including the Utilities and Transmission Companies, have been the subject of criticism on matters including the reliability of their distribution services and the speed with which they are able to respond to power outages, such as those caused by storm damage. Adverse publicity of this nature, as well as negative publicity associated with the operation of coal-fired generation or proceedings seeking regulatory recoveries may cause less favorable legislative and regulatory outcomes and damage our reputation, which could have an adverse impact on our business.
Current wording
Energy companies, including the Electric Companies and Transmission Companies, have been the subject of criticism on matters including the reliability of their distribution or transmission services and systems and the speed with which they are able to respond to power outages, such as those caused by storm damage. Adverse publicity of this nature, as well as negative publicity associated with the operation of coal-fired generation or proceedings seeking regulatory recoveries may cause less favorable legislative and regulatory outcomes and damage our reputation, which could have an adverse impact on our business and financial condition.
Previous wording
Our results of operations could be adversely affected by events beyond our control, such as natural disasters, public health crises, political crises, negative global climate patterns, mine subsidence, or other catastrophic events.
Current wording
Our results of operations could be adversely affected by events beyond our control, such as natural disasters, public health crises, government shutdowns, trade wars, recessions, political crises, negative global climate patterns, mine subsidence, or other catastrophic events.
Previous wording
Our operations, or those of our vendors or suppliers, could be negatively impacted by various events beyond our control, including, but not limited to: natural disasters, such as hurricanes, tornadoes, floods, earthquakes, extreme cold weather events and other adverse weather conditions; public health crises, such as pandemics and epidemics; political crises, such as terrorist attacks, war, labor unrest, and other political instability (including, without limitation, the ongoing conflict between Russia and Ukraine and the war between Israel and Hamas); negative global climate patterns, especially in water stressed regions; surface subsidence from underground mining impacting our facilities; or other catastrophic events, such as fires or other disasters occurring at our distribution facilities or our service providers’ facilities, whether occurring in the United States or internationally. These events could disrupt the operations of our corporate offices and our supply chain and those of our vendors and service providers, as well as disrupting our infrastructure and that of third parties with whom we are connected. To the extent any of these events occur, our operations and financial results could be adversely affected.
Current wording
Our operations, or those of our vendors or suppliers, could be negatively impacted by various events beyond our control, including, but not limited to: natural disasters, such as hurricanes, tornadoes, floods, earthquakes, wildfires, extreme cold weather events and other adverse weather conditions; public health crises, such as pandemics and epidemics; prolonged government or regulator furloughs or shutdowns; trade wars; recessions; political crises, such as terrorist attacks, war, labor unrest, and other political instability; negative global climate patterns, especially in water stressed regions; surface subsidence from underground mining impacting our facilities; or other catastrophic events, such as fires or other disasters occurring at our distribution facilities or our service providers’ facilities, whether occurring in the United States or internationally. These events could disrupt the operations of our corporate offices and our supply chain and those of our vendors and service providers, as well as disrupting our infrastructure and that of third parties with whom we are connected. To the extent any of these events occur, our operations and financial results could be adversely affected.
Previous wording
Our aspirations and disclosures related to EESG matters expose us to risks that could adversely affect our reputation and performance.
Current wording
Our aspirations and disclosures related to climate matters expose us to risks that could adversely affect our reputation and performance.
Showing the first 40 of 61 pairs. Open the source sections for the rest.
Rearranged current paragraphs (2)
Current report — wording carried from elsewhere
If we are found to have breached the terms of the DPA, the U.S. Attorney’s Office may elect to prosecute, or bring a civil action against, us for conduct alleged in the DPA or known to the government, which could result in fines or penalties and could have a material adverse impact on our reputation or relationships with regulatory and legislative authorities, customers and other stakeholders, as well as our consolidated financial statements. Failure to comply with the DPA, including alleged failures to comply with anti-corruption and anti-bribery laws, may also result in a breach of certain covenants contained in our credit agreements and could result in an event of default under such agreements, and we would not be able to access our credit facilities for additional borrowings and letters of credit during the existence of any such default.
Current report — wording carried from elsewhere
Climate change poses other financial risks as well. To the extent weather conditions are affected by climate change, customers’ energy use could increase or decrease depending on the duration and magnitude of the changes. Increased energy use due to weather changes may require us to invest in additional system assets and purchase additional power. Additionally, decreased energy use due to weather changes may affect our financial condition through decreased revenues, margins or earnings.