CONNECTICUT LIGHT & POWER CO
For the period ended Sep 30, 2024. Filed Nov 6, 2024.
View on SEC.govAbout this filing
A company's report for each of its first three quarters. The financial statements are not audited. It shows how the business has moved since the last annual report, and what management says changed.
Sep 30, 2024 · Filed Nov 6, 2024
What changed in Management’s Discussion and Analysis?
Read the current filingPrevious report: 10-Q
Period ended 2024-06-30; filed 2024-08-02.
0000072741-24-000018
ITEM 2. Management's Discussion and Analysis of Financial Condition and Results of OperationsCurrent report: 10-Q
Period ended 2024-09-30; filed 2024-11-06.
0000072741-24-000023
ITEM 2. Management's Discussion and Analysis of Financial Condition and Results of OperationsThe baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.
Compared 165 previous paragraphs and 168 current paragraphs.
82 unchanged; 65 reworded; 15 added; 16 removed; 2 previous and 6 current paragraphs rearranged.
Tables are not compared: 12 previous and 12 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.
A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.
Added paragraphs (15)
Current report
•the ability to qualify for investment tax credits and investment tax credit adders,
Current report
•variability in the costs and final investment returns of the Revolution Wind and South Fork Wind offshore wind projects as it relates to the purchase price post-closing adjustment under the terms of the sale agreement for these projects,
Current report
•We had a loss of $118.1 million, or $0.33 per share, in the third quarter of 2024, compared with earnings of $339.7 million, or $0.97 per share, in the third quarter of 2023. We earned $739.1 million, or $2.08 per share, in the first nine months of 2024, compared with $846.2 million, or $2.42 per share, in the first nine months of 2023.
Current report
•In the third quarter of 2024, we received preliminary indicative bids for our Aquarion water distribution business, and we are supporting due diligence with potential buyers.
Current report
•On July 9, 2024, Eversource completed the sale of its 50 percent ownership share of Sunrise Wind to Ørsted for adjusted proceeds of $152 million. Ørsted paid Eversource $118 million at the closing of the sale transaction, and the remaining proceeds of $34 million will be paid after onshore construction is completed and certain other construction milestones are achieved. On September 30, 2024, Eversource completed the sale of its 50 percent ownership share in the South Fork Wind and Revolution Wind projects to GIP for adjusted gross proceeds of $745 million, which were received at closing. Adjusted gross proceeds from the sale were reduced by approximately $375 million as compared with the previously estimated purchase price. Proceeds from the transactions were used to pay off parent company debt. Upon the completion of both sale transactions, Eversource recognized an aggregate after-tax loss on the sale of its offshore wind investments of $524 million in the third quarter of 2024. Eversource recorded a liability of $365 million reflecting its best estimate of the future obligations under the GIP sale terms, which primarily include the expected cost overrun sharing obligation, expected obligation to maintain GIP’s internal rate of return for the Revolution Wind project, and obligation of other future costs. Eversource will not have any ongoing financial obligations associated with Sunrise Wind.
Current report
•On August 29, 2024, the DPU approved NSTAR Electric’s ESMP for a five-year period commencing July 1, 2025. For the five-year period from 2025 through 2029, the incremental capital investment is $608 million and the incremental expense amount is $211 million.
Current report
Our natural gas distribution segment losses decreased $3.5 million in the third quarter of 2024, as compared to the third quarter of 2023, due primarily to higher revenues from capital tracking mechanisms due to continued investments in natural gas infrastructure, the absence of a prior year unfavorable regulatory adjustment resulting from NSTAR Gas’ GSEP reconciliation filing, and a lower effective tax rate. Those improvements were partially offset by higher property tax expense, higher depreciation expense, higher operations and maintenance expense, and higher interest expense.
Current report
Excluding these charges, Eversource parent and other companies non-GAAP earnings increased by $10.8 million in the third quarter period due primarily to a lower effective tax rate, partially offset by higher interest expense. Eversource parent and other companies non-GAAP earnings decreased $51.1 million in the first nine months period due primarily to higher interest expense and the absence of a benefit in 2023 from the liquidation of Eversource parent’s equity method investment in a renewable energy fund, partially offset by the absence of a charitable contribution made in 2023 with a portion of the proceeds from the liquidation, and a lower effective tax rate.
Current report
Offshore Wind Business: Eversource’s offshore wind business included 50 percent ownership interests in each of North East Offshore and South Fork Class B Member, LLC. In the third quarter of 2024, Eversource sold its interest in these entities, and in doing so, sold its interests in the Revolution Wind project, the South Fork Wind project, and the Sunrise Wind project. Eversource’s offshore wind business continues to hold a noncontrolling tax equity investment in South Fork Wind through a 100 percent ownership in South Fork Wind Holdings, LLC Class A interests.
Current report
On February 13, 2024, Eversource executed an agreement to sell its 50 percent interests in the South Fork Wind and Revolution Wind projects to Global Infrastructure Partners (GIP) for an initial gross purchase price of approximately $1.1 billion. The initial purchase price was subject to adjustments based on, among other things, the progress, timing and the construction cost of Revolution Wind, including changes in actual versus forecasted capital spending between signing the agreement and closing of the transaction. On September 30, 2024, Eversource completed the sale of its 50 percent ownership share in the South Fork Wind and Revolution Wind projects to GIP for adjusted gross proceeds of $745 million, which were received at closing. Adjusted gross proceeds from the sale were reduced by approximately $375 million as compared with the previously estimated purchase price. This reduction reflects approximately $150 million resulting from lower capital spending between announcing the transaction and closing, and approximately $225 million related to the final terms of the sale transaction, primarily due to the delay of the commercial operations date of Revolution Wind. Proceeds from the transaction were used to pay off parent company debt.
Current report
Upon the completion of both sale transactions, the total proceeds were compared to the carrying value of the investments, including an estimate of liability for post-closing adjustment payments to GIP, and Eversource recognized an aggregate after-tax loss on the sale of its offshore wind investments of $524 million in the third quarter of 2024. The aggregate after-tax loss is comprised of (1) the lower proceeds related to final terms of the sale transaction to GIP of approximately $225 million related to non-construction costs for the Revolution Wind and South Fork Wind projects, primarily due to a purchase price reduction of $150 million resulting from the delay of the commercial operations date of Revolution Wind, (2) recently identified forecasted construction costs as a result of a delay in the anticipated commercial operation date related to Revolution Wind of approximately $350 million, which includes an estimate for the anticipated post-closing adjustment to GIP related to Eversource’s expected cost overrun sharing obligation, and (3) approximately $326 million, which includes an estimate for the anticipated post-closing adjustment related to Eversource’s expected obligations to GIP as a result of final economics of the Revolution Wind and South Fork Wind projects and other future costs as well as a net $60 million increase in income tax expense including an increase in the valuation allowance for unused capital losses. These losses were partially offset by the $377 million gain on the sale of Sunrise Wind.
Current report
Upon sale, Eversource recorded a liability of $365 million reflecting its best estimate of the future obligations under the GIP sale terms, which primarily include the expected cost overrun sharing obligation, expected obligation to maintain GIP’s internal rate of return for the Revolution Wind project, and obligation of other future costs. The majority of this liability is expected to be settled in 2026. The long-term portion of the liability of $350 million was recorded in Other Long-Term Liabilities, and the remainder was recorded in Other Current Liabilities on Eversource’s balance sheet as of September 30, 2024.
Current report
On October 17, 2024, FERC issued an order on the remand of the MISO ROE proceedings. The order addressed the Court’s decision that the reintroduction of the risk-premium financial model in the ROE methodology was arbitrary and capricious by removing the risk-premium financial model from the ROE methodology. The removal of the risk-premium financial model was the only revision to FERC’s ROE methodology and resulted in a two-model approach utilizing the two-step discounted cash flow model and the capital asset pricing model. MISO was directed to provide refunds for the period November 12, 2013 to February 11, 2015 (the first MISO ROE complaint refund period) and for the period from September 28, 2016 (the date of FERC’s order on the first MISO ROE complaint) to October 17, 2024 by December 1, 2025. The order also stated that FERC does not preclude the use of the risk-premium financial model in future proceedings if the parties can demonstrate that FERC’s stated concerns around the inclusion of the model have been addressed.
