A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.

FY2025 · Filed Feb 18, 2026

EIX$59.37-2.5%Stored close · as of Nov 6, 2026

What changed in Risk Factors?

Read the current filing

The baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.

Compared 84 previous paragraphs and 83 current paragraphs.

62 unchanged; 21 reworded; 0 added; 0 removed; 1 previous and 0 current paragraphs rearranged.

Tables are not compared: 0 previous and 0 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.

A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.

Reworded paragraphs (21)

Previous wording

Edison International's ability to obtain financing, as well as its ability to refinance debt and make scheduled payments of principal and interest, are dependent on numerous factors, including its levels of indebtedness, maintenance of acceptable credit ratings, financial performance, liquidity and cash flow, and other market conditions. In addition, the factors affecting

Current wording

Edison International's ability to obtain financing, as well as its ability to refinance debt and make scheduled payments of principal and interest, are dependent on numerous factors, including its levels of indebtedness, maintenance of acceptable credit ratings, financial performance, liquidity and cash flow, and other market conditions. In addition, the factors affecting SCE's business will impact Edison International's ability to obtain financing. Edison International's inability to borrow funds from time to time could have a material effect on Edison International's liquidity and operations.

Previous wording

The CPUC or the FERC may not allow SCE to recover costs on the basis that such costs were not reasonably or prudently incurred or for other reasons. Further, SCE may incur expenses before the relevant regulatory agency approves the recovery of such costs. For example, SCE has incurred, and expects to further incur, wildfire mitigation expenses before it is clear whether such costs will be recoverable from customers. Also, the CPUC may deny recovery of costs incurred by SCE, including uninsured wildfire-related costs, if the CPUC determines that SCE was not prudent. For further information on recovery of uninsured wildfire-related costs see "Business—Southern California Wildfires—Recovery of Wildfire-Related Costs" and "Management Overview—Southern California Wildfires and Mudslides" in the MD&A. In addition, while SCE supports California's environmental goals, it may be prevented from fully executing on its strategy to support such goals by regulatory delay or lack of approval of cost-recovery for the costs of such strategic actions and electrification programs from the relevant regulatory agencies, including as a result of customer affordability concerns. For example, the CPUC issued a decision denying SCE’s Building Electrification Program Application, citing, among other things, a desire to avoid increasing rates.

Current wording

The CPUC or the FERC may not allow SCE to recover costs on the basis that such costs were not reasonably or prudently incurred or for other reasons. Further, SCE may incur expenses before the relevant regulatory agency approves the recovery of such costs. For example, SCE has incurred, and expects to further incur, wildfire mitigation expenses before it is clear whether such costs will be recoverable from customers. Also, the CPUC may deny recovery of costs incurred by SCE, including uninsured wildfire-related costs, if the CPUC determines that SCE was not prudent. For further information on recovery of uninsured wildfire-related costs see "Business—Southern California Wildfires—Recovery of Wildfire-Related Costs" and "Management Overview—Southern California Wildfires and Mudslides" in the MD&A. In addition, while SCE supports California's environmental goals, it may be prevented from fully executing on its strategy to support such goals by regulatory delay or lack of approval of cost-recovery for the costs of such strategic actions and electrification programs from the relevant regulatory agencies, including as a result of customer affordability concerns. For example, in the 2025 GRC final decision, the CPUC denied 50% of SCE’s requested upfront funding for its Transportation Electrification Grid Readiness program, citing uncertain market conditions and considering intervenor positions, many of which raised affordability concerns.

Previous wording

The Wildfire Insurance Fund and other provisions of AB 1054 may not be sufficient or effectively mitigate the significant risk faced by California investor-owned utilities related to liability for damages arising from catastrophic wildfires where utility facilities are a substantial cause, which could have a detrimental effect on SCE's business and financial condition. The effectiveness of AB 1054 to mitigate the wildfire-related risk faced by SCE is conditioned in part on the performance of OEIS and various entities formed under AB 1054 and related legislation to, among other things, administer the Wildfire Insurance Fund, approve WMPs, issue safety certifications, oversee and enforce compliance with wildfire safety standards, and develop metrics to reduce risk and measure compliance with risk reduction.

