SOUTHWEST AIRLINES CO
For the period ended Jun 30, 2024. Filed Jul 29, 2024.
View on SEC.govAbout this filing
A company's report for each of its first three quarters. The financial statements are not audited. It shows how the business has moved since the last annual report, and what management says changed.
Jun 30, 2024 · Filed Jul 29, 2024
Contents
9. Commitments and Contingencies
- COMMITMENTS AND CONTINGENCIES
Commitments
The Company's contractual order book with The Boeing Company ("Boeing") for 737-7 ("-7") and 737-8 ("-8") aircraft, which extends to 2031, was designed to support the Company's growth and fleet modernization plans, while also providing significant flexibility and optionality to manage its fleet gauge and size, including opportunities to accelerate fleet modernization efforts if growth opportunities do not materialize. The Company received five -8 aircraft deliveries from Boeing in second quarter 2024 and retiredsix -700 aircraft andone 737-800 ("-800") aircraft.
Boeing continues to experience delays in fulfilling its commitments with regards to delivery of MAX aircraft to the Company, as a result of manufacturing challenges, as well as delays in achieving FAA certification of one of its new aircraft types, the -7, for which Southwest expects to be the launch customer. During first quarter 2024, as a result of Boeing's delivery delays, the Company conservatively re-planned its capacity and delivery expectations for the remainder of this year and for 2025. While the Company has not further adjusted capacity expectations this quarter, it will continue to closely monitor the ongoing aircraft delivery delays with Boeing and adjust expectations, conservatively, as needed.
During April 2024, the Company shiftedone 2025 -8 option into 2026. As of June 30, 2024, the Company had the following firm orders and options for future periods:
| Notes to Condensed Consolidated Financial Statements | Southwest Airlines Co.Notes to Condensed Consolidated Financial Statements(unaudited) |
|---|
| The Boeing Company | ||||||
|---|---|---|---|---|---|---|
| -7 Firm Orders · -8 Firm Orders · -7 or -8 Options · Total | ||||||
| 2024 | 27 | 58 | — | 85(c) | ||
| 2025 | 40 | 19 | 14 | 73 | ||
| 2026 | 59 | — | 27 | 86 | ||
| 2027 | 19 | 46 | 25 | 90 | ||
| 2028 | 15 | 50 | 25 | 90 | ||
| 2029 | 38 | 34 | 18 | 90 | ||
| 2030 | 45 | — | 45 | 90 | ||
| 2031 | 45 | — | 45 | 90 | ||
| 288(a) | 207(b) | 199 | 694 | |||
(a) The delivery timing for the -7 is dependent on the Federal Aviation Administration ("FAA") issuing required certifications and approvals to Boeing and the Company. The FAA will ultimately determine the timing of the -7 certification and entry into service, and the Company therefore offers no assurances that current estimations and timelines are correct.
(b) The Company has flexibility to designate firm orders or options as -7s or -8s, upon written advance notification as stated in the contract.
(c) Includes 10 -8 deliveries received year-to-date through June 30, 2024. Given the Company's continued discussions with Boeing and expected aircraft delivery delays, the Company continues to plan for approximately 20 -8 aircraft deliveries in 2024.
Based on the Company's current agreement with Boeing, capital commitments associated with firm ordersas of June 30, 2024, were: $1.8 billion remaining in 2024, $1.7 billion in 2025, $1.8 billion in 2026, $2.6 billion in 2027, $2.9 billion in 2028, $2.5 billion in 2029, and $2.8 billion thereafter.
Subsequent to June 30, 2024 and through July 25, 2024, the Company exercisedtwo -7 options for delivery in 2025, and convertedtwo 2025 -7 firm orders to -8 firm orders, resulting in the Company's 2025 capital commitments increasing to $1.8 billion.
Contingencies
The Company is from time to time subject to various legal proceedings and claims arising in the ordinary course of business and records a liability for such claims when it is probable that a loss will be incurred and the amount is reasonably estimable.
The Company is a defendant in class action litigation asserting it has not provided paid short-term military leave to certain employees, in violation of the federal Uniformed Services Employment and Reemployment Rights Act (“USERRA”). The United States District Court for the Northern District of California previously issued an order to effectively stay the action, pending an appeal from an order by the United States District Court for the Eastern District of Washington granting summary judgment in favor of an airline in a separate case involving substantially the same claims at issue in this action. On February 1, 2023, the Ninth Circuit reversed the district court’s grant of summary judgment and remanded the separate airline case to the District Court. The Ninth Circuit’s decision may adversely affect the Company’s defenses in the USERRA proceeding and may give rise to additional litigation in this or other areas. On March 22, 2024, the parties in the Company's case submitted a proposed case schedule through trial. The Court subsequently set a trial date of July 21, 2025. The Company is currently not able to estimate a range of possible loss with regards to the litigation to which it is a defendant.
The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.