Item 1A. Risk Factors

Current report: 10-K

Period ended 2024-12-31; filed 2025-02-27.

0000950170-25-028387

Item 1A. Risk Factors

The baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.

Compared 72 previous paragraphs and 70 current paragraphs.

44 unchanged; 24 reworded; 1 added; 2 removed; 2 previous and 1 current paragraphs rearranged.

Tables are not compared: 0 previous and 0 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.

A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.

Added paragraphs (1)

Current report

The construction of the CVOW Commercial Project is dependent on the Companies’ ability to maintain various local, state and federal permits, rights of way and other regulatory approvals and authorizations, including Virginia Commission approval for rider recovery of project costs. In addition, determination of costs allocated by PJM to the project for network upgrades remains subject to change, even after the CVOW Commercial Project is placed in service, as such amounts are driven by the ultimate costs of development of the transmission lines and related facilities that PJM determines is necessary to support various generation facilities within PJM, including the CVOW Commercial Project. The final determination of such costs is outside the control of the CVOW Commercial Project and may be impacted by events affecting the developers of such transmission lines, including any increases in costs for permitting, inflation, tariffs, supply chain constraints or other factors affecting the ultimate costs to complete such facilities. Also, the CVOW Commercial Project may become the subject of litigation or other forms of intervention by third parties, including stakeholders or advocacy groups, that may seek to challenge permits or other regulatory approvals received, including for routing of onshore electric transmission, which could delay or increase the cost of the project.
Removed paragraphs (2)

Previous report

Dominion Energy may be unable to complete one or all the proposed sales of certain regulated gas distribution operations to Enbridge under the current terms and/or expected timing. The ability of Dominion Energy to complete the East Ohio, PSNC and Questar Gas Transactions, each of which are not conditioned upon the completion of the others, is dependent upon receiving clearance or approval under or by the Hart-Scott-Rodino Act, CFIUS, FCC and applicable state utility commissions, including the North Carolina, Utah and Wyoming Commissions, as well as other customary closing and regulatory conditions. The ability to obtain any remaining requisite regulatory approvals for each sale as well as the timing of such approvals is outside of Dominion Energy’s control. In addition, the terms and conditions associated with such approvals may result in additional requirements or obligations which may be burdensome or potentially result in the inability to complete one or all of the proposed sales under the current terms and/or expected timing. Such events could negatively impact Dominion Energy’s ability to implement certain of the recommendations in connection with the comprehensive business review announced in November 2022 as well as have a material adverse effect on Dominion Energy’s reputation, its financial condition, results of operations or cash flows.

Previous report

The Companies may be unable to complete the proposed sale of a 50% noncontrolling interest in the CVOW Commercial Project to Stonepeak under the current terms and/or expected timing. The ability of Virginia Power to complete the proposed sale of a 50% noncontrolling interest in the CVOW Commercial Project to Stonepeak through the formation of OSWP, is dependent upon receiving approval from the Virginia and North Carolina Commissions, consent from BOEM and other customary closing and regulatory conditions. The ability to obtain requisite regulatory approval as well as the timing of such approvals is outside of the Companies’ control. In addition, the terms and conditions associated with such approvals may result in additional requirements or obligations which may be burdensome or potentially result in the inability to complete the proposed transaction under the current terms and/or expected timing. Such events could negatively impact Dominion Energy’s ability to implement certain of the recommendations in connection with the comprehensive business review announced in November 2022 as well as have a material adverse effect on the Companies’ reputation, its financial condition, results of operations or cash flows.
Reworded paragraphs (24)

Previous wording

The Companies’ businesses are influenced by many factors that are difficult to predict, involve uncertainties that may materially affect actual results and are often beyond their control. A number of these factors have been identified below. For other factors that may cause actual results to differ materially from those indicated in any forward-looking statement or projection contained in this report, see Forward-Looking Statements in Item 7. MD&A. As discussed in Future Issues in Item 7. MD&A, Dominion Energy has commenced a comprehensive business review. The outcomes of the business review and the implementation of the resulting recommendations may be subject to various risks and uncertainties (some of which may include the risks and uncertainties discussed below or other risks and uncertainties that cannot yet be determined) that could have a material impact on the Companies’ future results of operations, cash flows and/or financial condition.

Current wording

The Companies’ businesses are influenced by many factors that are difficult to predict, involve uncertainties that may materially affect actual results and are often beyond their control. A number of these factors have been identified below. For other factors that may cause actual results to differ materially from those indicated in any forward-looking statement or projection contained in this report, see Forward-Looking Statements in Item 7. MD&A.

Previous wording

At the federal level, the Companies’ wholesale rates for electric transmission service are regulated by FERC. Rates for electric transmission services are updated annually according to a FERC-approved formula rate mechanism, and may be subject to additional prospective adjustments and retroactive corrections. A failure by the Companies to support these rates could result in rate decreases from current rate levels, which could adversely affect the Companies’ results of operations, cash flows and financial condition.

Current wording

At the federal level, the Companies’ wholesale rates for electric transmission service are regulated by FERC. Rates for electric transmission services are updated annually according to a FERC-approved formula rate mechanism, and may be subject to additional prospective adjustments and retroactive corrections. A failure by the Companies to support these rates or a change in FERC policy could result in rate decreases from current rate levels, which could adversely affect the Companies’ results of operations, cash flows and financial condition.

Previous wording

At the state level, Virginia Power’s retail base rates, terms and conditions for generation and distribution services to customers in Virginia are reviewed by the Virginia Commission in a proceeding that involves the determination of Virginia Power’s actual earned ROE during a historic test period, and the determination of Virginia Power’s authorized ROE prospectively. The GTSA reinstated base rate reviews commencing with the 2021 Triennial Review. Legislation enacted in Virginia in April 2023 reset the frequency of base rate reviews to a biennial period commencing with the 2023 Biennial Review. Under certain circumstances described in the Regulation Act, Virginia Power may be required to refund a portion of its earnings to customers through a refund process and to reduce its rates. Virginia Power makes assessments throughout the review period and will record a regulatory liability for refunds to customers in any period it is determined probable, which could be material to the Companies’ results of operations in the period recognized and to cash flows on completion of any biennial review.