Current wording

The Wildfire Fund and other provisions of the California Wildfire Legislation may not be sufficient or effectively mitigate the significant risk faced by California investor-owned utilities related to liability for damages arising from catastrophic wildfires where utility facilities are a substantial cause, which could have a detrimental effect on SCE's business and financial condition. The effectiveness of the California Wildfire Legislation to mitigate the wildfire-related risk faced by SCE is conditioned in part on the performance of OEIS and various entities formed under AB 1054 and related legislation to, among other things, administer the Wildfire Fund, approve WMPs, issue safety certifications, oversee and enforce compliance with wildfire safety standards, and develop metrics to reduce risk and measure compliance with risk reduction.

Previous wording

In addition, existing regulations may be revised or re-interpreted and new laws and regulations may be adopted or become applicable to SCE, or its facilities or operations, in a manner that may have a detrimental effect on SCE's business or result in significant additional costs. In addition, regulations adopted via the public initiative or legislative process may apply to SCE, or its facilities or operations, in a manner that may have a detrimental effect on SCE's business or result in significant additional costs.

Current wording

Existing regulations may be revised or re-interpreted and new laws and regulations may be adopted, via the public initiative or legislative process, or become applicable to SCE, or its facilities or operations, in a manner that may have a detrimental effect on SCE's business or result in significant additional costs.

Previous wording

Severe wildfires and urban development in and near high fire risk areas in California have given rise to large damage claims against California utilities for fire-related losses alleged to be the result of utility practices and/or the failure of electric and other utility equipment. Catastrophic wildfires can occur in SCE's service area even if SCE effectively implements its WMPs. California courts have previously found utilities to be strictly liable for property damage, regardless of fault, by applying the theory of inverse condemnation when a utility's facilities were determined to be a substantial cause of a wildfire that caused the property damage. An inability to recover uninsured wildfire-related costs could materially affect SCE's business, financial condition and results of operations. For example, if SCE is unable to, or believes that it may be unable to, recover damages related to catastrophic wildfires through insurance, the Wildfire Insurance Fund (which is only available for fires ignited after July 12, 2019) or electric rates, or access the bank and capital markets on reasonable terms, SCE may not have sufficient cash or equity to pay dividends or may be restricted from declaring such dividends because it does not meet CPUC or California law requirements related to the declaration of dividends. For information on the California law requirements on the declaration of dividends, see "Notes to Consolidated Financial Statements—Note 1. Summary of Significant Accounting Policies—SCE Dividends." Also see "Notes to Consolidated Financial Statements—Note 12. Commitments and Contingencies—Contingencies—Southern California Wildfires and Mudslides."

Current wording

Severe wildfires and urban development in and near high fire risk areas in California have given rise to large damage claims against California utilities for fire-related losses alleged to be the result of utility practices and/or the failure of electric and other utility equipment. Catastrophic wildfires can occur in SCE's service area even if SCE effectively implements its WMPs. California courts have previously found utilities to be strictly liable for property damage, regardless of fault, by applying the theory of inverse condemnation when a utility's facilities were determined to be a substantial cause of a wildfire that caused the property damage. An inability to recover uninsured wildfire-related costs could materially affect SCE's business, financial condition and results of operations. For example, if SCE is unable to, or believes that it may be unable to, recover damages related to catastrophic wildfires through insurance, the Wildfire Fund (which is only available for fires ignited after July 12, 2019) or electric rates, or access the bank and capital markets on reasonable terms, SCE may not have sufficient cash or equity to pay dividends or may be restricted from declaring such dividends because it does not meet CPUC or California law requirements related to the declaration of dividends. For information on the California law requirements on the declaration of dividends, see "Notes to Consolidated Financial Statements—Note 1. Summary of Significant Accounting Policies—SCE Dividends." Also see "Notes to Consolidated Financial Statements—Note 12. Commitments and Contingencies—Contingencies—Southern California Wildfires and Mudslides."

Previous wording

Edison International's and SCE's costs of accessing capital markets has increased due to the risks associated with wildfires in Southern California. Edison International's and SCE's access to the bank and capital markets could also be constrained and/or the costs of accessing those markets could increase further as a result of wildfire risk, including if Edison International's and/or SCE's credit ratings are downgraded or placed on negative watch due to concerns about Edison International and/or SCE's financial health as a result of wildfires.

