COPT DEFENSE PROPERTIES
For the period ended Oct 29, 2026. Filed Oct 29, 2026.
View on SEC.govAbout this filing
A notice of a major event between regular reports, such as results, a deal or a change of executives. It is often the first formal record of the news.
Oct 29, 2026 · Filed Oct 29, 2026
Use the contents to explore the available documents and sections.
Contents
EX-99.1 · Summary of Development Projects
Summary of Development Projects as of 9/30/26 (1)
| Total Rentable Square Feet · % Leased as of 9/30/26 · as of 9/30/26 (2) · Actual or Anticipated Shell Completion Date · Anticipated Operational Date (3) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|
| Anticipated Total Cost | Cost to Date | |||||||||
| Property and Segment/Sub-Segment | Location | |||||||||
| Defense/IT Portfolio | ||||||||||
| Fort Meade/BW Corridor | ||||||||||
| 4400 River Road | College Park, MD | 110 | 100% | $62,528 | $16,875 | 1Q 27 | 1Q 27 | |||
| 620 Guardian Way | Annapolis Junction, MD | 236 | 100% | 145,970 | 28,705 | 4Q 27 | 4Q 27 | |||
| Fort Meade/BW Corridor Subtotal / Average | 346 | 100% | 208,498 | 45,580 | ||||||
| Redstone Arsenal | ||||||||||
| 8500 Advanced Gateway | Huntsville, AL | 155 | 89% | 54,326 | 36,785 | 2Q 26 | 1Q 27 | |||
| 7700 Advanced Gateway | Huntsville, AL | 101 | 100% | 32,895 | 26,379 | 1Q 27 | 1Q 27 | |||
| 2200 Rideout Road | Huntsville, AL | 59 | 0% | 23,248 | 1,766 | 4Q 27 | 2Q 28 | |||
| 410 Goss Road | Huntsville, AL | 149 | 0% | 57,212 | 29,150 | 3Q 27 | 3Q 28 | |||
| 6300 Redstone Gateway | Huntsville, AL | 175 | 0% | 64,631 | 4,796 | 1Q 28 | 4Q 28 | |||
| Redstone Arsenal Subtotal / Average | 639 | 37% | 232,312 | 98,876 | ||||||
| Lackland Air Force Base | ||||||||||
| Project EL 2 | San Antonio, TX | 132 | 100% | 87,600 | 41,029 | 3Q 27 | 3Q 27 | |||
| Total Defense/IT Portfolio Under Development | 1,117 | 64% | $528,410 | $185,485 | ||||||
(1)Includes properties under, or contractually committed for, development as of 9/30/26.
(2)Cost includes land, development, leasing costs, and allocated portion of structured parking and other shared infrastructure, if applicable.
(3)Anticipated operational date is the earlier of the estimated date when leases have commenced on 100% of a property’s space or one year from the cessation of major construction activities.