Current wording

At the state level, Virginia Power’s retail base rates, terms and conditions for generation and distribution services to customers in Virginia are reviewed by the Virginia Commission in a proceeding that involves the determination of Virginia Power’s actual earned ROE during a historic test period, and the determination of Virginia Power’s authorized ROE prospectively. Legislation enacted in Virginia in April 2023 reset the frequency of base rate reviews to a biennial period commencing with the 2023 Biennial Review. Under certain circumstances described in the Regulation Act, Virginia Power may be required to refund a portion of its earnings to customers through a refund process and to reduce its rates. Virginia Power makes assessments throughout the review period and will record a regulatory liability for refunds to customers in any period it is determined probable, which could be material to the Companies’ results of operations in the period recognized and to cash flows on completion of any biennial review.

Previous wording

The Companies’ generation business may be negatively affected by possible FERC actions that could change market design in the wholesale markets or affect pricing rules or revenue calculations in the RTO markets. The Companies’ generation stations operating in RTO markets sell capacity, energy and ancillary services into wholesale electricity markets regulated by FERC. The wholesale markets allow these generation stations to take advantage of market price opportunities, but also expose them to market risk. Properly functioning competitive wholesale markets depend upon FERC’s continuation of clearly identified market rules. From time to time FERC may investigate and authorize RTOs to make changes in market design. FERC also periodically reviews the Companies’ authority to sell at market-based rates. Material changes by FERC to the design of the wholesale markets or its interpretation of market rules, the Companies’ authority to sell power at market-based rates, or changes to pricing rules or rules involving revenue calculations, could adversely impact the future results of the Companies’ generation business. For example, in September 2021, FERC issued a final order that allows distributed energy resource aggregators to compete in regional wholesale electric markets. This rule followed a previous order which mandated that distributed energy resources be allowed to participate in wholesale markets. RTOs, including PJM, are responsible for issuing implementation rules to FERC for approval. In addition, changes to the interpretation and application of FERC’s market manipulation rules may occur from time to time. A failure to comply with these market manipulation rules could lead to civil and criminal penalties.

Current wording

The Companies’ generation business may be negatively affected by possible FERC actions that could change market design in the wholesale markets or affect pricing rules or revenue calculations in the RTO markets. The Companies’ generation stations operating in RTO markets sell capacity, energy and ancillary services into wholesale electricity markets regulated by FERC. The wholesale markets allow these generation stations to take advantage of market price opportunities, but also expose them to market risk. Properly functioning competitive wholesale markets depend upon FERC’s continuation of clearly identified market rules. From time to time FERC may investigate and authorize RTOs to make changes in market design. FERC also periodically reviews the Companies’ authority to sell at market-based rates. Material changes by FERC to the design of the wholesale markets or its interpretation of market rules, the Companies’ authority to sell power at market-based rates, or changes to pricing rules or rules involving revenue calculations, could adversely impact the future results of the Companies’ generation business. For example, in April 2024, FERC issued an order that accepted proposed changes to the PJM wholesale capacity market that significantly changed how a generation resource’s capacity value is calculated and decreased the total amount of capacity recognized in the PJM region as eligible to meet reserve requirements. In addition, changes to the interpretation and application of FERC’s market manipulation rules may occur from time to time. A failure to comply with these market manipulation rules could lead to civil and criminal penalties.

Previous wording

The Companies are subject to complex governmental regulation, including tax regulation, that could adversely affect their results of operations and subject the Companies to monetary penalties. The Companies’ operations are subject to extensive federal, state and local laws and regulations and require numerous permits, approvals and certificates from various governmental agencies. Such laws and regulations govern the terms and conditions of the services the Companies offer, relationships with affiliates, protection of critical electric infrastructure assets and pipeline safety, among other matters. The Companies are also subject to legislation and associated regulation governing taxation at the federal, state and local level. They must also comply with environmental legislation and associated regulations. Management believes that the necessary approvals have been obtained for existing operations and that the businesses are conducted in accordance with applicable laws. The Companies’ businesses are subject to regulatory regimes which could result in substantial monetary penalties if either of the Companies is found not to be in compliance, including mandatory reliability standards and interaction in the wholesale markets. New laws or regulations, the revision or reinterpretation of existing laws or regulations, changes in enforcement practices of regulators, or penalties imposed for non-compliance with existing laws or regulations may result in substantial additional expense. Recent legislative and regulatory changes that are impacting the Companies include legislation enacted in Virginia in April 2023, the IRA, the VCEA, the 2017 Tax Reform Act and tariffs imposed on imported solar panels by the U.S. government in 2018.

Current wording

The Companies are subject to complex governmental regulation, including tax regulation, that could adversely affect their results of operations and subject the Companies to monetary penalties. The Companies’ operations are subject to extensive federal, state and local laws and regulations and require numerous permits, approvals and certificates from various governmental agencies. Such laws and regulations govern the terms and conditions of the services the Companies offer, relationships with affiliates and protection of critical electric infrastructure assets, among other matters. The Companies are also subject to legislation and associated regulation governing taxation at the federal, state and local level. They must also comply with environmental legislation and associated regulations. Management believes that the necessary approvals have been obtained for existing operations and that the businesses are conducted in accordance with applicable laws. The Companies’ businesses are subject to regulatory regimes which could result in substantial monetary penalties if either of the Companies is found not to be in compliance, including mandatory reliability standards and interaction in the wholesale markets. New laws or regulations, the revision or reinterpretation of existing laws or regulations, the imposition of new tariffs, changes in enforcement practices of regulators, or penalties imposed for non-compliance with existing laws or regulations may result in substantial additional expense. Adverse developments in tax laws, credits or other incentives including changes in legislation, administrative interpretations or judicial determinations could result in material modifications to business models or otherwise negatively affect the Companies’ results of operations, financial condition and/or cash flows. Recent legislative and regulatory changes that are impacting the Companies include legislation enacted in Virginia in April 2023, the IRA, the VCEA, the 2017 Tax Reform Act and tariffs imposed on imported solar panels by the U.S. government in 2018.