Current wording

Edison International's and SCE's costs of accessing capital markets have increased due to the risks associated with wildfires in Southern California. Edison International's and SCE's access to the bank and capital markets could also be constrained and/or the costs of accessing those markets could increase further as a result of wildfire risk, including if Edison International's and/or SCE's credit ratings are downgraded or placed on negative watch due to concerns about Edison International and/or SCE's financial health as a result of wildfires.

Previous wording

SCE may not be able to recover uninsured losses (including amounts paid for self-insured retention and co-insurance) in electric rates. Additionally, SCE’s contractors may experience coverage reductions and/or increased wildfire insurance costs in future years. For losses associated with claims occurring before the authorization of SCE’s CPUC-authorized customer-funded self-insurance program, no assurance can be given that losses will not exceed the limits of SCE's or its contractors' insurance coverage. Losses which are not fully insured or cannot be recovered from contractors, through the Wildfire Insurance Fund or electric rates, including any such losses that exceed funds available through the Wildfire Insurance Fund and are ultimately not authorized to be recovered through rates, could materially affect Edison International's and SCE's financial condition and results of operations. For more information on wildfire insurance risk, see "Notes to Consolidated Financial Statements—Note 12. Commitments and Contingencies—Contingencies—Southern California Wildfires and Mudslides."

Current wording

SCE may not be able to recover uninsured losses (including amounts paid for self-insured retention and co-insurance) in electric rates. Additionally, SCE’s contractors may experience coverage reductions and/or increased wildfire insurance costs in future years. For losses associated with claims occurring before the authorization of SCE’s CPUC-authorized customer-funded self-insurance program, no assurance can be given that losses will not exceed the limits of SCE's or its contractors' insurance coverage. Losses which are not fully insured or cannot be recovered from contractors, through the Wildfire Fund or electric rates, including any such losses that exceed funds available through the Wildfire Fund and are ultimately not authorized to be recovered through rates, could materially affect Edison International's and SCE's financial condition and results of operations. For more information on wildfire insurance risk, see "Notes to Consolidated Financial Statements—Note 12. Commitments and Contingencies—Contingencies—Southern California Wildfires and Mudslides."

Previous wording

SCE will face a higher likelihood of catastrophic wildfires in its service area if it cannot effectively implement its WMPs. For example, SCE may not be able to effectively implement its WMPs if it experiences unanticipated difficulties relative to permitting delays, sourcing, engaging, and retaining effectively trained contract workers or procuring materials it needs to fulfill its mitigation obligations under the WMPs. In addition, if SCE does not have an approved WMP, SCE will not be issued a safety certification from the CPUC and will consequently not benefit from the presumption of prudency or the AB 1054 Liability Cap.

Current wording

SCE will face a higher likelihood of catastrophic wildfires in its service area if it cannot effectively implement its WMPs. For example, SCE may not be able to effectively implement its WMPs if it experiences unanticipated difficulties relative to permitting delays, sourcing, engaging, and retaining effectively trained contract workers or procuring materials it needs to fulfill its mitigation obligations under the WMPs. In addition, if SCE does not have an approved WMP, SCE will not be issued a safety certification from the CPUC and will consequently not benefit from the presumption of prudency or the Liability Cap. Furthermore, approval of a WMP by the OEIS does not ensure that the CPUC will authorize recovery of the associated costs. If the CPUC denies or limits cost recovery for work needed to execute an approved WMP, SCE may be required to absorb those costs or may need to reduce the scope or timing of its mitigation activities. For more information about the WMP process, see "Business—Southern California Wildfires— Safety Certification and Wildfire Mitigation Plan."

Previous wording

For more information on AB 1054, see "Business—Southern California Wildfires—Recovery of Wildfire-Related Costs—2019 Wildfire Legislation."

Current wording

For more information on the presumption of prudency and the Liability Cap, see "Business—Southern California Wildfires—Recovery of Wildfire-Related Costs— California Wildfire Legislation."

Previous wording

SCE will not benefit from all of the features of AB 1054 if the Wildfire Insurance Fund is exhausted.

Current wording

SCE will not benefit from all of the features of the California Wildfire Legislation if the Wildfire Fund is exhausted.