Current report
CL&P Advanced Metering Infrastructure Filing: On July 31, 2020, CL&P submitted to PURA its proposed $512 million Advanced Metering Infrastructure (AMI) investment and implementation plan. On November 8, 2021, CL&P submitted an Amended Proposal in response to PURA’s request with an updated schedule for the years 2022 through 2028, which included additional information as required by PURA. As required, the plan includes a full deployment of advanced metering functionality and a composite business case in support of the Advanced Metering Infrastructure plan. On January 3, 2024, PURA issued a final decision regarding CL&P’s Advanced Metering Infrastructure investment and implementation plan, which CL&P had most recently estimated at $766.4 million for capital costs and operating expenses. In CL&P’s view, the final decision does not provide a reasonable path for cost recovery and delays implementation by at least a year during the pendency of the cost recovery proceeding. In addition, in CL&P’s view, the final decision modifies the prudence standard for recovery of costs expended on the project, improperly linking recovery to outcomes not known at the outset of the project. On January 18, 2024, CL&P submitted a motion for reconsideration to PURA asking that the agency modify these aspects of the decision, which PURA subsequently denied on February 14, 2024. On March 6, 2024, CL&P filed written comments citing four major problems associated with PURA’s guidelines for recovery of the costs of AMI implementation, which if not addressed, represent obstacles to AMI implementation in Connecticut. On April 16, 2024, PURA issued a procedural order directing Eversource and inviting all parties and intervenors to submit pre-filed testimony pertaining to AMI by May 14, 2024, and rebuttal testimony by May 29, 2024. CL&P witnesses pre-filed testimony, including an updated estimate of $855 million for capital costs and operating expenses, and then subsequently participated in the AMI cost recovery hearing on June 6, 2024. On October 17, 2024, PURA issued a proposed final decision on recovery of the costs for AMI implementation. Written exceptions to the proposed final decision were filed on October 31, 2024, and oral arguments are scheduled for November 7, 2024. CL&P’s written exceptions focused on three main aspects of the proposed decision, which include (1) clarifying the prudence standard to be used in evaluating AMI investments, (2) timing of prudency reviews, and (3) cost recovery related to incremental O&M expenses. A final decision is currently expected on November 20, 2024.
Current report
NSTAR Electric’s Electric Sector Modernization Plan (ESMP) Filing: On January 29, 2024, in accordance with Massachusetts state law, NSTAR Electric filed its ESMP with the DPU. The law required each electric distribution company to develop and file a comprehensive distribution system plan to proactively upgrade the distribution system (and, where applicable, the associated transmission system) to: (i) improve grid reliability, communications and resiliency; (ii) enable increased, timely adoption of renewable energy and distributed energy resources; (iii) promote energy storage and electrification technologies necessary to decarbonize the environment and economy; (iv) prepare for future climate-driven impacts on the transmission and distribution systems; (v) accommodate increased transportation electrification, increased building electrification and other potential future demands on distribution and, where applicable, the transmission system; and (vi) minimize or mitigate impacts on Massachusetts ratepayers, thereby helping the state realize its statewide greenhouse gas emissions limits and sublimits under the law. NSTAR Electric’s plan meets these requirements by providing a comprehensive view of all the investments required to build a safer, more reliable, more resilient electric distribution system to enable an affordable, equitable clean energy transition taking into account the needs of environmental justice communities. For the five-year period from 2025 through 2029, the proposed incremental capital investment is $608 million and the incremental expense amount is $211 million. On August 29, 2024, the DPU approved the overall ESMP for a five-year period commencing July 1, 2025. The DPU has indicated that it will open a second phase of the proceeding to consider a short-term ESMP-focused cost-recovery mechanism for completion prior to the start of the plan in July 2025.
Removed paragraphs (16)
Previous report
•our ability to complete the sale of our offshore wind investments in the South Fork Wind and Revolution Wind projects on the timeline, terms and pricing we expect; if we and the counterparty are unable to satisfy all closing conditions and consummate the purchase and sale transaction with respect to these offshore wind assets; if we are unable to qualify for investment tax credits related to these projects; if we experience variability in the projected construction costs of these offshore wind projects, if there is a deterioration of market conditions in the offshore wind industry; andif the projects do not commence operation as scheduled or within budget or are not completed,
Previous report
•On February 13, 2024, we initiated an exploratory assessment of a potential sale of our water distribution business.
Previous report
Our water distribution segment earnings decreased $1.3 million in the second quarter of 2024, as compared to the second quarter of 2023, due primarily to higher operations and maintenance expense, higher interest expense, and higher depreciation expense.
Previous report
As a result of the Yankee Gas long-term debt issuances in July 2024, $100.0 million of current portion of long-term debt was reclassified to Long-Term Debt on Eversource parent’s balance sheet as of June 30, 2024.
Previous report
Credit Ratings: On June 18, 2024, Moody’s revised the outlook from stable to negative for CL&P.
Previous report
Offshore Wind Business: As of June 30, 2024, Eversource’s offshore wind business includes 50 percent ownership interests in wind partnerships, which collectively hold the Revolution Wind, South Fork Wind and Sunrise Wind projects, and a tax equity investment in South Fork Wind. The offshore wind projects are being developed and constructed through joint and equal partnerships with Ørsted.
Previous report
As of June 30, 2024 and December 31, 2023, Eversource's total equity investment balance in its offshore wind business was $806.1 million and $515.5 million, respectively.
Previous report
Sales of Offshore Wind Investments: On January 24, 2024, Ørsted signed an agreement with Eversource to acquire Eversource’s 50 percent share of Sunrise Wind, subject to the successful selection of Sunrise Wind in the New York fourth solicitation for offshore wind capacity, signing of an OREC contract with NYSERDA, finalization of agreements including the equity and asset purchase agreement, receipt of the final approval by BOEM of the Sunrise Wind Construction and Operations Plan (COP), and relevant regulatory approvals. On February 29, 2024, Sunrise Wind was selected for contract negotiation in the offshore wind solicitation by NYSERDA, and was subsequently awarded a contract, which was finalized and completed on May 31, 2024. In June 2024, Sunrise Wind received final approval by BOEM of its COP and all remaining regulatory approvals.
Previous report
Closing the transaction with GIP is subject to customary conditions, including certain regulatory approvals, as well as other conditions, among which is the completion and execution of the partnership agreements between GIP and Ørsted that will govern GIP’s new ownership interest in those projects following Eversource’s divestiture. All regulatory approvals have been received and the review period under the Hart Scott Rodino Act has expired. Closing of this transaction is currently expected to occur in the third quarter of 2024.
Previous report
Under the agreement with GIP, Eversource’s existing credit support obligations are expected to roll off for each project around the time that each project completes its expected capital spend. Eversource will continue to make future cash expenditures for required cash contributions up to the time of disposition of the Revolution Wind and South Fork Wind projects and changes in the timing and amounts of these contributions would be adjusted in the purchase price.
Previous report
Upon close of the sale transactions in the third quarter of 2024, the total proceeds will be compared to the current carrying value of the investments, and the difference will be reflected in the statement of income. At that time, Eversource will also record an estimate of future obligations under the terms of the GIP transaction, which primarily could include the potential cost overrun sharing obligation and potential obligation to maintain GIP’s internal rate of return for the Revolution Wind project. Eversource is currently evaluating the combined impact of the Sunrise Wind sale and the expected sale of Revolution Wind and South Fork Wind, and at this time, does not expect a material financial impact on our 2024 results. Proceeds from the transactions will be used to pay off parent company debt.
Previous report
Impairment: Equity method investments are assessed for impairment when conditions exist as of the balance sheet date that indicate that the fair value of the investment may be less than book value. Eversource continually monitors and evaluates its equity method investments to determine if there are indicators of an other-than-temporary impairment. If the decline in value is considered to be other-than-temporary, the investment is written down to its estimated fair value, which establishes a new cost basis in the investment. Subsequent declines or recoveries after the reporting date are not considered in the impairment recognized. Investments that are other-than-temporarily impaired and written down to their estimated fair value cannot subsequently be written back up for increases in estimated fair value. Impairment evaluations involve a significant degree of judgment and estimation, including identifying circumstances that indicate an impairment may exist at the equity method investment level, selecting discount rates used to determine fair values, and developing an estimate of discounted future cash flows expected from investment operations or the sale of the investment. In the second quarter of 2024, there were no indicators of an other-than-temporary impairment in Eversource’s equity method investment balance.
Previous report
Permitting and Construction of Offshore Wind Projects: The offshore wind projects require receipt of federal, state and local approvals necessary to construct and operate the projects. The federal permitting process is led by BOEM, and state approvals are required from New York, Rhode Island and Massachusetts. South Fork Wind, Revolution Wind and Sunrise Wind have each received final federal approval from BOEM. All state and local approvals have been received for South Fork and Revolution Wind. For Sunrise Wind, all state and local approvals required to start construction have been received.
Previous report
Installation of South Fork Wind’s twelve 11-megawatt wind turbines was completed in February 2024 and the project is in-service. For Revolution Wind, major construction began in the fourth quarter of 2023 and onshore and offshore construction is underway. For Sunrise Wind, onshore construction is in progress.