Previous wording

The EPA has issued regulations concerning the management and storage of CCRs, which Virginia has adopted. These CCR regulations require the Companies to make additional capital expenditures and increase operating and maintenance expenses. In addition, the Companies will incur expenses and other costs associated with closing, corrective action and ongoing monitoring of certain ash ponds and landfills. The Companies also may face litigation concerning their coal ash facilities.

Current wording

The EPA has issued regulations concerning the management and storage of CCRs, which Virginia has adopted. These CCR regulations require the Companies to make additional capital expenditures and increase operating and maintenance expenses. In addition, the Companies will incur expenses and other costs associated with closing, corrective action and ongoing monitoring of certain ash ponds and landfills. The EPA’s May 2024 final rule regulates inactive surface impoundments located at the retired generation stations that contained CCR and liquids after 2015, and certain other inactive or previously closed surface impoundments, landfills or other areas that contain accumulations of CCR. The Companies believe that they may have inactive or closed units or areas that could be subject to the final rule at up to 19 different locations, including 12 at Virginia Power. The Companies also may face litigation concerning their coal ash facilities.

Previous wording

The development and construction of the CVOW Commercial Project involves significant risks. The CVOW Commercial Project is a large-scale, complex project that will take several years to complete. Significant delays or cost increases, or an inability to recover certain project costs, could have an adverse effect on the Companies’ financial condition, cash flows and results of operations. If the Companies are unable to complete the development and construction of the CVOW Commercial Project or decide in the future to delay or cancel the project, the Companies may not be able to recover all or a portion of their investment in the project and may incur substantial cancellation payments under existing contracts or other substantial costs associated with any such delay or cancellation. The Companies’ ability to complete the CVOW Commercial Project within the currently proposed timeline, or at all, and consistent with current cost estimates is subject to various risks and uncertainties, certain of which are beyond the Companies’ control.

Current wording

The construction of the CVOW Commercial Project involves significant risks. The CVOW Commercial Project is a large-scale, complex project that will take several years to complete. Significant delays or cost increases, or an inability to recover certain project costs, could have an adverse effect on the Companies’ financial condition, cash flows and results of operations. If the Companies are unable to complete the construction of the CVOW Commercial Project or decide in the future to delay or cancel the project, the

Previous wording

The development and construction of the CVOW Commercial Project is also dependent on the ability of certain key suppliers and contractors to timely satisfy their obligations under contracts entered into or expected to be entered into. Given the unique equipment and expertise required for this project, the Companies may not be able to remedy in a timely and cost-effective manner, if at all, any failure by one or more of these suppliers or contractors to timely satisfy their contractual obligations. Certain of the fixed price contracts for major offshore construction and equipment components are denominated in Euros and Danish kroner, including those which contain commodity indexing provisions linked to steel. In May 2022, Virginia Power entered into forward purchase agreements with a notional amount of approximately €3.2 billion. Accordingly, to the extent the instruments do not effectively hedge the Companies’ exposure to these currencies, including by default of the counterparty, adverse fluctuations in the applicable exchange rates would likely adversely affect the cost of the CVOW Commercial Project. Similarly, adverse fluctuations in the price of certain raw materials, including steel, would likely, to the extent not hedged by the Companies, adversely affect the overall costs incurred to develop and construct the project.

Current wording

The construction of the CVOW Commercial Project is also dependent on the ability of certain key suppliers and contractors to timely satisfy their obligations under contracts entered into or expected to be entered into. Given the unique equipment and expertise required for this project, the Companies may not be able to remedy in a timely and cost-effective manner, if at all, any failure by one or more of these suppliers or contractors to timely satisfy their contractual obligations. Certain of the fixed price contracts for major offshore construction and equipment components are denominated in Euros and Danish kroner. In May 2022, Virginia Power entered into forward purchase agreements with a notional amount of approximately €3.2 billion. Accordingly, to the extent the instruments do not effectively hedge the Companies’ exposure to these currencies, including by default of the counterparty, adverse fluctuations in the applicable exchange rates would likely adversely affect the cost of the CVOW Commercial Project. Similarly, adverse fluctuations in the price of fuel used for transportation and installation, would likely adversely affect the overall costs to construct the project. In addition, the cost of the CVOW Commercial Project could be adversely affected by the impact of applicable tariffs, if any.

Previous wording

The development and construction of the CVOW Commercial Project is dependent on the Companies’ ability to obtain and maintain various local, state and federal permits, rights of way and other regulatory approvals, including Virginia Commission approval for rider recovery of project costs. In addition, the design and route of the project’s onshore electric transmission, network upgrades and other facilities remain subject to regulatory and PJM review and approval. Changes in the design and route of these onshore facilities, including an increase in amount of undergrounding, would likely increase project costs. Also, the CVOW Commercial Project may become the subject of litigation or other forms of intervention by third parties, including stakeholders or advocacy groups, that may impact the timing and receipt of permits or other regulatory approvals or otherwise delay or increase the cost of the project. The Companies’ ability to recover unforeseen cost increases associated with construction of the CVOW Commercial Project is potentially limited which could negatively impact the Companies’ future financial condition, results of operations and/or cash flows. In accordance with the Virginia Commission’s order in December 2022, the Companies are subject to a cost sharing mechanism in which Virginia Power will be eligible to recover 50% of such incremental costs which fall between $10.3 billion and $11.3 billion with no recovery of such incremental costs which fall between $11.3 billion and $13.7 billion. There is no cost sharing mechanism for any total construction costs in excess of $13.7 billion, the recovery of which would be determined in a future Virginia Commission preceding. In addition, the order includes enhanced performance reporting provisions for the operation of the CVOW Commercial Project. To the extent the net annual net capacity factor is below 42%, as determined on a three-year rolling average, Virginia Power is required to provide detailed explanation of the factors contributing to any shortfall to the Virginia Commission which could determine in a future proceeding a remedy for incremental costs incurred associated with any deemed unreasonable or imprudent actions of Virginia Power. Any such action by the Virginia Commission could adversely impact the Companies’ future financial condition, results of operations and/or cash flows.

