What changed in Management’s Discussion and Analysis?

Read the current filing

Previous report: 10-K

Period ended 2024-12-31; filed 2025-02-27.

0000077543-25-000025

Item 7. Management’s Discussion and Analysis of Financial Condition and Results of Operations

Current report: 10-K

Period ended 2025-12-31; filed 2026-02-26.

0000077543-26-000028

Item 7. Management’s Discussion and Analysis of Financial Condition and Results of Operations

The baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.

Compared 113 previous paragraphs and 114 current paragraphs.

51 unchanged; 35 reworded; 28 added; 26 removed; 1 previous and 0 current paragraphs rearranged.

Tables are not compared: 6 previous and 7 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.

A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.

Added paragraphs (28)

Current report

Consolidated revenue for 2025 was $5.5 billion, up 28% compared to $4.3 billion for 2024. The Company experienced strong growth in all three segments in 2025, primarily driven by increased project execution activities on certain newer, larger and higher-margin projects, all of which have significant scope of work remaining. These projects are in the early stages and are expected to ramp up substantially over the next several years.

Current report

Diluted earnings per common share for 2025 was $1.51 compared to diluted loss per common share of $3.13 for 2024. Adjusted diluted earnings per common share, which is a non-GAAP financial measure and excludes share-based compensation expense (and the associated tax benefit) for 2025 was $4.29, compared to an adjusted diluted loss per common share of $2.37 for 2024. The improvement for 2025 was primarily due to the factors discussed above that resulted in the change in income (loss) from construction operations for such period. Refer to the Non-GAAP Financial Measures section below for further information and a reconciliation of the Company's financial results reported under generally accepted accounting principles in the United States (“GAAP”) to the reported adjusted results.

Current report

The Company generated record cash flow from operations of $748.1 million in 2025 largely driven by collections from newer and ongoing projects and, to a much lesser extent, from collections related to recent dispute resolutions. The Company utilized some of its cash flow from operations in 2025 to voluntarily prepay its outstanding Term Loan B debt of $121.9 million.

Current report

Consolidated new awards in 2025 were $7.4 billion compared to $12.8 billion in 2024. The Civil and Building segments were the primary contributors to the new awards activity in 2025. Significant new awards and contract adjustments in 2025 included the $1.87 billion Midtown Bus Terminal Replacement - Phase 1 project in New York; the $1.18 billion Manhattan Tunnel project in New York; a healthcare facility project in California valued at approximately $1 billion; a $538 million healthcare project in California; $241 million of additional funding for the Apra Harbor Waterfront Repairs project in Guam; a $182 million military defense project in Guam; a $155 million education facility project in California; $131 million of additional funding for an electrical project in Texas; and another electrical project in Texas valued at more than $100 million. The Company has continued to be successful in winning its share of major new project opportunities due to a combination of its strategic bidding approach and favorable market dynamics, including limited competition in select markets for some of the larger projects. This environment, which is supported by strong public funding and demand, has allowed the Company to differentiate itself and deliver compelling proposals that align with the customer’s goals and expectations. The Company expects that this environment will continue for the foreseeable future.

Current report

With respect to potential concerns regarding the U.S. government’s scrutiny and curtailment of federal funding for certain projects, as well as concerns about recent federal government shutdowns and varying new tariff policies that have been and may continue to be implemented, the Company does not currently anticipate any significant impacts to its business related to these factors. Most of the Company’s major projects are funded at the state or local level, or with some combination of federal, state and local funding. For projects that are wholly or partially funded with federal dollars, the funding for those projects has already been committed and/or those projects are strategically important to the United States. Despite this, there have recently been, and there may in the future be, occasions where even previously authorized and committed funding is withheld by the government, which could delay the progress of certain projects or the awards of new projects. The Company does not anticipate any material adverse impacts to its financial results as the result of such temporary project delays.

Current report

Specifically related to potential tariff impacts, the Company utilizes a pre-award and post-award strategy. As part of its pre-award strategy, the Company’s detailed estimating process includes consideration of anticipated cost increases over the performance period of the contract, as well as additional contingencies to address other potential incremental costs related to unforeseen risks. Prior to its bid or proposal submission, the Company also works to negotiate favorable contract provisions that provide entitlement for certain compensable events, which may include price escalation and allowances. Once the project is awarded, the Company’s strategy shifts to entering into purchase orders or “buy-outs” of materials, such as steel and concrete, as well as large pieces of equipment at the onset of projects, which mitigate the risk of future equipment and commodity price increases by passing that risk to vendors. Also at that time, the Company enters into fixed-price contracts with its key project subcontractors whereby the risk of unforeseen escalation is transferred to the subcontractors. The Company benefits from its long-term relationships with key suppliers, vendors and subcontractors, which minimize supply chain disruptions that could arise as a result of tariffs. While the Company believes this strategy appropriately mitigates the current risk of potential tariff impacts, there could be other unforeseen future developments. The Company will continue to monitor and assess its exposure to the economic environment.

Current report

To supplement our audited Consolidated Financial Statements presented under GAAP, we are presenting certain

Current report

non-GAAP financial measures. These non-GAAP financial measures are intended to provide additional insights that facilitate the comparison of our past and present performance, and they are among the indicators management uses to assess the Company’s financial performance and to forecast future performance. By presenting these non-GAAP financial measures, we aim to provide investors and stakeholders with a clearer understanding of our operating results and enhance transparency with respect to the key financial metrics used by our management in its financial and operational decision-making.

Current report

These non-GAAP financial measures, which exclude share-based compensation expense for the years ended December 31, 2025, 2024 and 2023 (as well as the tax benefit associated with the expense), consist of adjusted net income (loss) attributable to the Company and adjusted earnings (loss) per share. We exclude share-based compensation expense because this expense could result in significant volatility in our reported earnings, driven primarily by fluctuations in the expense recognized for certain long-term incentive compensation awards with payouts that are indexed to the Company’s common stock. By adjusting for share-based compensation, our non-GAAP measures present a supplemental depiction of our operational performance and financial health. This approach allows stakeholders to focus on our core operational efficiency and profitability without the variable impact to earnings caused by significant changes in our stock price. Our non-GAAP measures are intended to offer a consistent basis for evaluating the Company’s performance, which management believes is meaningful to stakeholders.

Current report

The non-GAAP financial measures included in this Annual Report on Form 10-K as calculated by the Company are not necessarily comparable to similarly titled measures reported by other companies. Additionally, these non-GAAP financial measures are not meant to be considered as indicators of performance in isolation from or as a substitute for the most directly comparable measures prepared in accordance with GAAP and should be read only in conjunction with financial information presented on a GAAP basis.

Current report

Reconciliations of these non-GAAP financial measures are found in the table below:

Current report

(a)The amount represents share-based compensation expense recorded during the years ended December 31, 2025, 2024 and 2023. This includes expense associated with certain long-term incentive compensation awards that have payouts indexed to the Company’s common stock. As such, significant fluctuations in the price of the Company’s common stock during any reporting period have caused and could continue to cause significant fluctuations in the reported expense. The increase in the expense for the year ended December 31, 2025 as compared to the prior-year periods was driven by the substantial increase in the price of the Company’s stock during the 2025 period.

Current report

Revenue for 2025 increased 34% compared to 2024, and set a new record for the segment. The substantial growth was primarily due to increased project execution activities on certain newer, larger and higher-margin projects, all of which have substantial scope of work remaining.

Current report

Operating margin was 13.7% for 2025 compared to 6.5% in 2024. The increase in operating margin for 2025 was primarily due to the above-mentioned factors that drove the increases in revenue and income from construction operations.

Current report

New awards and contract adjustments in the Civil segment totaled $4.2 billion in 2025 compared to $6.7 billion in 2024. Significant new awards and contract adjustments in 2025 included the $1.87 billion Midtown Bus Terminal Replacement - Phase 1 project in New York; the $1.18 billion Manhattan Tunnel project in New York; $241 million of additional funding for the Apra Harbor Waterfront Repairs project in Guam; and a $182 million military defense project in Guam.