Previous wording

Catastrophic wildfires could rapidly exhaust the Wildfire Insurance Fund and SCE will not be reimbursed by the Wildfire Insurance Fund or benefit from the AB 1054 Liability Cap if the fund has been exhausted as a result of damage claims previously incurred by SCE or the other participating utilities. AB 1054 does not have a mechanism for adding to or replenishing the Wildfire Insurance Fund.

Current wording

Catastrophic wildfires could rapidly exhaust the Wildfire Fund and SCE will not be reimbursed by the Wildfire Fund or benefit from the Liability Cap if the fund has been exhausted as a result of damage claims previously incurred by SCE or the other participating utilities.

Previous wording

For more information on AB 1054, see "Business—Southern California Wildfires and Mudslides—Recovery of Wildfire-Related Costs—2019 Wildfire Legislation."

Current wording

For more information on the California Wildfire Legislation , see "Business—Southern California Wildfires and Mudslides—Recovery of Wildfire-Related Costs—California Wildfire Legislation."

Previous wording

Climate change has caused, and exacerbated, extreme weather events and wildfires in southern California, and wildfires could cause, among other things, public safety issues, property damage and operational issues. In addition, the risk of flooding and debris flows occurring as a result of rain may be heightened. For example, the Eaton Fire that ignited in Los Angeles County in January 2025 resulted in loss of life, property damage and loss of service and subsequent extreme weather events such as increased rain or flooding could further impact the affected areas. For more information on liabilities related to wildfire events, see "Notes to Consolidated Financial Statements—Note 12. Commitments and Contingencies—Contingencies—Southern California Wildfires and Mudslides."

Current wording

Climate change has caused, and exacerbated, extreme weather events and wildfires in southern California, and wildfires could cause, among other things, public safety issues, property damage and operational issues. In addition, the risk of flooding and debris flows occurring as a result of rain may be heightened. For example, the Eaton Fire that ignited in Los Angeles County in January 2025 resulted in loss of life, property damage and loss of service and subsequent extreme weather events such as increased rain or flooding could further impact the affected areas. If reimbursements from the Wildfire Fund for eligible claims related to the Eaton Fire are received later than projected, SCE could experience short‑term liquidity pressure, which may adversely affect SCE’s cash flows and liquidity position. For more information on liabilities related to wildfire events, see "Notes to Consolidated Financial Statements—Note 12. Commitments and Contingencies—Contingencies—Southern California Wildfires and Mudslides."

Previous wording

Weather-related incidents and other natural disasters can lead to lost revenue and increased expense, including higher maintenance and repair costs, which SCE may not be able to recover from its customers. These incidents can also result in regulatory penalties and disallowances, particularly if SCE encounters difficulties in restoring power to its customers on a timely basis or if fire-related losses are found to be the result of utility practices and/or the failure of electric and other utility equipment. In addition, these occurrences could lead to significant claims for damages, including for loss of life and property damage. These occurrences could materially affect SCE's business, financial condition and results of operations, and the inability to restore power to SCE's customers could also materially damage the business reputation of SCE and Edison International.

Current wording

Weather-related incidents and other natural disasters can lead to lost revenue and increased costs, including higher maintenance and repair costs, which SCE may not be able to recover from its customers. These incidents can also result in regulatory penalties and disallowances, particularly if SCE encounters difficulties in restoring power to its customers on a timely basis or if fire-related losses are found to be the result of utility practices and/or the failure of electric and other utility equipment. In addition, these occurrences could lead to significant claims for damages, including for loss of life and property damage. These occurrences could materially affect SCE's business, financial condition and results of operations, and the inability to restore power to SCE's customers could also materially damage the business reputation of SCE and Edison International.