Current wording

The Companies’ ability to recover unforeseen cost increases associated with construction of the CVOW Commercial Project is potentially limited which could negatively impact the Companies’ future financial condition, results of operations and/or cash flows. In accordance with the Virginia Commission’s December 2022 order, the Companies are subject to a cost sharing mechanism in which Virginia Power will be eligible to recover 50% of such incremental costs which fall between $10.3 billion and $11.3 billion with no recovery of such incremental costs which fall between $11.3 billion and $13.7 billion. There is no cost sharing mechanism for any total construction costs in excess of $13.7 billion, the recovery of which would be determined in a future Virginia Commission preceding. In addition, the order includes enhanced performance reporting provisions for the operation of the CVOW Commercial Project. To the extent the net annual net capacity factor is below 42%, as determined on a three-year rolling average, Virginia Power is required to provide detailed explanation of the factors contributing to any shortfall to the Virginia Commission which could determine in a future proceeding a remedy for incremental costs incurred associated with any deemed unreasonable or imprudent actions of Virginia Power. Any such action by the Virginia Commission could adversely impact the Companies’ future financial condition, results of operations and/or cash flows.

Previous wording

In connection with the February 2024 agreement to sell a 50% noncontrolling interest to Stonepeak, certain activities prior to closing require the consent of Stonepeak. Stonepeak’s interests and objectives may differ from those of the Companies and, accordingly, disputes may arise that may result in delays, litigation or operational impasses.

Current wording

In October 2024, Virginia Power completed the sale of a 50% noncontrolling interest to Stonepeak. Virginia Power and Stonepeak will each contribute 50% of the remaining capital necessary to fund construction of the CVOW Commercial Project provided the total project cost, excluding financing costs, is less than $11.3 billion. For capital funding necessary, if any, for total project costs, excluding financing costs, of $11.3 billion through $13.7 billion, Stonepeak will have the option to make additional capital contributions. If Stonepeak elects to make additional capital contributions for project costs, excluding financing costs, in excess of $11.3 billion, if any, Virginia Power shall contribute between 67% and 83% of such capital with Stonepeak contributing the remainder. To the extent that Stonepeak elects not to make such contributions, Virginia Power shall receive an increase in its ownership percentage of OSWP for any contributed capital based on a tiered unit price for membership interests in OSWP as set forth in the agreement. Virginia Power and Stonepeak have the right to provide capital contributions for any total project costs, excluding financing costs, in excess of $13.7 billion. The inability of Stonepeak to satisfy its share of funding requirements in a timely manner could have a negative effect on the Companies. In addition, Stonepeak’s interests and objectives may differ from those of the Companies and, accordingly, disputes may arise that may result in delays, litigation or operational impasses.

Previous wording

The development and construction of the CVOW Commercial Project involves the use of evolving turbine technology and will take place in a marine environment, which presents unique challenges and will require the use of a specialized workforce and specialized equipment. In addition, the timely installation of the turbines is dependent on the completion and availability of a Jones Act compliant vessel currently under construction.

Current wording

The construction of the CVOW Commercial Project involves the use of evolving turbine technology and takes place in a marine environment, which presents unique challenges and requires the use of a specialized workforce and specialized equipment. In addition, the timely installation of the turbines is dependent on the completion and availability of a Jones Act compliant vessel currently under construction.

Previous wording

The timeline for development and construction of the CVOW Commercial Project may also be negatively impacted by severe weather events or marine wildlife, including migration patterns of endangered and protected species, both of which are outside of the control of the Companies and their contractors.

Current wording

The timeline for construction of the CVOW Commercial Project may also be negatively impacted by severe weather events or marine wildlife, including migration patterns of endangered and protected species, both of which are outside of the control of the Companies and their contractors.

Previous wording

Commercial Project, electric transmission lines, pipeline replacements, facility expansions or renewed licensing, conversions and other infrastructure developments or construction. Additional projects may be considered in the future. The Companies compete for projects with companies of varying size and financial capabilities, including some that may have competitive advantages. Commencing construction on announced and future projects may require approvals from applicable state and federal agencies, and such approvals could include mitigation costs which may be material to the Companies. Projects may not be able to be completed on time or in accordance with estimated costs as a result of weather conditions, need for new land and right of ways, delays in obtaining or failure to obtain regulatory and other, including PJM, approvals, delays in obtaining key materials, labor difficulties, difficulties with partners or potential partners, concerns raised during stakeholder engagement, a decline in the credit strength of counterparties or vendors, inflation, or other factors beyond the Companies’ control. For example, Dominion Energy has been involved with projects which have experienced certain delays in obtaining and maintaining permits necessary for construction along with construction delays due to judicial actions which impacted the cost and schedule such as the Atlantic Coast Pipeline Project and ultimately led to its cancellation in July 2020. Even if facility construction, pipeline, expansion, electric transmission line, conversion and other infrastructure projects are completed, the total costs of the projects may be higher than anticipated and the performance of the business of the Companies following completion of the projects may not meet expectations.

Current wording

The Companies’ infrastructure build and expansion plans often require regulatory approval, including environmental permits, before commencing construction and completing projects. The Companies may not complete the facility construction, conversion or other infrastructure projects that they commence, or they may complete projects on materially different terms, costs or timing than initially estimated or anticipated, and they may not be able to achieve the intended benefits of any such project, if completed. A number of large- and small-scale projects have been announced, including the CVOW Commercial Project, electric transmission lines, facility expansions or renewed licensing, conversions and other infrastructure developments or construction. Additional projects may be considered in the future, such as those necessary to meet the projected demand growth driven by data centers and artificial intelligence, including to address the concentration of data centers primarily in Loudoun County, Virginia. The Companies compete for projects with companies of varying size and financial capabilities, including some that may have competitive advantages. Commencing construction on announced and future projects may require approvals from applicable state and federal agencies, and such approvals could include mitigation costs which may be material to the Companies. Projects may not be able to be completed on time or in accordance with estimated costs as a result of weather conditions, need for new land and right of ways, delays in obtaining or failure to obtain regulatory and other, including PJM, approvals, changes in laws or regulations, delays in obtaining key materials, labor difficulties, difficulties with partners or potential partners, concerns raised during stakeholder engagement, a decline in the credit strength of counterparties or vendors, inflation, the impact of applicable tariffs or other factors beyond the Companies’ control. For example, Dominion Energy has been involved with projects which have experienced certain delays in obtaining and maintaining permits necessary for construction along with construction delays due to judicial actions which impacted the cost and schedule such as the Atlantic Coast Pipeline Project and ultimately led to its cancellation in July 2020. Even if facility construction, expansion, electric transmission line, conversion and other infrastructure projects are completed, the total costs of the projects may be higher than anticipated and the performance of the business of the Companies following completion of the projects may not meet expectations.