Previous report
NSTAR Electric CIP Filing: On December 30, 2022, the DPU approved a provisional system planning tariff for the recovery of costs associated with a capital investment project (CIP) proposal submitted by NSTAR Electric for one of six geographic study areas in its service territory in accordance with DPU’s directives. The DPU established a new, provisional framework for planning and funding upgrades to the electric power system to foster development and interconnection of distributed energy facilities. Under the DPU program, NSTAR Electric has filed infrastructure upgrade proposals to be built within a four-year construction timeframe that allocate the costs of interconnection upgrades between the interconnecting distributed generation facility and distribution customers based on a technical analysis of capacity benefits. Payments made by the distributed generation facility will be applied against the total capital investment made by NSTAR Electric and NSTAR Electric will earn a return on the net investment. The amount allocated to distribution customers will be recovered through a reconciling mechanism, the Provisional System Planning Tariff. The DPU approved the first of these provisional system planning projects, the Marion-Fairhaven group study area, which will enable 141 MW of distributed energy resources (DER) to be interconnected at a total estimated cost of $120 million. Of the total $120 million, $66 million will be allocated to distribution customers, once the enabled distributed energy facilities capacity is fully subscribed by distributed energy facilities interconnecting customers. Additionally, NSTAR Electric will proceed with construction of approximately $54 million of transmission upgrades necessary to improve local reliability and integrate distribution energy resources in the Marion-Fairhaven area and recover the amount through local transmission rates.
Previous report
On June 4, 2024, the DPU approved four of the remaining five CIPs that were originally submitted by NSTAR Electric. These included the Plainfield-Blandford CIP, which will enable 40 MW of DER to be interconnected at a total estimated distribution investment of $37 million, the Dartmouth-Westport CIP which enables 60 MW of DER for a total distribution investment of $58 million, the Plymouth CIP which enables 380 MW of DER for a total distribution investment of $152 million and the Cape Cod CIP which enables 296 MW of DER for a total distribution investment of $170 million. Of the total $417 million for these four recently approved CIPs, $183 million will be allocated to distribution customers, once the enabled distributed energy facilities capacity is fully subscribed by distributed energy facilities interconnecting customers. Additionally, NSTAR Electric will proceed with construction of approximately $64 million of transmission upgrades necessary to improve local reliability and integrate distribution energy resources in the four CIP areas and recover the amount through local transmission rates. The sixth and final originally filed CIP, Freetown, is still pending approval with the DPU.
Reworded paragraphs (65)
Previous wording
The following discussion and analysis should be read in conjunction with our unaudited condensed consolidated financial statements and related combined notes included in this combined Quarterly Report on Form 10-Q, the combined Quarterly Report on Form 10-Q for the quarter ended March 31, 2024, as well as the Eversource 2023 combined Annual Report on Form 10-K. References in this combined Quarterly Report on Form 10-Q to "Eversource," the "Company," "we," "us," and "our" refer to Eversource Energy and its consolidated subsidiaries. All per-share amounts are reported on a diluted basis. The unaudited condensed consolidated financial statements of Eversource, NSTAR Electric and PSNH and the unaudited condensed financial statements of CL&P are herein collectively referred to as the "financial statements."
Current wording
The following discussion and analysis should be read in conjunction with our unaudited condensed consolidated financial statements and related combined notes included in this combined Quarterly Report on Form 10-Q, the combined Quarterly Reports on Form 10-Q for the quarters ended March 31, 2024 and June 30, 2024, as well as the Eversource 2023 combined Annual Report on Form 10-K. References in this combined Quarterly Report on Form 10-Q to "Eversource," the "Company," "we," "us," and "our" refer to Eversource Energy and its consolidated subsidiaries. All per-share amounts are reported on a diluted basis. The unaudited condensed consolidated financial statements of Eversource, NSTAR Electric and PSNH and the unaudited condensed financial statements of CL&P are herein collectively referred to as the "financial statements."
Previous wording
The only common equity securities that are publicly traded are common shares of Eversource. Our earnings discussion includes financial measures that are not recognized under GAAP (non-GAAP) referencing our earnings and EPS excluding the impairment charge for the offshore wind investments, a loss on the disposition of land that was initially acquired to construct the Northern Pass Transmission project and was subsequently abandoned, and certain transaction and transition costs. EPS by business is also a non-GAAP financial measure and is calculated by dividing the Net Income Attributable to Common Shareholders of each business by the weighted average diluted Eversource common shares outstanding for the period. The earnings and EPS of each business do not represent a direct legal interest in the assets and liabilities of such business, but rather represent a direct interest in our assets and liabilities as a whole.
Current wording
The only common equity securities that are publicly traded are common shares of Eversource. Our earnings discussion includes financial measures that are not recognized under GAAP (non-GAAP) referencing our earnings and EPS excluding the losses on the offshore wind investments, a loss on the disposition of land that was initially acquired to construct the Northern Pass Transmission project and was subsequently abandoned, and certain transaction and transition costs. EPS by business is also a non-GAAP financial measure and is calculated by dividing the Net Income Attributable to Common Shareholders of each business by the weighted average diluted Eversource common shares outstanding for the period. The earnings and EPS of each business do not represent a direct legal interest in the assets and liabilities of such business, but rather represent a direct interest in our assets and liabilities as a whole.
Previous wording
We use these non-GAAP financial measures to evaluate and provide details of earnings results by business and to more fully compare and explain our results without including these items. This information is among the primary indicators we use as a basis for evaluating performance and planning and forecasting of future periods. We believe the impacts of the impairment charge for the offshore wind investments, the loss on the disposition of land associated with an abandoned project, and transaction and transition costs are not indicative of our ongoing costs and performance. We view these charges as not directly related to the ongoing operations of the business and therefore not an indicator of baseline operating performance. Due to the nature and significance of the effect of these items on Net Income Attributable to Common Shareholders and EPS, we believe that the non-GAAP presentation is a more meaningful representation of our financial performance and provides additional and useful information to readers of this report in analyzing historical and future performance of our business. These non-GAAP financial measures should not be considered as alternatives to reported Net Income Attributable to Common Shareholders or EPS determined in accordance with GAAP as indicators of operating performance.
Current wording
We use these non-GAAP financial measures to evaluate and provide details of earnings results by business and to more fully compare and explain our results without including these items. This information is among the primary indicators we use as a basis for evaluating performance and planning and forecasting of future periods. We believe the impacts of the losses on the offshore wind investments, the loss on the disposition of land associated with an abandoned project, and transaction and transition costs are not indicative of our ongoing costs and performance. We view these charges as not directly related to the ongoing operations of the business and therefore not an indicator of baseline operating performance. Due to the nature and significance of the effect of these items on Net Income Attributable to Common Shareholders and EPS, we believe that the non-GAAP presentation is a more meaningful representation of our financial performance and provides additional and useful information to readers of this report in analyzing historical and future performance of our business. These non-GAAP financial measures should not be considered as alternatives to reported Net Income Attributable to Common Shareholders or EPS determined in accordance with GAAP as indicators of operating performance.
Previous wording
•We earned $335.3 million, or $0.95 per share, in the second quarter of 2024, compared with $15.4 million, or $0.04 per share, in the second quarter of 2023. We earned $857.2 million, or $2.43 per share, in the first half of 2024, compared with $506.6 million, or $1.45 per share, in the first half of 2023. Our results for the second quarter and first half of 2023 include an after-tax impairment charge of $331.0 million, or $0.95 per share, recorded within Eversource Parent and Other Companies to reflect our estimate of the fair value of the offshore wind projects. Our 2023 results also include after-tax land abandonment and other charges recorded within Eversource Parent and Other Companies of $6.2 million, or $0.01 per share, in the second quarter of 2023 and $6.7 million, or $0.01 per share, in the first half of 2023. Excluding the offshore wind impairment and these other charges, our 2023 non-GAAP earnings were $352.6 million, or $1.00 per share, in the second quarter of 2023 and $844.3 million, or $2.41 per share, in the first half of 2023.
Current wording
•Our 2024 results include an after-tax loss on the sale of our offshore wind investments of $524.0 million, or $1.48 per share on a year-to-date basis. Our results for the first nine months of 2023 include an after-tax impairment charge on our offshore wind investments of $331.0 million, or $0.95 per share. Our results for the first nine months of 2023 also include after-tax land abandonment and other charges recorded of $6.9 million, or $0.01 per share. These 2024 and 2023 charges were recorded within Eversource Parent and Other Companies. Excluding these charges, our 2024 non-GAAP earnings were $405.9 million, or $1.13 per share, in the third quarter of 2024 and $1.26 billion, or $3.56 per share, in the first nine months of 2024, and our 2023 non-GAAP earnings were $1.18 billion, or $3.38 per share, in the first nine months of 2023.
