TETRA TECHNOLOGIES INC
For the period ended Jun 30, 2026. Filed Aug 4, 2026.
View on SEC.govAbout this filing
A company's report for each of its first three quarters. The financial statements are not audited. It shows how the business has moved since the last annual report, and what management says changed.
Jun 30, 2026 · Filed Aug 4, 2026
What changed in Risk Factors?
Read the current filingPrevious report: 10-Q
Period ended 2026-03-31; filed 2026-04-29.
0000844965-26-000040
Item 1A. Risk FactorsCurrent report: 10-Q
Period ended 2026-06-30; filed 2026-08-04.
0000844965-26-000058
Item 1A. Risk FactorsThe baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.
Compared 2 previous paragraphs and 6 current paragraphs.
1 unchanged; 1 reworded; 4 added; 0 removed; 0 previous and 0 current paragraphs rearranged.
Tables are not compared: 0 previous and 0 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.
A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.
Added paragraphs (4)
Current report
We may not be able to fund or complete the Arkansas Bromine Project on the timeline or at the cost we currently anticipate, which could have a material adverse effect on our business and the market price of our common stock.
Current report
The Arkansas Bromine Project represents a significant ongoing capital project for TETRA. Phase 1 of the Arkansas Bromine Project, which included site preparation, power infrastructure, and installation of the bromine tower, was completed in December 2025. Phase 2, which encompasses the major infrastructure and equipment supporting the plant, is currently underway with mechanical completion targeted by the end of 2026. The entire facility is expected to be operational by the end of 2027, with first production anticipated in early 2028. If other working interest owners do not fund their share of the upstream costs, the capital expenditures necessary to complete the Arkansas Bromine Project may increase from current estimates. Construction projects of this scale carry inherent execution risks, including the potential for cost overruns, schedule delays, supply chain disruptions, contractor performance issues, labor availability constraints, regulatory or permitting delays, environmental matters, and other factors outside of our control. We intend to use a portion of the net proceeds from the June 2026 Offering to fund a portion of the construction costs of the Arkansas Bromine Project. We will need to seek additional financing to fund the remaining portion of the capital expenditures for the project. To the extent other sources, including cash generated from operations and amounts available under our credit facilities, are insufficient or unavailable, we may have to delay construction or modify the scope of the project. There can be no assurance that the Arkansas Bromine Project will be completed on the timeline currently anticipated, at the cost currently anticipated, or that it will achieve the projected installed capacity or operating results once completed. Any failure to complete the Arkansas Bromine Project as planned could have a material adverse effect on our business, financial condition, results of operations, prospects and the market price of our common stock.
Current report
There is no assurance that we will be able to extend or renew customer contracts after the end of the initial contractual term. Any such nonrenewal, or renewals at reduced rates or the loss of contracts with any significant customer, could adversely impact our financial results.
Current report
From time to time, we enter into long-term contracts with customers, which are subject to renegotiation in the normal course of business as they near the end of their initial terms. There is no assurance that any of our contracts with our customers will be extended or renewed by our customers or that any of our customers will continue to contract with the Company following the expiration of the relevant term. The inability to negotiate extensions or renew a substantial portion of our contracts, the renewal of such contracts at reduced rates, the inability to contract for additional services with our customers, or the loss of all or a significant portion of our services contracts with any significant customer, could lead to a reduction in revenue and net income and could require us to record additional asset impairments. This could have a material adverse effect upon our business, results of operations and financial condition.
Reworded paragraphs (1)
Previous wording
As of the date of this filing, TETRA and its operations continue to be subject to the risk factors previously disclosed in the “Risk Factors” sections contained in our 2025 Annual Report.
Current wording
As of the date of this filing, TETRA and its operations continue to be subject to the risk factors previously disclosed in the “Risk Factors” sections contained in our 2025 Annual Report. In addition, we are subject to the following supplemental risk factors.