Previous wording

Start-up and operational issues can arise in connection with the commencement of commercial operations at the Companies’ facilities. Such issues may include failure to meet specific operating parameters, which may require adjustments to meet or amend these operating parameters. Additionally, the Companies may not be able to timely and effectively integrate the projects into their operations and such integration may result in unforeseen operating difficulties or unanticipated costs. Further, regulators may disallow recovery of some of the costs of a project if they are deemed not to be prudently incurred. Any of these or other factors could adversely affect the Companies’ ability to realize the anticipated benefits from the facility construction, pipeline, electric transmission line, expansion, conversion and other infrastructure projects.

Current wording

Start-up and operational issues can arise in connection with the commencement of commercial operations at the Companies’ facilities. Such issues may include failure to meet specific operating parameters, which may require adjustments to meet or amend these operating parameters. Additionally, the Companies may not be able to timely and effectively integrate the projects into their operations and such integration may result in unforeseen operating difficulties or unanticipated costs. Any delays in the timely completion of necessary PJM interconnection projects for new electric generation facilities under development by Virginia Power, including the CVOW Commercial Project, may result in capacity constraints if, and until, such projects are completed. Further, regulators may disallow recovery of some of the costs of a project if they are deemed not to be prudently incurred. Any of these or other factors could adversely affect the Companies’ ability to realize the anticipated benefits from the facility construction, electric transmission line, expansion, conversion and other infrastructure projects.

Previous wording

The development, construction and commissioning of several large-scale infrastructure projects simultaneously involves significant execution risk. To achieve Dominion Energy’s commitment to net zero emissions by 2050 and comply with the requirements of the VCEA, the Companies are currently simultaneously developing or constructing several electric generation projects, including subsequent license renewal projects at Surry and North Anna, the CVOW Commercial Project, several electric transmission projects and various solar projects. Several of the Companies’ key projects are increasingly large-scale, complex and being constructed in constrained geographic areas or in unfamiliar environments such as the marine environment for the Coastal Virginia Offshore Wind projects. The advancement of the Companies’ ventures is also affected by the interventions, litigation or other activities of stakeholder and advocacy groups, some of which oppose natural gas-related and energy infrastructure projects. For example, certain stakeholder groups oppose solar farms due to the increasing quantities of land tracts required for these facilities. Given that these projects provide the foundation for the Companies’ strategic growth plan, if the Companies are unable to obtain or maintain the required regulatory and other, including PJM, approvals, develop the necessary technical expertise, allocate and coordinate sufficient resources, adhere to budgets and timelines, effectively handle public outreach efforts, including its commitment to environmental justice, or otherwise fail to successfully execute the projects, there could be an adverse impact to the Companies’ financial position, results of operations and cash flows. Failure to comply with regulatory approval conditions or an adverse ruling in any future litigation could adversely affect the Companies’ ability to execute their business plan.

Current wording

The development, construction and commissioning of several large-scale infrastructure projects simultaneously involves significant execution risk. To achieve Dominion Energy’s commitment to net zero emissions by 2050 and comply with the requirements of the VCEA, the Companies are currently simultaneously developing or constructing several electric generation projects, including subsequent license renewal projects at Surry and North Anna, the CVOW Commercial Project, several electric transmission projects and various solar projects. Several of the Companies’ key projects are increasingly large-scale, complex and being constructed in constrained geographic areas or in unfamiliar environments such as the marine environment for the CVOW Commercial Project. The advancement of the Companies’ ventures is also affected by the interventions, litigation or other activities of stakeholder and advocacy groups, some of which oppose natural gas-related and energy infrastructure projects. For example, certain stakeholder groups oppose solar farms due to the increasing quantities of land tracts required for these facilities. Similarly, certain stakeholder groups oppose new natural gas generation facilities, such as the proposed Chesterfield Energy Reliability Center. Given that these projects provide the foundation for the Companies’ strategic growth plan and to meet projected growth, if the Companies are unable to obtain or maintain the required regulatory and other, including PJM, approvals, develop the necessary technical expertise, allocate and coordinate sufficient resources, adhere to budgets and timelines, effectively handle public outreach efforts, including its commitment to fair treatment, community involvement and effective communication, or otherwise fail to successfully execute the projects, there could be an adverse impact to the Companies’ financial position, results of operations and cash flows. Failure to comply with regulatory approval conditions or an adverse ruling in any future litigation could adversely affect the Companies’ ability to execute their business plan.

Previous wording

Further, an inability to obtain financing or otherwise provide liquidity for the projects on acceptable terms, including any potential adverse conditions arising from or in connection with the comprehensive business review announced in November 2022, could negatively affect the Companies’ financial condition, cash flows, the projects’ anticipated financial results and/or impair the Companies’ ability to execute the business plan for the projects as scheduled.

Current wording

Further, an inability to obtain financing or otherwise provide liquidity for the projects on acceptable terms could negatively affect the Companies’ financial condition, cash flows, the projects’ anticipated financial results and/or impair the Companies’ ability to execute the business plan for the projects as scheduled.