Current report

Revenue for 2025 increased 15% compared to 2024, primarily due to increased project execution activities on two large detention facility projects in New York and a large healthcare facility project in California, all of which have substantial scope of work remaining.

Current report

New awards and contract adjustments in the Building segment totaled $2.2 billion in 2025 compared to $4.5 billion in 2024. Significant new awards and contract adjustments in 2025 included a healthcare facility project in California valued at approximately $1 billion; a $538 million healthcare project in California; and a $155 million education facility project in California. Certain Building segment end markets, such as healthcare, education, industrial/manufacturing, and hospitality and gaming, continue to demonstrate strong demand for new and renovated facilities.

Current report

Revenue for 2025 increased 43% compared to 2024, primarily due to increased project execution activities on the electrical and mechanical components of various newer projects across diverse end markets, all with substantial scope of work remaining and driven by overall strong market demand.

Current report

Loss from construction operations for 2025 was $7.5 million compared to $103.3 million for 2024. The significant improvement was primarily due to contributions related to the increased project execution activities discussed above. Many of these projects are in the early stages and are expected to ramp up substantially over the next several years. The improvement was also driven by a reduction in net unfavorable adjustments in 2025, primarily due to the absence of certain prior-year unfavorable adjustments on several completed projects due to the impact of judgments and settlements that totaled $57.2 million in 2024, including $17.7 million due to an unfavorable judgment on a completed mass-transit project in California and certain other adjustments that were individually immaterial.

Current report

New awards and contract adjustments in the Specialty Contractors segment totaled $1.1 billion in 2025 compared to $1.7 billion in 2024. The most significant new awards and contract adjustments in 2025 included five mechanical projects in Florida collectively valued at $155 million, $136 million for the electrical component of a mass-transit project in the Northeast, $131 million of additional funding for an electrical project in Texas and another electrical project in Texas valued at more than $100 million.

Current report

Other income, net for the year ended December 31, 2025 increased $7.6 million compared to the same period in 2024.

Current report

Interest expense decreased $34.1 million in 2025 compared to 2024 primarily due to lower outstanding debt driven by the early payoff of the Term Loan B in the first quarter of 2025, as discussed further in Liquidity and Capital Resources.

Current report

As noted above, cash flow from operating activities increased $244.6 million when comparing 2025 with 2024. The increase in cash flow from operating activities primarily reflects higher cash generated by earning sources, partially offset by a smaller decrease in net project working capital in 2025 compared to 2024. The smaller decrease in net project working capital in 2025 compared to 2024 was primarily due to current-year increases in accounts receivable, other current assets and retention receivable compared to decreases last year, mostly offset by a larger current-year increase in billings in excess of costs and estimated earnings compared to last year. While both periods were positively impacted by collections associated with previously disputed matters, such collections were significant in 2024 whereas they were comparatively lower in 2025.

Current report

(a)The ratio was negative because the Company’s cash and cash equivalents available for general corporate purposes exceeded secured Indebtedness, resulting in negative First Lien Net Indebtedness, both as defined in the 2020 Credit Agreement.

Current report

In November 2025, our Board of Directors declared a cash dividend of $0.06 per share payable on December 23, 2025 to all shareholders of record as of December 9, 2025. Total dividends declared in 2025 amounted to $3.4 million, including $0.3 million of accrued dividends relating to unvested share-based awards that are payable at the time of vesting.

Current report

In November 2025, the Company’s Board of Directors authorized a $200 million share repurchase program. Under this program, the Company plans to purchase outstanding common shares from time to time in open market transactions or through privately negotiated transactions at the Company’s discretion, subject to market conditions and other factors and at such times and in amounts that the Company deems appropriate. There were no share repurchases under this program in 2025.
Removed paragraphs (26)

Previous report

Consolidated revenue for 2024 was $4.3 billion, up 12% compared to $3.9 billion for 2023. The increase was primarily driven by significant growth in the Building and Civil segments, as the Company has been successful in pursuing and winning new work and has experienced increased project execution activities on several of the newer projects. The increase was partially offset by reduced project execution activities in the Specialty Contractors segment due to several projects that have completed or are nearing completion. The increase in 2024 was also due to the absence of certain prior-year net unfavorable adjustments, as discussed in more detail below and in Results of Segment Operations. The 2024 period was also adversely impacted by certain current-year net unfavorable adjustments, also discussed in more detail below and in Results of Segment Operations.

Previous report

Legal judgments or decisions during 2024 resulted in net unfavorable impacts of $167.7 million, including $101.6 million pertaining to an unexpected adverse arbitration decision on a legacy dispute related to a completed Civil segment bridge project in California, which the Company is appealing; $17.7 million due to an unfavorable judgment on a completed Specialty Contractors segment mass-transit project in California; and $17.4 million due to an unfavorable legal ruling on a completed Civil segment highway project in Virginia.

Previous report

Legal judgments or decisions during 2023 resulted in net unfavorable impacts of $122.2 million, including an adverse legal ruling on a completed mixed-use project in New York, which resulted in a non-cash charge of $83.6 million, of which $72.2 million impacted the Building segment and $11.4 million impacted the Specialty Contractors segment, and a $24.7 million non-cash charge that resulted from an adverse court ruling on a Specialty Contractors segment educational facilities project in New York.

Previous report

Settlements during 2024 had a net unfavorable impact of $45.8 million, which included an unfavorable adjustment of $20.0 million associated with the settlement of a legacy dispute related to a completed Building segment government facility project in Florida and the net unfavorable impact of various other settlements that were individually immaterial. The impact of these unfavorable adjustments was partially offset by a favorable adjustment of $18.4 million due to a settlement of a claim associated with a completed Civil segment highway tunneling project in the western United States.

Previous report

Settlements during 2023 had a net favorable impact of $8.4 million, which included favorable adjustments totaling $58.1 million resulting from the settlement of change orders and changes in estimates due to improved performance on a Civil segment project on the West Coast. This favorable impact was mostly offset by the net unfavorable impacts from other settlements including the net unfavorable impact of $14.4 million from a settlement that affected multiple components of a Civil segment mass-transit project in California. This settlement included the resolution of certain ongoing disputes and increased the expected profit from work to be performed in the future. The settlement resulted in an unfavorable non-cash adjustment of $23.2 million to one component of the project that is nearing completion, partially offset by a favorable adjustment of $8.8 million on the other component of the project that has substantial scope of work remaining. The net unfavorable impact in 2023 from these two adjustments is expected to be mitigated by the increased profit generated from future work on the project. Other settlements in 2023 included a $13.1 million unfavorable non-cash impact (split evenly between the Civil and Building segments) related to a completed transportation project in the Northeast and the net unfavorable impact of various other settlements that were individually immaterial.

Previous report

Temporary aggregate negative project adjustments referred to above for 2024 of $97.2 million included a temporary non-cash impact of $31.8 million in the fourth quarter for a Civil segment project on the West Coast, which primarily resulted from significant changes that have been negotiated, or are being negotiated, that carry lower margin (and lower risk) that reduced the project’s percentage of completion and overall margin percentage. The remaining amount of temporary negative project adjustments reflected individually immaterial non-cash adjustments due to the successful negotiation of significant lower margin (and lower risk) change orders and growth of unapproved change orders. The temporary impact to earnings resulting from these adjustments is expected to reverse itself over the remaining life of the project.

Previous report

Temporary aggregate negative project adjustments referred to above for 2023 of $79.2 million included a temporary unfavorable non-cash impact of $40.7 million resulting from the successful negotiation of significant lower margin (and lower risk) change orders on a Civil segment project on the West Coast. These approved change orders increased the project’s overall estimated profit but reduced the project’s percentage of completion and overall margin percentage. This temporary reduction to earnings is expected to reverse itself over the remaining life of the project. The remaining amount of temporary negative project adjustments were individually immaterial and were due to growth in unapproved change orders on various projects that reduced the projects’ percentage of completion and profit margin, which are also expected to reverse over the remaining lives of the projects.