Previous wording
•We reaffirmed our projection to earn within a 2024 non-GAAP earnings guidance range of between $4.50 per share and $4.67 per share, which excludes the impact of the sales of our 50 percent interests in the three jointly-owned offshore wind projects and related transaction costs. We also reaffirmed our projection of our long-term EPS growth rate through 2028 within a 5 to 7 percent range.
Current wording
•We updated our projection to earn within a 2024 non-GAAP earnings guidance range of between $4.52 per share and $4.60 per share, which excludes the impact of the sales of our 50 percent interests in the three jointly-owned offshore wind projects and related transaction costs. We also reaffirmed our projection of our long-term EPS growth rate through 2028 within a 5 to 7 percent range, and increased our previously forecasted capital investments of $23.1 billion to $23.7 billion for the period 2024 to 2028, as a result of the recently approved Electric Sector Modernization Plan (ESMP) in Massachusetts.
Previous wording
•Cash flows provided by operating activities totaled $962.0 million in the first half of 2024, compared with $647.3 million in the first half of 2023. Investments in property, plant and equipment totaled $2.22 billion in the first half of 2024, compared with $2.04 billion in the first half of 2023.
Current wording
•Cash flows provided by operating activities totaled $1.52 billion in the first nine months of 2024, compared with $1.17 billion in the first nine months of 2023. Investments in property, plant and equipment totaled $3.29 billion in the first nine months of 2024, compared with $3.13 billion in the first nine months of 2023.
Previous wording
•Cash totaled $33.4 million as of June 30, 2024, compared with $53.9 million as of December 31, 2023. Our available borrowing capacity under our commercial paper programs totaled $1.21 billion as of June 30, 2024.
Current wording
•Cash and Cash Equivalents totaled $97.9 million as of September 30, 2024, compared with $53.9 million as of December 31, 2023. Our available borrowing capacity under our commercial paper programs totaled $1.79 billion as of September 30, 2024.
Previous wording
•In the first half of 2024, we issued $3.85 billion of new long-term debt and we repaid $900 million of long-term debt.
Current wording
•In the first nine months of 2024, we issued $4.40 billion of new long-term debt and we repaid $1.26 billion of long-term debt.
Previous wording
Consolidated: Below is a summary of our earnings by business, which also reconciles the non-GAAP financial measures of consolidated non-GAAP earnings and EPS, as well as EPS by business, to the most directly comparable GAAP measures of consolidated Net Income Attributable to Common Shareholders and diluted EPS.
Current wording
Consolidated: Below is a summary of our earnings/(loss) by business, which also reconciles the non-GAAP financial measures of consolidated non-GAAP earnings and EPS, as well as EPS by business, to the most directly comparable GAAP measures of consolidated Net (Loss)/Income Attributable to Common Shareholders and diluted EPS.
Previous wording
(1)In the second quarter of 2023, we recorded an impairment charge resulting from the expected sales of our offshore wind investments and to reflect the estimate of the fair value of the offshore wind projects at that time. For further information, see "Business Development and Capital Expenditures – Offshore Wind Business" included in this Management's Discussion and Analysis of Financial Condition and Results of Operations.
Current wording
(1)In the third quarter of 2024, we recorded a loss on the sales of our offshore wind investments. In the second quarter of 2023, we recorded an impairment charge resulting from the expected sales of these offshore wind investments. For further information, see "Business Development and Capital Expenditures – Offshore Wind Business" included in this Management's Discussion and Analysis of Financial Condition and Results of Operations.
Previous wording
(2)The 2023 charges primarily include a loss on the disposition of land. The land was initially acquired to construct the Northern Pass Transmission project and was subsequently abandoned.
Current wording
(2)The 2023 charges primarily include a loss on the disposition of previously abandoned land intended to be used for the cancelled Northern Pass Transmission project.
Previous wording
Our electric distribution segment earnings decreased $15.8 million and $13.1 million in the second quarter and the first half of 2024, respectively, as compared to the second quarter and the first half of 2023, due primarily to higher operations and maintenance expense driven by higher storm restoration costs, the absence of a prior year benefit at PSNH related to the establishment of a new regulatory tracking mechanism that allowed for the recovery of previously incurred operating expenses associated with poles acquired on May 1, 2023, higher interest expense, higher depreciation expense, and higher property tax expense. Those earnings decreases were partially offset by higher revenues from a base distribution rate increase at NSTAR Electric effective January 1, 2024 and from CL&P's capital tracking mechanism due to increased electric system improvements, and an increase in interest income primarily on regulatory deferrals.
Current wording
Our electric distribution segment earnings increased $17.0 million in the first nine months of 2024, as compared to the first nine months of 2023, due primarily to higher revenues from base distribution rate increases at NSTAR Electric effective January 1, 2024 and at PSNH effective August 1, 2024 and from CL&P's capital tracking mechanism due to increased electric system improvements, and an increase in interest income primarily on regulatory deferrals. Those earnings increases were partially offset by higher interest expense, higher operations and maintenance expense, higher depreciation expense, the absence of a prior year benefit at PSNH related to the establishment of a new regulatory tracking mechanism that allowed for the recovery of previously incurred operating expenses associated with poles acquired on May 1, 2023, and higher property tax expense.
Previous wording
Our electric transmission segment earnings increased $28.0 million and $49.6 million in the second quarter and the first half of 2024, respectively, as compared to the second quarter and the first half of 2023, due primarily to a higher transmission rate base as a result of our continued investment in our transmission infrastructure, the impact of the annual billing and cost reconciliation filing with FERC, and higher AFUDC equity income.
Current wording
Our electric transmission segment earnings increased $14.6 million and $64.2 million in the third quarter and the first nine months of 2024, respectively, as compared to the third quarter and the first nine months of 2023, due primarily to a higher transmission rate base as a result of our continued investment in our transmission infrastructure. Additionally, the earnings benefit in the nine month period was due to the impact of the annual rate reconciliation filing with FERC.
Previous wording
Our natural gas distribution segment earnings increased $15.4 million and $35.7 million in the second quarter and the first half of 2024, respectively, as compared to the second quarter and the first half of 2023, due primarily to higher revenues from capital tracking mechanisms due to continued investments in natural gas infrastructure and a base distribution rate increase effective November 1, 2023 at NSTAR Gas, and lower operations and maintenance expense. Those earnings increases were partially offset by higher depreciation expense and higher interest expense.
Current wording
Our natural gas distribution segment earnings increased $39.2 million in the first nine months of 2024, as compared to the first nine months of 2023, due primarily to higher revenues from capital tracking mechanisms due to continued investments in natural gas infrastructure and a base distribution rate increase effective November 1, 2023 at NSTAR Gas, lower operations and maintenance expense, the absence of a prior year unfavorable regulatory adjustment resulting from NSTAR Gas’ GSEP reconciliation filing, and a lower effective tax rate. Those earnings increases were partially offset by higher depreciation expense, higher interest expense, and higher property tax expense.
Previous wording
Our water distribution segment earnings increased $2.6 million in the first half of 2024, as compared to the first half of 2023, due primarily to an after-tax benefit of $6.3 million recorded to recognize the impacts of the Aquarion Water Company of Connecticut’s rate case decision from PURA from the effective date of the order on March 15, 2023 through June 30, 2024. The adjustment was recorded as a result of the State of Connecticut Superior Court’s decision on the rate case appeal on March 25, 2024. The impacts primarily include a reduction to depreciation expense to reflect lower depreciation rates ordered by PURA in its final decision, partially offset by a reserve recorded for revenues subject to refund as a result of the lower authorized revenues not yet reflected in current rates. The earnings increase was partially offset by higher interest expense, higher depreciation expense, and higher operations and maintenance expense.
Current wording
Our water distribution segment earnings increased $7.1 million and $9.7 million in the third quarter and the first nine months of 2024, respectively, as compared to the third quarter and the first nine months of 2023, due primarily to after-tax benefits of $3.4 million and $9.7 million recorded in the third quarter and first nine months of 2024, respectively, to recognize the impacts of the Aquarion Water Company of Connecticut’s rate case decision from PURA. The impacts of PURA’s rate case decision on March 15, 2023 were recorded beginning in March 2024 as a result of the State of Connecticut Superior Court’s decision on the rate case appeal on March 25, 2024. The impacts primarily include a reduction to depreciation expense to reflect lower depreciation rates ordered by PURA in its final decision, partially offset by lower authorized revenues. The earnings increase in both periods was also due to revenues from a water company acquisition, partially offset by higher year-to-date operations and maintenance expense.