Previous wording

The Companies’ financial performance and condition can be affected by changes in the weather, including the effects of global climate change. Fluctuations in weather can affect demand for the Companies’ services. For example, milder than normal weather can reduce demand for electricity and gas distribution services. In addition, severe weather or acts of nature, including hurricanes, winter storms, earthquakes, floods and other natural disasters can stress systems, disrupt operation of the Companies’ facilities and cause service outages, production delays and property damage that require incurring additional expenses. Changes in weather conditions can result in reduced water levels or changes in water temperatures that could adversely affect operations at some of the Companies’ power stations. Furthermore, the Companies’ operations could be adversely affected and their physical plant placed at greater risk of damage should changes in global climate produce, among other possible conditions, unusual variations in temperature and weather patterns, resulting in more intense, frequent and extreme weather events, abnormal levels of precipitation and, for operations located on or near coastlines, a change in sea level or sea temperatures. Due to the location of the Companies’ electric utility service territories and a number of its other facilities in the eastern portions of the states of South Carolina, North Carolina and Virginia which are frequently in the path of hurricanes, the Companies experience the consequences of these weather events to a greater degree than many industry peers.

Current wording

The Companies’ financial performance and condition can be affected by changes in the weather, including the effects of global climate change. Fluctuations in weather can affect demand for the Companies’ services. For example, milder than normal weather can reduce demand for electricity and gas distribution services. In addition, severe weather or acts of nature, including hurricanes, winter storms, wildfires, earthquakes, floods and other natural disasters can stress systems, disrupt operation of the Companies’ facilities and cause service outages, production delays and property damage that require incurring additional expenses. Changes in weather conditions can result in reduced water levels or changes in water temperatures that could adversely affect operations at some of the Companies’ power stations. Furthermore, the Companies’ operations could be adversely affected and their physical plant placed at greater risk of damage should changes in global climate produce, among other possible conditions, unusual variations in temperature and weather patterns, resulting in more intense, frequent and extreme weather events, abnormal levels of precipitation and, for operations located on or near coastlines, a change in sea level or sea temperatures. Due to the location of the Companies’ electric utility service territories and a number of its other facilities in the eastern portions of the states of South Carolina, North Carolina and Virginia which are frequently in the path of hurricanes, the Companies experience the consequences of these weather events to a greater degree than many industry peers.

Previous wording

The Companies’ financial results can be adversely affected by various factors driving supply and demand for electricity and gas and related services. Demand for the Companies’ services can be driven by changing populations within its utility service territories, significant new commercial or industrial customers or other changes in consumer habits. For example, data centers in Virginia Power’s service territory have been a source of significant increase in demand which is expected to continue over the next decade. Technological advances required by federal laws mandate new levels of energy efficiency in end-use devices, including lighting, furnaces and electric heat pumps and could lead to declines in per capita energy consumption. Additionally, certain regulatory and legislative bodies have introduced or are considering requirements and/or incentives to reduce energy consumption by a fixed date. Likewise, certain regulatory and legislative bodies have introduced or are considering actions which could limit the use or installation of new natural gas appliances. Consumer demand for the Companies’ services may also be impacted by any price increases, including those driven by factors beyond the Companies’ control such as inflation or increased prices in natural gas. Further, Virginia Power’s business model is premised upon the cost efficiency of the production, transmission and distribution of large-scale centralized utility generation. However, advances in distributed generation technologies, such as solar cells, gas microturbines, battery storage and fuel cells, may make these alternative generation methods competitive with large-scale utility generation, and change how customers acquire or use the Companies’ services. The widescale implementation of alternative generation methods could negatively impact the reliability of the Companies’ electric grid and/or result in significant costs to enhance the grid. Virginia Power has an exclusive franchise to serve retail electric customers in Virginia. However, Virginia’s Retail Access Statutes allow certain electric generation customers exceptions to this franchise. As market conditions change, Virginia Power’s customers may further pursue exceptions and Virginia Power’s exclusive franchise may erode.

Current wording

The Companies’ financial results can be adversely affected by various factors driving supply and demand for electricity and related services. Demand for the Companies’ services can be driven by changing populations within its utility service territories, significant new commercial or industrial customers or other changes in consumer habits. For example, data centers in Virginia Power’s service territory, particularly in Loudoun County, Virginia, have been a source of significant increase in demand which is expected to continue over the next decade. Technological advances may enhance energy efficiency in end-use devices, including lighting, furnaces and electric heat pumps and could lead to declines in per capita energy consumption. Additionally, regulatory and/or legislative bodies could introduce requirements and/or incentives to reduce energy consumption. Consumer demand for the Companies’ services may also be impacted by any price increases, including those driven by factors beyond the Companies’ control such as inflation or increased prices in natural gas. Further, Virginia Power’s business model is premised upon the cost efficiency of the production, transmission and distribution of large-scale centralized utility generation. However, advances in distributed generation technologies, such as solar cells, gas microturbines, battery storage and fuel cells, may make these alternative generation methods competitive with large-scale utility generation, and change how customers acquire or use the Companies’ services. The widescale implementation of alternative generation methods could negatively impact the reliability of the Companies’ electric grid and/or result in significant costs to enhance the grid. Virginia Power has an exclusive franchise to serve retail electric customers in Virginia. However, Virginia’s Retail Access Statutes allow certain electric generation customers exceptions to this franchise. As market conditions change, Virginia Power’s customers may further pursue exceptions and Virginia Power’s exclusive franchise may erode.

Previous wording

Increased energy demand or significant accelerated growth in demand due to new data centers, widespread adoption of electric vehicles or other customer changes could require enhancements to the Companies’ infrastructure. As discussed above, the ability of the Companies to construct new facilities is dependent upon factors outside of their control, including obtaining regulatory approvals, environmental and other permits. Any delays in, or inability to complete, construction of new facilities or expand and/or renew existing facilities could have an adverse effect on the Companies’ financial results. In addition, purchased power from PJM or others may be from generation sources which emit more emissions than the Companies’ facilities, which could negatively impact Dominion Energy’s ability to meet its commitment to net zero emissions. Alternatively, reduced energy demand or significantly slowed growth in demand due to customer adoption of energy efficient technology, conservation, distributed generation, regional economic conditions, or the impact of additional compliance obligations, unless substantially offset through regulatory cost allocations, could adversely impact the value of the Companies’ business activities.

