What changed in Risk Factors?
Read the current filingPrevious report: 10-K
Period ended 2024-06-30; filed 2024-09-10.
0000866273-24-000092
Item 1A. Risk FactorsCurrent report: 10-K
Period ended 2025-06-30; filed 2025-09-10.
0000866273-25-000069
Item 1A. Risk FactorsThe baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.
Compared 124 previous paragraphs and 117 current paragraphs.
104 unchanged; 8 reworded; 5 added; 10 removed; 2 previous and 0 current paragraphs rearranged.
Tables are not compared: 0 previous and 0 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.
A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.
Added paragraphs (5)
Current report
Changes in global trade policy and the impact on tariffs may have a material adverse effect on business operations and financial performance.
Current report
The new U.S. presidential administration has announced tariffs on U.S. imports generally, with higher rates for select U.S. trade partners. Certain foreign governments have also announced retaliatory tariffs. The tariff policy environment has been and is expected to continue to be dynamic, and we cannot predict what additional actions may ultimately be taken by the United States or other governments with respect to tariffs or trade relations.
Current report
Additionally, tariffs or other trade restrictions may lead to continuing uncertainty and volatility in U.S. economic conditions and commodity markets, declining consumer confidence, significant inflation, and diminished expectations for the economy. These factors could increase our costs and reduce our customers’ demand for our services, including decisions by our clients on project viability or timing, which could negatively impact our operating results and financial condition.
Current report
Customers may require us to provide forms of performance security, including letters of credit, or surety bonds. We are often required to provide performance security to customers to indemnify the customer should we fail to perform our obligations under the contract. Failure to provide the required performance security on terms required by a customer may result in an inability to bid, win or comply with the contract. Historically, we have had adequate letters of credit capacity but such capacity beyond our Senior Credit Facility is generally at the provider’s sole discretion. Due to events that affect the banking and insurance markets, letters of credit or surety bonds may be difficult to obtain or may only be available at significant cost. In addition, future projects may require us to obtain letters of credit that extend beyond the term of our Senior Credit Facility. Any inability to bid for or win new contracts due to the failure of obtaining adequate letters of credit, surety bonds or other customary forms of performance security could have a material adverse effect on our business prospects and future revenues.
Removed paragraphs (10)
Previous report
Our project managers are involved in most aspects of contracting and contract execution, including:
Previous report
•supervising the bidding process, including providing estimates of significant cost components, such as material and equipment needs, and the size, productivity and composition of the workforce;
Previous report
•supervising project performance, including performance by our employees, subcontractors and other third-party suppliers and vendors;
Previous report
•estimating costs for completion of contracts that is used to estimate amounts that can be reported as revenue and earnings on the contract under the percentage-of-completion method of accounting;
Previous report
•negotiating requests for change orders and the final terms of approved change orders; and
Previous report
•determining and documenting claims by us for increased costs incurred due to the failure of customers, subcontractors and other third-party suppliers of equipment and materials to perform on a timely basis and in accordance with contract terms.
Previous report
A portion of our business depends on our ability to provide surety bonds or letters of credit. Current or future market conditions, including losses incurred in the construction industry or as a result of large corporate bankruptcies, as well as changes in our sureties’ assessment of our operating and financial risk, could cause our surety providers and lenders to decline to issue or renew, or substantially reduce the amount of, bid or performance bonds for our work and could increase our costs associated with collateral. These actions could be taken on short notice. If our surety providers or lenders were to limit or eliminate our access to bonding or letters of credit, our alternatives would include seeking capacity from other sureties and lenders or finding more business that does not require bonds or that allows for other forms of collateral for project performance, such as cash. We may be unable to secure these alternatives in a timely manner, on acceptable terms, or at all, which could affect our ability to bid for or work on certain future projects requiring financial assurances.
Previous report
Under standard terms in the surety market, sureties issue or continue bonds on a project-by-project basis and can decline to issue bonds at any time or require the posting of additional collateral as a condition to issuing or renewing bonds. If we were to experience an interruption or reduction in the availability of bonding capacity as a result of these or other reasons, we may be unable to compete for or work on certain projects that require bonding.
