What changed in Management’s Discussion and Analysis?

Read the current filing

Previous report: 10-K

Period ended 2024-12-31; filed 2025-02-20.

0000067716-25-000016

Item 7. Management's Discussion and Analysis of Financial Condition and Results of Operations

Current report: 10-K

Period ended 2025-12-31; filed 2026-02-20.

0000067716-26-000014

Item 7. Management's Discussion and Analysis of Financial Condition and Results of Operations

The baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.

Compared 384 previous paragraphs and 258 current paragraphs.

113 unchanged; 76 reworded; 67 added; 187 removed; 8 previous and 2 current paragraphs rearranged.

Tables are not compared: 18 previous and 17 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.

A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.

Added paragraphs (67)

Current report

The Company generates, transmits and distributes electricity and provides natural gas distribution, transportation and storage services. Through a strategy focusing on its "CORE," the Company strives to deliver superior value and achieve industry-leading performance as a pure-play regulated energy delivery company, while pursuing organic growth opportunities. The Company's "CORE" strategy prioritizes customers and communities, operational excellence, returns focused initiatives and an employee driven culture.

Current report

One Big Beautiful Bill Act On July 4, 2025, the reconciliation bill was enacted into law, extending key provisions of the 2017 Tax Cuts and Jobs Act while scaling back clean energy tax incentives of the IRA. Changes in tax laws may affect recorded deferred tax assets and deferred tax liabilities or the Company's effective tax rates in the future. The Company has evaluated new legislation, and it does not expect a material impact to the consolidated financial statements or ongoing tax rate as a result of this legislation.

Current report

Results of Operations The Company's discussion and analysis for the year ended December 31, 2025 compared to 2024 is included herein. For discussion and analysis for the year ended December 31, 2024 compared to 2023 refer to Part II, Item 7. "Management's Discussion and Analysis of Financial Condition and Results of Operations" in the Company's report on Form 10-K for the year ended December 31, 2024, filed with the SEC on February 20, 2025.

Current report

•Earnings at the electric business were impacted by higher operation and maintenance expense, primarily increased payroll-related costs, contract services related to Coyote Station planned outage-related costs, software expense, which include certain costs associated with services provided under the Transition Services Agreement with Everus that are recovered in other income, and insurance expense. Partially offsetting the increased operation and maintenance expense were higher retail sales revenue and retail sales volumes, partially driven by a data center near Ellendale, North Dakota.

Current report

•Increased earnings at the natural gas distribution business was largely the result of higher retail sales revenue, driven largely by rate relief in Washington, Montana, South Dakota and Wyoming. The increase was partially offset by higher operation and maintenance expense, primarily higher insurance expense, payroll-related costs, and software expense, which include certain costs associated with services provided under the Transition Services Agreement with Everus that are recovered in other income.

Current report

▪Higher net transmission revenue of $3.5 million, including data center revenue.

Current report

◦Partially offset by lower renewable tracker revenues, partially associated with higher production tax credits offset in income tax benefit, as described below.

Current report

▪Higher contract services related to Coyote generating station planned outage-related costs of $3.5 million.

Current report

◦Also reflected are higher costs associated with services provided to Everus as part of the transition services agreement, offset in other income, as described below. The transition services are expected to be complete as of March 2026.

Current report

•Other income decreased $800,000, primarily due to lower interest income related to a data center project and lower regulatory deferral balances, partially offset by higher transition services agreement income, as described above.

Current report

•Interest expense increased $1.7 million, largely the result of lower AFUDC due to lower interest rates and average CWIP balances.

Current report

▪Higher purchased natural gas sold of $47.0 million, including net environmental compliance costs, recovered in customer rates and offset in expense, as described below.

Current report

▪Rate relief of $25.2 million, primarily in Washington, Montana, South Dakota and Wyoming.

Current report

▪Higher revenue-based taxes of $3.6 million, recovered in rates and offset in expense, as described below.

Current report

▪Higher retail sales volumes of $2.0 million, which includes weather normalization and decoupling mechanism in certain jurisdictions, and higher volumes to commercial customer classes. This increase was largely offset by lower volumes to residential customer classes, largely due to warmer weather in certain jurisdictions.

Current report

•Purchased natural gas sold increased $47.0 million, primarily due to higher net environmental compliance costs of $38.1 million, commodity costs of $4.9 million and volumes of natural gas purchased of $4.0 million.

Current report

▪Higher costs associated with MAOP projects of $1.7 million.

Current report

◦Also reflected are higher costs associated with services provided to Everus as part of the transition services agreement, offset in other income, as described below. The transition services are expected to be complete as of March 2026.

Current report

•Depreciation and amortization increased $3.0 million, of which $6.6 million resulted from increased property, plant and equipment balances related to growth and replacement projects placed in service, partially offset by lower depreciation rates implemented from rate cases in Montana, North Dakota, Wyoming, Washington and Oregon of $2.9 million, and lower regulatory amortizations.

Current report

•Taxes, other than income increased $5.5 million, due to higher revenue-based taxes, as described above, and higher property taxes, largely in Montana and Washington.

Current report

▪Lower returns of $500,000 on the Company's nonqualified benefit plans.

Current report

◦Offset in part by higher transition services agreement income, as described above.

Current report

•Interest expense decreased $3.6 million, largely due to lower long-term debt balances.

Current report

In December 2025, the Company completed the acquisition of a 49 percent ownership interest in Badger Wind Farm and placed the asset in service. The completed transaction secures 122.5 MW of the project's total 250 MW generation capacity for the Company and follows the NDPSC's Advance Determination of Prudence and Certificate of Public Convenience and Necessity approvals, confirming the project is a prudent, cost-effective investment for customers. The Company previously executed a PPA for 150 MW of output from the project, which included the option to purchase the 49 percent ownership interest. With the closing now complete, the PPA has been reduced to 27.5 MW.

Current report

•In February 2026, the EPA published a final rule that rescinded the 2009 Endangerment Finding and related standards for motor vehicle GHG emissions under the Clean Air Act. The final rule does not directly address or repeal GHG regulations for power plants and other non-motor vehicle sources. The Company is currently evaluating this rulemaking.

Current report

•In Washington, the Climate Commitment Act was adopted by the Washington Legislature in 2021 and became effective in 2023. The Climate Commitment Act establishes a cap-and-invest program designed to reduce GHG emissions over time, while using auctioned allowances to fund state energy and environmental policy goals. The Company intends to meet its compliance obligations through a combination of energy efficiency measures, no-cost allowances, purchased allowances, and carbon offsets. Compliance costs for these regulations are being recovered through customer rates. Due to the timing of regulatory recovery, the purchase of allowances could impact the Company's operating cash flow.

