A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.

FY2025 · Filed Feb 25, 2026

XEL$79.67-0.9%Stored close · as of Nov 6, 2026

What changed in Management’s Discussion and Analysis?

Read the current filing

Previous report: 10-K

Period ended 2024-12-31; filed 2025-02-27.

0000072903-25-000029

Item 7. Management’s Discussion and Analysis of Financial Condition and Results of Operations

Current report: 10-K

Period ended 2025-12-31; filed 2026-02-25.

0000072903-26-000009

Item 7. Management’s Discussion and Analysis of Financial Condition and Results of Operations

The baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.

Compared 375 previous paragraphs and 353 current paragraphs.

201 unchanged; 77 reworded; 72 added; 94 removed; 3 previous and 3 current paragraphs rearranged.

Tables are not compared: 41 previous and 45 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.

A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.

Added paragraphs (72)

Current report

(a)Includes $2 million of interest costs associated with short-term debt used to pay settlement, which is presented as interest expense on the consolidated statements of income.

Current report

Marshall Wildfire Litigation — In the third quarter of 2025, PSCo recognized a non-recurring $287 million charge as a result of a settlement reached with the plaintiffs in the Marshall Wildfire litigation. In the fourth quarter of 2025, an additional $12 million was recognized for estimated remaining settlement costs as well as legal and other costs.

Current report

PSCo— GAAP earnings decreased $0.24 per share and ongoing earnings increased $0.14 per share for 2025 (difference in GAAP and ongoing due to Marshall Wildfire settlement in 2025, see Non-GAAP Financial Measures for reconciliation from GAAP to ongoing earnings). Ongoing earnings increased due to higher recovery of electric and natural gas infrastructure investments and increased AFUDC, which was partially offset by increased depreciation, interest and O&M charges.

Current report

SPS — GAAP and ongoing earnings decreased $0.03 per share for 2025 . The decrease was driven by increased interest charges, O&M expenses and the negative impact of weather, partially offset by sales growth and higher recovery of electric infrastructure investments.

Current report

(a)Cost of electric fuel and purchased power and natural gas sold and transported are generally recovered through regulatory recovery mechanisms and offset in revenue.

Current report

•NSP-Wisconsin — Residential sales increased due to increased use per customer (1.1%) and customer growth (0.9%). The increase in C&I sales was due to customer growth.

Current report

•Decrease in natural gas sales was driven primarily by decreased use per customer in PSCo residential and C&I, partially offset by customer growth in all jurisdictions.

Current report

Electric fuel and purchased power expenses increased $173 million in 2025. The increase is primarily due to increased commodity prices and transmission expense.

Current report

O&M Expenses — O&M expenses increased $192 million in 2025 primarily due to increased benefits and healthcare costs, wildfire mitigation (largely offset in non-fuel rider revenue), nuclear generation costs and insurance costs.

Current report

(a)Amounts primarily include gains from debt repurchases, partially offset by taxes.

Current report

2025 Minnesota Natural Gas Rate Case— In October 2025, NSP-Minnesota filed a natural gas rate case in Minnesota, seeking a total revenue increase of $63 million (8.2%). The filing is based on a 2026 forecast test year and includes an ROE of 10.65%, a 52.5% equity ratio and rate base of $1.5 billion. NSP-Minnesota requested interim rates of $51 million effective January 1, 2026, which were approved by the MPUC. An MPUC decision is expected in the fourth quarter of 2026.

Current report

In August 2025, eight parties filed testimony. The DOC, OAG, XLI, the CUB, Walmart and Joint Intervenors were the only parties to quantify recommended financial adjustments. The DOC and XLI recommended $306 million and $190 million of adjustments, respectively, largely based on a reduction in ROE, certain O&M expenses and other costs offset in trackers. Other parties recommended adjustments based on reduced ROE and issue specific recommendations.

Current report

In October 2025, NSP-Minnesota filed rebuttal testimony, updating its total revenue request to $365 million. Of NSP-Minnesota’s proposed adjustments, approximately $100 million relates to depreciation expense and $50 million are largely offset in trackers. In November 2025, the DOC filed surrebuttal testimony, re-asserting their proposed ROE of 9.25%.

Current report

An ALJ report is expected in April 2026, with a MPUC decision expected in the third quarter of 2026.

Current report

2025 South Dakota Electric Rate Case — In June 2025, NSP-Minnesota filed a request with the SDPUC for a net annual electric rate increase of $44 million (15%). The filing is based on a 2024 historic test year, a requested ROE of 10.3%, rate base of approximately $1.2 billion and an equity ratio of 52.87%. Interim rates were implemented on Jan. 1, 2026. If approved as filed, this rate request would result in an average annual residential bill increase of 3% over the period from 2016-2026.

Current report

2026 North Dakota Natural Gas Rate Case— In January 2026, NSP-Minnesota filed a natural gas rate case in North Dakota, for an annual rate increase of $14 million (11.9%). The filing is based on a 2026 forecast test year and includes an ROE of 10.85%, a 52.5% equity ratio and rate base of $235 million. NSP-Minnesota requested interim rates of $12 million effective April 1, 2026.

Current report

Wisconsin Electric and Natural Gas Rate Case– In March 2025, NSP-Wisconsin filed a request with the PSCW for a multi-year electric and natural gas rate increase. Both the electric and natural gas rate requests were based on forward-looking 2026 and 2027 test years, with a 10.0% ROE and an equity ratio of 53.5%.