Previous wording
Eversource Parent and Other Companies: Eversource parent and other companies’ losses improved by $293.6 million and $275.8 million in the second quarter and the first half of 2024, respectively, as compared to the second quarter and the first half of 2023, due primarily to the absence of the impairment of Eversource parent’s offshore wind investments in the second quarter of 2023, which resulted in an after-tax charge of $331.0 million, or $0.95 per share and the absence of a loss on the disposition of land in the second quarter of 2023 that was initially acquired to construct the Northern Pass Transmission project and was subsequently abandoned. These earnings improvements were partially offset by higher interest expense in both periods. Additionally, earnings in the second quarter were negatively impacted by a higher effective tax rate.
Current wording
Eversource Parent and Other Companies: Eversource parent and other companies’ losses increased by $513.2 million and $237.2 million in the third quarter and the first nine months of 2024, respectively, as compared to the third quarter and the first nine months of 2023, due primarily to the loss on the sale of Eversource parent’s offshore wind investments in the third quarter of 2024, which resulted in an after-tax charge of $524.0 million, as compared to an impairment charge on these investments in the second quarter of 2023 of $331.0 million. Results for the first nine months of 2023 also include a loss on the disposition of land that was initially acquired to construct the Northern Pass Transmission project and was subsequently abandoned and other charges recorded of $6.9 million.
Previous wording
Eversource, CL&P, NSTAR Electric and PSNH each uses its available capital resources to fund its respective construction expenditures, meet debt requirements, pay operating costs, including storm-related costs, pay dividends, and fund other corporate obligations, such as pension contributions. Eversource's regulated companies recover their electric, natural gas and water distribution construction expenditures as the related project costs are depreciated over the life of the assets. This impacts the timing of the revenue stream designed to fully recover the total investment plus a return on the equity and debt used to finance the investments. Eversource's regulated companies spend a significant amount of cash on capital improvements and construction projects that have a long-term return on investment and recovery period. In addition, Eversource uses its capital resources to fund investments in its offshore wind business, which are recognized as long-term assets.
Current wording
Eversource, CL&P, NSTAR Electric and PSNH each uses its available capital resources to fund its respective construction expenditures, meet debt requirements, pay operating costs, including storm-related costs, pay dividends, and fund corporate obligations. Eversource's regulated companies recover their electric, natural gas and water distribution construction expenditures as the related project costs are depreciated over the life of the assets. This impacts the timing of the revenue stream designed to fully recover the total investment plus a return on the equity and debt used to finance the investments. Eversource's regulated companies spend a significant amount of cash on capital improvements and construction projects that have a long-term return on investment and recovery period.
Previous wording
Cash totaled $33.4 million as of June 30, 2024, compared with $53.9 million as of December 31, 2023.
Current wording
Cash and Cash Equivalents totaled $97.9 million as of September 30, 2024, compared with $53.9 million as of December 31, 2023.
Previous wording
Amounts outstanding under the commercial paper programs are included in Notes Payable and classified in current liabilities on the Eversource and NSTAR Electric balance sheets, as all borrowings are outstanding for no more than 364 days at one time. As a result of the CL&P long-term debt issuance in January 2024, $207.3 million of commercial paper borrowings under the Eversource parent commercial paper program were reclassified to Long-Term Debt on Eversource parent’s balance sheet as of December 31, 2023. As a result of the Yankee Gas long-term debt issuances in July 2024, $37.9 million of commercial paper borrowings under the Eversource parent commercial paper program were reclassified to Long-Term Debt on Eversource parent’s balance sheet as of June 30, 2024.
Current wording
Amounts outstanding under the commercial paper programs are included in Notes Payable and classified in current liabilities on the Eversource and NSTAR Electric balance sheets, as all borrowings are outstanding for no more than 364 days at one time. As a result of the CL&P long-term debt issuance in January 2024, $207.3 million of commercial paper borrowings under the Eversource parent commercial paper program were reclassified to Long-Term Debt on Eversource parent’s balance sheet as of December 31, 2023. As a result of the EGMA long-term debt issuance in October 2024, $100.0 million of commercial paper borrowings under the Eversource parent commercial paper program were reclassified to Long-Term Debt on Eversource parent’s balance sheet as of September 30, 2024.
Previous wording
Intercompany Borrowings: Eversource parent uses its available capital resources to provide loans to its subsidiaries to assist in meeting their short-term borrowing needs. Eversource parent records intercompany interest income from its loans to subsidiaries, which is eliminated in consolidation. Intercompany loans from Eversource parent to its subsidiaries are eliminated in consolidation on Eversource's balance sheets. As of June 30, 2024, there were intercompany loans from Eversource parent to CL&P of $407.8 million and to PSNH of $132.0 million. As of December 31, 2023, there were intercompany loans from Eversource parent to CL&P of $457.0 million and to PSNH of $233.0 million. Eversource parent charges interest on these intercompany loans at the same weighted-average interest rate as its commercial paper program. Intercompany loans from Eversource parent are included in Notes Payable to Eversource Parent and classified in current liabilities on the respective subsidiary's balance sheets, as these intercompany borrowings are outstanding for no more than 364 days at one time. As a result of the CL&P long-term debt issuance in January 2024, $207.3 million of CL&P’s intercompany borrowings were reclassified to Long-Term Debt on CL&P’s balance sheet as of December 31, 2023.
Current wording
Intercompany Borrowings: Eversource parent uses its available capital resources to provide loans to its subsidiaries to assist in meeting their short-term borrowing needs. Eversource parent records intercompany interest income from its loans to subsidiaries, which is eliminated in consolidation. Intercompany loans from Eversource parent to its subsidiaries are eliminated in consolidation on Eversource's balance sheets. As of September 30, 2024, there were intercompany loans from Eversource parent to CL&P of $135.0 million and to PSNH of $89.3 million. As of December 31, 2023, there were intercompany loans from Eversource parent to CL&P of $457.0 million and to PSNH of $233.0 million. Eversource parent charges interest on these intercompany loans at the same weighted-average interest rate as its commercial paper program. Intercompany loans from Eversource parent are included in Notes Payable to Eversource Parent and classified in current liabilities on the respective subsidiary's balance sheets, as these intercompany borrowings are outstanding for no more than 364 days at one time. As a result of the CL&P long-term debt issuance in January 2024, $207.3 million of CL&P’s intercompany borrowings were reclassified to Long-Term Debt on CL&P’s balance sheet as of December 31, 2023.
Previous wording
Long-Term Debt Issuance Authorizations: On February 8, 2024, the NHPUC approved PSNH’s request for authorization to issue up to $300 million in long-term debt through December 31, 2024. On May 1, 2024, the DPU approved NSTAR Electric’s request for authorization to issue up to $2.4 billion in long-term debt through December 31, 2026. On July 24, 2024, PURA approved CL&P’s request for authorization to issue up to $1.0 billion in long-term debt through December 31, 2025.
Current wording
Long-Term Debt Issuance Authorizations: On February 8, 2024, the NHPUC approved PSNH’s request for authorization to issue up to $300 million in long-term debt through December 31, 2024. On May 1, 2024, the DPU approved NSTAR Electric’s request for authorization to issue up to $2.4 billion in long-term debt through December 31, 2026. On July 24, 2024, PURA approved CL&P’s request for authorization to issue up to $1.0 billion in long-term debt through December 31, 2025. On August 12, 2024, the DPU approved EGMA’s request for authorization to issue up to $325 million in long-term debt through December 31, 2026.
Previous wording
Rate Reduction Bonds: PSNH's RRB payments consist of principal and interest and are paid semi-annually. PSNH paid $21.6 million of RRB principal payments and $7.6 million of interest payments in the first half of 2024, and paid $21.6 million of RRB principal payments and $8.3 million of interest payments in the first half of 2023.
Current wording
Rate Reduction Bonds: PSNH's RRB payments consist of principal and interest and are paid semi-annually. PSNH paid $43.2 million of RRB principal payments and $14.9 million of interest payments in the first nine months of 2024, and paid $43.2 million of RRB principal payments and $16.2 million of interest payments in the first nine months of 2023.
Previous wording
Common Share Issuances and Equity Distribution Agreement: On May 11, 2022, Eversource entered into an equity distribution agreement pursuant to which it may offer and sell up to $1.2 billion of its common shares from time to time through an “at-the-market” (ATM) equity offering program. In the first six months of 2024, Eversource issued 4,206,649 common shares, which resulted in proceeds of $248.2 million, net of issuance costs. Eversource used the net proceeds received for general corporate purposes.
Current wording
Common Share Issuances: Eversource has an equity distribution agreement pursuant to which it may offer and sell up to $1.2 billion of its common shares from time to time through an “at-the-market” (ATM) equity offering program. In the first nine months of 2024, Eversource issued 13.3 million common shares, which resulted in proceeds of $830.2 million, net of issuance costs. Eversource used the net proceeds received for general corporate purposes.