Current report

•In November 2025, the Minot Expansion Project was placed in service and increased system capacity by 7 MMcf of natural gas per day.

Showing the first 40 of 67 passages. Open the source sections for the rest.

Removed paragraphs (187)

Previous report

The Company provides essential services, delivering reliable energy that powers lives. Through its infrastructure investments and operations the Company drives economic growth, supports communities, and energizes businesses that keep America moving.

Previous report

Based on the Company becoming a pure-play regulated energy delivery business, the Company's board of directors established a long-term dividend payout ratio target of 60 percent to 70 percent of regulated energy delivery earnings. The Company has an 87-year history of uninterrupted dividend payments to stockholders and remains committed to paying a competitive dividend.

Previous report

•The electric business experienced higher retail sales revenue due to rate relief in North Dakota, South Dakota and Montana. Lower volumes from the majority of customers, primarily due to cooler weather in the second quarter, and higher operation and maintenance expense, primarily contract services costs, partially offset the increases.

Previous report

•Decreased earnings at the natural gas distribution business was largely the result of higher operation and maintenance expense, primarily higher contract services costs, higher payroll-related costs, and higher software expenses. Also decreasing net income was higher depreciation and amortization expense, primarily due to increased asset additions. These decreases were partially offset by higher retail sales revenue, primarily due to rate relief in North Dakota and South Dakota.

Previous report

2023 compared to 2022 The Company's consolidated earnings increased $47.2 million. The Company experienced increased earnings at each of its continuing businesses.

Previous report

•The electric business experienced higher retail sales due to rate relief in North Dakota and Montana, an electric service agreement to provide power to a data center near Ellendale, North Dakota, and higher transmission interconnect upgrades. Electric earnings were partially offset by lower residential volumes, primarily due to cooler weather in the third quarter of the year.

Previous report

•Natural gas distribution experienced higher retail sales revenue due to rate relief in Idaho and Washington, higher basic service charges, and recovery of short-term debt interest expense in Idaho related to increased gas costs. These increases were largely offset by higher operation and maintenance expense, primarily higher payroll-related costs. The natural gas distribution business also experienced a 6.6 percent decrease in retail sales volumes to all customer classes, largely due to warmer weather, which was partially offset by weather normalization and decoupling mechanisms.

Previous report

•The pipeline's earnings increase was driven by higher transportation volumes, primarily from increased contracted volume commitments from the North Bakken Expansion project and a full year of benefit from this project; as well as organic growth projects placed in service in November 2023 and August 2022. In addition, revenues increased from new transportation and storage rates effective August 1, 2023 and higher storage-related activity. The pipeline also benefited from higher allowance for funds used during construction on organic growth projects, lower property taxes and higher non-regulated project margin. The increase was offset in part by higher operation and maintenance expense primarily attributable to payroll-related costs and contract services. The pipeline business also incurred higher interest expense as a result of higher interest rates and higher debt balances.

Previous report

•Other experienced a realized gain of $186.6 million related to the tax-free exchange of its retained interest in Knife River and higher interest income. Partially offsetting these items were higher interest expense, primarily related to debt issued in connection with the Knife River separation. Other also benefited from improved claims experience at the captive insurer in 2023 compared to 2022.

Previous report

•The Company's earnings from continuing operations were further impacted by $18.6 million in higher returns on the Company's nonqualified benefit plan investments, as discussed in Note 9, partially offset by higher costs incurred in connection with other strategic initiatives of $6.1 million, after tax.

Previous report

The Company’s CODM, the chief executive officer of MDU Resources Group, Inc., regularly reviews discrete financial information of each reportable segment and uses net income to assess performance of each reportable segment. The CODM uses this information to assess performance and make decisions about resources to be allocated to each reportable segment, including capital and personnel. The information provided to the CODM is prepared at the reportable segment level in quarterly financial packages and on a more summarized basis monthly. Budget and forecast information is also provided to the CODM at the reportable segment level.

Previous report

In December 2022 and January 2023, natural gas prices significantly increased across the Pacific Northwest from multiple price-pressuring events including wide-spread below-normal temperatures and higher natural gas consumption; reduced natural gas flows due to pipeline constraints, including maintenance in West Texas; and historically low regional natural gas storage levels. Natural gas prices stabilized by March 2023. The higher natural gas prices in December 2022 and January 2023 impacted both Intermountain and Cascade, both of which borrowed short-term debt of $125.0 million and $150.0 million, respectively, in January 2023 to finance the increased natural gas costs. To assist in the recovery of higher natural gas costs, Intermountain filed an out-of-cycle purchased gas adjustment with the IPUC that was effective February 1, 2023, and collected interest costs associated with short-term borrowing. Effective November 1, 2023, as approved by the WUTC, Cascade started recovery in Washington of these increased gas costs over a period of two years rather than the normal one year period. In January 2024, Cascade and Intermountain made the final repayment on short-term debt of $50.0 million and $45.0 million, respectively. For a discussion of the Company's most recent cases by jurisdiction, see Item 8 - Note 20.

Previous report

▪Rate relief of $7.1 million in North Dakota, South Dakota and Montana.

Previous report

▪Higher miscellaneous revenue of $2.4 million, including higher transmission interconnect upgrades.

Previous report

◦Partially offset by lower retail sales volumes of $2.6 million, driven primarily by lower residential volumes due to 37.0 percent cooler weather in the second quarter of 2024. There was a 1.2 percent increase in volumes, which includes an increase in commercial volumes from the data center as further discussed in the Outlook section.

Previous report

•Operation and maintenance increased $2.3 million, largely the result of increased contract services and higher payroll-related costs.

Previous report

▪Higher depreciation rates, which are recovered in operating revenues.

Previous report

◦Higher interest income of $2.7 million, largely related to a data center project of $1.6 million.

Previous report

◦Amounts related to higher deferred fuel and purchased power balances.

Previous report

•Interest expense increased $2.0 million, largely the result of higher long-term interest expense due to incremental debt issuances.

Previous report

2023 compared to 2022 Electric earnings increased $14.5 million as a result of:

Previous report

▪Rate relief of $4.4 million in North Dakota and Montana.

Previous report

▪Higher data center revenue of $3.4 million, including net transmission.

Previous report

▪Higher transmission interconnect upgrades of $2.9 million.

Previous report

•Electric fuel and purchased power increased $15.4 million, largely due to higher retail sales volumes, partially offset by lower commodity prices.

Previous report

◦Decreased Coyote Station costs of $1.7 million due to the absence of the planned outage in 2022.