Current report

In December 2025, the PSCW issued final written approval on NSP-Wisconsin’s request, with a final rate increase of $126 million for the electric utility ($68 million in 2026, with an incremental $58 million in 2027) and $22 million for the natural gas utility ($18 million in 2026, with an incremental $4 million in 2027), based on a ROE of 9.8% and an equity ratio of 52.5%.

Current report

(a)Since filing the case, the MPUC authorized a reduction to the annual nuclear decommissioning accrual. This reduction, which flows to NSP-Wisconsin through the interchange agreement, reduced the NSP-Wisconsin rate request and is earnings neutral.

Current report

Michigan Natural Gas Rate Case– In July 2025, NSP-Wisconsin filed a natural gas rate case in Michigan, seeking a revenue increase of $2.2 million. In December 2025, the MPSC issued a final written approval of the settlement order, with a final rate increase of $1.6 million ($0.7 million in 2026, with an incremental $0.9 million in 2027) based on a ROE of 9.8% and an equity ratio of 50%.

Current report

•In December 2025, NSP-Minnesota and NSP-Wisconsin jointly issued an RFP seeking up to 3,500 MW of wind, solar, hydro, standalone storage, or hybrid capacity that will achieve commercial operation by December 31, 2030. Additionally, NSP-Minnesota is seeking to procure up to 600 MW of solar or solar + storage capacity that will achieve commercial operation by December 31, 2029, and meet Minnesota’s Distributed Solar Energy Standard eligibility requirements. Bids are due in March 2026, and filing for MPUC approval is expected by the end of 2026, ahead of the established procedural schedule.

Current report

•NSP-Minnesota and NSP-Wisconsin may continue to file additional RFPs throughout 2026 and 2027 for resource needs as part of its Upper Midwest resource planning efforts.

Current report

Large Load Agreement —In the first quarter of 2026, NSP-Minnesota entered into an electric service agreement to power a new Google data center in Minnesota. Under the agreement, Google will pay all costs for its new service for the duration of the agreement, in accordance with Minnesota’s regulatory and legislative requirements for large loads. Requests for approval of the Electric Service Agreement and 1,900 MW of proposed renewable generation to support the data center is expected to be filed with the MPUC by April 2026.

Current report

2025 Colorado Electric Rate Case —In November 2025, PSCo filed an electric rate case with the CPUC seeking an increase in revenue of $356 million (9.9%) ($526 million inclusive of rider roll-ins). The request is based on a 9.8% ROE, an equity ratio of 55% and a 2025 test year with a projected rate base of $13 billion.

Current report

(a)The case includes request for rider recovery of any costs associated with extending operations at Comanche Unit 2.

Current report

A CPUC decision and implementation of final rates is anticipated in the third quarter of 2026.

Current report

A CPUC decision and implementation of final rates is anticipated in the third quarter of 2026.

Current report

In September 2025, the CPUC authorized a process for company-owned and PPA resources to seek up to 15% relief for tariff impacts to projects. Relief requests are due by Dec. 31, 2025 or 18 months prior to COD. The CPUC will ultimately review and approve/deny requests.

Current report

PSCo has filed all generation CPCNs associated with company-owned generation from the Colorado Resource Plan and expects to continue filing transmission CPCNs throughout 2026.

Current report

PSCo filed a request for reconsideration of various aspects of the decision which were verbally approved in January 2026 (with a written decision related to those reconsideration requests expected in the first quarter of 2026). This decision is expected to initiate the Phase II competitive solicitation process with an RFP expected to be issued in the third quarter of 2026. This RFP will seek to acquire the balance of resource needs through 2031 (after consideration of any approved acquisitions from the Near-Term Procurement RFP).

Current report

Near-Term Procurement —In August 2025, PSCo filed a joint motion with state agencies to initiate a “fast-tracked” solution for tax-advantaged new generation resources. The CPUC approved the request in September 2025 with bids submitted in October 2025. The procurement seeks to accelerate development of up to 4,000 nameplate MW of clean energy resources, 200 accredited MW of firm, dispatchable resources, and up to 300 accredited MW of other dispatchable resources.

Current report

The table below summarizes the recommended portfolio of resources filed in December 2025 (a decision is expected in February 2026):

Current report

In February 2026, the CPUC approved 3,200 MW of resources, which included PPAs and a 200 MW company-owned natural gas combustion turbine. Additionally, in March 2026 PSCo will file additional information related to 600-1,500 MW of company-owned wind, solar and storage resources that have been conditionally approved.

Current report

Grid Modernization Adjustment Clause (GMAC) —In December 2024, PSCo filed its 2025-2029 Distribution System Plan which included a request to implement the GMAC for recovery of distribution investments. The CPUC issued their decision in December 2025, as modified by an ARRR in February 2026, approving the inclusion of capacity expansion projects and certain other related costs. The CPUC indicated other categories of distribution costs may be considered for recovery within the GMAC in a future regulatory process, expected in late 2026 or 2027.

Showing the first 40 of 72 passages. Open the source sections for the rest.

Removed paragraphs (94)

Previous report

Comanche Unit 3 Litigation — In the third quarter of 2023, PSCo recognized a non-recurring $34 million charge as a result of a jury verdict in Denver County District Court awarding CORE Electric Cooperative lost power damages and other costs.

Previous report

Workforce Reduction —In 2023, Xcel Energy implemented workforce actions to align resources and investments with our evolving business and customer needs and streamline the organization for long-term success. Xcel Energy initiated a Voluntary Retirement Program, under which approximately 400 eligible non-bargaining employees retired. Xcel Energy also eliminated approximately 150 non-bargaining employees through an involuntary severance program. Workforce reduction expenses of $72 million were recorded in the fourth quarter of 2023.