Previous wording
Cash Flows: Cash flows from operating activities primarily result from the transmission and distribution of electricity, and the distribution of natural gas and water. Cash flows provided by operating activities totaled $962.0 million in the first half of 2024, compared with $647.3 million in the first half of 2023. Operating cash flows were favorably impacted by the timing of cash payments made on our accounts payable, the timing of other working capital items, a decrease in cost of removal expenditures, a $48.8 million increase in income tax refunds received in 2024 compared to 2023, and a $42.6 million decrease in cash payments to vendors for storm costs. These favorable impacts were partially offset by the timing of cash collections on our accounts receivable and an increase in regulatory under-recoveries driven primarily by the timing of collections for energy and natural gas supply costs and other regulatory tracking mechanisms. The impacts of regulatory collections are included in both Regulatory Recoveries and Amortization on the statements of cash flows.
Current wording
Cash Flows: Cash flows from operating activities primarily result from the transmission and distribution of electricity, and the distribution of natural gas and water. Cash flows provided by operating activities totaled $1.52 billion in the first nine months of 2024, compared with $1.17 billion in the first nine months of 2023. Operating cash flows were favorably impacted by the timing of cash payments made on our accounts payable, an improvement in regulatory recoveries driven primarily by the timing of collections for CL&P’s non-bypassable FMCC and other regulatory tracking mechanisms, a $47.6 million increase in income tax refunds received in 2024 compared to 2023, a $45.3 million decrease in cash payments to vendors for storm costs, and a decrease in cost of removal expenditures. The impacts of regulatory collections are included in both Regulatory Recoveries and Amortization on the statements of cash flows. These favorable impacts were partially offset by the timing of cash collections on our accounts receivable and the timing of other working capital items.
Previous wording
On May 1, 2024, our Board of Trustees approved a common share dividend payment of $0.715 per share, paid on June 28, 2024 to shareholders of record as of May 16, 2024. In the first half of 2024, we paid cash dividends of $490.9 million and issued non-cash dividends of $12.0 million in the form of treasury shares, totaling dividends of $502.9 million. In the first half of 2023, we paid cash dividends of $459.0 million and issued non-cash dividends of $11.8 million in the form of treasury shares, totaling dividends of $470.8 million.
Current wording
On September 12, 2024, our Board of Trustees approved a common share dividend payment of $0.715 per share, paid on September 30, 2024 to shareholders of record as of September 23, 2024. In the first nine months of 2024, we paid cash dividends of $745.2 million and issued non-cash dividends of $17.8 million in the form of treasury shares, totaling dividends of $763.0 million. In the first nine months of 2023, we paid cash dividends of $688.9 million and issued non-cash dividends of $17.6 million in the form of treasury shares, totaling dividends of $706.5 million.
Previous wording
In the first half of 2024, CL&P, NSTAR Electric and PSNH paid $82.5 million, $393.9 million and $62.0 million respectively, in common stock dividends to Eversource parent.
Current wording
In the first nine months of 2024, CL&P, NSTAR Electric and PSNH paid $247.6 million, $643.9 million and $62.0 million respectively, in common stock dividends to Eversource parent.
Previous wording
Investments in Property, Plant and Equipment on the statements of cash flows do not include amounts incurred on capital projects but not yet paid, cost of removal, AFUDC related to equity funds, and the capitalized and deferred portions of pension and PBOP income/expense. In the first half of 2024, investments for Eversource, CL&P, NSTAR Electric, and PSNH were $2.22 billion, $532.2 million, $729.8 million, and $289.7 million, respectively. Capital expenditures were primarily for continuing projects to maintain and improve infrastructure and operations, including enhancing reliability to the transmission and distribution systems.
Current wording
Investments in Property, Plant and Equipment on the statements of cash flows do not include amounts incurred on capital projects but not yet paid, cost of removal, AFUDC related to equity funds, and the capitalized and deferred portions of pension and PBOP income/expense. In the first nine months of 2024, investments for Eversource, CL&P, NSTAR Electric, and PSNH were $3.29 billion, $759.0 million, $1.07 billion, and $461.4 million, respectively. Capital expenditures were primarily for continuing projects to maintain and improve infrastructure and operations, including enhancing reliability to the transmission and distribution systems.
Previous wording
Our consolidated capital expenditures, including amounts incurred but not paid, cost of removal, AFUDC, and the capitalized and deferred portions of pension and PBOP income/expense (all of which are non-cash factors), totaled $2.26 billion in the first half of 2024, compared to $1.98 billion in the first half of 2023. These amounts included$152.7 million and $119.1 million in the first half of 2024 and 2023, respectively, related to information technology and facilities upgrades and enhancements, primarily at Eversource Service and The Rocky River Realty Company.
Current wording
Our consolidated capital expenditures, including amounts incurred but not paid, cost of removal, AFUDC, and the capitalized and deferred portions of pension and PBOP income/expense (all of which are non-cash factors), totaled $3.40 billion in the first nine months of 2024, compared to $3.21 billion in the first nine months of 2023. These amounts included$209.4 million and $172.3 million in the first nine months of 2024 and 2023, respectively, related to information technology and facilities upgrades and enhancements, primarily at Eversource Service and The Rocky River Realty Company.
Previous wording
Electric Transmission Business: Our consolidated electric transmission business capital expenditures increased by $135.6 million in the first half of 2024, as compared to the first half of 2023. A summary of electric transmission capital expenditures by company is as follows:
Current wording
Electric Transmission Business: Our consolidated electric transmission business capital expenditures increased by $44.8 million in the first nine months of 2024, as compared to the first nine months of 2023. A summary of electric transmission capital expenditures by company is as follows:
Previous wording
In September of 2023, Eversource made a contribution of $528 million using the proceeds from the lease area sale to invest in a tax equity interest for South Fork Wind. South Fork Wind was restructured as a tax equity investment, with Eversource purchasing 100 percent ownership of a new Class A tax equity membership interest. This investment will result in Eversource receiving cash flow benefits from investment tax credits (ITC) and other future cash flow benefits as well. As of June 30 2024, all twelve South Fork Wind turbines met the requirements to qualify for the investment tax credits. As a result, $385 million of expected investment tax credits were reclassified from the South Fork Wind tax equity investment balance reported in Investments in Unconsolidated Affiliates as a reduction in current taxes payable of $54 million and an increase in deferred tax assets of $331 million on the Eversource balance sheet as of June 30, 2024.
Current wording
In September of 2023, Eversource made a contribution of $528 million to invest in a tax equity interest for South Fork Wind. South Fork Wind was restructured as a tax equity investment, with Eversource purchasing 100 percent ownership of a new Class A tax equity membership interest. This investment will result in Eversource receiving cash flow benefits from investment tax credits (ITC) and other future cash flow benefits as well. As of September 30, 2024, $459 million of expected investment tax credits and other expected tax benefits were reclassified from the South Fork Wind tax equity investment balance reported in Investments in Unconsolidated Affiliates as a reduction in current taxes payable of $54 million and a decrease in Accumulated Deferred Income Taxes of $405 million on the Eversource balance sheet as of September 30, 2024. As a result of these investment tax credits, Eversource expects lower federal income tax payments between 2024 through 2026. As of September 30, 2024, the tax equity interest in South Fork Wind totaled $22.2 million.
Previous wording
•On April 18, 2024, Eversource and Ørsted executed the equity and asset purchase agreement to sell Eversource’s 50 percent interest in Sunrise Wind to Ørsted for a gross purchase price of $230 million. The purchase price was subject to reduction for actual capital spending less than forecasted spending between signing the agreement in January and closing of the transaction. On July 9, 2024, Eversource completed the sale of its 50 percent ownership share of Sunrise Wind to Ørsted. In accordance with the equity and asset purchase agreement and after adjustment for the reduction in capital spending compared to forecasted, Ørsted paid Eversource $118 million at the closing of the sale transaction, and the remaining proceeds of $34 million will be paid after onshore construction is completed and certain other construction milestones are achieved.
Current wording
On January 24, 2024, Eversource signed an agreement with Ørsted to sell Eversource’s 50 percent share of Sunrise Wind, subject to certain conditions and regulatory approvals. On April 18, 2024, Eversource and Ørsted executed an equity and asset purchase agreement for a gross purchase price of $230 million. The purchase price was subject to reduction for actual capital spending less than forecasted spending between signing the agreement in January and closing of the transaction. On July 9, 2024, Eversource completed the sale of its 50 percent ownership share of Sunrise Wind to Ørsted. In accordance with the equity and asset purchase agreement and after adjustment for the reduction in capital spending compared to forecasted amounts, adjusted proceeds totaled $152 million. Ørsted paid Eversource $118 million at the closing of the sale transaction, which was used to pay off parent company debt. Remaining proceeds of $34 million will be paid after onshore construction is completed and certain other construction milestones are achieved. The remaining expected proceeds have been recorded in Other Long-Term Assets on Eversource’s balance sheet as of September 30, 2024. Eversource recorded a pre-tax gain on the sale of Sunrise Wind of $377 million in the third quarter of 2024. With completion of the sale, Eversource will not have any ongoing financial obligations associated with Sunrise Wind.
Previous wording
The post-closing purchase price adjustment payments include cost sharing obligations that provide Eversource will share equally with GIP in GIP’s funding obligations for up to approximately $240 million of incremental capital expenditure overruns incurred during the construction phase for Revolution Wind, after which obligations for any additional capital expenditure overruns would be shared equally by Eversource and Ørsted. The purchase price is also subject to post-closing adjustments as a result of final project economics, which includes Eversource’s obligation to maintain GIP’s internal rate of return for each project as specified in the agreement. Post-closing purchase price adjustment payments will be made following the sale closing date for South Fork and following the commercial operation of Revolution Wind. South Fork Wind construction has been completed, and Eversource does not expect any material cost sharing or other purchase price adjustment payments for South Fork Wind.
Current wording
As part of the Revolution Wind and South Fork Wind sale, Eversource and GIP agreed to make certain post-closing purchase price adjustment payments, which could further impact the final purchase price. The post-closing purchase price adjustment payments include cost sharing obligations that provide Eversource will share equally with GIP in GIP’s funding obligations up to an effective cap of approximately $240 million of incremental capital expenditure overruns incurred during the construction phase for Revolution Wind, after which Eversource will have responsibility for GIP’s obligations for any additional capital expenditure overruns in excess of the capped amount. The purchase price is also subject to post-closing adjustments as a result of final project economics, which includes Eversource’s obligation to maintain GIP’s internal rate of return for each project as specified in the agreement. Post-closing purchase price adjustment payments will be made following the commercial operation of Revolution Wind.
Previous wording
On February 13, 2024, Eversource executed an agreement to sell its existing 50 percent interests in the South Fork Wind and Revolution Wind projects to Global Infrastructure Partners (GIP) for $1.1 billion of cash proceeds to be received upon closing, subject to adjustment. The purchase price is inclusive of the sales value related to a 40 percent level of federal investment tax credits, 10 percent of which is the energy community ITC adder of approximately $170 million related to Revolution Wind. The purchase price is subject to adjustments based on, among other things, the progress, timing and the construction cost of Revolution Wind, including changes in actual versus forecasted capital spending between signing the agreement and closing of the transaction. Factors that could result in Eversource’s total net proceeds from the transaction to be lower, resulting in post-closing adjustment payments owed to GIP, include the ultimate cost of construction and extent of cost overruns for Revolution Wind, delays in constructing Revolution Wind, which would impact the economics associated with the purchase price adjustment, and Revolution Wind’s eligibility for federal investment tax credits at less than the value included in the purchase price. Total net proceeds could also be adjusted for a benefit due to Eversource if there are lower operation costs or higher availability of the projects through the period that is four years following the commercial operation date of the Revolution Wind project.
Current wording
Factors that could increase the post-closing adjustment payments owed to GIP include the ultimate cost of construction and extent of cost overruns for Revolution Wind, delays in constructing Revolution Wind, which would impact the economics associated with the purchase price adjustment, and Revolution Wind’s eligibility for federal investment tax credits at less than the value included in the purchase price. The purchase price included the sales value related to a 40 percent level of federal investment tax credits, 10 percent of which is the energy community ITC adder of approximately $170 million related to Revolution Wind. It is possible that new information or future developments could require a reassessment of the potential exposure of the estimated liability for the post-closing adjustment payments. As this information becomes available, Eversource will continue to assess the potential exposure and adjust the liability if needed. Incremental exposure of this estimated liability remains possible, but management cannot reasonably estimate a range of loss beyond the amount recorded at this time. Total net proceeds could also be adjusted for a benefit due to Eversource if there are lower operation costs or higher availability of the projects through the period that is four years following the commercial operation of Revolution Wind. South Fork Wind has achieved commercial operation and, as a result, Eversource does not expect any material cost sharing or other purchase price adjustment payments related to this project.
Previous wording
With the completion of the sale, Eversource has divested all of its ownership interest in Sunrise Wind and will not have any ongoing ownership interest in the project, nor any ongoing financial obligations associated with project costs. Eversource’s existing credit support obligations were either terminated or indemnified by Ørsted as a result of the sale. Eversource has entered into a separate amended and restated construction management agreement to manage Sunrise Wind’s onshore construction through completion. In this role, Eversource will solely be a service provider to Sunrise Wind.
Current wording
Under the agreement with GIP, Eversource’s existing and certain additional credit support obligations for Revolution Wind are expected to roll off as the project completes construction. Under the agreement with Ørsted, Eversource’s existing credit support obligations for Sunrise Wind were either terminated or indemnified by Ørsted as a result of the sale. Eversource has entered into separate construction management agreements to manage Sunrise Wind’s and Revolution Wind’s onshore construction through completion. In this role, Eversource will be solely a service provider to Sunrise Wind and Revolution Wind.
Previous wording
In the second quarter of 2023, in connection with the process to divest its offshore wind business, Eversource identified indicators for impairment. In the impairment assessment, Eversource evaluated its investments and determined that the carrying value of the equity method offshore wind investments exceeded the fair value of the investments and that the decline in fair value was other-than-temporary. The completion of the strategic review in the second quarter of 2023 resulted in Eversource recording a pre-tax other-than-temporary impairment charge of $401 million ($331 million after-tax) to reflect the investment at estimated fair value based on the expected purchase price at that time. In the fourth quarter of 2023, Eversource recognized an additional pre-tax other-than-temporary impairment charge of $1.77 billion ($1.62 billion after-tax) in its offshore wind investments and established a new cost basis in the investments as of December 31, 2023. The impairment charges were non-cash charges and did not impact Eversource’s cash position.
Current wording
Impairments: In the second quarter of 2023, in connection with the process to divest its offshore wind business, Eversource identified indicators for impairment. In the impairment assessment, Eversource evaluated its investments and determined that the carrying value of the equity method offshore wind investments exceeded the fair value of the investments and that the decline in fair value was other-than-temporary. The completion of the strategic review in the second quarter of 2023 resulted in Eversource recording a pre-tax other-than-temporary impairment charge of $401 million ($331 million after-tax) to reflect the investment at estimated fair value based on the expected purchase price at that time. In the fourth quarter of 2023, Eversource recognized an additional pre-tax other-than-temporary impairment charge of $1.77 billion ($1.62 billion after-tax) in its offshore wind investments and established a new cost basis in the investments as of December 31, 2023. The impairment charges were non-cash charges and did not impact Eversource’s cash position. In the third quarter of 2024, Eversource sold its interest in its offshore wind investments.
Previous wording
On November 21, 2019, FERC issued Opinion No. 569 affecting the two pending transmission ROE complaints against the Midcontinent ISO (MISO) transmission owners, in which FERC adopted a new methodology for determining base ROEs. Various parties sought rehearing. On December 23, 2019, the NETOs filed supplementary materials in the NETOs' four pending cases to respond to this new methodology because of the uncertainty of the applicability to the NETOs' cases. On May 21, 2020, the FERC issued its order in Opinion No. 569-A on the rehearing of the MISO transmission owners' cases, in which FERC again changed its methodology for determining the MISO transmission owners' base ROEs. On November 19, 2020, the FERC issued Opinion No. 569-B denying rehearing of Opinion No. 569-A and reaffirmed the methodology previously adopted in Opinion No. 569-A. The new methodology differs significantly from the methodology proposed by FERC in its October 16, 2018 order to determine the NETOs' base ROEs in its four pending cases. FERC Opinion Nos. 569-A and 569-B were appealed to the Court. On August 9, 2022, the Court issued its decision vacating MISO ROE FERC Opinion Nos. 569, 569-A and 569-B and remanded to FERC to reopen the proceedings. The Court found that FERC’s development of the new return methodology was arbitrary and capricious due to FERC’s failure to offer a reasonable explanation for its decision to reintroduce the risk-premium financial model in its new methodology for calculating a just and reasonable return. At this time, Eversource cannot predict how and when FERC will address the Court’s findings on the remand of the MISO FERC opinions or any potential associated impact on the NETOs’ four pending ROE complaint cases.
Current wording
On November 21, 2019, FERC issued Opinion No. 569 affecting the two pending transmission ROE complaints against the Midcontinent ISO (MISO) transmission owners, in which FERC adopted a new methodology for determining base ROEs. Various parties sought rehearing. On December 23, 2019, the NETOs filed supplementary materials in the NETOs' four pending cases to respond to this new methodology because of the uncertainty of the applicability to the NETOs' cases. On May 21, 2020, the FERC issued its order in Opinion No. 569-A on the rehearing of the MISO transmission owners' cases, in which FERC again changed its methodology for determining the MISO transmission owners' base ROEs. On November 19, 2020, the FERC issued Opinion No. 569-B denying rehearing of Opinion No. 569-A and reaffirmed the methodology previously adopted in Opinion No. 569-A. The new methodology differs significantly from the methodology proposed by FERC in its October 16, 2018 order to determine the NETOs' base ROEs in its four pending cases. FERC Opinion Nos. 569-A and 569-B were appealed to the Court. On August 9, 2022, the Court issued its decision vacating MISO ROE FERC Opinion Nos. 569, 569-A and 569-B and remanded to FERC to reopen the proceedings. The Court found that FERC’s development of the new return methodology was arbitrary and capricious due to FERC’s failure to offer a reasonable explanation for its decision to reintroduce the risk-premium financial model in its new methodology for calculating a just and reasonable return.
Previous wording
Given the significant uncertainty regarding the applicability of the FERC opinions in the MISO transmission owners’ two complaint cases to the NETOs’ pending four complaint cases, Eversource concluded that there is no reasonable basis for a change to the reserve or recognized ROEs for any of the complaint periods at this time. As well, Eversource cannot reasonably estimate a range of loss for any of the four complaint proceedings at this time. Eversource, CL&P, NSTAR Electric and PSNH currently record revenues at the 10.57 percent base ROE and incentive cap at 11.74 percent established in the October 16, 2014 FERC order.
Current wording
Given the significant uncertainty regarding the applicability of the FERC order in the MISO transmission owners’ two complaint cases to the NETOs’ pending four complaint cases due to the complex differences between the cases, Eversource concluded that there is no reasonable basis for a change to the reserve or recognized ROEs for any of the complaints or subsequent periods at this time and Eversource cannot reasonably estimate a range of loss for any of the four complaint proceedings at this time. The resolution of these proceedings could have a material impact on the results of operations, financial condition and cash flows.
Previous wording
A change of 10 basis points to the base ROE used to establish the reserves would impact Eversource’s after-tax earnings by an average of approximately $3 million for each of the four 15-month complaint periods. Prospectively from the date of a final FERC order implementing a new base ROE, based off of 2023 rate base, a change of 10 basis points to the base ROE would impact Eversource’s future annual after-tax earnings by approximately $5.5 million per year, and will increase slightly over time as we continue to invest in our transmission infrastructure.
Current wording
A change of 10 basis points to the base ROE used to establish the reserves would impact Eversource’s after-tax earnings by an average of approximately $3 million for each of the four 15-month complaint periods. Prospectively from the date of a final FERC order implementing a new base ROE, based off of estimated 2024 rate base, a change of 10 basis points to the base ROE would impact Eversource’s future annual after-tax earnings by approximately $6 million per year, and will increase slightly over time as we continue to invest in our transmission infrastructure.
Previous wording
On April 15, 2021, FERC issued a Supplemental NOPR that proposes to eliminate the existing 50 basis point return on equity for utilities that have been participating in a regional transmission organization (RTO ROE incentive) for more than three years. On June 25, 2021, the NETOs jointly filed comments strongly opposing FERC’s proposal. On July 26, 2021, the NETOs filed Supplemental NOPR reply comments responding to various parties advocating for the elimination of the RTO Adder. If FERC issues a final order eliminating the RTO ROE incentive as proposed in the Supplemental NOPR, the estimated annual impact (using 2023 rate base) on Eversource's after-tax earnings is approximately $20 million. The Supplemental NOPR contemplates an effective date 30 days from the final order.
Current wording
On April 15, 2021, FERC issued a Supplemental NOPR that proposes to eliminate the existing 50 basis point return on equity for utilities that have been participating in a regional transmission organization (RTO ROE incentive) for more than three years. On June 25, 2021, the NETOs jointly filed comments strongly opposing FERC’s proposal. On July 26, 2021, the NETOs filed Supplemental NOPR reply comments responding to various parties advocating for the elimination of the RTO Adder. If FERC issues a final order eliminating the RTO ROE incentive as proposed in the Supplemental NOPR, the estimated annual impact (using estimated 2024 rate base) on Eversource's after-tax earnings is approximately $23 million. The Supplemental NOPR contemplates an effective date 30 days from the final order.
Previous wording
Electric, Natural Gas and Water Utility Base Distribution Rates: The regulated companies’ distribution rates are set by their respective state regulatory commissions, and their tariffs include mechanisms for periodically adjusting their rates for the recovery of specific incurred costs. Other than as described below, for the first half of 2024, changes made to the regulated companies’ rates did not have a material impact on their earnings. For further information, see "Financial Condition and Business Analysis – Regulatory Developments and Rate Matters" included in Item 7, "Management’s Discussion and Analysis of Financial Condition and Results of Operations," of the Eversource 2023 Form 10-K.
Current wording
Electric, Natural Gas and Water Utility Base Distribution Rates: The regulated companies’ distribution rates are set by their respective state regulatory commissions, and their tariffs include mechanisms for periodically adjusting their rates for the recovery of specific incurred costs. Other than as described below, for the first nine months of 2024, changes made to the regulated companies’ rates did not have a material impact on their earnings. For further information, see "Financial Condition and Business Analysis – Regulatory Developments and Rate Matters" included in Item 7, "Management’s Discussion and Analysis of Financial Condition and Results of Operations," of the Eversource 2023 Form 10-K.
Showing the first 40 of 65 pairs. Open the source sections for the rest.
Rearranged current paragraphs (6)
Current report — wording carried from elsewhere
Our electric distribution segment earnings increased $30.2 million in the third quarter of 2024, as compared to the third quarter of 2023, due primarily to higher revenues from base distribution rate increases at NSTAR Electric effective January 1, 2024 and at PSNH effective August 1, 2024 and from CL&P's capital tracking mechanism due to increased electric system improvements, lower operations and maintenance expense driven by lower storm-related costs, and an increase in interest income primarily on regulatory deferrals. Those earnings increases were partially offset by higher interest expense, higher depreciation expense, and higher property tax expense.
Current report — wording carried from elsewhere
Eversource, CL&P, NSTAR Electric and PSNH currently record revenues at the 10.57 percent base ROE and incentive cap at 11.74 percent established in the October 16, 2014 FERC order.
Current report — wording carried from elsewhere
On April 18, 2024, PURA initiated a docket to address the matters on remand. On July 31, 2024, PURA issued a final decision in this docket and increased AWC-CT’s approved revenue requirement by $0.1 million above the amount authorized in the March 15, 2023 decision. Rates went into effect on July 31, 2024. On September 13, 2024, AWC-CT filed an appeal of PURA’s July 31, 2024 final decision to the Connecticut Superior Court. A ruling on the appeal is pending.
Current report — wording carried from elsewhere
NSTAR Gas Distribution Rates: NSTAR Gas’ PBR mechanism allows for an annual adjustment to base distribution rates for inflation and exogenous events. On September 16, 2024, NSTAR Gas submitted its annual PBR Adjustment filing for a $12.7 million increase to base distribution rates for effect on November 1, 2024. On October 30, 2024, the DPU approved this filing.
Current report — wording carried from elsewhere
NSTAR Electric’s PBR mechanism allows for an annual adjustment to base distribution rates for inflation, exogenous events and future capital additions based on a historical five-year average of total capital additions. On December 26, 2023, the DPU approved a $104.9 million increase to NSTAR Electric’s base distribution rates effective January 1, 2024.
Current report — wording carried from elsewhere
The variance in Other Income, Net for the nine month period was also dueto the absence in 2024 of abenefit in both the first and second quarters of 2023 from the liquidation of Eversource’s equity method investment in a renewable energy fund in excess of its carrying value, partially offset by a charitable contribution made with a portion of the proceeds from the liquidation in the first quarter of 2023, as well as the absence in 2024 of a loss on the disposition of land in the second quarter of 2023.
Rearranged previous paragraphs (2)
Previous report — wording carried elsewhere
As a result of these investment tax credits generated from our wind investments, Eversource expects lower federal income tax payments between 2024 through 2026.
Previous report — wording carried elsewhere
On April 18, 2024, Eversource and Ørsted executed the equity and asset purchase agreement to sell Eversource’s 50 percent interest in Sunrise Wind to Ørsted for a gross purchase price of $230 million. The purchase price was subject to reduction for actual capital spending less than forecasted spending between signing the agreement in January and closing of the transaction. On July 9, 2024, Eversource completed the sale of its 50 percent ownership share of Sunrise Wind to Ørsted. In accordance with the equity and asset purchase agreement and after adjustment for the reduction in capital spending compared to forecasted, Ørsted paid Eversource $118 million at the closing of the sale transaction, and the remaining proceeds of $34 million will be paid after onshore construction is completed and certain other construction milestones are achieved.