Previous report

◦Lower materials expense of $500,000, partially due to the closure of Units 1 and 2 at Heskett Station.

Showing the first 40 of 187 passages. Open the source sections for the rest.

Reworded paragraphs (76)

Previous wording

Strategic Initiatives On May 31, 2023, the Company completed the separation of Knife River, its construction materials and contracting business, resulting in Knife River becoming an independent, publicly-traded company. The Company's board of directors approved the distribution of approximately 90 percent of the issued and outstanding shares of Knife River to the Company's stockholders. Stockholders of the Company received one share of Knife River common stock for every four shares of the Company's common stock held on May 22, 2023, the record date for the distribution. The Company retained approximately 10 percent or 5.7 million shares of Knife River common stock immediately following the separation, which were disposed of in a tax-free exchange in November 2023. The separation of Knife River was a tax-free spinoff transaction to the Company's stockholders for U.S. federal income tax purposes.

Current wording

Strategic Initiatives On May 31, 2023, the Company completed the separation of Knife River, its construction materials and contracting business, resulting in Knife River becoming an independent, publicly-traded company. The Company's board of directors approved the distribution of approximately 90 percent of the issued and outstanding shares of Knife River to the Company's stockholders. Stockholders of the Company received one share of Knife River common stock for every four shares of the Company's common stock held on May 22, 2023, the record date for the distribution. The Company retained approximately 10 percent or 5.7 million shares of Knife River common stock immediately following the separation, which were disposed of in a tax-free exchange in November 2023. The separation of Knife River was a tax-free spinoff transaction to the Company's stockholders for U.S. federal income tax purposes, except for cash received in lieu of fractional shares.

Previous wording

The Company incurred costs in connection with the strategic initiatives in 2022, 2023 and 2024, as noted in the Business Segment Financial and Operating Data section, and expects the majority of the separation costs have already been incurred.

Current wording

The Company incurred costs in connection with the strategic initiatives in 2023, 2024 and 2025, as noted in the Business Segment Financial and Operating Data section.

Previous wording

Market Trends The Company continues to manage the inflationary pressures experienced throughout the United States, including the impact that inflation, higher interest rates, commodity price volatility and supply chain disruptions may have on its business and customers and proactively looks for ways to lessen the impact to its business. The Company has observed supply chain improvements in lead times for certain commodities. Although the Company has started to see some reduction to interest rates, they remain elevated and have resulted in and may continue to result in increased borrowing costs on new debt, impacts to the Company's asset valuations and negatively impacting the purchasing power of its customers. For more information on possible impacts to the Company's businesses, see the Outlook for each segment below and Item 1A - Risk Factors.

Current wording

Market Trends The Company continues to manage the inflationary pressures experienced throughout the United States, including the impact that inflation, interest rates, changes in tariffs, commodity price volatility and supply chain disruptions may have on its business and customers and proactively looks for ways to lessen the impact to its business. The Company has observed supply chain improvements in lead times for certain commodities. The Company has experienced impacts related to the changes in tariffs and continues to navigate the current environment and monitor the future for impacts that could occur. For more information on possible impacts to the Company's businesses, see the Outlook for each segment below and Item 1A - Risk Factors.

Previous wording

The Company completed the separations of Knife River on May 31, 2023, its former construction materials and contracting segment, and of Everus on October 31, 2024, its former construction services segment, into new independent publicly-traded companies. As a result of these separations, the historical results of operations for Knife River and Everus are shown in discontinued operations, net of tax, except for allocated general corporate overhead costs of the Company, which did not meet the criteria for discontinued operations and are reflected in Other. Also included in discontinued operations are certain strategic initiative costs associated with the separations of Knife River and Everus. Other includes activity for Everus for ten months in 2024 compared to the full year in 2023 and Knife River activity for five months in 2023 compared to the full year in 2022.

Current wording

The Company completed the separations of Knife River on May 31, 2023, its former construction materials and contracting segment, and of Everus on October 31, 2024, its former construction services segment, into new independent publicly-traded companies. As a result of these separations, the historical results of operations for Knife River and Everus are shown in discontinued operations, net of tax, except for allocated general corporate overhead costs of the Company, which did not meet the criteria for discontinued operations and are reflected in Other. Also included in discontinued operations are certain strategic initiative costs associated with the separations of Knife River and Everus. Other includes activity for Everus for ten months in 2024 compared to the full year in 2023 and Knife River activity for five months in 2023.

Previous wording

2024 compared to 2023 The Company's consolidated earnings decreased $133.6 million primarily due to the absence of the Company's 2023 gain of $186.6 million related to the tax-free exchange of its retained shares in Knife River, partially offset by increased earnings at the pipeline and electric businesses.

Current wording

2025 compared to 2024 The Company's consolidated earnings decreased $90.7 million primarily due to the absence of income from discontinued operations in 2025, partially offset by increased earnings at the natural gas distribution business.

Previous wording

•The pipeline's earnings increase was driven by higher transportation volumes, primarily from growth projects placed in service in November 2023 and throughout 2024 and increased contracted volume commitments beginning February 2023. Higher storage-related revenue and a full year of new transportation and storage service rates in 2024 further drove the increase. The business also benefited from proceeds received from a customer settlement that was recorded in other income and a decrease in the Company's effective state income tax rate. The increase was offset in part by higher operation and maintenance expense primarily attributable to payroll-related costs and higher materials, contract services and pipeline safety fees. The business incurred higher depreciation and amortization expense due to growth projects placed in service as discussed earlier, which was partially offset by fully depreciated assets. The business also incurred higher interest expense largely as a result of higher debt balances and higher property taxes.

Current wording

•The pipeline's slight earnings increase was driven by growth projects placed in service throughout 2024 and in late 2025 and customer demand for short-term firm natural gas transportation contracts. Higher use of the company's interruptible natural gas transportation services further drove the increase. The increase was partially offset by higher operation and maintenance expense primarily attributable to payroll-related costs. The increase was further offset by the absence of $1.5 million, net of tax proceeds received in 2024 from a customer settlement as well as the absence of a benefit from an adjustment related to the Company's effective state income tax rate change. The business also incurred higher depreciation expense due to growth projects placed in service, as previously discussed, and higher property taxes in Montana.

Previous wording

•Other was impacted by the absence of the Company's 2023 gain of $186.6 million related to the tax-free exchange of its retained shares in Knife River. Partially offsetting the decrease in net income was lower operation and maintenance expense, largely a result of corporate overhead costs classified as continuing operations allocated to the construction materials business in 2023, which are not included in Other in 2024, and lower strategic initiative costs. Other also benefited from lower interest expense due to lower borrowings associated with funding strategic initiatives.