Previous report

SPS — GAAP earnings were flat and ongoing earnings decreased $0.01 per share for 2024. Ongoing earnings were impacted by increased depreciation, O&M and interest charges, largely offset by regulatory rate outcomes and sales growth.

Previous report

NSP-Wisconsin — GAAP and ongoing earnings decreased $0.01 per share for 2024. The decrease in ongoing earnings was primarily a result of higher depreciation.

Previous report

•NSP-Wisconsin — Residential sales declined due to a 2.7% decrease in use per customer, offset by a 1.0% increase in customers. The C&I sales decline was associated with lower use per customer, experienced particularly in the professional services and manufacturing sectors.

Previous report

•Natural gas sales reflect 1.7% residential use per customer and 1.4% C&I use per customer decreases. Partially offsetting these were increased residential and C&I customers in all jurisdictions.

Previous report

Natural gas sold and transported decreased $505 million in 2024. The decrease is primarily due to lower commodity prices and volumes.

Previous report

O&M Expenses — O&M expenses increased $96 million in 2024 primarily due to operational activities, including generation maintenance, storm response, wildfire mitigation costs and damage prevention. The impact of prior year regulatory deferrals also contributed to increased O&M expenses, partially offset by lower labor and benefit costs and lower bad debt expenses.

Previous report

(a)Amounts include gain from open market debt repurchases in 2024.

Previous report

2024 Minnesota Natural Gas Rate Case — In November 2023, NSP-Minnesota filed a request with the MPUC for a natural gas rate increase of approximately $59 million, or 9.6%.

Previous report

In June 2024, NSP-Minnesota and various parties filed an uncontested settlement, which includes the following terms:

Previous report

In October 2024, an ALJ recommended the MPUC approve the rate case settlement. In February 2025, the MPUC verbally approved the settlement agreement. NSP-Minnesota expects to implement a rate increase of $50 million (trued up for 2024 weather normalized actual sales) in July 2025.

Previous report

2024 North Dakota Natural Gas Rate Case— In December 2023, NSP-Minnesota filed a request with the NDPSC seeking an increase in natural gas rates of $8.5 million (9.4%), based on a ROE of 10.20%, an equity ratio of 52.5%, 2024 test year and rate base of $168 million.

Previous report

Michigan Electric Rate Case —In July 2024, NSP-Wisconsin filed a Michigan electric rate case with the MPSC. In December 2024, the MPSC approved NSP-Wisconsin’s settlement agreement. The settlement order includes an electric rate increase of $1.75 million in 2025 and a step increase of $0.55 million in 2026, based on a ROE of 9.8% and an equity ratio of 50%.

Previous report

Wisconsin 2025 Stay-Out Proposal — In June 2024, NSP-Wisconsin filed a 2025 stay-out proposal with the PSCW. In December 2024, the PSCW approved NSP-Wisconsin’s filing, which offsets $27 million in electric deficiencies and $3 million in natural gas deficiencies by amortizing IRA deferrals, stopping a deferral related to IRA benefits ordered in a previous rate case, and deferring revenue requirement impacts of two natural gas capital projects.

Previous report

Resource Acquisition —In February 2024, NSP filed its Upper Midwest Resource Plan with the MPUC. In October 2024, NSP-Minnesota filed a settlement with several parties reaching agreement on the resource plan, as well as the proposed projects to be approved in the pending 800 MW firm dispatchable resource acquisition.

Previous report

In February 2025, the MPUC verbally approved the terms of the settlement agreement, including:

Previous report

•The selection of the company owned 420 MW Lyon County combustion turbine.

Previous report

•The selection of the company owned 300 MW 4-hour Sherco battery energy storage system.

Previous report

•The addition of 3,200 MW of wind, 400 MW of solar and 600 MW of stand-alone storage to be added through 2030 based on an RFP process (a portion of which is expected to be fulfilled with the resources acquired as part of the 2024 RFPs). Of these amounts, approximately 2,800 MW of wind are projected to utilize the Minnesota Energy Connection transmission line.

Previous report

•Planned life extensions of the Prairie Island and Monticello nuclear plants through the early 2050s.

Previous report

Additionally, the MPUC approved life extensions of the Red Wing and Mankato RDF plants to 2037 and ordered NSP-Minnesota to file a proposed tariff for customers with super-large load, largely data centers, by July 15, 2025.

Previous report

NSP-Minnesota will file additional RFPs for approved resource needs beginning in late 2025 or early 2026.

Previous report

•Use of a historic 2023 test year, with a 13-month average rate base.

Previous report

•Weighted-average cost of capital of 7.0%, based on an ROE range of 9.2%-9.5% and an equity ratio range of 52%-55%.

Previous report

•Acceleration of $15 million per year of depreciation expense (incremental to PSCo’s original rate request), to be held in an external trust for future decommissioning costs.

Previous report

In December 2023, the CPUC approved a framework for two PIMs associated with the generation projects in the portfolio — a PIM related to capital construction costs and another related to ongoing levelized energy costs with details to be further defined via subsequent proceedings throughout 2024. In September 2024, PSCo filed a proposal for implementation of the PIMs. Intervenor testimony is due Feb. 27, 2025, with a final decision expected in summer 2025.