Previous wording

SCE's infrastructure is aging and could pose a risk to system reliability if not sufficiently maintained and expanded to meet load growth and electrification needs. In addition, as described above, natural disasters such as wildfires in SCE's service area can cause significant public safety issues, property damage and operational issues. SCE is engaged in a significant and ongoing infrastructure investment program. This investment program, which includes transmission projects and constructing utility owned storage to mitigate possible state-wide capacity shortages in 2025 and later years, has inherent operational risks and elevates the need for effective execution in SCE's activities. For example, utility owned storage facilities utilize lithium-ion battery technology that in certain circumstances can and have caused a thermal event that can ignite nearby materials, including other lithium-ion cells particularly when deployed in indoor facilities. SCE's financial condition and results of operations could be materially affected if it is unable to successfully manage these risks as well as the risks inherent in constructing, operating, and maintaining its facilities, the operation of which can be hazardous and important for system reliability. SCE's inherent operating risks include such matters as the risks of human performance, availability of skilled workforce and workforce capabilities, contractor management, data and records accuracy, public opposition to infrastructure projects, delays, environmental remediation and mitigation costs, difficulty in estimating costs or in recovering costs that are above original estimates, system limitations and degradation, maintaining physical security of workforce and assets, maintaining cybersecurity of data and assets, and delays and interruptions in necessary supplies, including key components necessary for the timely construction of utility owned storage. For example, SCE's financial condition may be materially affected as a result of safety incidents, delays, permitting violations and violations of regulatory requirements, among other things, caused by SCE's failure to appropriately manage its contractor workforce or from contractual violations by SCE's contractors and the inability for SCE to recover through contractual indemnities or insurance held by the contractor. SCE's financial condition may also be materially affected as a result of data or records inaccuracies, for example, inaccurate records could lead to missing or delayed compliance with SCE's policies and regulatory requirements, and could contribute to safety incidents.

Current wording

SCE's infrastructure is aging and could pose a risk to system reliability if not sufficiently maintained and expanded to meet load growth and electrification needs. In addition, as described above, natural disasters such as wildfires in SCE's service area can cause significant public safety issues, property damage and operational issues. SCE is engaged in a significant and ongoing infrastructure investment program. This investment program, which includes transmission projects and constructing utility owned storage to mitigate possible state-wide capacity shortages, has inherent operational risks and elevates the need for effective execution in SCE's activities. For example, utility owned storage facilities utilize lithium-ion battery technology that in certain circumstances can and have caused a thermal event that can ignite nearby materials, including other lithium-ion cells particularly when deployed in indoor facilities. SCE's financial condition and results of operations could be materially affected if it is unable to successfully manage these risks as well as the risks inherent in constructing, operating, and maintaining its facilities, the operation of which can be hazardous and important for system reliability. SCE's inherent operating risks include such matters as the risks of human performance; availability of skilled workforce and workforce capabilities; contractor management; data and records accuracy; public opposition to infrastructure projects; delays; environmental remediation and mitigation costs; difficulty in estimating costs or in recovering costs that are above original estimates; system limitations and degradation; unexpected cascading critical system failure; maintaining physical security of workforce and assets; maintaining cybersecurity of data and assets; and delays and interruptions in necessary supplies. For example, SCE's financial condition may be materially affected as a result of safety incidents, delays, permitting violations and violations of regulatory requirements, among other things, caused by SCE's failure to appropriately manage its contractor workforce or from contractual violations by SCE's contractors and the inability for SCE to recover through contractual indemnities or insurance held by the contractor. SCE's financial condition may also be materially affected as a result of data or records inaccuracies, for example, inaccurate records could lead to missing or delayed compliance with SCE's policies and regulatory requirements, and could contribute to safety incidents.

Previous wording

The costs of decommissioning San Onofre are subject to reasonableness reviews by the CPUC. These costs may not be recoverable through regulatory processes or otherwise unless SCE can establish that the costs were reasonably incurred. In addition, SCE faces inherent execution risks including such matters as the risks of human performance, workforce capabilities, public opposition, permitting delays, and governmental approvals. Decommissioning costs ultimately incurred could exceed the current estimates and cost increases resulting from contractual disputes, delays in performance by DCG, elevated levels of inflation, or permitting delays, among other things, could cause SCE to materially overrun current decommissioning cost estimates and could materially impact the sufficiency of trust funds. See "Liquidity and Capital Resources—SCE—Decommissioning of San Onofre" in the MD&A.

Current wording

The costs of decommissioning San Onofre are subject to reasonableness reviews by the CPUC. These costs may not be recoverable through regulatory processes or otherwise unless SCE can establish that the costs were reasonably incurred. In addition, SCE faces inherent execution risks including such matters as the risks of human performance, workforce capabilities, public opposition, permitting delays, governmental approvals, and force majeure events. Decommissioning costs ultimately incurred could exceed the current estimates and cost increases resulting from contractual disputes, delays in performance by DGC, elevated levels of inflation, permitting delays, or force majeure events, among other things, could cause SCE to materially overrun current decommissioning cost estimates and could materially impact the sufficiency of trust funds. See "Liquidity and Capital Resources—SCE—Decommissioning of San Onofre" in the MD&A.