Current wording

•Other was impacted by the absence of the income from discontinued operations in 2025. Partially offsetting the decrease was lower operation and maintenance expense, largely a result of corporate overhead costs classified as continuing operations allocated to the construction services business in 2024, which are not included in Other in 2025.

Previous wording

Following are key financial and operating data for each of the Company's business segments. Also included are highlights on key growth strategies, projections and certain assumptions for the Company and its subsidiaries and other matters of the Company's business segments. Many of these highlighted points are "forward-looking statements." For more information, see Part I - Forward-Looking Statements. There is no assurance that the Company's projections, including estimates for growth and changes in earnings, will in fact be achieved. Please refer to assumptions contained in this section, as well as the various important factors listed in Item 1A - Risk Factors. Changes in such assumptions and factors could cause actual future results to differ materially from the Company's projections.

Current wording

The following are key financial and operating data for each of the Company's business segments. Highlights of key growth strategies, projections and certain assumptions for the Company and its subsidiaries, and other matters concerning the Company's business segments are included below. Many of these highlighted points are "forward-looking statements." For more information, see Part I - Forward-Looking Statements. There is no assurance that the Company's projections, including estimates for growth and changes in earnings, will in fact be achieved. Please refer to assumptions contained in this section, as well as the various important factors listed in Item 1A - Risk Factors. Changes in such assumptions and factors could cause actual future results to differ materially from the Company's projections.

Previous wording

Strategy and challenges The electric and natural gas distribution segments provide electric and natural gas distribution services to customers, as discussed in Items 1 and 2 - Business Properties. Both segments strive to be top performing utility companies with a commitment to customers and communities, operational excellence, returns focused initiatives and an employee driven culture. The segments provide safe, reliable, competitively priced and environmentally responsible energy service to customers while focusing on growth and expansion opportunities within and beyond its existing territories. The Company is focused on cultivating organic growth while managing operating costs and monitoring opportunities for these segments to retain, grow and expand their customer base through extensions of existing operations, including building and upgrading electric generation, transmission and distribution, and natural gas systems, and through selected acquisitions of companies and properties with similar operating and growth objectives at prices that will provide stable cash flows and an opportunity to earn a competitive return on investment. The continued efforts to create operational improvements and efficiencies across both segments promotes the Company's business integration strategy. The primary factors that impact the results of these segments are the ability to earn authorized rates of return; weather; climate change laws, regulations and initiatives; competitive factors in the energy industry; population growth; and economic conditions in the segments' service areas.

Current wording

Strategy and challenges The electric and natural gas distribution segments provide electric and natural gas distribution services to customers, as discussed in Item 1 - Business. Both segments strive to be top performing utilities and provide safe, reliable, competitively priced and environmentally responsible energy services to customers. The segments are focused on cultivating organic growth while managing operating costs and monitoring opportunities for these segments to retain, grow and expand their customer base through extensions of existing operations, including building and upgrading electric generation, transmission and distribution, and natural gas systems. The continued efforts to create operational improvements and efficiencies across both segments promotes the Company's business integration strategy. The primary factors that impact the results of these segments are the ability to earn authorized rates of return; weather; climate change laws, regulations and initiatives; competitive factors in the energy industry; population growth; and economic conditions in the segments' service areas.

Previous wording

The electric and natural gas distribution segments are subject to extensive regulation in the jurisdictions where they conduct operations with respect to costs, timely recovery of investments and permitted returns on investment. The Company is focused on modernizing utility infrastructure to meet the varied energy needs of both its customers and communities while ensuring the delivery of safe, reliable, affordable and environmentally responsible energy. The segments continue to invest in facility upgrades to be in compliance with existing and known future regulations. To assist in the reduction of regulatory lag in obtaining revenue increases to align with increased investments, tracking mechanisms have been implemented in certain jurisdictions. The Company also seeks rate adjustments for operating costs and capital investments, as well as reasonable returns on investments not covered by tracking mechanisms. For more information on the Company's tracking mechanisms and recent rate cases, see Items 1 and 2 - Business Properties and Item 8 - Note 20.

Current wording

The electric and natural gas distribution segments are subject to extensive regulation in the jurisdictions where they conduct operations with respect to costs, timely recovery of investments and permitted returns on investment. The Company is focused on modernizing utility infrastructure to meet the varied energy needs of both its customers and communities while working to deliver safe, reliable, affordable and environmentally responsible energy. The segments continue to invest in facility upgrades to be in compliance with existing and known future regulations. To assist in the reduction of regulatory lag in obtaining revenue increases to align with increased investments, tracking mechanisms have been implemented in certain jurisdictions. The Company also seeks rate adjustments for operating costs and capital investments, as well as reasonable returns on investments not covered by tracking mechanisms. For more information on the Company's tracking mechanisms and recent rate cases, see Item 1 - Business and Item 8 - Note 6.

Previous wording

To date, many states have enacted, and others are considering, mandatory clean energy standards requiring utilities to meet certain thresholds of renewable and/or carbon-free energy supply. Over the long-term, the Company expects overall electric demand to be positively impacted by increased electrification trends, including electric vehicle adoption, as a means to address economy-wide carbon emission concerns, data center growth and changing customer conservation patterns. Recently, MISO and NERC announced concerns with reliability of the electric grid due to rapid expansion of renewables and retirement of baseload resources such as coal and the uncertainty of adequate energy production during certain periods of time, while load growth has increased faster than expected. Montana-Dakota filed its 2024 IRP with the NDPSC on July 12, 2024. With MISO's filed changes in resources adequacy at FERC and the adoption of direct loss of load accreditation for generation resources around riskiest hours on the system versus peak load hours, Montana-Dakota is seeing the need to add additional capacity resources to its system in 2028 versus 2034 as identified in its previous IRP. The Company will continue to monitor the progress of these changes and assess the potential impacts they may have on its stakeholders, business processes, results of operations, cash flows and disclosures.