Previous report

In September 2024, PSCo filed a proposed framework for CPUC review of pricing adjustments for both company owned and PPA resources to enable delivery of the approved portfolio in light of supply chain and geopolitical developments. In January 2025, the CPUC issued a decision granting limited potential pricing relief, subject to evaluation in future CPCN proceedings for company owned projects.

Previous report

PSCo filed or expects to file generation and transmission CPCNs throughout 2024 and 2025.

Previous report

2024 Colorado Electric Resource Plan — In October 2024, PSCo filed its electric resource plan with the CPUC. The filing reflects the expected growth on the system, the generation resources needed to meet the projected growth and the future evaluation of competitive bids for new generation resources.

Previous report

•The plan reflects a base sales forecast with 7% compound annual sales growth through 2031.

Previous report

•The resource plan includes forecasted need of 5-14 GW of new generation capacity through 2031, including renewables and firm dispatchable resources to meet the two different scenarios. The acquisitions of generation resources will be determined through a competitive solicitation after the CPUC determines the portfolio. The table below summarizes two of the proposed portfolios based on the different sales scenarios:

Showing the first 40 of 94 passages. Open the source sections for the rest.

Reworded paragraphs (77)

Previous wording

The following discussion includes financial information prepared in accordance with GAAP, as well as certain non-GAAP financial measures such as ongoing ROE, ongoing earnings and ongoing diluted EPS. Generally, a non-GAAP financial measure is a measure of a company’s financial performance, financial position or cash flows that is adjusted from measures calculated and presented in accordance with GAAP.

Current wording

The following discussion includes financial information prepared in accordance with GAAP, as well as certain non-GAAP financial measures such as ongoing ROE, ongoing earnings and ongoing diluted EPS. Generally, a non-GAAP financial measure is a measure of a company’s financial performance, financial position or cash flows that adjusts measures calculated and presented in accordance with GAAP.

Previous wording

GAAP diluted EPS reflects the potential dilution that could occur if securities or other agreements to issue common stock (i.e., common stock equivalents) were settled. The weighted average number of potentially dilutive shares outstanding used to calculate Xcel Energy Inc.’s diluted EPS is calculated using the treasury stock method. Ongoing earnings reflect adjustments to GAAP earnings (net income) for certain items. Ongoing diluted EPS is calculated by dividing the net income or loss of each subsidiary, adjusted for certain items, by the weighted average fully diluted Xcel Energy Inc. common shares outstanding for the period. Ongoing diluted EPS for each subsidiary is calculated by dividing the net income or loss of such subsidiary, adjusted for certain items, by the weighted average fully diluted Xcel Energy Inc. common shares outstanding for the period.

Current wording

GAAP diluted EPS reflects the potential dilution that could occur if securities or other agreements to issue common stock (i.e., common stock equivalents) were settled. The weighted average number of potentially dilutive shares outstanding used to calculate Xcel Energy Inc.’s diluted EPS is calculated using the treasury stock method. Ongoing earnings reflect adjustments to GAAP earnings (net income) for certain items. Ongoing diluted EPS for Xcel Energy is calculated by dividing net income or loss, adjusted for certain items, by the weighted average fully diluted Xcel Energy Inc. common shares outstanding for the period. Ongoing diluted EPS for each subsidiary is calculated by dividing the net income or loss for such subsidiary, adjusted for certain items, by the weighted average fully diluted Xcel Energy Inc. common shares outstanding for the period.

Previous wording

Sherco Unit 3 2011 Outage Refunds — NSP-Minnesota’s Sherco Unit 3 experienced an extended outage following a 2011 incident which damaged its turbine. In 2024, following contested case procedures, Xcel Energy recognized a customer refund of $47 million for replacement power incurred during the outage.

Current wording

Sherco Unit 3 2011 Outage Refunds — NSP-Minnesota’s Sherco Unit 3 experienced an extended outage following a 2011 incident which damaged its turbine. In October 2024 following contested case procedures, the MPUC ordered a customer refund of $46 million for replacement power incurred during the outage, which is presented as a non-recurring charge to electric revenues.

Previous wording

Xcel Energy — GAAP earnings were $3.44 per share compared to $3.21 per share in 2023 and ongoing earnings were $3.50 per share in 2024, compared with $3.35 per share in 2023. The change in EPS was driven by increased recovery of infrastructure investments, partially offset by higher depreciation, interest charges and O&M expenses.

Current wording

Xcel Energy — GAAP diluted earnings were $3.42 per share compared to $3.44 per share in 2024 and ongoing diluted earnings were $3.80 per share in 2025, compared with $3.50 per share in 2024. The change in ongoing EPS was driven by increased recovery of infrastructure investments and electric sales growth, partially offset by higher interest, depreciation and O&M expenses.

Previous wording

NSP-Minnesota— GAAP earnings increased $0.13 per share and ongoing earnings increased $0.15 per share for 2024 compared to 2023. Ongoing earnings increased due to higher recovery of electric and natural gas infrastructure investments, partially offset by increased depreciation and interest charges.

Current wording

NSP-Minnesota— GAAP earnings increased $0.12 per share and ongoing earnings increased $0.06 per share for 2025 compared to 2024. Ongoing earnings increased due to higher recovery of electric infrastructure investments, partially offset by increased O&M expenses, depreciation and interest charges.

Previous wording

PSCo— GAAP earnings increased $0.13 per share and ongoing earnings increased $0.06 per share for 2024. Higher ongoing earnings primarily reflects higher recovery of electric and natural gas infrastructure investments, which was partially offset by increased depreciation, O&M and interest charges.

