ALABAMA POWER CO
For the period ended Sep 30, 2026. Filed Nov 5, 2026.
View on SEC.govAbout this filing
A company's report for each of its first three quarters. The financial statements are not audited. It shows how the business has moved since the last annual report, and what management says changed.
Sep 30, 2026 · Filed Nov 5, 2026
What changed in Management’s Discussion and Analysis?
Read the current filingPrevious report: 10-Q
Period ended 2026-06-30; filed 2026-07-30.
0000092122-26-000054
Item 2. Management's Discussion and Analysis of Financial Condition and Results of OperationsOverviewCurrent report: 10-Q
Period ended 2026-09-30; filed 2026-11-05.
0000092122-26-000069
Item 2. Management's Discussion and Analysis of Financial Condition and Results of OperationsOverviewThe baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.
Compared 20 previous paragraphs and 36 current paragraphs.
14 unchanged; 5 reworded; 13 added; 0 removed; 1 previous and 4 current paragraphs rearranged.
Tables are not compared: 1 previous and 1 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.
A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.
Added paragraphs (13)
Current report
On November 4, 2026, in conjunction with a Rate CNP New Plant filing, Alabama Power requested authorization from the Alabama PSC to defer until 2029 the recovery of the costs associated with the Lindsay Hill Generating Station to reconcile the timing of that recovery with the apparent intent of the Power to the People Act. In this filing, Alabama Power proposed providing bill credits to retail customers during 2028 to offset any rate impact of the previously approved cost recovery associated with the Lindsay Hill Generating Station through Rate CNP New Plant beginning January 2028. Alabama Power also proposed establishing a regulatory asset for the associated costs in 2028 to be recovered over a five-year period starting in 2029 in order to effectuate the previously approved cost recovery. The ultimate outcome of this matter cannot be determined at this time. See Note (B) to the Condensed Financial Statements under "Alabama Power – Power to the People Act" herein and Note 15 to the financial statements under "Alabama Power" in Item 8 of the Form 10-K for additional information.
Current report
In addition to comprehensive pricing, early termination fees, and security features such as guarantees or surety bonds, Alabama Power has included in certain electric service contracts an Incremental Revenue Component (IRC) designed to further help mitigate Potential Cost Exposure (PCE) associated with expected incremental investments.
Current report
On October 16, 2026, Alabama Power filed a petition with the Alabama PSC seeking authorization to establish a regulatory liability effective October 1, 2026 for future PCE to align with the IRC.
Current report
Alabama Power proposed in this petition that when the IRC amounts are billed, Alabama Power would identify a corresponding amount of PCE and record that amount as a regulatory liability, with a corresponding charge to amortization. This would allow Alabama Power to establish a regulatory liability to mitigate PCE when and if it materializes while the related IRC amounts are billed. Once risk mitigation thresholds are achieved, Alabama Power would begin systematically reducing the regulatory liability with a corresponding credit to amortization.
Current report
On August 26, 2026, as a result of additional large load contracts, Georgia Power filed a joint statement with the Georgia PSC Staff in which Georgia Power agreed to increase the amount of downward pressure on rates for non-large load customers to be included in its next base rate case to at least $949 million per year, on a levelized basis, for the years 2029, 2030, and 2031.
Current report
See Note (B) to the Condensed Financial Statements under "Georgia Power – Integrated Resource Plans" herein for additional information.
Current report
During the first nine months of 2026, Southern Power placed in service the 180-MW second phase of the Millers Branch solar facility, as well as all 200 MWs and all 152 MWs of the repowering projects at the Kay and Grant wind facilities, respectively.
Current report
On September 8, 2026, Nicor Gas, the staff of the Illinois Commission, and certain other parties entered into a stipulation to resolve Nicor Gas' general base rate case filed on January 9, 2026. On October 15, 2026, the Illinois Commission entered an order approving the stipulation, which provides for an annual base rate revenue increase of approximately $82 million, an ROE of 9.48%, and an equity ratio of 50%, effective November 16, 2026. Under the stipulation, Nicor Gas has agreed that once the order approving the stipulation becomes final, including the resolution of any rehearing requests, it will file a motion to dismiss its pending appeal of the Illinois Commission's November 19, 2025 base rate case decision. The order remains subject to rehearing requests and related procedural actions. The ultimate outcome of this matter cannot be determined at this time.
Current report
On August 4, 2026, Virginia Natural Gas filed a base rate case with the Virginia Commission seeking an increase in annual base revenues of $67 million, including $18 million related to the recovery of investments under the SAVE program. The requested increase is based on a projected 12-month period beginning January 1, 2027, an ROE of 10.45%, and an equity ratio of 54.86%. Rate adjustments will be effective January 1, 2027, subject to refund. The Virginia Commission is expected to issue an order on the requested increase in the third quarter 2027. The ultimate outcome of this matter cannot be determined at this time.
Reworded paragraphs (5)
Previous wording
In December 2025, the Alabama PSC issued a consent order to keep retail rates stable through 2027. On April 2, 2026, the State of Alabama enacted legislation providing that retail base rates established and in place on October 1, 2026 may not be increased before January 1, 2029 for utilities that are regulated by the Alabama PSC and that provide retail electric service. The ultimate outcome of this matter cannot be determined at this time. See Note 2 to the financial statements under "Alabama Power" in Item 8 of the Form 10-K for additional information.
Current wording
In December 2025, the Alabama PSC issued a consent order to keep retail rates stable through 2027. On April 2, 2026, the State of Alabama enacted legislation (Power to the People Act) providing that retail base rates established and in place on October 1, 2026 may not be increased before January 1, 2029 for utilities that are regulated by the Alabama PSC and that provide retail electric service. The ultimate outcome of this matter cannot be determined at this time. See Note 2 to the financial statements under "Alabama Power" in Item 8 of the Form 10-K for additional information.
Previous wording
In the first quarter 2026, Southern Power committed to development projects to upgrade certain turbines at its existing Franklin and Wansley natural gas facilities, which are projected to add up to 400 MWs of incremental capacity. Commercial operations for the incremental capacity at the natural gas facilities are projected to occur between the second quarter 2029 and the fourth quarter 2030. The ultimate outcome of these matters cannot be determined at this time. In addition, during the first six months of 2026 and subsequent to June 30, 2026, Southern Power placed in service all 200 MWs of the repowering project at the Kay wind facility. See Note (K) to the Condensed Financial Statements under "Southern Power" herein for additional information.
Current wording
In the first quarter 2026, Southern Power committed to development projects to uprate certain turbines at its existing Franklin and Wansley natural gas facilities, which are projected to add up to 400 MWs of incremental capacity.
Previous wording
At June 30, 2026, Southern Power's average investment coverage ratio for its generating assets, including those owned with various partners, based on the ratio of investment under contract to total investment using the respective facilities' net book value (or expected in-service value for facilities under construction) as the investment amount was 97% through 2030 and 88% through 2035, with an average remaining contract duration of approximately 12 years.
Current wording
At September 30, 2026, Southern Power's average investment coverage ratio for its generating assets, including those owned with various partners, based on the ratio of investment under contract to total investment using the respective facilities' net book value (or expected in-service value for facilities under construction) as the investment amount was 98% through 2030 and 89% through 2035, with an average remaining contract duration of approximately 12 years.
Previous wording
On June 16, 2026, in connection with Nicor Gas' 2023 general base rate case proceeding, the Illinois Appellate Court determined that the Illinois Commission did not provide sufficient support for its disallowance of $43 million of Nicor Gas' planned capital investments that were expected to be completed by December 31, 2024. As the disallowance related to planned capital investments for which costs had not yet been incurred, it was not included in the pre-tax charge to income recorded in 2023. This matter remains subject to further proceedings before the Illinois Commission and had no impact on the current period financial statements.
Current wording
On June 16, 2026, in connection with Nicor Gas' 2023 general base rate case proceeding, the Illinois Appellate Court determined that the Illinois Commission did not provide sufficient support for its disallowance of $43 million of Nicor Gas' planned capital investments that were expected to be completed by December 31, 2024. As the disallowance related to planned capital investments for which costs had not yet been incurred, it was not included in the pre-tax charge to income recorded in 2023. This matter remains subject to further proceedings before the Illinois Commission and had no impact on the current period financial statements. The ultimate outcome of this matter cannot be determined at this time.
Previous wording
On July 21, 2026, Nicor Gas filed a petition for leave to appeal with the Illinois Supreme Court related to the capital structure approved in Nicor Gas' 2023 general base rate case proceeding. The Illinois Supreme Court is expected to rule on the petition on September 30, 2026.
Current wording
On July 21, 2026, Nicor Gas filed a petition for leave to appeal with the Illinois Supreme Court related to the capital structure approved in Nicor Gas' 2023 general base rate case proceeding. On September 30, 2026, the Illinois Supreme Court denied Nicor Gas' petition. This matter is now concluded.
Rearranged current paragraphs (4)
Current report — wording carried from elsewhere
The ultimate outcome of this matter cannot be determined at this time.
Current report — wording carried from elsewhere
Commercial operations for the incremental capacity at the natural gas facilities are projected to occur between the second quarter 2029 and the fourth quarter 2030. The ultimate outcome of these matters cannot be determined at this time.
Current report — wording carried from elsewhere
In addition, during the first nine months of 2026 and subsequent to September 30, 2026, Southern Power placed in service 82 MWs of the 147-MW repowering project at the Grant Plains wind facility. The ultimate outcome of this matter cannot be determined at this time.
Current report — wording carried from elsewhere
See Note (K) to the Condensed Financial Statements under "Southern Power" herein for additional information.
Rearranged previous paragraphs (1)
Previous report — wording carried elsewhere
The ultimate outcome of these matters cannot be determined at this time.