Current wording

To date, many states have enacted, and others are considering, mandatory energy standards requiring utilities to meet certain thresholds of renewable and/or carbon-free energy supply. Over the long-term, the Company expects overall electric demand to be positively impacted by increased electrification trends as a means to address economy-wide carbon emission concerns, large data center growth and changing customer conservation patterns. MISO and NERC announced concerns with reliability of the electric grid due to rapid expansion of renewables and retirement of baseload resources such as coal and the uncertainty of adequate energy production during certain periods of time, while load growth has increased faster than expected due to growth in the data center industry. Montana-Dakota filed its 2024 IRP with the NDPSC in July 2024. With MISO's filed changes in resources adequacy at FERC and the adoption of direct loss of load accreditation for generation resources around riskiest hours on the system versus peak load hours, Montana-Dakota identified the need to add additional capacity resources to its system by 2028 versus 2034 as identified in its previous IRP. The Company previously executed a PPA for 150 MW of output from Badger Wind Farm, which included the option to purchase a 49 percent ownership interest. With the closing now complete, the PPA has been reduced to 27.5 MW. The ownership stake in Badger Wind Farm reduced the Company's capacity and energy purchase requirements as identified in the 2024 IRP. The Company will continue to monitor the progress of these changes, including the impacts associated with the implementation of MISO's direct loss of load accreditation in 2028, and assess the potential impacts they may have on its stakeholders, business processes, results of operations, cash flows and disclosures.

Previous wording

Revenues are impacted by both customer growth and usage, the latter of which is primarily impacted by weather, as well as impacts associated with commercial and industrial slow-downs, including economic recessions, and energy efficiencies. Very cold winters increase demand for natural gas and to a lesser extent, electricity, while warmer than normal summers increase demand for electricity, especially among residential and commercial customers. Average consumption among both electric and natural gas customers has tended to decline as more efficient appliances and furnaces are installed, and as the Company has implemented conservation programs. Natural gas weather normalization and decoupling mechanisms in certain jurisdictions have been implemented to largely mitigate the effect that would otherwise be caused by variations in volumes sold to these customers due to weather and changing consumption patterns on the Company's distribution margins, as further discussed in Items 1 and 2 - Business Properties.

Current wording

Revenues are impacted by both customer growth and usage, the latter of which is primarily impacted by weather, as well as impacts associated with commercial and industrial slow-downs, including economic recessions, and energy efficiencies. Very cold winters increase demand for natural gas and to a lesser extent, electricity, while warmer than normal summers increase demand for electricity, especially among residential and commercial customers. Average consumption among both electric and natural gas customers has tended to decline as more efficient appliances and furnaces are installed, and as the Company has implemented conservation programs. Natural gas weather normalization and decoupling mechanisms in certain jurisdictions have been implemented to largely mitigate the effect that would otherwise be caused by variations in volumes sold to these customers due to weather and changing consumption patterns on the Company's distribution margins, as further discussed in Item 1 - Business.

Previous wording

In late summer and fall of 2023, electric fuel and purchased power prices increased across Montana-Dakota's integrated system. This was caused by transmission congestion in northwest North Dakota due to delays in additional SPP transmission line build-out, as well as additional load growth in the Bakken region. Electric fuel and purchased power prices remained elevated through January 2024. To assist in the recovery of the higher electric fuel and purchased power costs, Montana-Dakota filed waiver requests with the NDPSC and SDPUC, which were approved deferring the increased costs to the annual fuel clause adjustment. In Montana, the waiver request is filed monthly and was unopposed by the MTPSC. Montana-Dakota filed a complaint with FERC related to this issue on January 23, 2024. MISO also filed its own complaint with FERC against SPP on March 8, 2024. On September 10, 2024, FERC issued an order denying both Montana-Dakota and MISO's complaint regarding the issue. On October 10, 2024, Montana-Dakota and MISO filed with FERC for rehearing on FERC's decision to deny these complaints. Both rehearing requests were denied by operation of law on November 11, 2024. On January 2, 2025, Montana-Dakota filed a petition for review of the FERC decision with the United States Court of Appeals for the Eighth Circuit. MISO filed a petition for review of the FERC decision on January 8, 2025. On December 26, 2024, Montana-Dakota filed a request with the NDPSC for authorization to defer external legal expenses related to this congestion litigation and record those deferred expenses into a regulatory asset. Effective April 1, 2024, as approved by the NDPSC, Montana-Dakota started recovery in North Dakota of these increased costs over a period of two years rather than one year, which will lessen the impact to customers and allow more time for Montana-Dakota's FERC complaint to mature and have greater certainty of the outcome. In South Dakota and Montana, Montana-Dakota started recovery of these costs over a one-year period effective July 1, 2024.

Current wording

In the second half of 2023, electric fuel and purchased power prices increased across Montana-Dakota's integrated system and remained elevated through January 2024. This was caused by transmission congestion in northwest North Dakota due to delays in additional SPP transmission line build-out, as well as additional load growth in the Bakken region. To assist in the recovery of the higher electric fuel and purchased power costs, Montana-Dakota filed waiver requests with the NDPSC and SDPUC, deferring the increased costs to the annual fuel clause adjustment. In Montana, the waiver request is filed monthly and was unopposed by the MTPSC. Effective April 1, 2024, as approved by the NDPSC, Montana-Dakota started recovery in North Dakota of these increased costs over a period of two years rather than one year. In South Dakota and Montana, Montana-Dakota recovered these costs over a one-year period effective July 1, 2024. In July 2025, the NDPSC approved Montana-Dakota's request to defer external legal expenses related to this congestion litigation and record those deferred expenses into a regulatory asset. Montana-Dakota and MISO each filed a petition for review of the FERC decision with the Eighth Circuit with a decision expected in the first half of 2026.

Previous wording

The Company continues to proactively monitor and work with its manufacturers to reduce the effects of increased pricing and lead times on delivery of certain raw materials and equipment used in electric generation, transmission and distribution system and natural gas pipeline projects. Long lead times are attributable to increased demand for steel products from pipeline companies as they continue pipeline system safety and integrity replacement projects driven by PHMSA regulations, as well as delays in the manufacturing and shipping of electrical equipment and increased demand for electrical equipment due to regulatory activity and grid expansion. The Company has been able to minimize the effects by working closely with suppliers or obtaining additional suppliers, as well as modifying project plans to accommodate extended lead times and increased costs. The Company expects these delays and inflationary pressures to continue.

Current wording

The Company continues to proactively monitor and work with its manufacturers to reduce the effects of increased pricing and lead times on delivery of certain raw materials and equipment used in electric generation, transmission and distribution system and natural gas pipeline projects. Long lead times are attributable to increased demand for steel products from pipeline companies as they continue pipeline system safety and integrity replacement projects driven by PHMSA regulations, as well as delays in the manufacturing and shipping of electrical equipment and increased demand for electrical equipment due to regulatory activity and grid expansion. The Company has been able to minimize the effects by working closely with suppliers or obtaining additional suppliers, as well as modifying project plans to accommodate extended lead times and increased costs. The Company expects these delays to continue. Inflationary pressures have moderated but costs for goods and services remain high. The Company also continues to monitor the impact tariffs will have on its costs. Tariff increases on raw materials could negatively affect the Company's construction projects and maintenance work. For additional discussion regarding risks and uncertainties, see Item 1A - Risk Factors.