Reworded paragraphs (8)
Previous wording
The availability of engineering and construction projects is dependent upon economic conditions and the outlook for renewable energy, hydrogen, natural gas, oil, petrochemical, industrial, and power industries, and specifically, the level of capital expenditures on energy infrastructure. Additionally, we expect our customers to benefit from bills such as the Infrastructure Investment and Jobs Act and the Inflation Reduction Act. While spending and stimulus bills are expected to provide funding in many of the markets in which we operate, we may not be able to obtain the expected benefits from these bills or similar bills in the future. Our failure to obtain projects, the delay of project awards, the cancellation of projects or delays in the execution of contracts has resulted and may continue to result in under-utilization of our resources, which could adversely impact our revenue, margins, operating results and cash flow. There are numerous factors beyond our control that influence the level of maintenance and capital expenditures of our customers, including:
Current wording
The availability of engineering and construction projects is dependent upon economic conditions and the outlook for renewable energy, hydrogen, natural gas, oil, petrochemical, industrial, and power industries, and specifically, the level of capital expenditures on energy infrastructure. Our failure to obtain projects, the delay of project awards, the cancellation of projects or delays in the execution of contracts has resulted and may continue to result in under-utilization of our resources, which could adversely impact our revenue, margins, operating results and cash flow. There are numerous factors beyond our control that influence the level of maintenance and capital expenditures of our customers, including:
Previous wording
Our ability to attract and retain qualified engineers, project managers, skilled craftsmen and other experienced professionals in accordance with our need is an important factor in our ability to maintain profitability and grow our business. The market for these professionals is competitive, particularly during periods of economic growth when the supply is limited. We cannot provide any assurance that we will be successful in our efforts to retain or attract qualified personnel when needed. Therefore, when we anticipate or experience growing demand for our services, we may incur additional cost to maintain a professional staff in excess of our current contract needs in an effort to have sufficient qualified personnel available to address this anticipated demand. If we do incur additional compensation and benefit costs, our customer contracts may not allow us to pass through these costs.
Current wording
Our ability to attract and retain qualified engineers, project managers, skilled craftsmen and other experienced professionals in accordance with our need is an important factor in our ability to maintain profitability and grow our business. Competent and experienced engineers, project estimators, project managers, and craft workers are especially critical to the profitable performance of our contracts, particularly on our fixed-price contracts where superior design and execution of the project can result in profits greater than originally estimated or where inferior design and project execution can reduce or eliminate estimated profits or even result in a loss. The market for these professionals is competitive, particularly during periods of economic growth when the supply is limited. We cannot provide any assurance that we will be successful in our efforts to retain or attract qualified personnel when needed. Therefore, when we anticipate or experience growing demand for our services, we may incur additional cost to maintain a professional staff in excess of our current contract needs in an effort to have sufficient qualified personnel available to address this anticipated demand. If we do incur additional compensation and benefit costs, our customer contracts may not allow us to pass through these costs.
Previous wording
One or more customers have in the past and may in the future contribute a material portion of our revenue in any one year. Because these significant customers generally contract with us for specific projects or for specific periods of time, we may lose these customers from year to year as the projects or maintenance contracts are completed. The loss of business from any one of these customers could have a material adverse effect on our business or results of operations.
Current wording
One or more customers have in the past and may in the future contribute a material portion of our revenue in any one year. One customer accounted for $133.9 million or 17.4% of our consolidated revenue in fiscal 2025, which was primarily included in the Utilities and Power Infrastructure segment. Another customer accounted for $80.8 million or 10.5% of our consolidated revenue in fiscal 2025, which was primarily included in the Storage and Terminal Solutions segment. Because these significant customers generally contract with us for specific projects or for specific periods of time, we may lose these customers from year to year as the projects or maintenance contracts are completed. The loss of business from any one of these customers could have a material adverse effect on our business or results of operations.
Previous wording
Domestic and foreign trade tariffs could raise the price and reduce the availability of raw materials to us, which could negatively impact our operating results and financial condition.
Current wording
Domestic and foreign trade tariffs could raise the price and reduce the availability of raw materials such as steel plate and steel pipe, which are key materials used by us. Increased costs of raw materials could cause us to experience lower gross margins, operational inefficiencies and project delays. We include contract provisions that mitigate our exposure to fluctuations in material costs and to the impact of changes in laws and regulations. We also utilize contracting strategies that allow us to spread the risk of cost increases to other involved parties. However, we may be unable to pass through some or all of these increases in costs to other parties which may materially affect our results of operations. To the extent we can, we also mitigate these risks primarily by procuring materials upon contract execution to ensure that our purchase price approximates the costs included in the project estimate.