Previous wording

SCE owns and operates the water distribution system that serves Catalina Island, California and a propane gas distribution system that serves the City of Avalon on Catalina Island, California. Production, storage, treatment and distribution of water for human use and the transportation, storage, distribution and use of gas can be hazardous, and can cause damage to private property and the environment and injury to employees and the general public if equipment fails or does not perform as anticipated. For example, the risks of operating a water distribution system include the potential for burst pipes and water contamination and the risks of operating gas distribution system include the potential for gas leaks, fire or explosion. The risks related to SCE's operation of its water and gas distribution systems may be exacerbated due to aging infrastructure. SCE has, in the past, requested that the CPUC allow SCE to include certain water system costs in electric rates and may make similar requests for the water and gas systems in the future. If such requests are denied, significant costs may not be recoverable from customers. In addition, SCE may have to pay fines, penalties and remediation costs if it does not comply with laws and regulations in the operation of the water and gas distribution systems. An inability to recover costs associated with any such damages or injuries or any fines, penalties or remediation costs, from insurance or through electric rates, could materially affect SCE's business, financial condition and results of operations.

Current wording

SCE owns and operates the water distribution system that serves Catalina Island, California and a propane gas distribution system that serves the City of Avalon on the island. Production, storage, treatment and distribution of water for human use and the transportation, storage, distribution and use of gas can be hazardous, and can cause damage to private property and the environment and injury to employees and the general public if equipment fails or does not perform as anticipated. For example, the risks of operating a water distribution system include the potential for burst pipes and water contamination and the risks of operating gas distribution system include the potential for gas leaks, fire or explosion. The risks related to SCE's operation of its water and gas distribution systems may be exacerbated due to aging infrastructure. SCE has, in the past, requested that the CPUC allow SCE to include certain water system costs in electric rates and may make similar requests for the water and gas systems in the future. If such requests are denied, significant costs may not be recoverable from customers. In addition, SCE may have to pay fines, penalties and remediation costs if it does not comply with laws and regulations in the operation of the water and gas distribution systems. An inability to recover costs associated with any such damages or injuries or any fines, penalties or remediation costs, from insurance or through electric rates, could materially affect SCE's business, financial condition and results of operations.

Previous wording

Customer-owned generation and load departures to CCAs or Electric Service Providers each reduce the amount of electricity that customers purchase from utilities and have the effect of increasing utility rates unless customer rates are designed to allocate the costs of the distribution grid across all customers that benefit from its use. For example, some customers in California who generate their own power are not currently required to pay all transmission and distribution charges and non-bypassable charges, subject to limitations, which results in increased costs for other customers. If there are not updates in regulations to further support the need for customers pay their share of transmission and distribution costs and non-bypassable charges, for example through a higher fixed charge, and the demand for electricity reduces so significantly that SCE is no longer effectively able to recover such costs from its customers, SCE's business, financial condition and results of operations will be materially impacted.

Current wording

Customer-owned generation and load departures to CCAs or Electric Service Providers each reduce the amount of electricity that customers purchase from utilities and have the effect of increasing utility rates unless customer rates are designed to allocate the costs of the distribution grid across all customers that benefit from its use. For example, some customers in California who generate their own power are not currently required to pay all transmission and distribution charges and non-bypassable charges, subject to limitations, which results in increased costs for other customers. If there are no updates in regulations to further support the need for customers to pay their share of transmission and distribution costs and non-bypassable charges, and the demand for electricity reduces so significantly that SCE is no longer effectively able to recover such costs from its customers, SCE's business, financial condition and results of operations will be materially impacted.

Previous wording

Edison International and SCE systems, assets and personnel are targets for physical and cyber attacks. Regulators such as NERC and U.S. Government agencies, including the Departments of Defense, Homeland Security, and Energy, have increasingly stressed that threat sources continue to seek to identify and exploit vulnerabilities in the U.S. national electric grid and other critical energy infrastructures, and that such attacks and disruptions, both physical and cyber, are highly sophisticated and dynamic. Several U.S. Government agencies have highlighted the increasing risks related to physical and cybersecurity attacks, including ransomware attacks, related to the electric sector, including its supply chain, and that the risks may escalate during periods of heightened geopolitical tensions.

Current wording

Edison International and SCE systems, assets and personnel are targets for physical and cyber attacks. Regulators such as NERC and U.S. Government agencies, including the Departments of Defense, Homeland Security, and Energy, have increasingly stressed that threat sources, including nation-state actors, continue to seek to identify and exploit vulnerabilities in the U.S. national electric grid and other critical energy infrastructures, and that such attacks and disruptions, both physical and cyber, are highly sophisticated and dynamic. Several U.S. Government agencies have highlighted the increasing risks related to physical and cybersecurity attacks, including ransomware attacks, related to the electric sector, including its supply chain, and that the risks may escalate during periods of heightened geopolitical tensions.

Previous wording

SCE interacts with a wide array of third parties and depends on vendors to provide it with products and services. Malicious actors may attack vendors to disrupt the services they provide to SCE, or to use those vendors as a conduit to attack SCE. SCE system data and architecture are also disclosed, either voluntarily or by mandate, to third parties and the public by regulators, employees, contractors, and vendors. This system data may be used by malicious actors to understand SCE’s systems to prepare for a cyber or physical attack.

Current wording

SCE interacts with a wide array of third parties and depends on vendors to provide it with products and services. These products and services may contain vulnerabilities and could require patching which could cause disruptions to SCE's operations. Malicious actors may attack vendors to disrupt the services they provide to SCE, or to use those vendors as a conduit to attack SCE. SCE system data and architecture are also disclosed, either voluntarily or by mandate, to third parties and the public by regulators, employees, contractors, and vendors. This system data may be used by malicious actors to understand SCE’s systems to prepare for a cyber or physical attack.

Previous wording

Edison International and SCE could be materially and adversely impacted by catastrophic, macroeconomic and geopolitical events, such as the effects of increased inflationary pressures and interest rates, potential economic downturns or recessions, geopolitical pressures, and pandemics and regional health emergencies. For example, the global spread of COVID-19, which was declared a pandemic by the World Health Organization in March 2020, created significant uncertainty, volatility and disruption globally that resulted in, among other things, disruption to supply chains, economies, and workforce and impacted the operations of Edison International and SCE. Additionally, the geopolitical developments involving the Russia-Ukraine conflict, China and the Middle East, could cause delays and disruptions in the supply chain and the availability and timely delivery of services, materials and components used in SCE’s operations. Political changes following the United States presidential election could lead to changes in economic conditions or economic uncertainties in the United States and globally, including impacts to infrastructure investments, tariffs, taxes, and energy, environmental and social policies.

Current wording

Edison International and SCE could be materially and adversely impacted by catastrophic, macroeconomic and geopolitical events, such as the effects of increased inflationary pressures and interest rates, potential economic downturns or recessions, geopolitical pressures, and pandemics and regional health emergencies. For example, the global spread of COVID-19, which was declared a pandemic by the World Health Organization in March 2020, created significant uncertainty, volatility and disruption globally that resulted in, among other things, disruption to supply chains, economies, and workforce and impacted the operations of Edison International and SCE. Additionally, the geopolitical developments involving the Russia-Ukraine conflict, China and the Middle East, could cause delays and disruptions in the supply chain and the availability and timely delivery of services, materials and components used in SCE’s operations. Geopolitical tensions can also heighten cybersecurity risks, including the risk of malicious activity by state‑sponsored actors. For additional information regarding these cybersecurity threats, see “—Cybersecurity and Physical Security Risks.” Evolving U.S. and California governmental policies and regulatory initiatives could lead to changes in economic conditions or economic uncertainties in the State of California, United States and globally, including impacts to infrastructure investments, tariffs, taxes, and energy, environmental and social policies.
Rearranged previous paragraphs (1)

Previous report — wording carried elsewhere

SCE's business will impact Edison International's ability to obtain financing. Edison International's inability to borrow funds from time to time could have a material effect on Edison International's liquidity and operations.