Previous wording

The ability to grow through acquisitions is subject to significant competition and acquisition premiums. In addition, the ability of the segments to grow their service territory and customer base is affected by regulatory constraints, the economic environment of the markets served, population changes and competition from other energy providers and fuel. The construction of new electric generating facilities, transmission lines and other service facilities is subject to increasing costs and lead times, extensive permitting procedures, and federal and state legislative and regulatory initiatives, which may necessitate increases in electric energy prices. As the industry continues to expand the use of renewable energy sources, the need for additional transmission infrastructure is growing. As part of MISO's long range transmission plan, in August 2022, the Company announced its intent to develop, construct and co-own JETx with Otter Tail Power Company in central North Dakota. On October 6, 2023, the FERC issued an order approving the Company's request for CWIP Incentive Rate and Abandoned Plant Incentive treatment on this project.

Current wording

The ability to grow through acquisitions is subject to significant competition and acquisition premiums. In addition, the ability of the segments to grow their service territory and customer base is affected by regulatory constraints, the economic environment of the markets served, population changes and competition from other energy providers and fuel. The construction of new electric generating facilities, transmission lines and other service facilities is subject to higher costs and long lead times for equipment, extensive permitting procedures, and federal and state legislative and regulatory initiatives, which may necessitate increases in electric energy prices. As the industry continues to expand the use of renewable energy sources, the need for additional transmission infrastructure is growing. As part of MISO's long range transmission plan, in August 2022, the Company announced its intent to develop, construct and co-own JETx with Otter Tail Power Company in central North Dakota. In October 2023, the FERC issued an order approving the Company's request for CWIP Incentive Rate and Abandoned Plant Incentive treatment on this project. Montana-Dakota and Otter Tail Power Company received approval of a Certificate of Public Convenience and Necessity from the NDPSC in November 2024 on this project. The route permit for the JETx line was filed with the NDPSC in August 2025. JETx is expected to be placed in service at the end of 2028.

Previous wording

2024 compared to 2023 Electric earnings increased $3.2 million as a result of:

Current wording

2025 compared to 2024 Electric earnings decreased $9.9 million as a result of:

Previous wording

▪Higher fuel and purchased power costs of $6.4 million recovered in customer rates and offset in expense, as described below.

Current wording

▪Higher fuel and purchased power costs of $17.8 million recovered in customer rates and offset in expense, as described below.

Previous wording

◦Partially offset by lower retail sales volumes of $2.4 million, driven primarily by lower residential volumes, largely due to cooler weather in the third quarter of the year. Although residential volumes were lower, there was a 25.5 percent increase in volumes overall, which was largely driven by the data center as previously discussed and further discussed in the outlook section.

Current wording

▪Higher retail sales volumes of $1.2 million, driven primarily by higher residential volumes, largely due to colder weather in the first quarter of the year, and higher commercial volumes from the data center as further discussed in the Outlook section.

Previous wording

•Electric fuel and purchased power increased $6.4 million, largely the result of higher commodity prices.

Current wording

•Electric fuel and purchased power increased $17.8 million, largely the result of higher retail sales volumes and higher commodity prices.

Previous wording

▪Increased depreciation of $2.2 million associated with higher property, plant and equipment balances, as a result of transmission projects placed in service to improve reliability and update aging infrastructure.

Current wording

•Depreciation and amortization increased $3.1 million, largely due to increased property, plant and equipment balances, as a result of transmission projects placed in service to improve reliability and update aging infrastructure.

Previous wording

•Taxes, other than income increased $900,000, largely as a result of higher payroll tax and higher property tax, primarily in Montana.

Current wording

•Taxes, other than income increased $1.2 million, largely as a result of higher property tax, primarily in Montana.

Previous wording

•Income tax benefit increased $1.4 million, primarily due to higher production tax credits due to higher wind production.

Current wording

•Income tax benefit increased $7.2 million, largely due to lower income before income taxes, and higher production tax credits of $2.5 million driven by higher wind production and wind farm repowers.

Previous wording

2023 compared to 2022 Natural gas distribution earnings increased $3.3 million as a result of:

Current wording

2025 compared to 2024: Natural gas distribution earnings increased $9.2 million as a result of:

Previous wording

▪Higher conservation revenues of $4.1 million that were offset in expense, as described below.

Current wording

▪Higher conservation revenues of $3.5 million, offset in expense, as described below.

Current wording

▪Higher basic service charges of $2.1 million due to customer growth.

Previous wording

▪Higher conservation-related costs of $4.1 million which are recovered in rates, as discussed above.

Current wording

▪Higher conservation-related costs, recovered in rates, as discussed above.

Current wording

▪Lower interest on regulatory deferral balances, primarily lower purchased gas cost deferral balances.

Previous wording

▪Higher interest income associated with RNG projects of $2.2 million.

Current wording

▪The absence of $2.2 million of interest income associated with prior year renewable natural gas projects.

Previous wording

•Income tax expense in continuing operations increased $1.9 million, largely due to higher income before income taxes, partially offset by permanent tax adjustments.

Current wording

•Income tax expense increased $1.6 million, largely the result of higher income before income taxes, partially offset by lower permanent tax adjustments.

Previous wording

Outlook In 2024, the utility business experienced rate base growth of 6.8 percent and expects these segments will grow rate base by approximately 7 percent to 8 percent annually over the next five years on a compound basis. Operations are spread across eight states where the Company expects customer growth to be higher than the national average. In 2024 and 2023, these segments experienced retail customer growth of approximately 1.4 percent and 1.3 percent, respectively, and the Company expects customer growth to continue to average 1 percent to 2 percent per year. This customer growth, along with system upgrades and replacements needed to supply safe and reliable service, will require investments in new and replacement electric and natural gas systems.

Current wording

Outlook In 2025, the utility business experienced rate base growth of 16.0 percent, which includes the purchase of its ownership stake in Badger Wind Farm. These segments grew rate base by 8.7 percent annually over the last five years on a compound basis and expects to invest approximately $2.5 billion of capital expenditures over the next five years. Operations are spread across eight states where the Company expects customer growth to be higher than the national average. In 2025 and 2024, these segments experienced retail customer growth of approximately 1.5 percent and 1.4 percent, respectively, and the Company expects customer growth to continue to average 1 percent to 2 percent per year. This customer growth, along with system upgrades and replacements needed to supply safe and reliable service, will require investments in new and replacement electric and natural gas systems.