Previous wording
Management believes it has sufficient cash on hand and will generate sufficient cash from operations to fund the business. However, should we require additional liquidity, there is risk that we will be unable to access the amount of additional liquidity needed from our Credit Agreement if the level of assets included in the borrowing base is insufficient. The borrowing base includes restricted cash plus a percentage of the value of certain accounts receivable, inventory and equipment, reduced for certain reserves. Accounts receivable eligible to be included in the borrowing base are generally limited to receivables associated with time and materials and other cost reimbursable contracts. While receivables associated with fixed price work do not increase the borrowing base, such work often has upfront billings, which help support the liquidity needs of the business. As of June 30, 2024, our borrowing base was $60.9 million. Our borrowing base has ranged from $60.9 million to $74.6 million during fiscal 2024.
Current wording
Management believes it has sufficient cash on hand and will generate sufficient cash from operations to fund the business. However, should we require additional liquidity, there is risk that we will be unable to access the amount of additional liquidity needed from our Credit Agreement if the level of assets included in the borrowing base is insufficient. The borrowing base includes restricted cash plus a percentage of the value of certain accounts receivable, inventory and equipment, reduced for certain reserves. Accounts receivable eligible to be included in the borrowing base are generally limited to receivables associated with time and materials and other cost reimbursable contracts. While receivables associated with fixed price work do not increase the borrowing base, such work often has upfront billings, which help support the liquidity needs of the business.
Previous wording
To the extent that cash on hand, cash flow from operations, and borrowing availability under the Credit Agreement are insufficient to make future investments, or provide needed working capital, we may require additional financing from other sources. Our ability to obtain such additional financing in the future will depend in part upon prevailing capital market conditions, as well as conditions in our business and our operating results; and those factors may affect our efforts to arrange additional financing on terms that are satisfactory to us. If adequate funds are not available, or are not available on acceptable terms, we may not be able to make future investments or respond to competitive challenges.
Current wording
To the extent that cash on hand, cash flow from operations, and borrowing availability under the Credit Agreement are insufficient to make future investments, or provide needed working capital or letters of credit, we may require additional financing from other sources. Our ability to obtain such additional financing in the future will depend in part upon prevailing capital market conditions, as well as conditions in our business and our operating results; and those factors may affect our efforts to arrange additional financing on terms that are satisfactory to us. If adequate funds are not available, or are not available on acceptable terms, we may not be able to make future investments or respond to competitive challenges.
Previous wording
•accruals for estimated liabilities, including litigation and insurance reserves.
Current wording
•accruals for estimated liabilities, including litigation reserves.
Previous wording
Because we have grown in part through acquisitions, goodwill and other acquired intangible assets represent a substantial portion of our assets. We perform annual goodwill impairment reviews in the fourth quarter of every fiscal year. In addition, we perform an impairment review whenever events or changes in circumstances indicate the fair value of a goodwill reporting unit may be less than its carrying value or the carrying value of an intangible or fixed asset may not recoverable. As of June 30, 2024, we had $1.7 million of amortizing intangible assets and $29.0 million of non-amortizing goodwill representing 0.4% and 6.4% of our total assets, respectively.
Current wording
Because we have grown in part through acquisitions, goodwill and other acquired intangible assets represent a substantial portion of our assets. We perform annual goodwill impairment reviews in the fourth quarter of every fiscal year. In addition, we perform an impairment review whenever events or changes in circumstances indicate the fair value of a goodwill reporting unit may be less than its carrying value or the carrying value of an intangible or fixed asset may not recoverable. As of June 30, 2025, we had $29.0 million of non-amortizing goodwill representing 4.8% of our total assets.
Rearranged previous paragraphs (2)
Previous report — wording carried elsewhere
Competent and experienced engineers, project estimators, project managers, and craft workers are especially critical to the profitable performance of our contracts, particularly on our fixed-price contracts where superior design and execution of the project can result in profits greater than originally estimated or where inferior design and project execution can reduce or eliminate estimated profits or even result in a loss.
Previous report — wording carried elsewhere
Domestic and foreign trade tariffs could raise the price and reduce the availability of raw materials such as steel plate and steel pipe, which are key materials used by us. Supplies of these materials are available throughout the United States and globally from numerous sources. We anticipate that adequate amounts of these materials will be available in the foreseeable future. However, if trade tariffs should significantly impact the price and availability of these materials, we could experience lower gross margins, operational inefficiencies and project delays.