Current wording

NSP-Wisconsin — GAAP and ongoing earnings increased $0.03 per share for 2025. The increase was driven by higher recovery of electric and natural gas infrastructure investments, which was partially offset by increased depreciation and O&M expenses.

Previous wording

Xcel Energy Inc. and Other — Primarily includes financing costs and interest income at the holding company and earnings from investment funds, which are accounted for as equity method investments. The decline in earnings for 2024 is largely due to higher debt levels and increased interest rates, partially offset by a gain on debt repurchases.

Current wording

Xcel Energy Inc. and Other — Primarily includes financing costs and interest income at the holding company and earnings from investment funds, which are accounted for as equity method investments. The change in earnings was due to gains on debt repurchases, partially offset by higher interest rates and debt levels.

Previous wording

Estimated Impact of Temperature Changes on Regulated Earnings— Unusually hot summers or cold winters increase electric and natural gas sales, while mild weather reduces electric and natural gas sales. The estimated impact of weather on earnings is based on the number of customers, temperature variances, the amount of natural gas or electricity historically used per degree of temperature and excludes any incremental related operating expenses that could result due to storm activity or vegetation management requirements. As a result, weather deviations from normal levels can affect Xcel Energy’s financial performance. However, electric sales true-up and gas decoupling mechanisms in Minnesota predominately mitigate the positive and adverse impacts of weather in that jurisdiction.

Current wording

Estimated Impact of Temperature Changes on Regulated Earnings— Unusually hot summers or cold winters increase electric and natural gas sales, while mild weather reduces electric and natural gas sales. The estimated impact of weather on earnings is based on the number of customers, temperature variances, the amount of natural gas or electricity historically used per degree of temperature and excludes any incremental related operating expenses that could result due to storm activity or vegetation management requirements.

Previous wording

HDD is the measure of the variation in the weather based on the extent to which the average daily temperature falls below 65° Fahrenheit. CDD is the measure of the variation in the weather based on the extent to which the average daily temperature rises above 65° Fahrenheit.

Current wording

Degree-day or THI data is used to estimate amounts of energy required to maintain comfortable indoor temperature levels based on each day’s average temperature and humidity. HDD is the measure of the variation in the weather based on the extent to which the average daily temperature falls below 65° Fahrenheit. CDD is the measure of the variation in the weather based on the extent to which the average daily temperature rises above 65° Fahrenheit.

Previous wording

In Xcel Energy’s more humid service territories, a THI is used in place of CDD, which adds a humidity factor to CDD. HDD, CDD and THI are most likely to impact the usage of Xcel Energy’s residential and commercial customers. Industrial customers are less sensitive to weather.

Current wording

Each degree of temperature above 65° Fahrenheit is counted as one CDD, and each degree of temperature below 65° Fahrenheit is counted as one HDD. In Xcel Energy’s more humid service territories, a THI is used in place of CDD, which adds a humidity factor to CDD. HDD, CDD and THI are most likely to impact the usage of Xcel Energy’s residential and commercial customers. Industrial customers are less sensitive to weather.

Previous wording

•NSP-Minnesota — Residential sales declined due to a 1.5% decrease in use per customer, partially offset by a 1.4% increase in customers. The decline in C&I sales was due to lower use per customer, particularly in the manufacturing sector.

Current wording

•NSP-Minnesota — Residential sales increased due to customer growth (1.1%) and use per customer (0.4%). The decrease in C&I sales was due to lower use per customer.

Previous wording

•PSCo — Residential sales increased due to a 1.4% increase in customers, partially offset by a 0.7% decrease in use per customer. The decline in C&I sales was attributable to decreased use per customer, particularly in the wholesale trade and mining.

Current wording

•PSCo — Residential sales increased due to customer growth (1.1%) and use per customer (0.6%). The increase in C&I sales was due to higher use per customer, particularly in the information and energy sectors.

Previous wording

•SPS — Residential sales declined due to a 2.2% decrease in use per customer partially offset by a 0.7% increase in customers. C&I sales increased due to higher use per customer, primarily driven by the energy sector and cryptocurrency mining.

Current wording

•SPS — Residential sales increased due to increased use per customer (3.6%) and customer growth (0.7%). The increase in C&I sales was due to higher use per customer, primarily driven by the energy sector.

Previous wording

Electric revenues are impacted by changing sales, fluctuations in the price of natural gas, coal and uranium, regulatory outcomes, market prices and seasonality. In addition, electric customers receive a credit for PTCs generated (wind, nuclear and solar), which reduce electric revenue and income taxes.

Current wording

Electric revenues are impacted by fluctuations in the price of natural gas, coal and uranium, regulatory outcomes, market prices and seasonality. In addition, electric customers receive a credit for PTCs generated (wind, nuclear and solar), which reduce electric revenue and income taxes.

Previous wording

Electric Fuel and Purchased Power— Expenses incurred for electric fuel and purchased power are impacted by fluctuations in market prices of natural gas, coal and uranium, as well as seasonality. These incurred expenses are generally recovered through various regulatory recovery mechanisms. As a result, changes in these expenses are largely offset in operating revenues and have minimal earnings impact.

Current wording

Electric Fuel and Purchased Power— Expenses incurred for electric fuel and purchased power are impacted by fluctuations in market prices of electricity, natural gas, coal and uranium, as well as seasonality. These incurred expenses are generally recovered through various regulatory recovery mechanisms. As a result, changes in these expenses are largely offset in operating revenues and have minimal earnings impact.