Previous wording

These segments are exposed to energy price volatility and may be impacted by changes in oil and natural gas exploration and production activity. Rate schedules in the jurisdictions in which the Company's natural gas distribution segment operates contain clauses that permit the Company to file for rate adjustments for changes in the cost of purchased natural gas. Although changes in the price of natural gas are passed through to customers and have minimal impact on the Company's earnings, the natural gas distribution segment's customers benefit from lower natural gas prices through the Company's utilization of storage and fixed price contracts.

Current wording

These segments are exposed to energy price volatility and may be impacted by changes in oil and natural gas exploration and production activity. Rate schedules in the jurisdictions in which the Company's natural gas distribution segment operates contain clauses that permit the Company to file for rate adjustments for changes in the cost of purchased natural gas. Although changes in the price of natural gas are passed through to customers and have minimal impact on the Company's earnings, the natural gas distribution segment's customers may benefit through the Company's utilization of storage and fixed price contracts to help manage price volatility.

Previous wording

Existing and proposed emissions reduction plans from the EPA could require the owners of Coyote Station to incur significant new costs. The EPA's GHG and mercury emissions standards finalized in May 2024 would require additional pollution controls to operate beyond 2031 and 2027, respectively, with a potential extension to add pollution controls that may be granted. If the owners decide to incur such costs, the costs could, dependent on determination by state regulatory commissions on approval to recover such costs from customers, negatively impact the Company's results of operations, financial position and cash flows. On December 2, 2024, the EPA issued a final decision on the NDDEQ's state implementation plan, maintaining the proposed disapproval of the state's conclusion that no additional controls are warranted during this implementation period. The EPA did not issue a federal implementation plan in place of the state plan and would have two years from state plan disapproval to either propose a federal plan or approve a new state plan. Coyote Station co-owners filed a petition for review with the Eighth Circuit Court of Appeals on January 31, 2025, challenging EPA's NDDEQ state plan disapproval, and filed a petition for reconsideration with the EPA on February 6, 2025. The Company is one of four owners of Coyote Station and cannot make a unilateral decision on the plant's future; therefore, the Company could be negatively impacted by decisions of the other owners. The joint owners continue to collaborate in analyzing data and weighing decisions that impact the plant and its employees as well as each company's customers and communities served.

Current wording

The EPA's GHG and mercury emissions standards finalized in May 2024 would have required additional pollution controls for Coyote Station to operate beyond 2031 and 2027, respectively. In April 2025, the EPA granted a two year extension for Coyote Station to add pollution controls to comply with the mercury emissions standard. In June 2025, the EPA proposed rules to repeal both the mercury emissions standard and the electric generation GHG emissions standard. If the rules go into effect, it could require owners of Coyote station to incur significant new costs. These costs could, dependent on determination by state regulatory commissions on approval to recover such costs from customers, negatively impact the Company's results of operations, financial position and cash flows. In December 2024, the EPA issued a final decision on the NDDEQ's Regional Haze state implementation plan, maintaining the proposed disapproval of the state's conclusion that no additional controls are warranted during this implementation period. The EPA did not issue a federal implementation plan in place of the state plan and would have two years from the state plan disapproval to either propose a federal plan or approve a new state plan. Coyote Station co-owners filed a petition for review with the Eighth Circuit in January 2025, challenging EPA's NDDEQ state plan disapproval, and in February 2025, filed a petition for reconsideration with the EPA, which was granted in April 2025. In June 2025, the Eighth Circuit granted a request by the EPA to continue to hold the petition of review proceeding in abeyance so that the EPA could review the previous administration's findings and actions. In March 2025, the EPA announced the agency is restructuring the regulations for implementing the Regional Haze Program. Further, in October 2025, the EPA released an advanced notice of proposed rulemaking seeking input on restructuring the program with the intent to streamline regulatory requirements for states' visibility improvement obligations. The Company is one of four owners of Coyote Station and cannot make a unilateral decision on the plant's future; therefore, the Company could be negatively impacted by decisions of the other owners. The joint owners continue to collaborate in analyzing data and weighing decisions that impact the plant and its employees as well as each company's customers and communities served.

Previous wording

On March 4, 2023, the Company began to provide power for Applied Digital's data center near Ellendale, North Dakota under an interim electric service agreement approved by the NDPSC, and on June 6, 2023, the NDPSC unanimously approved the Company's electric service agreement request. At full capacity, the data center requires 180 megawatts of electricity, which is the equivalent of about 28 percent of the Company's generation portfolio. Applied Digital's load is purchased from the MISO market and does not impact other customers' power supply. On October 2, 2023, the Company filed with the NDPSC an electric service agreement request to serve an additional 225 megawatt data center load with Applied Digital in its service territory, which was approved on May 23, 2024. On September 5, 2024, the Company filed an amendment to the electric service agreement previously approved by the NDPSC, increasing the service provided from 225 megawatts to 350 megawatts, which was approved on February 5, 2025. A portion of the additional data center load is expected to be online in 2025.

Current wording

In March 2023, the Company began to provide power for Applied Digital's data center near Ellendale, North Dakota. At full capacity, the data center requires 180 MW of electricity, which is the equivalent of about 21 percent of the Company's generation portfolio. Applied Digital's load is purchased from the MISO market and does not impact other customers' power supply. An electric service agreement to serve an additional 350 MW data center load with Applied Digital in the Company's service territory was approved by the NDPSC. 100 MW of the additional data center load is expected to be fully online in the second quarter of 2026.

Previous wording

On August 5, 2024, the Company filed a request with the SDPUC seeking approval on an electric service agreement to provide up to 50 megawatts of electricity to a data center near Leola, South Dakota. Construction on the data center is scheduled to begin in the spring of 2025, pending delays due to the development of new local siting requirements for the data center.

Current wording

In August 2024, the Company filed a request with the SDPUC seeking approval on an electric service agreement to provide up to 50 MW of electricity to a data center near Leola, South Dakota. Construction of the data center and approval of the electric service agreement which had been pending development of new local siting requirements for data center loads by McPherson County in South Dakota, were effective August 5, 2025. Approval of the electric service agreement with the SDPUC is still pending filing an updated conditional use permit for the data center siting with McPherson County.

Previous wording

The Infrastructure Investment and Jobs Act, commonly known as the Bipartisan Infrastructure Law, was enacted in the fourth quarter of 2021 and is providing long-term opportunities by designating funds for investments such as upgrades to electric and grid infrastructure, transportation systems, and electric vehicle infrastructure. In addition, the IRA provides $369 billion in new funding for clean energy programs. These programs include new tax incentives for solar, battery storage and hydrogen development along with funding to expand the production of electric vehicles and the build out of infrastructure to support electric vehicles. The Company is pursuing various opportunities under the Grid Resilience and Innovative Partnerships Program, which is a part of the Infrastructure Investment and Jobs Act, and is also pursuing a biogas property at the Knott Landfill site in Bend, Oregon which may qualify for an investment tax credit and clean fuel production credits as part of the IRA. The Company will continue to monitor additional opportunities from these legislative items.