Current wording

Increased energy demand or significant accelerated growth in demand due to new data centers, expanded use of artificial intelligence, widespread adoption of electric vehicles or other customer changes could require enhancements to the Companies’ infrastructure. As discussed above, the ability of the Companies to construct new facilities is dependent upon factors outside of their control, including obtaining regulatory approvals, environmental and other permits. Any delays in, or inability to complete, construction of new facilities or expand and/or renew existing facilities could have an adverse effect on the Companies’ financial results. In addition, purchased power from PJM or others may be from generation sources which emit more emissions than the Companies’ facilities, which could negatively impact Dominion Energy’s ability to meet its commitment to net zero emissions. Alternatively, reduced energy demand or significantly slowed growth in demand due to customer adoption of energy efficient technology, conservation, distributed generation, regional economic conditions, or the impact of additional compliance obligations, unless substantially offset through regulatory cost allocations, could adversely impact the value of the Companies’ business activities.

Previous wording

In addition, there are many risks associated with the Companies’ principal operations and the transportation and storage of natural gas including nuclear accidents, fires, explosions, uncontrolled release of natural gas and other environmental hazards, pole strikes, electric contact cases, the collision of third party equipment with pipelines and avian and other wildlife impacts. Such incidents could result in loss of human life or injuries among employees, customers or the public in general, environmental pollution, damage or destruction of facilities or business interruptions and associated public or employee safety impacts, loss of revenues, increased liabilities, heightened regulatory scrutiny and reputational risk. Further, the location of natural gas pipelines and associated distribution facilities, or electric generation, transmission, substations and distribution facilities near populated areas, including residential areas, commercial business centers and industrial sites, could increase the level of damages resulting from these risks.

Current wording

In addition, there are many risks associated with the Companies’ principal operations including nuclear accidents, fires, explosions, uncontrolled release of natural gas and other environmental hazards, pole strikes, electric contact cases, the collision of third party equipment with pipelines and avian and other wildlife impacts. Such incidents could result in loss of human life or injuries among employees, customers or the public in general, environmental pollution, damage or destruction of facilities or business interruptions and associated public or employee safety impacts, loss of revenues, increased liabilities, heightened regulatory scrutiny and reputational risk. Further, the location of electric generation, transmission, substations and distribution facilities or natural gas distribution facilities near populated areas, including residential areas, commercial business centers and industrial sites, could increase the level of damages resulting from these risks.

Previous wording

Dominion Energy conducts certain operations through partnership arrangements involving third-party investors which may limit Dominion Energy’s operational flexibility or result in an adverse impact on its financial results. Certain of Dominion Energy’s operations are conducted through entities subject to partnership arrangements under which Dominion Energy has significant influence but does not control the operations of such entities or in which Dominion Energy’s control over such entities may be subject to certain rights of third-party investors. Accordingly, while Dominion Energy may have a certain level of control or influence over these entities, it may not have unilateral, or any, control over the day-to-day operations of these entities or over decisions that may have a material financial impact on the partnership participants, including Dominion Energy. In each case such partnership arrangements operate in accordance with their respective governance documents, and Dominion Energy is dependent upon third parties satisfying their respective obligations, including, as applicable, funding of their required share of capital expenditures. Such third-party investors have their own interests and objectives which may differ from those of Dominion Energy and, accordingly, disputes may arise amongst the owners of such partnership arrangements that may result in delays, litigation or operational impasses.

Current wording

The Companies conduct certain operations through partnership arrangements involving third-party investors which may limit the Companies’ operational flexibility or result in an adverse impact on its financial results. Certain of the Companies’ operations, including the CVOW Commercial Project, are conducted through entities subject to partnership arrangements under which Dominion Energy or Virginia Power has significant influence but does not control the operations of such entities or in which Dominion Energy or Virginia Power’s control over such entities may be subject to certain rights of third-party investors. Accordingly, while Dominion Energy or Virginia Power may have a certain level of control or influence over these entities, it may not have unilateral, or any, control over the day-to-day operations of these entities or over decisions that may have a material financial impact on the partnership participants, including the Companies. In each case such partnership arrangements operate in accordance with their respective governance documents, and the Companies are dependent upon third parties satisfying their respective obligations, including, as applicable, funding of their required share of capital expenditures. Such third-party investors have their own interests and objectives which may differ from those of the Companies and, accordingly, disputes may arise amongst the owners of such partnership arrangements that may result in delays, litigation or operational impasses.

Previous wording

The Companies may be materially adversely affected by negative publicity or the inability of Dominion Energy to meet its stated commitments. From time to time, political and public sentiment may result in a significant amount of adverse press coverage and other adverse public statements affecting the Companies. Any failure by Dominion Energy to realize its commitments to achieve net zero carbon and methane emissions by 2050, increase workforce diversity, enhance the customer experience or other long-term goals could lead to adverse press coverage and other adverse public statements affecting the Companies. The ability to comply with some or all of Dominion Energy’s voluntary commitments may be outside of its control. For example, Dominion Energy is dependent on the actions of third parties to meet the expanded commitment regarding Scope 2 emissions and Scope 3 emissions. If downstream customers or upstream suppliers do not sufficiently reduce their GHG emissions, Dominion Energy may not achieve its net zero emissions goal. In addition, while the Atlantic Coast Pipeline Project was cancelled in July 2020 and the legal proceedings and governmental investigations relating to the abandonment of the NND Project have been resolved, there is a risk that lingering negative publicity may continue. Adverse press coverage and other adverse statements, whether or not driven by political or public sentiment, may also result in investigations by regulators, legislators and law enforcement officials or in legal claims as well as adverse outcomes.

Current wording

The Companies may be materially adversely affected by negative publicity or the inability of Dominion Energy to meet its stated commitments. From time to time, political and public sentiment may result in a significant amount of adverse press coverage and other adverse public statements affecting the Companies. Any failure by Dominion Energy to realize its commitments to achieve net zero carbon and methane emissions by 2050, enhance the customer experience or other long-term goals could lead to adverse press coverage and other adverse public statements affecting the Companies. The ability to comply with some or all of Dominion Energy’s voluntary commitments may be outside of its control. For example, the ability to reduce emissions while meeting the Companies’ increasing demand growth is expected to be dependent on the technological and economic feasibility of large-scale battery storage, carbon capture and storage, small modular reactors, hydrogen and/or other clean energy technologies. Dominion Energy is also dependent on the actions of third parties to meet the expanded commitment regarding Scope 2 emissions and Scope 3 emissions. If downstream customers or upstream suppliers do not sufficiently reduce their GHG emissions, Dominion Energy may not achieve its net zero emissions goal. In addition, while the Atlantic Coast Pipeline Project was cancelled in July 2020 and the legal proceedings and governmental investigations relating to the abandonment of the NND Project have been resolved, there is a risk that lingering negative publicity may continue. Adverse press coverage and other adverse statements, whether or not driven by political or public sentiment, may also result in investigations by regulators, legislators and law enforcement officials or in legal claims as well as adverse outcomes.

Previous wording

Deterioration in the Companies’ creditworthiness, as evaluated by credit rating agencies or otherwise, or declines in market reputation either for the Companies or their industry in general, or general financial market disruptions outside of the Companies’ control could increase their cost of borrowing or restrict their ability to access one or more financial markets. In addition, any potential adverse conditions arising from or in connection with the comprehensive business review announced in November 2022 could affect the availability and/or cost of capital. Market disruptions could stem from general market disruption due to general credit market or political events, the reform or replacement of benchmark rates, the failure of financial institutions on which the Companies rely or the bankruptcy of an unrelated company. Increased costs and restrictions on the Companies’ ability to access financial markets may be severe enough to affect their ability to execute their business plans as scheduled.

Current wording

An inability to access financial markets and, in the case of Dominion Energy, obtain cash from subsidiaries could adversely affect the execution of the Companies’ business plans. The Companies rely on access to short-term money markets and longer-term capital markets as significant sources of funding and liquidity for business plans with increasing capital expenditure needs, normal working capital and collateral requirements related to hedges of future sales and purchases of energy-related commodities. Deterioration in the Companies’ creditworthiness, as evaluated by credit rating agencies or otherwise, or declines in market reputation either for the Companies or their industry in general, or general financial market disruptions outside of the Companies’ control could increase their cost of borrowing or restrict their ability to access one or more financial markets. Market disruptions could stem from general market disruption due to general credit market or political events, the reform or replacement of benchmark rates, the failure of financial institutions on which the Companies rely or the bankruptcy of an unrelated company. Increased costs and restrictions on the Companies’ ability to access financial markets may be severe enough to affect their ability to execute their business plans as scheduled.

Previous wording

Future impairments of goodwill or other intangible assets or long-lived assets may have a material adverse effect on the Companies’ results of operations. Goodwill is evaluated for impairment annually or more frequently if an event or circumstance occurs that would more likely than not reduce the fair value of a reporting unit below its carrying amount. Other intangible assets and long-lived assets are evaluated for impairment on an annual basis or more frequently whenever events or circumstances indicate that an asset’s carrying value may not be recoverable. If Dominion Energy’s goodwill or the Companies’ other intangible assets or long-lived assets are in the future determined to be impaired, the applicable registrant would be required during the period in which the impairment is determined to record a noncash charge to earnings that may have a material adverse effect on the registrant’s results of operations. For example, in the fourth quarter of 2022, Dominion Energy determined that its nonregulated solar generation assets within Contracted Energy were impaired, resulting in a $685 million after-tax charge. In addition, Dominion Energy recorded a $286 million after-tax charge in the fourth quarter of 2023 for the impairment of certain goodwill associated with the East Ohio and Questar Gas Transactions.

Current wording

Future impairments of goodwill or other intangible assets or long-lived assets may have a material adverse effect on the Companies’ results of operations. Goodwill is evaluated for impairment annually or more frequently if an event or circumstance occurs that would more likely than not reduce the fair value of a reporting unit below its carrying amount. Other intangible assets and long-lived assets are evaluated for impairment on an annual basis or more frequently whenever events or circumstances indicate that an asset’s carrying value may not be recoverable. If Dominion Energy’s goodwill or the Companies’ other intangible assets or long-lived assets are in the future determined to be impaired, the applicable registrant would be required during the period in which the impairment is determined to record a noncash charge to earnings that may have a material adverse effect on the registrant’s results of operations. For example, in the fourth quarter of 2022, Dominion Energy determined that its nonregulated solar generation assets within Contracted Energy were impaired, resulting in a $685 million after-tax charge. In addition, Dominion Energy recorded an aggregate $309 million after-tax charge in the fourth quarter of 2023 and first quarter of 2024 for the impairment of certain goodwill associated with the Questar Gas Transaction.
Rearranged current paragraphs (1)

Current report — wording carried from elsewhere

Companies may not be able to recover all or a portion of their investment in the project and may incur substantial cancellation payments under existing contracts or other substantial costs associated with any such delay or cancellation. The Companies’ ability to complete the CVOW Commercial Project within the currently proposed timeline, or at all, and consistent with current cost estimates is subject to various risks and uncertainties, certain of which are beyond the Companies’ control.
Rearranged previous paragraphs (2)

Previous report — wording carried elsewhere

The Companies’ infrastructure build and expansion plans often require regulatory approval, including environmental permits, before commencing construction and completing projects. The Companies may not complete the facility construction, pipeline, conversion or other infrastructure projects that they commence, or they may complete projects on materially different terms, costs or timing than initially estimated or anticipated, and they may not be able to achieve the intended benefits of any such project, if completed. A number of large and small scale projects have been announced, including the CVOW

Previous report — wording carried elsewhere

An inability to access financial markets and, in the case of Dominion Energy, obtain cash from subsidiaries could adversely affect the execution of the Companies’ business plans. The Companies rely on access to short-term money markets and longer-term capital markets as significant sources of funding and liquidity for business plans with increasing capital expenditure needs, normal working capital and collateral requirements related to hedges of future sales and purchases of energy-related commodities.