Previous wording

Electric fuel and purchased power expenses decreased $490 million in 2024. The decrease is primarily due to timing of fuel recovery mechanisms and lower commodity prices, partially offset by increased volumes.

Current wording

Natural gas sold and transported increased $90 million in 2025. The increase is primarily due to increased commodity prices and volumes, partially offset by timing of fuel recovery mechanisms.

Previous wording

Depreciation and Amortization—Depreciation and amortization increased $296 million for the year, primarily related to system expansion, partially offset by the impacts of various rate cases, including recognition of previously deferred costs as well as wind and nuclear life extensions.

Current wording

Depreciation and Amortization—Depreciation and amortization increased $209 million for the year, primarily related to system investment.

Previous wording

Other Income— Other income increased $121 million for the year, primarily related to interest earned on significant cash balances throughout the year and a gain on debt repurchases, which helped to offset increased spending in our electric and natural gas operations to reduce risk, including wildfire mitigation.

Current wording

Other Income— Other income increased $92 million for the year, primarily related to gains on debt repurchases.

Previous wording

Interest Charges— Interest charges increased $200 million in 2024. The increase was largely due to higher long-term debt levels to fund capital investments and higher interest rates.

Current wording

Interest Charges— Interest charges increased $213 million in 2025. The increase was largely due to higher long-term and short-term debt levels and higher interest rates.

Previous wording

AFUDC, Equity and Debt—AFUDC increased $99 million in 2024. This increase was largely due to increased investment in renewable and transmission projects.

Current wording

AFUDC, Equity and Debt—AFUDC increased $165 million in 2025, due to system investment.

Previous wording

The FERC and various state and local regulatory commissions regulate Xcel Energy Inc.’s utility subsidiaries and West Gas Interstate. Xcel Energy is subject to rate regulation by state utility regulatory agencies, which have jurisdiction with respect to the rates of electric and natural gas distribution companies in Minnesota, North Dakota, South Dakota, Wisconsin, Michigan, Colorado, New Mexico and Texas.

Current wording

The FERC and various state and local regulatory commissions regulate Xcel Energy Inc.’s utility subsidiaries and WGI. Xcel Energy is subject to rate regulation by state utility regulatory agencies, which have jurisdiction with respect to the rates of electric and natural gas distribution companies in Minnesota, North Dakota, South Dakota, Wisconsin, Michigan, Colorado, New Mexico and Texas.

Previous wording

In January 2025, the Court issued its opinion, which upheld the commission's determination on insurance expense, but reversed and remanded the executive compensation and prepaid pension asset decisions back to the MPUC. The opinion is currently pending further action from the MPUC.

Current wording

In January 2025, the Court issued its opinion, which upheld the commission's determination on insurance expense, but reversed and remanded the executive compensation and prepaid pension asset decisions back to the MPUC. In June 2025, the MPUC ordered proceedings to reconsider the treatment of prepaid pension assets and executive compensation, with a decision expected in 2026.

Previous wording

2024 Minnesota Electric Rate Case — In November 2024, NSP-Minnesota filed an electric rate case in Minnesota, seeking a total revenue increase of $491 million (13.2%) over two years, based on an ROE of 10.3%, a 52.5% equity ratio and rate base of $13.2 billion in 2025 and $14 billion in 2026. NSP-Minnesota also requested interim rates of $224 million for 2025. In December 2024, the MPUC reduced the interim rate request for wildfire mitigation costs (as these costs were deemed as new costs not previously approved in a rate case) and approved interim rates of $192 million, effective January 1, 2025. A decision is expected in 2026.

Current wording

2024 Minnesota Electric Rate Case — In November 2024, NSP-Minnesota filed an electric rate case in Minnesota based on an ROE of 10.3%, a 52.5% equity ratio and rate base of $13.2 billion in 2025 and $14 billion in 2026. In December 2024, the MPUC approved interim rates of $192 million, effective Jan. 1, 2025. In March 2025, NSP-Minnesota filed supplemental direct testimony, updating its total revenue request to $473 million.

Previous wording

2024 North Dakota Electric Rate Case — In December 2024, NSP-Minnesota filed a request with the NDPSC for an annual electric rate increase of approximately $45 million, or 19.3% over current rates established in 2021. The filing is based on a 2025 forecast test year and includes a requested ROE of 10.3%, rate base of approximately $817 million and an equity ratio of 52.5%. In January 2025, the NDPSC approved interim rates, subject to refund, of approximately $27 million (implemented on Feb. 1, 2025).

Current wording

2024 North Dakota Electric Rate Case — In December 2024, NSP-Minnesota filed a request with the NDPSC for an annual electric rate increase of $45 million (19.3% over current rates established in 2021). The filing is based on a 2025 forecast test year and includes a requested ROE of 10.3%, rate base of approximately $817 million and an equity ratio of 52.5%. In January 2025, the NDPSC approved interim rates, subject to refund, of approximately $27 million (implemented on Feb. 1, 2025).

Previous wording

In November 2024, the NDPSC approved a settlement, reflecting a natural gas rate increase of $7.2 million (8.0%), based on a ROE of 9.9% and an equity ratio of 52.5%. Rates were implemented on Jan. 1, 2025.

Current wording

In February 2026, the NDPSC approved a settlement agreement filed by NSP-Minnesota and NDPSC Staff, effective April 1st, 2026, including a base revenue increase of $24 million, based on a ROE of 9.8% and equity ratio of 52.5%.