Current wording

The Infrastructure Investment and Jobs Act, commonly known as the Bipartisan Infrastructure Law, was enacted in the fourth quarter of 2021 designating funds for investments such as upgrades to electric and grid infrastructure, transportation systems, and electric vehicle infrastructure. In July 2025, the North Dakota Industrial Commission awarded the Company a grant award under the Grid Resilience and Innovative Partnerships Program, which is part of the Infrastructure Investment and Jobs Act. The funds from the award will be used by the Company to build a 46 kV transmission line that will connect the Merricourt Transmission Substation to a 46 kV line near Fredonia, North Dakota. In addition, the IRA provided new funding for clean energy programs. The Company continues to pursue various opportunities under the Grid Resilience and Innovative Partnerships Program, and is also pursuing a biogas property at the Knott Landfill site in Bend, Oregon which may qualify for an investment tax credit and clean fuel production credits as part of the IRA. As discussed previously, the Company has evaluated the OBBBA and does not expect a material impact as a result of this legislation.

Previous wording

•In May 2024, the EPA published four final rules, three of which will impose stricter standards on GHG emissions from existing coal-fired and new natural gas-fired generation units, require a further reduction of mercury emissions from coal-fired generation units, and impose additional regulations around the storage and management of coal ash.

Current wording

•In May 2024, the EPA published four final rules, three of which will impose stricter standards on GHG emissions from existing coal-fired and new natural gas-fired generation units, require a further reduction of mercury emissions from coal-fired generation units, and impose additional regulations around the storage and management of coal ash. In March 2025, the EPA announced reconsideration of the Electric Generation and Greenhouse Gas Rule, Mercury and Air Toxics Standards Rule, and Effluent Limitations Guidelines Rule. Comments on certain of these proposed rules were due in August 2025. If the rules were to remain as originally proposed and if the costs to comply with these rules are not fully recoverable from customers, they could have a material adverse effect on the Company's results of operations and cash flows.

Previous wording

On July 30, 2024, the ODEQ released the proposed new Climate Protection Program Rule. On November 21, 2024, the Oregon Environmental Quality Commission adopted the new Climate Protection Program Rule. Like the prior rule, natural gas companies are required to significantly reduce GHG emissions 50 percent below the baseline by 2035 and 90 percent below the baseline by 2050. Each year, ODEQ will distribute compliance instruments to the Company at no cost and will decline annually in step with the reduction from baseline. The first compliance period is three years, from 2025 to 2027, with compliance demonstrations required by December 9 of the year following the end of a compliance period. Compliance periods are two years in length thereafter. The Company intends to meet its obligations through surrendering no cost emissions allowances and will fill remaining compliance obligations by investing in additional customer conservation and energy efficiency programs, purchasing community climate investment credits, and purchasing low carbon fuels such as RNG. Cascade is evaluating customer bill impacts from the new rule.

Current wording

•In July 2024, the ODEQ published its proposed rules to create a new Climate Protection Program. The Oregon Environmental Quality Commission adopted the rules in November 2024. The Company intends to meet its obligations first through no-cost emissions allowances and will fill remaining compliance obligations by investing in additional customer conservation and energy efficiency programs, purchasing community climate investment credits, and acquiring environmental attributes from low-carbon fuel projects such as RNG. Compliance costs for these regulations are being recovered through customer rates. Due to the timing of regulatory recovery, future compliance obligation purchases could impact the Company's operating cash flow.

Previous wording

•The Washington SBCC on November 28, 2023 and December 12, 2023, adopted residential and commercial building code amendments that will significantly limit the use of natural gas for space and water heating in new and retrofitted commercial and multifamily buildings and proposed the review of similar restrictions in the future for residential buildings. These amendments came after previous, similar state building code amendments were stayed by the SBCC after legal challenge by Cascade, along with two other local natural gas distribution companies in Washington and a coalition of homeowners, builders, and suppliers. Cascade did not believe such revisions addressed the issues which existed in the initial amendments. On May 15, 2024, the Company filed a joint complaint seeking declaratory and injunctive relief under federal law against the Washington SBCC's adoption of the Washington State Energy Code.

Current wording

•The Washington SBCC in 2023 adopted residential and commercial building code amendments that will significantly limit the use of natural gas for space and water heating in new and retrofitted commercial and residential buildings. In May 2024, the Company filed a joint complaint seeking declaratory and injunctive relief under federal law against the Washington SBCC's adoption of the amended Washington State Energy Code. This complaint was dismissed by the federal district court. Petitioners have appealed this decision to the United States Court of Appeals for the Ninth Circuit. The Company's opening brief was filed in July 2025. Oral argument before a three-judge panel of the Ninth Circuit was held on February 10, 2026.

Showing the first 40 of 76 pairs. Open the source sections for the rest.

Rearranged current paragraphs (2)

Current report — wording carried from elsewhere

At December 31, 2025, the pension plans' projected benefit obligations exceeded these plans' assets by approximately $18.5 million. Pretax pension expense reflected in the Consolidated Statements of Income for the years ended

Current report — wording carried from elsewhere

Consequently, the Company's financial position or results of operations may be materially different when reported under different conditions or when using different assumptions in the application of the following critical accounting estimates.
Rearranged previous paragraphs (8)

Previous report — wording carried elsewhere

▪Higher fuel and purchased power costs of $15.4 million recovered in customer rates and offset in expense, as described below.

Previous report — wording carried elsewhere

◦Partially offset by increased depreciation of $1.2 million associated with higher property, plant and equipment balances, the result of transmission projects placed in service to improve reliability and update aging infrastructure.

Previous report — wording carried elsewhere

◦Partially offset by lower permanent tax adjustments.

Previous report — wording carried elsewhere

▪Higher software related expenses of $900,000.

Previous report — wording carried elsewhere

If the costs to comply with these rules are not fully recoverable from customers, they could have a material adverse effect on the Company's results of operations and cash flows.

Previous report — wording carried elsewhere

•In November 2023, the Line Section 15 Expansion project was placed in service and increased system capacity by 25 MMcf of natural gas per day.

Previous report — wording carried elsewhere

2023 compared to 2022 Pipeline earnings increased $11.6 million as a result of:

Previous report — wording carried elsewhere