Previous report

Other significant project charges during 2024 had a net unfavorable impact of $36.4 million, as discussed above, which consisted of the negative impact from changes in estimates on various projects, mostly offset by positive impacts from improved productivity and efficiencies on certain projects. Other significant project charges during 2024 included unfavorable adjustments of $25.9 million on a Building segment government building project in Florida that is now nearing completion, primarily due to increased costs associated with external subcontractors and resolution of certain delay change orders, $15.1 million due to changes in estimates on an otherwise profitable Civil segment mass-transit project in California that is nearly complete, and the net favorable impact of changes in estimates on various other projects that were individually immaterial. All of these project charges and changes in estimates were due to changes in facts and circumstances that were identified in 2024.

Previous report

Other significant project charges during 2023 had a net unfavorable impact of $117.2 million, and included $62.2 million of unfavorable non-cash adjustments due to changes in estimates on the electrical and mechanical scope of a completed transportation project in the Northeast associated with changes in the expected recovery on certain unapproved change orders resulting from ongoing negotiations; an unfavorable adjustment of $16.9 million on a Specialty Contractors segment multi-unit residential project in New York due to changes in estimates resulting from incremental costs to complete the project and ongoing negotiations on unapproved change orders; a $14.9 million unfavorable adjustment due to changes in estimates due to recent negotiations and incremental cost incurred during project closeout (split evenly between the Civil and Building segments) on the same completed transportation project in the Northeast discussed above; a $14.6 million unfavorable adjustment on a Building segment government building project in Florida primarily due to increased costs associated with an external subcontractor; and the net unfavorable impact of changes in estimates on various other projects that were individually immaterial. All of these project charges and changes in estimates were due to changes in facts and circumstances that were identified in 2023.

Previous report

Diluted loss per common share for 2024 was $3.13 compared to $3.30 for 2023. The change in 2024 was primarily due to the factors discussed above that led to the change in loss from construction operations.

Previous report

The Company generated record cash flow from operations of $503.5 million in 2024 as a result of significant progress made in the resolution of various disputed matters, including those discussed above, and cash generation related to project execution activities for new and existing projects. The Company utilized some of its cash flow from operations for repayments of its outstanding Term Loan B debt, which was paid down by $245.3 million in 2024. During the first quarter of 2025, the Company voluntarily repaid the remaining $121.9 million outstanding balance of the Term Loan B.

Previous report

Revenue for 2024 increased 12% compared to 2023, primarily due to a net increase in project execution activities driven by certain large mass-transit projects in California and Hawaii, two airport projects in the Northern Mariana Islands, and the tunneling component of an energy project in British Columbia, partially offset by reduced project execution activities on a mass-transit project in the Midwest that is nearing completion. The increase was also partially offset by an unfavorable adjustment related to an unexpected adverse arbitration decision on a legacy dispute related to a completed bridge project in California, which the Company is appealing.

Previous report

The decrease in income from construction operations was also partially offset by a net favorable impact of $9.6 million due to the absence of the following prior-year adjustments: 1) a net unfavorable adjustment of $14.4 million due to the aforementioned settlement that affected multiple components of a mass-transit project in California; 2) an unfavorable adjustment of $14.2 million due to changes in estimates on the Civil segment’s portion of a completed transportation project in the Northeast primarily related to the settlement of certain change orders, changes in estimates associated with recent negotiations and incremental cost incurred during project closeout; and 3) net favorable adjustments totaling $19.0 million for a project on the West Coast.

Previous report

Operating margin was 6.5% for 2024 compared to 10.5% in 2023. The decrease in operating margin for 2024 was primarily due to the aforementioned unfavorable adjustment of $101.6 million related to the unexpected adverse arbitration decision on a legacy dispute related to a completed bridge project in California.

Previous report

New awards and contract adjustments in 2023 included $788 million of additional funding for certain mass-transit projects in California; a $222 million military facilities project at Tinian International Airport in the Commonwealth of the Northern Mariana Islands; and $127 million of additional funding for a mass-transit project in Minnesota.

Previous report

Revenue for 2024 increased 24% compared to 2023, with the growth driven by increased project execution activities on various healthcare and educational facility projects in California and a detention facility project in New York with substantial scope of work remaining, as well as the absence of a prior-year unfavorable adjustment related to an adverse legal ruling on a completed mixed-use project in New York.

Previous report

Certain Building segment end markets, such as healthcare, education, industrial/manufacturing, and hospitality and gaming, continue to show strong demand for new and renovated facilities. However, the proliferation of remote and hybrid work settings at many companies, along with continued elevated interest rates, could continue to result in delayed or canceled Building segment project opportunities, particularly in the corporate office end market.

Previous report

New awards and contract adjustments in 2023 included the $2.95 billion Brooklyn Jail project in New York (which includes more than $630 million of electrical and mechanical subcontract work to be performed by the Specialty Contractors segment) and $287 million of additional funding for two large healthcare projects in California.

Previous report

Revenue for 2024 decreased 15% compared to 2023, principally due to reduced project execution activities on various electrical and mechanical projects in New York and Florida and an industrial facility project in Arizona, all of which are completed or nearing completion. The decrease was partially offset by the absence of certain prior-year unfavorable adjustments described in the paragraph below.

Previous report

Loss from construction operations for 2024 was $103.3 million compared to a loss of $144.8 million for 2023. The improvement was primarily due to the absence of certain prior-year unfavorable adjustments, including $62.2 million of unfavorable non-cash adjustments due to changes in estimates on the electrical and mechanical scope of a completed transportation project in the Northeast associated with changes in the expected recovery on certain unapproved change orders resulting from ongoing negotiations; a non-cash charge of $24.7 million on an educational facilities project in New York that resulted from an adverse court ruling; an unfavorable adjustment of $16.9 million on a multi-unit residential project in New York due to changes in estimates resulting from incremental costs to complete the project and ongoing negotiations on unapproved change orders; and an adverse legal ruling on a completed mixed-use project in New York that resulted in a non-cash charge of $83.6 million, of which $11.4 million impacted the Specialty Contractors segment. The improvement was partially offset by certain 2024 unfavorable adjustments on several completed projects due to the impact of judgments and settlements totaling $57.2 million, including $17.7 million due to an unfavorable judgment on a completed mass-transit project in California and certain other adjustments that were individually immaterial. The improvement was also offset by the reduced project execution activities discussed above.

Previous report

New awards in 2023 included more than $630 million of electrical and mechanical subcontract work to be performed on the Brooklyn Jail project in New York; a $67 million communications systems integration project in New York; and the Central District Wastewater Treatment Plant electrical project in Florida, valued at more than $40 million.

Previous report

Other income, net increased by $2.7 million in 2024 compared to 2023 primarily due to an increase in interest income associated with a larger amount of cash on hand in 2024 compared to the prior year.

Previous report

Interest expense increased $3.9 million in 2024 compared to 2023. The Company expects interest expense to decrease in 2025 and beyond as a result of the paydown of $245.3 million of the outstanding Term Loan B during 2024, as well as the repayment of the remaining $121.9 million Term Loan B balance in the first quarter of 2025, as discussed further in Liquidity and Capital Resources. Interest expense on the Term Loan B amounted to $36.9 million and $41.9 million for 2024 and 2023, respectively.

Previous report

As noted above, cash flow from operating activities increased $195.1 million when comparing 2024 with 2023. The increase was primarily driven by a larger decrease in investments in working capital and a lower use of cash from earnings sources in

Previous report

2024 compared to the prior year. Both periods benefited from strong cash collections related to project execution activities on newer and ongoing projects, as well as significant cash collections associated with the resolution of previously disputed matters.

Previous report

The 2020 Credit Agreement requires the Company to make prepayments on the Term Loan B in connection with certain asset sales, receipts of insurance proceeds, incurrences of certain indebtedness and annual excess cash flow (in each case, subject to certain customary exceptions). At December 31, 2023, current maturities of long-term debt in the accompanying Consolidated Balance Sheets included $91.0 million of principal on the Term Loan B relating to the mandatory prepayment provision of the 2020 Credit Agreement in respect of annual excess cash flow, which was due by the first week of April 2024 and paid in February 2024. In addition to the mandatory prepayment discussed above, the Company made voluntary, early prepayments totaling $150.0 million of the Term Loan B during 2024. During the first quarter of 2025, the Company voluntarily repaid the remaining $121.9 million outstanding balance of the Term Loan B.
Reworded paragraphs (35)

Previous wording

Loss from construction operations for 2024 was $103.8 million compared to $114.6 million for 2023. The reduced loss from construction operations in 2024 was primarily due to contributions related to an overall net increase in project execution activities that totaled $93.2 million. The improvement was also driven by 1) various changes in estimates for project charges, net of positive impacts from improved productivity and efficiencies on certain projects, which had an aggregate net unfavorable impact of $36.4 million in 2024 compared to $117.2 million in 2023, partially offset by 2) certain legal judgments or decisions that had net unfavorable impacts totaling $167.7 million in 2024 compared to $122.2 million in 2023; 3) various settlements that had a net unfavorable impact of $45.8 million in 2024 compared to a net favorable impact of $8.4 million in 2023; and 4) temporary aggregate negative project adjustments of $97.2 million in 2024 compared to $79.2 million in 2023 due to both the successful negotiation of significant lower margin (and lower risk) change orders and increases in unapproved work on various projects, the temporary impacts to earnings of which are expected to reverse themselves over the remaining lives of the projects.

Current wording

Income from construction operations for 2025 was $232.0 million, a dramatic improvement compared to a loss from construction operations of $103.8 million for 2024. The increase in income from construction operations in 2025 was primarily due to contributions related to an overall net increase in project execution activities that totaled $172.1 million and a lower amount of net unfavorable adjustments in 2025 driven by changes in the estimate at completion for various projects, including: 1) impacts from improved productivity and efficiencies on certain projects, net of project charges, which had an aggregate net favorable impact of $104.3 million in 2025 compared to a net unfavorable impact of $36.4 million in 2024; 2) certain legal judgments or decisions that had net unfavorable impacts totaling $32.5 million in 2025 compared to $167.7 million in 2024; and 3) temporary aggregate negative project adjustments of $78.7 million in 2025 compared to $97.2 million in 2024 due to both the successful negotiation of significant lower margin (and lower risk) change orders and increases in unapproved work on various projects, the temporary impacts to earnings of which are expected to reverse themselves over the remaining lives of the projects. The improvement was partially offset by the impact of various settlements that had a net unfavorable impact of $61.8 million in 2025 compared to $45.8 million in 2024. The significant adjustments in 2025 and 2024 resulting from the above items are discussed in more detail in Results of Segment Operations.

Previous wording

Furthermore, loss from construction operations for the year ended December 31, 2024 was negatively impacted by share-based compensation expense of $40.4 million compared to share-based compensation expense of $12.3 million in 2023. The increase in share-based compensation expense in 2024 was primarily due to a substantial increase in the Company’s stock price throughout the year, which impacted the fair value of liability-classified awards. These liability-classified awards are remeasured at fair value at the end of each reporting period with the change recognized in earnings. These types of awards were issued in past years as a short-term solution to deal with a depleted share pool under the Tutor Perini Corporation Omnibus Incentive Plan and a low stock price.

Current wording

Furthermore, income from construction operations for the year ended December 31, 2025 was negatively impacted by share-based compensation expense of $150.0 million compared to share-based compensation expense of $40.4 million in 2024. The increase in share-based compensation expense in 2025 was primarily due to a substantial increase of 176.9% in the Company’s stock price during 2025, which impacted the fair value of liability-classified awards. These liability-classified awards are remeasured at fair value at the end of each reporting period with the change recognized in earnings. These types of awards were issued in past years as a short-term solution to deal with a depleted share pool under the Tutor Perini Corporation Omnibus Incentive Plan (the “Plan”) and a low stock price. The Company currently projects a decrease in share-based compensation expense in 2026 and a much more significant decrease in 2027 as certain such awards have vested and most of the remaining liability-classified awards will vest by the end of 2026. After the Company’s shareholders approved additional shares under the Plan in May 2025, the Company stopped issuing liability-classified, long-term incentive compensation awards, which will help to reduce future earnings volatility.

Previous wording

The effective income tax rate for 2024 was 29.3% compared to 30.1% for 2023. See Corporate, Tax and Other Matters below for a discussion of the change in the effective tax rate.

Current wording

The effective income tax rate for 2025 was 30.0% compared to 29.3% for 2024. See Corporate, Tax and Other Matters below for a discussion of the change in the effective tax rate.

Previous wording

Consolidated backlog as of December 31, 2024 was $18.7 billion, up 84% compared to $10.2 billion as of December 31, 2023, and set a new all-time record that far exceeded the previous record backlog of $14.0 billion reported for the third quarter of 2024. Backlog as of December 31, 2024 for all three segments also set new all-time records. As of December 31, 2024, the mix of backlog by segment was 47% for Civil, 38% for Building and 15% for Specialty Contractors, compared to 42% for Civil, 41% for Building and 17% for Specialty Contractors at the end of 2023.

Current wording

Consolidated backlog as of December 31, 2025 was $20.6 billion, up 10% compared to $18.7 billion as of December 31, 2024. As of December 31, 2025, the mix of backlog by segment was 49% for Civil, 36% for Building and 15% for Specialty Contractors, compared to 47% for Civil, 38% for Building and 15% for Specialty Contractors at the end of 2024.

Previous wording

Most projects in the Civil segment’s backlog typically convert to revenue over a period of three to five years and in the Building and Specialty Contractors segments over a period of one to three years. We estimate that approximately $4.5 billion, or approximately 24%, of our backlog as of December 31, 2024 will be recognized as revenue in 2025.

Current wording

Most projects in the Civil segment’s backlog typically convert to revenue over a period of three to five years and in the Building and Specialty Contractors segments over a period of one to three years. Certain larger projects across all three segments may extend over a longer duration. We estimate that approximately $6 billion, or approximately 29%, of our backlog as of December 31, 2025 will be recognized as revenue in 2026.

Previous wording

The outlook for the Company’s revenue growth over the next several years is highly favorable, particularly due to strong new award bookings in 2024, as well as other significant new awards that have been and could be booked in 2025. For example, the Company announced in the first quarter of 2025 the award of the $1.18 billion Manhattan Tunnel project in New York and $232 million for several owner-authorized scope options on the Apra Harbor Waterfront Repairs project in Guam. The Company plans to bid various other large new projects in 2025, including the multi-billion-dollar Midtown Bus Terminal Replacement project in New York that is expected to bid in March 2025. Many of the Company’s newer projects are design-build projects that have an initial design phase over the first six to eighteen months during which smaller revenue and earnings are generated prior to the start of a multi-year construction phase that generates substantially larger revenue and earnings. Revenue growth could be impacted by unanticipated project delays or the timing of project bids, awards, commencements, ramp-up activities and completions. We anticipate that we will continue to win our share of significant new project awards resulting from long-term, well-funded capital spending plans by state, local and federal customers, as well as limited competition for many of the larger project opportunities.

Current wording

The outlook for the Company’s revenue growth over the next several years remains highly favorable due to strong new award bookings of large, long-duration projects over the past two years, as well as other new awards that are expected to be booked in the future. For example, the Company has certain building projects in California, mostly in the healthcare, education, and hospitality and gaming sectors, that are in the preconstruction phase. These projects are expected to transition from preconstruction to construction over the next few years, and they include a large, multi-billion-dollar healthcare project in California that is anticipated to be incrementally added to backlog over the next two to three years. Many of the Company’s newer projects are design-build projects that have an initial six to eighteen month design phase during which smaller revenue and earnings are generated prior to the start of a multi-year construction phase that generates substantially larger revenue and earnings. We anticipate that we will continue to win our share of significant new project awards resulting from long-term, well-funded capital spending plans by various state, local and federal customers, as well as limited competition for many of the larger project opportunities.

Previous wording

Nationally, support for transportation-related ballot measures has remained high over the last decade. Since 2014, voters in 43 states approved 84 percent of nearly 3,000 state and local measures on general election ballots. The largest of these was in Los Angeles County, where in 2016 Measure M, a half-cent sales tax increase, was approved and is expected to generate $120 billion of funding over 40 years. Funding from this measure is supporting, and is expected to continue to support, several of the Company’s current and prospective projects. More recently, in the November 2024 elections, voters approved 77 percent of 370 transportation funding measures on state and local ballots throughout the country. These measures are expected to generate an estimated $41.4 billion in new and renewed funding for roads, bridges, rail and other infrastructure. For the first time in four years, interest rates were lowered in September 2024, and some economists expect further rate reductions in 2025, though the actual timing and extent of any future rate reductions remains uncertain. Lower interest rates could support additional demand for continued infrastructure spending. In contrast, should interest rates rise, they could reach levels that may negatively impact demand, especially for certain types of Building segment projects that have already been experiencing such impacts, such as commercial offices and tenant improvement projects, which tend to be more economically sensitive than projects handled by our Civil segment.

Current wording

Nationally, support for transportation-related ballot measures has remained high over the last decade. Since 2014, voters in 43 states approved 84 percent of nearly 3,000 state and local measures on general election ballots. The largest of these was in Los Angeles County, where in 2016 Measure M, a half-cent sales tax increase, was approved and is expected to generate $120 billion of funding over 40 years. Funding from this measure is supporting, and is expected to continue to support, several of the Company’s current and prospective projects. More recently, in the November 2024 elections, voters approved 77 percent of 370 transportation funding measures on state and local ballots throughout the country. These measures are expected to generate an estimated $41.4 billion in new and renewed funding for roads, bridges, rail and other infrastructure. Additionally, the Federal Reserve lowered interest rates in the fall of 2024 and further reduced rates in the second half of 2025, and some economists expect continued interest rate reductions in 2026, though the actual timing and extent of such rate reductions remains uncertain. Lower interest rates could result in additional demand for continued general construction spending.

Previous wording

The Bipartisan Infrastructure Law provides for $1.2 trillion of federal infrastructure funding, including $550 billion in new spending for improvements to the country’s surface-transportation network and enhancements to core infrastructure. The Bipartisan Infrastructure Law initiated the largest federal investment in public transit ever, the single largest dedicated bridge investment since the construction of the interstate highway system and the largest federal investment in passenger rail since the creation of Amtrak, all in addition to providing for regular annual spending for numerous infrastructure projects. This significant incremental funding is anticipated to be spent over the 10 years from its enactment through 2031, and much of it is allocated for investment in end markets that are directly aligned with the Company’s market focus. Accordingly, the Company believes that this significant level of sustained, incremental funding has benefited, and will continue to favorably impact, the Company’s current work and prospective opportunities over the next decade.

Current wording

The Bipartisan Infrastructure Law was enacted into law in November 2021 and provided for $1.2 trillion of federal infrastructure funding, including $550 billion in new spending for improvements to the country’s surface-transportation network and enhancements to core infrastructure. The Bipartisan Infrastructure Law initiated the largest federal investment in public transit ever, the single largest dedicated bridge investment since the construction of the interstate highway system and the largest federal investment in passenger rail since the creation of Amtrak, all in addition to providing for regular annual spending for numerous infrastructure projects. This significant incremental funding is anticipated to be spent over the 10 years from its enactment through 2031, and much of it is allocated for investment in end markets that are directly aligned with our market focus. Accordingly, we believe that this significant funding has benefited, and will continue to favorably impact, our current work and prospective opportunities over the next decade. While the current funding window for the Bipartisan Infrastructure Law closes on September 30, 2026, we believe that Congress recognizes the long-term nature of infrastructure work and is already engaged in the legislative process to secure future funding beyond that date, although the amount and composition of such future funding is yet to be determined. In addition, various existing projects and future project opportunities in Guam and the Indo-Pacific region are being funded by the U.S. government’s Pacific Deterrence Initiative, which provides substantial multi-year funding to support significant improvements that enhance the U.S. military’s infrastructure and readiness. Finally, there are various large infrastructure projects across the U.S. for which future funding may be provided, in part or entirely, through public-private partnership (P3) arrangements, which would include mostly private capital investments.

Previous wording

Income from construction operations for 2024 decreased $60.3 million compared to 2023. The decrease was primarily due to unfavorable adjustments in 2024, including $101.6 million in the third quarter pertaining to the aforementioned unexpected adverse arbitration decision on a legacy dispute related to a completed bridge project in California, which the Company is appealing; a temporary non-cash impact of $31.8 million in the fourth quarter for a project on the West Coast, which primarily resulted from significant changes that have been negotiated, or are being negotiated, that carry lower margin (and lower risk) that reduced the project’s percentage of completion and overall margin percentage; $17.4 million due to an unfavorable legal ruling on a completed highway project in Virginia; and $15.1 million due to changes in estimates on an otherwise profitable mass-transit project in California that is nearly complete. The decrease was partially offset by contributions related to the net increase in project execution activities discussed above that totaled $70.4 million, as well as a favorable adjustment in 2024 of $18.4 million due to a settlement of a claim associated with a completed highway tunneling project in the western United States.

Current wording

Income from construction operations for 2025 increased $252.6 million compared to 2024, and also set a new record for the segment. The significant improvement was primarily due to contributions related to the increased project execution activities discussed above and the absence of certain prior-year net unfavorable adjustments. These prior-year net unfavorable adjustments included $101.6 million pertaining to an unexpected adverse arbitration decision on a legacy dispute related to a completed bridge project in California, which the Company is appealing; a temporary non-cash impact of $31.8 million for a project on the West Coast, which primarily resulted from significant changes that have been negotiated and carry lower margin (and lower risk) that reduced the project’s percentage of completion and overall margin percentage; $17.4 million due to an unfavorable legal ruling on a completed highway project in Virginia; and $15.1 million due to changes in estimates on an otherwise profitable mass-transit project in California that is nearly complete, partially offset by a prior-year favorable adjustment of $18.4 million due to a settlement of a claim associated with a completed highway tunneling project in the western United States. The 2025 period was also impacted by certain largely offsetting adjustments, including favorable adjustments of $57.6 million that resulted from the settlement of certain change orders and changes in estimates due to improved performance and a favorable project closeout on a domestic mass-transit project, mostly offset by an unfavorable adjustment of $54.7 million due to the settlement of a legacy dispute related to a tunneling project in Canada.

Previous wording

New awards in the Civil segment totaled $6.7 billion in 2024 compared to $1.7 billion in 2023. Significant new awards and contract adjustments in 2024 included the $1.66 billion City Center Guideway and Stations project in Hawaii; the $1.13 billion Newark AirTrain Replacement project in New Jersey; the $1.1 billion Kensico-Eastview Connection Tunnel project in New York; the Civil segment’s share of both the $3.76 billion Manhattan Jail project and the $2.95 billion Brooklyn Jail project, both in New York; $479 million of additional funding for certain mass-transit projects in California; $331 million for the Apra Harbor Waterfront Repairs project in Guam; and the Company’s proportionate share of the $1.3 billion Connecticut River Bridge Replacement project in Connecticut.

Current wording

New awards and contract adjustments in 2024 included the $1.66 billion City Center Guideway and Stations project in Hawaii; the $1.13 billion Newark AirTrain Replacement project in New Jersey; the $1.1 billion Kensico-Eastview Connection Tunnel project in New York; the Civil segment’s share of both the $3.76 billion Manhattan Jail project and the $2.95 billion Brooklyn Jail project, both in New York; $479 million of additional funding for certain mass-transit projects in California; $331 million for the Apra Harbor Waterfront Repairs project in Guam; and the Company’s proportionate share of the $1.3 billion Connecticut River Bridge Replacement project in Connecticut.

Previous wording

Backlog for the Civil segment was $8.8 billion as of December 31, 2024, up 108% compared to $4.2 billion as of December 31, 2023, and set a new all-time record for the segment. The segment continues to experience strong demand reflected in a large, multi-year pipeline of prospective projects, supported by substantial anticipated funding from various voter-approved transportation measures, the Bipartisan Infrastructure Law, and by public agencies’ long-term spending plans. We believe that the Civil segment is well-positioned to capture its share of these prospective projects.

Current wording

Backlog for the Civil segment was $10.2 billion as of December 31, 2025, up 15% compared to $8.8 billion as of December 31, 2024. The segment continues to experience strong demand reflected in a large, multi-year pipeline of prospective projects, and supported by substantial anticipated funding from various voter-approved state and local transportation measures, the Bipartisan Infrastructure Law, and by public agencies’ long-term spending plans. We believe that the Civil segment is well-positioned to continue capturing its share of these prospective projects, with the majority of near-term opportunities on the West Coast, in the Midwest, the Northeast, and the Indo-Pacific region.

Previous wording

Revenue and loss from construction operations for the Building segment are summarized as follows:

Current wording

Revenue and income (loss) from construction operations for the Building segment are summarized as follows:

Previous wording

Loss from construction operations for 2024 was $24.1 million compared to a loss of $91.2 million for 2023. The significant improvement was principally due to the absence of prior-year unfavorable adjustments, including the aforementioned prior-year unfavorable adjustment related to the adverse legal ruling on a completed mixed-use project in New York that resulted in a non-cash charge of $83.6 million, of which $72.2 million impacted the Building segment, a $14.6 million unfavorable adjustment on a government building project in Florida primarily due to increased costs associated with an external subcontractor, and a $14.2 million unfavorable adjustment due to changes in estimates on the Building segment’s portion of the aforementioned completed transportation project in the Northeast. The improvement was also due to contributions related to the increased project execution activities discussed above that totaled $26.6 million, partially offset by the impact of unfavorable adjustments in 2024 of $25.9 million on the government building project in Florida mentioned above, which is now nearing completion, primarily due to increased costs associated with external subcontractors and resolution of certain delay change orders, and $20.0 million associated with the settlement of a legacy dispute related to a completed government facility project in Florida.

Current wording

Income from construction operations for 2025 was $58.2 million compared to a loss of $24.1 million for 2024. The significant improvement was principally due to contributions related to the increased project execution activities discussed above and the absence of certain prior-year unfavorable adjustments, including $25.9 million on a completed government building project in Florida primarily due to increased costs associated with external subcontractors and resolution of certain delay change orders and $20.0 million associated with the settlement of a legacy dispute related to a completed government facility project in Florida.

Previous wording

Operating margin was (1.5)% in 2024 compared to (7.0)% in 2023. The increase in operating margin was driven by the factors mentioned above that drove the improved revenue and loss from construction operations.

Current wording

Operating margin was 3.1% in 2025 compared to (1.5)% in 2024. The increase in operating margin was driven by the above-mentioned factors that drove the increases in revenue and income (loss) from construction operations.

Previous wording

New awards in the Building segment totaled $4.5 billion in 2024 compared to $3.3 billion in 2023. Significant new awards and contract adjustments in 2024 included the Building segment’s portion of the $3.76 billion Manhattan Jail project in New York (which includes a substantial amount of electrical and mechanical scope of work that is expected to be performed by the Specialty Contractors segment); a $1.4 billion healthcare campus project in California; $449 million for two healthcare facility projects in California; and a $229 million airport terminal connectors project at Fort Lauderdale-Hollywood International Airport in Florida.

Current wording

New awards and contract adjustments in 2024 included the Building segment’s portion of the $3.76 billion Manhattan Jail project in New York (which includes a substantial amount of electrical and mechanical scope of work that will be performed by the Specialty Contractors segment); a $1.4 billion healthcare campus project in California; $449 million for two healthcare facility projects in California; and a $229 million airport terminal connectors project at Fort Lauderdale-Hollywood International Airport in Florida.

Previous wording

Backlog for the Building segment was $7.0 billion as of December 31, 2024, up 68% compared to $4.2 billion as of December 31, 2023, and set a new all-time record for the segment, with the increase largely driven by the award of the Manhattan Jail project mentioned above. The Building segment continues to experience strong customer demand as reflected by a large volume of prospective projects across various end markets and geographic locations. In addition, there are various healthcare and education projects underway in California that are in the preconstruction phase, with only a small amount of current backlog recorded for them. Some of these projects are soon expected to advance into the construction phase, and we anticipate that we will book significant additional backlog for these projects as a result.

Current wording

Backlog for the Building segment was $7.3 billion as of December 31, 2025, up 4% compared to $7.0 billion as of December 31, 2024. The Building segment continues to experience strong customer demand as reflected by a large volume of prospective projects across various end markets and geographic locations. In addition, there are certain healthcare, education, and hospitality and gaming projects underway in California that are in the preconstruction phase, with only a small portion of their full anticipated value included in our reported backlog. These projects are expected to transition from preconstruction to construction over the next few years, and they include a large, multi-billion-dollar healthcare project in California that is anticipated to be incrementally added to backlog over the next two to three years.

Previous wording

Operating margin was (17.5)% in 2024 compared to (20.9)% in 2023. The change in operating margin was mainly attributable to the aforementioned factors that drove the lower loss from construction operations in 2024.

Current wording

Operating margin was (0.9)% in 2025 compared to (17.5)% in 2024. The change in operating margin was mainly attributable to the aforementioned factors that drove the changes revenue and loss from construction operations in 2025.

Previous wording

New awards in the Specialty Contractors segment totaled $1.7 billion in 2024 compared to $1.1 billion in 2023. The most significant new awards and contract adjustments in 2024 included the Specialty Contractors segment’s electrical and mechanical scope of work booked as part of the Manhattan Jail project discussed above, two electrical projects in New York collectively valued at $195 million and a $64 million electrical project in Connecticut.

Current wording

New awards and contract adjustments in 2024 included the Specialty Contractors segment’s electrical and mechanical scope of work booked as part of the Manhattan Jail project discussed above, two electrical projects in New York collectively valued at $195 million and a $64 million electrical project in Connecticut.

Previous wording

Backlog for the Specialty Contractors segment was $2.8 billion as of December 31, 2024, up 62% compared to $1.7 billion as of December 31, 2023, and set a new all-time record for the segment. The Specialty Contractors segment continues to be primarily focused on servicing the Company’s current and prospective large Civil and Building segment projects, particularly in the Northeast and California. We believe that the segment remains well-positioned to capture its share of new projects, leveraging the size and scale of our business units that operate in New York, Texas, Florida and California and the strong reputation held by these business units for high-quality work on large, complex projects.

Current wording

Backlog for the Specialty Contractors segment was $3.1 billion as of December 31, 2025, up 9% compared to $2.8 billion as of December 31, 2024. The Specialty Contractors segment continues to be primarily focused on servicing the Company’s current and prospective large Civil and Building segment projects, particularly in the Northeast and California. We believe that the segment remains well-positioned to continue capturing its share of other new projects, leveraging the strong reputation held by the business units in this segment for high-quality work on large, complex projects.

Previous wording

Corporate general and administrative expenses were $110.2 million in 2024 compared to $75.2 million in 2023. The increase in corporate general and administrative expenses in 2024 compared to 2023 was primarily due to higher compensation-related expenses, mainly attributable to higher share-based compensation expense. The increase in share-based compensation expense was primarily due to a substantial increase in the Company’s stock price during the 2024 period, which impacted the fair value of liability-classified awards. These awards are remeasured at fair value at the end of each reporting period with the change recognized in earnings.

Current wording

Corporate general and administrative expenses were $210.8 million in 2025 compared to $110.2 million in 2024. The increase in corporate general and administrative expenses in 2025 compared to 2024 was primarily due to a substantial increase in share-based compensation expense that resulted from a higher stock price, which impacted the fair value of liability-classified awards. The Company currently projects a decrease in share-based compensation expense in 2026 and a much more significant decrease in 2027 as certain such awards have vested and most of the remaining liability-classified awards will vest by the end of 2026. After the Company’s shareholders approved additional shares under the Plan in May 2025, the Company stopped issuing liability-classified, long-term incentive compensation awards, which will help to reduce future earnings volatility.

Previous wording

Other Income, Net, Interest Expense and Income Tax Benefit

Current wording

Other Income, Net, Interest Expense and Income Tax (Expense) Benefit

Previous wording

The effective income tax rate was 29.3% for 2024 compared to 30.1% for 2023. The items that caused a lower effective tax rate in 2024 as compared to 2023 were primarily non-deductible compensation expenses and an increase in the valuation allowance, offset by higher state income taxes. For a further discussion of income taxes, refer to Note 5 of the Notes to Consolidated Financial Statements.

Current wording

The effective income tax rate was 30.0% for 2025 compared to 29.3% for 2024. The items that caused a higher effective tax rate in 2025 as compared to 2024 were primarily higher non-deductible expenses, partially offset by higher earnings attributable to noncontrolling interests (for which income taxes are not the responsibility of the Company), federal income tax credits and state income taxes. For a further discussion of income taxes, refer to Note 5 of the Notes to Consolidated Financial Statements.

Previous wording

Liquidity is provided by available cash and cash equivalents, cash generated from operations, credit facilities and access to capital markets. We have a committed line of credit totaling $170.0 million, which may be used for revolving loans, letters of credit and/or general purposes. We believe that cash generated from operations, along with our unused credit capacity and available cash balances as of December 31, 2024, will be sufficient to fund working capital needs and debt maturities for the next 12 months and beyond, as discussed further in Debt below. We generated record cash flow from operations in 2024 which was greater than the previous record set in 2023, as discussed below in Cash and Working Capital. This represented the third consecutive year in which we generated record cash flows from operations. We expect strong operating cash flow to continue in 2025 based on projected cash collections, both from project execution activities and the resolution of outstanding claims and change orders. We utilized some of our record cash flow from operations in 2024 to repay a total of $245.3 million of our outstanding Term Loan B during 2024. During the first quarter of 2025, we voluntarily repaid the remaining $121.9 million outstanding balance of the Term Loan B. In addition, we expect to benefit from the utilization of available net operating loss carryforwards to reduce our cash outflows for income taxes.

Current wording

Liquidity is provided by available cash and cash equivalents, cash generated from operations, credit facilities and access to capital markets. We have a committed line of credit totaling $170.0 million, which may be used for revolving loans, letters of credit and/or general purposes. We believe that cash generated from operations, along with our unused credit capacity and available cash balances as of December 31, 2025, will be sufficient to fund working capital needs, dividends, share repurchases, and debt maturities for the next 12 months and beyond, as discussed further in Debt below. During the first quarter of 2025, we voluntarily repaid the remaining $121.9 million outstanding balance of the Term Loan B. We generated a record amount of operating cash in 2025, as discussed below in Cash and Working Capital. We expect strong annual operating cash flow to continue in future years, both from project execution activities and the resolution of outstanding claims and change orders. In addition, we expect to continue to benefit from the utilization of available net operating loss carryforwards to reduce our cash outflows for income taxes.

Previous wording

Cash and cash equivalents were $455.1 million as of December 31, 2024 compared to $380.6 million as of December 31, 2023. Cash immediately available for general corporate purposes was $265.6 million and $145.1 million as of December 31, 2024 and 2023, respectively, with the remainder being amounts held by our consolidated joint ventures and also our proportionate share of cash held by our unconsolidated joint ventures. Cash held by our joint ventures is available only for joint venture-related uses, including distributions to joint venture partners. In addition, our restricted cash and restricted investments totaled $149.1 million as of December 31, 2024 compared to $144.4 million as of December 31, 2023. Restricted cash and restricted investments at December 31, 2024 were primarily held to secure insurance-related contingent obligations and deposits.

Current wording

Cash and cash equivalents were $734.6 million as of December 31, 2025 compared to $455.1 million as of December 31, 2024. Cash immediately available for general corporate purposes was $270.7 million and $265.6 million as of December 31, 2025 and 2024, respectively, with the remainder being amounts held by our consolidated joint ventures and also our proportionate share of cash held by our unconsolidated joint ventures. Cash held by our joint ventures is available only for joint venture-related uses, including distributions to joint venture partners. In addition, our restricted cash and restricted investments totaled $264.6 million as of December 31, 2025 compared to $149.1 million as of December 31, 2024. Restricted cash and restricted investments at December 31, 2025 were primarily held to secure insurance-related contingent obligations and deposits.

Previous wording

During the year ended December 31, 2024, net cash provided by operating activities was $503.5 million, compared to $308.5 million in 2023, representing an increase of $195.1 million, or 63%. The operating cash flow for 2024 was the largest result for any year since the merger between Tutor-Saliba Corporation and Perini Corporation in 2008, exceeding the previous records achieved in 2023 and 2022. The record operating cash flow in 2024 was primarily due to a decrease in costs and estimated earnings in excess of billings (“CIE”) largely associated with the resolution of various legacy disputed matters, an increase in accounts payable resulting from the timing of payments to subcontractors and vendors, and an increase in billings in excess of costs and estimated earnings (“BIE”) primarily due to advanced payments on newer projects for mobilization and other initial project costs, partially offset by cash utilized by earnings sources. During the year ended December 31, 2023, net cash provided by operating activities was $308.5 million primarily due to a decrease in investments in project working capital partially offset by cash utilized by earnings sources. The decrease in investments in project working capital was primarily due to improved collection activity, as reflected by a decrease in CIE and accounts receivable, and an increase in BIE.

Current wording

During the year ended December 31, 2025, net cash provided by operating activities was $748.1 million, compared to $503.5 million in 2024, representing an increase of $244.6 million, or 49%. The operating cash flow for 2025 was the largest result for any year since the merger between Tutor-Saliba Corporation and Perini Corporation in 2008, and represented the fourth consecutive year of record operating cash flow. The record operating cash flow in 2025 was primarily driven by strong collections on newer and ongoing projects, reflecting a significant increase in project execution and improved working capital management, with additional contributions from a reduction in costs and estimated earnings in excess of billings due to the resolution of certain legacy matters. The operating cash flow in 2024 was primarily driven by collections associated with dispute resolutions.

Previous wording

Net cash used in investing activities during 2024 was $40.7 million, which was primarily due to the acquisition of property and equipment (i.e., capital expenditures) totaling $37.4 million and net cash used in investment transactions of $8.0 million, partially offset by proceeds from the sale of property and equipment of $4.8 million. Net cash used in investing activities during 2023 was $78.2 million, which was primarily due to the acquisition of property and equipment totaling $53.0 million and net cash used in investment transactions of $35.4 million, partially offset by proceeds from the sale of property and equipment of $10.1 million.

Current wording

Net cash used in investing activities during 2025 was $257.3 million, which was primarily due to the acquisition of property and equipment (i.e., capital expenditures) totaling $180.9 million, mostly related to owner-funded equipment on newer projects, and net cash used in investment transactions of $85.3 million, partially offset by proceeds from the sale of property and equipment of $8.9 million. Net cash used in investing activities during 2024 was $40.7 million, which was primarily due to the acquisition of property and equipment totaling $37.4 million and net cash used in investment transactions of $8.0 million, partially offset by proceeds from the sale of property and equipment of $4.8 million.

Previous wording

Net cash used in financing activities during 2024 was $393.3 million, which was primarily driven by a $354.6 million net repayment of debt (including the 2024 Senior Notes issuance of $400 million and the 2017 Senior Notes redemption of $500 million, as well as additional principal prepayments on the Term Loan B, all of which are discussed below in Debt), $25.1 million of payments for debt issuance costs related to debt transactions during the year and $23.3 million of cash distributions to noncontrolling interests, partially offset by $15.2 million of cash contributions from noncontrolling interests. Net cash used in financing activities during 2023 was $109.4 million, which was primarily driven by net repayment of borrowings of $61.7 million and $46.5 million of cash distributions to noncontrolling interests, partially offset by $2.0 million of cash contributions from noncontrolling interests.

Current wording

Net cash used in financing activities during 2025 was $184.8 million, which was primarily driven by a $130.8 million net repayment of debt (including the $121.9 million repayment of the remaining balance on the Term Loan B discussed below in Debt) and $51.7 million of cash distributions to noncontrolling interests. Net cash used in financing activities during 2024 was $393.3 million, which was primarily driven by a $354.6 million net repayment of debt, $25.1 million of payments for debt issuance costs related to debt transactions during the year and $23.3 million of cash distributions to noncontrolling interests, partially offset by $15.2 million of cash contributions from noncontrolling interests.

Previous wording

As of December 31, 2024, we had working capital of $1.0 billion, a ratio of current assets to current liabilities of 1.41 and a ratio of debt to equity of 0.46 compared to working capital of $1.4 billion, a ratio of current assets to current liabilities of 1.66 and a ratio of debt to equity of 0.70 at December 31, 2023.

Current wording

As of December 31, 2025, we had working capital of $0.9 billion, a ratio of current assets to current liabilities of 1.27 and a ratio of debt to equity of 0.32 compared to working capital of $1.0 billion, a ratio of current assets to current liabilities of 1.41 and a ratio of debt to equity of 0.46 at December 31, 2024.

Previous wording

On April 22, 2024, the Company issued $400.0 million in aggregate principal amount of 11.875% Senior Notes due April 30, 2029 (the “2024 Senior Notes”) in a private placement offering. Interest on the 2024 Senior Notes is payable in arrears semi-annually in April and October of each year, beginning in October 2024.

Current wording

On April 22, 2024, the Company issued $400.0 million in aggregate principal amount of 11.875% Senior Notes due April 30, 2029 (the “2024 Senior Notes”) in a private placement offering. Interest on the 2024 Senior Notes is payable in arrears semi-annually in April and October of each year, beginning in October 2024. Proceeds from the 2024 Senior Notes were used to redeem the 2017 Senior Notes (as discussed below).

Previous wording

As of December 31, 2024, the Revolver had unused available borrowing capacity of $170.0 million, and the outstanding balance of the Term Loan B and the 2024 Senior Notes were$121.9 million and $400.0 million, respectively.

Current wording

As of December 31, 2025, the Revolver had unused available borrowing capacity of $170.0 million, and the outstanding balance of the 2024 Senior Notes was $400.0 million. During the first quarter of 2025, the Company voluntarily repaid the remaining $121.9 million outstanding balance of the Term Loan B.

Previous wording

Borrowings under the 2020 Credit Agreement bear interest at variable rates, which have increased since the latter part of 2022 due to changes in market conditions that resulted in increases in the Secured Overnight Financing Rate (“SOFR”) (and the London Interbank Offered Rate (“LIBOR”) prior to the transition to SOFR), in the case of the Term Loan B, and the administrative agent’s prime lending rate, in the case of the Revolver. Effective May 2, 2023, the 2020 Credit Agreement was amended to transition the Company’s original LIBOR option in respect of the Term Loan B to Adjusted Term SOFR. The average borrowing rates on the Term Loan B and the Revolver for the year ended December 31, 2024 were approximately 10.0% and 11.8%, resp ectively. At December 31, 2024, the borrowing rates on the Term Loan B and the Revolver were 9.2% and 10.8%, respectively. For more information regarding the terms of our 2020 Credit Agreement, refer to Note 7 of the Notes to Consolidated Financial Statements.

Current wording

Borrowings under the 2020 Credit Agreement bear interest at variable rates, which have increased since the latter part of 2022 due to changes in market conditions that resulted in increases in the Secured Overnight Financing Rate (“SOFR”) (and the London Interbank Offered Rate (“LIBOR”) prior to the transition to SOFR), in the case of the Term Loan B, and the administrative agent’s prime lending rate, in the case of the Revolver. Effective May 2, 2023, the 2020 Credit Agreement was amended to transition the Company’s original LIBOR option in respect of the Term Loan B to Adjusted Term SOFR. The average borrowing rates on the Term Loan B and the Revolver for the year ended December 31, 2025 were approximately 9.2% and 10.8%, resp ectively. At December 31, 2025, the borrowing rate on the Revolver was 10.0%. For more information regarding the terms of our 2020 Credit Agreement, refer to Note 7 of the Notes to Consolidated Financial Statements.

Previous wording

As amended, the 2020 Credit Agreement requires, solely with respect to the Revolver, the Company and its restricted subsidiaries to maintain a maximum First Lien Net Leverage Ratio of 3.50:1.00, effective the fiscal quarter ended December 31, 2022 and increasing to 3.75:1.00 for the fiscal quarter ending March 31, 2023 and subsequently stepping down to 3.00:1.00 for the fiscal quarter ending June 30, 2023, 2.50:1.00 for the fiscal quarter ending September 30, 2023 and 2.25:1.00 for the fiscal quarter ending December 31, 2023 and each fiscal quarter thereafter. As of December 31, 2024, we were in compliance and expect to continue to be in compliance with the covenants under the 2020 Credit Agreement.

Current wording

As of December 31, 2025, we were in compliance and expect to continue to be in compliance with the covenants under the 2020 Credit Agreement.

Previous wording

The Company has certain loans entered into for the purchase of specific property, plant and equipment and secured by the assets purchased. The aggregate balance of equipment financing loans was approximately $19.3 million and $26.4 million at December 31, 2024 and 2023, respectively, with interest rates ranging from 2.54% to 7.32% with equal monthly installment payments over periods up to 5 years. The aggregate balance of mortgage loans was approximately $5.8 million and $8.4 million at December 31, 2024 and 2023, respectively, with interest rates of SOFR plus 2.00% and monthly installment payments over periods up to 10 years.

Current wording

The Company has certain loans entered into for the purchase of specific property, plant and equipment and secured by the assets purchased. The aggregate balance of equipment financing loans was approximately $13.1 million and $19.3 million at December 31, 2025 and 2024, respectively, with interest rates ranging from 2.54% to 7.32% with equal monthly installment payments over periods up to 5 years. The aggregate balance of mortgage loans was approximately $5.1 million and $5.8 million at December 31, 2025 and 2024, respectively, with interest rates of SOFR plus 2.00% and monthly installment payments over periods up to 10 years.

Previous wording

•Debt obligations of $556.1 million (of which $24.1 million are due in 2025) and interest payments of $221.1 million (of which $53.4 million are due in 2025) based on rates in effect as of December 31, 2024. See Note 7 of the Notes to Consolidated Financial Statements for further detail of our debt and the timing of expected future principal and interest payments.

Current wording

•Debt obligations of $425.4 million (of which $14.6 million are due in 2026) and interest payments of $168.4 million (of which $48.4 million are due in 2026) based on rates in effect as of December 31, 2025. See Note 7 of the Notes to Consolidated Financial Statements for further detail of our debt and the timing of expected future principal and interest payments.

Previous wording

•Operating lease obligations of $67.1 million (of which $11.0 million are due in 2025). See Note 9 of the Notes to Consolidated Financial Statements for further detail of our lease obligations and the timing of expected future payments.

Current wording

•Operating lease obligations of $84.9 million (of which $16.5 million are due in 2026). See Note 9 of the Notes to Consolidated Financial Statements for further detail of our lease obligations and the timing of expected future payments.
Rearranged previous paragraphs (1)

Previous report — wording carried elsewhere

Consolidated new awards in 2024 were $12.8 billion compared to $6.1 billion in 2023. The Civil and Building segments were the primary contributors to the new award activity in 2024. Significant new awards and contract adjustments in 2024 included the $3.76 billion Manhattan Jail project in New York; the $1.66 billion City Center Guideway and Stations project in Hawaii; a $1.4 billion healthcare campus project in California; the $1.13 billion Newark AirTrain Replacement project in New Jersey; the $1.1 billion Kensico-Eastview Connection Tunnel project in New York; $479 million of additional funding for certain mass-transit projects in California; $449 million for two healthcare facility projects in California; $331 million for the Apra Harbor Waterfront Repairs project in Guam; a $229 million airport terminal connectors project at Fort Lauderdale-Hollywood International Airport in Florida; and the Company’s proportionate share of the $1.3 billion Connecticut River Bridge Replacement project in Connecticut.