Previous wording

Nuclear Spent Fuel Storage — NSP-Minnesota has interim on-site storage for spent nuclear fuel at its Monticello and Prairie Island nuclear generating plants. Authorized storage capacity is sufficient to allow NSP-Minnesota to operate until 2040 for Monticello, 2033 for Prairie Island Unit 1, and 2034 for Prairie Island Unit 2.

Current wording

Nuclear Spent Fuel Storage — NSP-Minnesota has interim on-site storage for spent nuclear fuel at its Monticello and Prairie Island nuclear generating plants. Authorized storage capacity is sufficient to allow NSP-Minnesota to operate until 2040 for Monticello, and 2054 for Prairie Island.

Previous wording

In February 2024, NSP-Minnesota filed a CON with the MPUC for additional storage at Prairie Island to support possible life extension to 2054. NSP-Minnesota has notified the NRC of intent to apply for Prairie Island SLR which would extend operation of Unit 1 to 2053 and Unit 2 to 2054.

Current wording

NSP-Minnesota has notified the NRC of intent to apply for Prairie Island Subsequent License Renewal which would extend operation of Unit 1 to 2053 and Unit 2 to 2054.

Previous wording

Excess Liability Insurance Deferral –In February 2025, NSP-Wisconsin filed a request with the PSCW for deferred accounting treatment for excess liability insurance expense of $9.6 million incurred as a result of the October 2024 policy renewal. A PSCW decision is expected in the third quarter of 2025.

Current wording

Excess Liability Insurance Deferral – In February 2025, NSP-Wisconsin filed a request with the PSCW for deferred accounting treatment for excess liability insurance expense of $9.6 million incurred as a result of the October 2024 policy renewal. The PSCW issued a written approval in November 2025 and authorized recovery of the deferral over 2026 and 2027 in the Wisconsin Electric and Natural Gas Rate Case described below.

Previous wording

•In October 2023, NSP-Minnesota issued an RFP seeking 1,200 MW of wind assets to replace capacity and reutilize interconnection rights associated with the retiring Sherco coal facilities. The RFP closed in December 2023. NSP-Minnesota expects to file for approval of recommended projects in summer 2025.

Current wording

•In October 2023, NSP-Minnesota issued an RFP seeking 1,200 MW of wind assets to replace capacity and reutilize interconnection rights associated with the retiring Sherco coal facilities. The RFP closed in December 2023. NSP-Minnesota expects to file for approval of recommended projects in early 2026.

Previous wording

•In 2024, NSP-Minnesota and NSP-Wisconsin each issued an RFP collectively seeking up to 1,600 MW of wind, solar, storage or hybrid resources to interconnect to the NSP System, including reutilization of the interconnection rights associated with the retiring Sherco coal units, and 650 MW of solar and storage resources to specifically reutilize the interconnection rights associated with the retiring King coal unit. Bids are currently under evaluation; NSP-Minnesota and NSP-Wisconsin announced the short listed projects in January 2025 and plan to file for the requisite approvals of the selected resources with the MPUC and PSCW, respectively, in the second half of 2025.

Current wording

•In 2024, NSP-Minnesota and NSP-Wisconsin each issued an RFP collectively seeking up to 1,600 MW of wind, solar, storage or hybrid resources to interconnect to the NSP System, including reutilization of the interconnection rights associated with the retiring Sherco coal units, and 650 MW of solar and storage resources to specifically reutilize the interconnection rights associated with the retiring King coal unit. NSP-Minnesota and NSP-Wisconsin announced the short listed projects in January 2025. NSP-Minnesota filed for requisite approvals of the selected resources with the MPUC in the fourth quarter of 2025 (decision expected in early 2026); NSP-Wisconsin expects to file for approvals with the PSCW in 2026.

Previous wording

Colorado Natural Gas Rate Case —In January 2024, PSCo, filed a request with the CPUC seeking an increase to retail natural gas rates of $171 million (9.5%). The request was based on a 10.25% ROE, an equity ratio of 55%, a 2023 test year and a $4.2 billion year-end rate base.

Current wording

2025 Colorado Natural Gas Rate Case —In December 2025, PSCo filed a natural gas rate case with the CPUC seeking an increase in revenue of $190 million (11.6%). The request is based on a 10.75% ROE, an equity ratio of 55% and a 2025 test year with a projected rate base of $4.7 billion.

Previous wording

PSCo placed new rates into effect in November, as modified on ARRR in February 2025, with an annual revenue increase of approximately $125 million, inclusive of $15 million of accelerated depreciation. The UCA filed a second ARRR in February 2025, which remains pending.

Current wording

2024 Colorado Natural Gas Rate Case —In January 2024, PSCo filed a natural gas rate case with the CPUC. In October 2024, as modified on ARRR in January 2025, the CPUC issued an order including an annual revenue increase of approximately $125 million, inclusive of $15 million of accelerated depreciation.

Previous wording

•Modifications to recoverability of certain operating expenses.

Current wording

In May 2025, PSCo filed an appeal with the Denver District Court seeking review of the CPUC’s decisions related to recovery of certain operating expenses, cost of capital and capital structure, and the treatment of gas storage inventory costs. Briefing was completed in the fourth quarter of 2025. In the first quarter of 2026, the Denver District Court affirmed the CPUC’s decision on all counts appealed by PSCo.

Previous wording

•The plan also presents a low sales forecast with a 3% compound annual sales growth through 2031.

Current wording

2024 Colorado Electric Resource Plan — In October 2024, PSCo filed its Phase I electric resource plan with the CPUC. In November 2025, the CPUC approved a load forecast that reflects a 3% compound annual sales growth through 2031 and generation capacity need of approximately 5,400 MW.

Previous wording

The legislation also calls for the CPUC to adopt rules to establish fuel cost mechanisms to align the financial incentives of a utility with the interests of the utility’s customers.

Current wording

Colorado Senate Bill 23-291 — In May 2023, Colorado Senate Bill 23-291 was signed into law. The legislation included a number of topics including for the CPUC to adopt rules to establish fuel cost mechanisms to align the financial incentives of a utility with the interests of the utility’s customers.

Previous wording

In December 2024, the CPUC adopted final rules applicable to PSCo’s natural gas utility that would assign to the Company four percent of the change in the price per MMbtu of natural gas compared to the three-year average, subject to rolling 12-month cap based on a percentage of rate base, currently estimated at $7 million. The rules require PSCo to make a filing to implement the mechanism within sixty days of becoming effective, expected later in 2025.

Current wording

In December 2024, the CPUC adopted final rules applicable to PSCo’s natural gas utility that would assign to the Company four percent of the change in the price per MMbtu of natural gas compared to the three-year average, subject to rolling 12-month cap based on a percentage of rate base, currently estimated at $7 million. PSCo made a filing in June 2025 to implement the mechanism and filed an unopposed settlement agreement in November 2025. In December 2025, a CPUC ALJ approved the settlement agreement, and PSCo implemented the gas fuel cost mechanism in January 2026.

Previous wording

In December 2024, the CPUC also adopted rules for electric utilities but did not adopt a specific PIM framework, which will be further considered through additional proceedings in 2025.

Current wording

In December 2024, the CPUC also adopted rules for electric utilities but did not adopt a specific PIM framework. PSCo made a filing in November 2025 to the CPUC to implement an electric fuel cost mechanism based on a current market-based index rather than a historical index as required for PSCo’s natural gas utility, subject to a cap currently estimated at $3 million. PSCo expects to implement the electric fuel cost mechanism in the second quarter of 2026.

Previous wording

New Mexico Resource Plan (IRP)— In October 2023, SPS filed its IRP with the NMPRC, which supports projected load growth and increasing reliability requirements, and secures replacement energy and capacity for retiring resources. SPS’ projected resource needs ranging from approximately 5,300 MW to 10,200 MW by 2030. In February 2024, the NMPRC accepted the IRP.

Current wording

SPS Resource Plan (IRP)— In October 2023, SPS filed its IRP with the NMPRC, which supports projected load growth and increasing reliability requirements, and secures replacement energy and capacity for retiring resources.

Current wording

Excess Liability Insurance Deferral– In March 2025, SPS filed a request with the PUCT and in April 2025, SPS filed a request with the NMPRC for deferred accounting treatment for incremental excess liability insurance expense incurred as a result of the October 2024 policy renewal, estimated at approximately $30 million across the two jurisdictions. In October 2025, the NMPRC approved the request, resulting in a deferral of approximately $15 million of incremental excess liability insurance costs in 2025. In January 2026, SPS, PUCT Staff and other intervenors filed a black box settlement expected to result in annual deferrals of approximately $8 million in 2026 and 2027. A PUCT decision is expected in the first half of 2026.

Previous wording

Texas System Resiliency Plan— In December 2024, SPS filed its Texas SRP with the PUCT. Consistent with PUCT requirements, SPS’ proposed plan discusses resiliency-related risks and the five measures that have been designed to help SPS prevent, withstand, mitigate or more promptly recover from resiliency events, including wildfire.

Current wording

Texas System Resiliency Plan— In December 2024, SPS filed its Texas SRP with the PUCT. Consistent with PUCT requirements, SPS’ proposed plan discusses resiliency-related risks and the five measures that have been designed to help SPS prevent, withstand, mitigate or more promptly recover from resiliency events, including wildfire. The proposed SRP covers 2025-2028 and includes a proposed $538 million of investment.

Showing the first 40 of 77 pairs. Open the source sections for the rest.

Rearranged current paragraphs (3)

Current report — wording carried from elsewhere

As a result, weather deviations from normal levels can affect Xcel Energy’s financial performance. Gas decoupling mechanisms (and electric sales true-up in 2024) in Minnesota predominately mitigate the positive and adverse impacts of weather in that jurisdiction.

Current report — wording carried from elsewhere

Tariffs, Trade Complaints and Federal Actions

Current report — wording carried from elsewhere

In October 2024, Xcel Energy renewed its excess liability coverage and now has $450 million of total coverage; including $450 million of wildfire coverage for the NSP System and $300 million of wildfire coverage for PSCo and SPS. The annual premium for this excess liability insurance is approximately $130 million. In October 2025, Xcel Energy renewed its excess liability coverage for the same level with an annual premium of approximately $135 million. Xcel Energy has received approval to defer incremental costs in Colorado, Wisconsin and New Mexico and is awaiting approval of a settlement agreement allowing deferral of certain costs in Texas.
Rearranged previous paragraphs (3)

Previous report — wording carried elsewhere

Degree-day or THI data is used to estimate amounts of energy required to maintain comfortable indoor temperature levels based on each day’s average temperature and humidity.

Previous report — wording carried elsewhere

Each degree of temperature above 65° Fahrenheit is counted as one CDD, and each degree of temperature below 65° Fahrenheit is counted as one HDD.

Previous report — wording carried elsewhere

In October 2024, as modified on ARRR in January 2025, the CPUC issued an order including the following key decisions: