A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.

FY2024 · Filed Feb 20, 2025

LNG$277.95-0.6%Stored close · as of Nov 6, 2026

What changed in Risk Factors?

Read the current filing

The baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.

Compared 153 previous paragraphs and 150 current paragraphs.

118 unchanged; 31 reworded; 1 added; 4 removed; 0 previous and 0 current paragraphs rearranged.

Tables are not compared: 0 previous and 0 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.

A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.

Added paragraphs (1)

Current report

Any inability to pay or increase dividends or distributions by us or our subsidiaries as a result of the foregoing restrictions could have a material adverse effect on our liquidity.
Removed paragraphs (4)

Previous report

Our subsidiaries’ inability to pay distributions to CQP or us as a result of the foregoing restrictions in the agreements governing their indebtedness may inhibit CQP’s ability to pay or increase distributions to us and its other unitholders or inhibit our access to cash flows from the CCL Project, which could have a material adverse effect on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.

Previous report

The IRA imposes a 15% CAMT effective in 2023, on an applicable corporation with average AFSI in excess of $1 billion for any three consecutive years preceding the current year. Cheniere expects to be an applicable corporation beginning in 2024. Based on the CAMT rules as currently enacted, the CAMT tax base would include any gains or losses arising from changes in fair value of our commodity derivatives that are recorded to our Consolidated Statements of Operations. Volatility in underlying commodity and financial markets could accelerate and cause volatility in our future cash tax payments, particularly in periods of significant commodity, currency or financial market variability. If the CAMT applies, we could be subject to an additional tax liability beyond the regular federal corporate tax liability, despite our federal net operating loss carryforwards, which could adversely impact our liquidity. Additionally, any implementing regulatory guidance related to the

Previous report

Our ability to utilize our net operating loss carryforwards and certain other tax attributes may be limited.

Previous report

As of December 31, 2023, our federal net operating loss (“NOL”) carryforwards were approximately $4.3 billion and not subject to expiration. We may experience an ownership change as a result of future changes in our stock ownership (some of which changes may not be within our control). If Cheniere undergoes an ownership change (generally defined as a greater than 50% cumulative change in the equity ownership of certain shareholders over a rolling three-year period) under Section 382 of the Internal Revenue Code, our ability to use our pre-ownership change NOL carryforwards to offset future taxable income may be limited. This, in turn, could materially delay our ability to use our NOLs to offset future taxable income and have an adverse effect on our future cash flows.
Reworded paragraphs (31)

Previous wording

An inability to source capital to supplement our available cash resources and existing credit facilities could cause us to have inadequate liquidity and could materially and adversely affect our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.

Current wording

An inability to source capital to supplement our available cash resources and existing credit facilities could cause us to have inadequate liquidity and could materially and adversely affect us.

Previous wording

As of December 31, 2023, we had, on a consolidated basis, $4.1 billion of cash and cash equivalents (of which $575 million was held by CQP), $459 million of restricted cash and cash equivalents (of which $56 million was held by CQP), a total of $7.6 billion of available commitments under our credit facilities and $23.9 billion of total debt outstanding (before unamortized discount and debt issuance costs). SPL, CQP, CCH and Cheniere operate with independent capital structures as further detailed in Note 11—Debt of our Notes to Consolidated Financial Statements. We incur, and will incur, significant interest expense relating to financing the assets at the Sabine Pass LNG Terminal and the Corpus Christi LNG Terminal, and we anticipate drawing on current committed facilities and/or incurring additional debt to finance the construction of the Corpus Christi Stage 3 Project, as well as the CCL Midscale Trains 8 & 9 Project and the SPL Expansion Project if a positive FID is made on these expansion projects. Our ability to fund our capital expenditures and refinance our indebtedness will depend on our ability to access additional project financing as well as the debt and equity capital markets. A variety of factors beyond our control could impact the availability or cost of capital, including domestic or international economic conditions, increases in key benchmark interest rates and/or credit spreads, the adoption of new or amended banking or capital market laws or regulations, lending institutions’ evolving policies on financing businesses linked to fossil fuels and the repricing of market risks and volatility in capital and financial markets. Our financing costs could increase or future borrowings or equity offerings may be unavailable to us or unsuccessful, which could cause us to be unable to pay or refinance our indebtedness or to fund our other liquidity needs. We also rely on borrowings under our credit facilities to fund our capital expenditures. If any of the lenders in the syndicates backing these facilities was unable to perform on its commitments, we may need to seek replacement financing, which may not be available as needed, or may be available in more limited amounts or on more expensive or otherwise unfavorable terms.

Current wording

As of December 31, 2024, we had, on a consolidated basis, $2.6 billion of cash and cash equivalents (of which $270 million was held by CQP), $552 million of restricted cash and cash equivalents (of which $109 million was held by CQP), a total of $7.7 billion of available commitments under our credit facilities and $23.1 billion of total debt outstanding (before unamortized discount and debt issuance costs). SPL, CQP, CCH and Cheniere operate with independent capital structures as further detailed in Note 10—Debt of our Notes to Consolidated Financial Statements. We incur, and will incur, significant interest expense relating to financing the assets at the Sabine Pass LNG Terminal and the Corpus Christi LNG Terminal, and we anticipate drawing on current committed facilities and/or incurring additional debt to finance the construction of the Corpus Christi Stage 3 Project, as well as the CCL Midscale Trains 8 & 9 Project and the SPL Expansion Project if a positive FID is made on these expansion projects. Our ability to fund our capital expenditures and refinance our indebtedness may depend on our ability to access additional project financing as well as the debt and equity capital markets. A variety of factors beyond our control could impact the availability or cost of capital, including domestic or international economic conditions, increases in key benchmark interest rates and/or credit spreads, the adoption of new or amended banking or capital market laws or regulations, lending institutions’ evolving policies on financing businesses linked to fossil fuels and the repricing of market risks and volatility in capital and financial markets. Our financing costs could increase or future borrowings or equity offerings may be unavailable to us or unsuccessful, which could cause us to be unable to pay or refinance our indebtedness or to fund our other liquidity needs. We also may rely on borrowings under our credit facilities to fund our capital expenditures. If any of the lenders in the syndicates backing these facilities was unable to perform on its commitments, we may need to seek replacement financing, which may not be available as needed, or may be available in more limited amounts or on more expensive or otherwise unfavorable terms.

Previous wording

Our subsidiaries may be restricted under the terms of their indebtedness from making distributions under certain circumstances, which may limit CQP’s ability to pay or increase distributions to us or inhibit our access to cash flows from the CCL Project and could materially and adversely affect us.

Current wording

We and our subsidiaries may be restricted under the terms of our and their indebtedness from paying dividends or distributions under certain circumstances, which could materially and adversely affect our liquidity.

Previous wording

The agreements governing our subsidiaries’ indebtedness restrict payments that our subsidiaries can make to CQP or us in certain events. For example, SPL is restricted from making distributions under agreements governing its indebtedness generally unless, among other requirements, appropriate reserves have been established for debt service using cash or letters of credit and a debt service coverage ratio of 1.25:1.00 is satisfied.

Current wording

The agreements governing our and our subsidiaries’ indebtedness contain customary terms and events of default and certain covenants that, among other things, may limit our and our subsidiaries’ ability to make certain investments or pay dividends or distributions. For example, CCH and SPL are restricted from making distributions under agreements governing their indebtedness generally unless, among other requirements, appropriate reserves have been established for debt service using cash or letters of credit and a historical and projected debt service coverage ratio of 1.25:1.00 is satisfied.

Previous wording

CCH is restricted from making distributions under agreements governing its indebtedness generally unless, among other requirements, appropriate reserves have been established for debt service using cash or letters of credit and a debt service coverage ratio of 1.25:1.00 is satisfied. In addition, prior to completion of the Corpus Christi Stage 3 Project, CCH is also required to confirm that it has sufficient funds, including senior debt commitments, equity funding and projected contracted cash flows from the fixed price component of its third party SPAs, to meet remaining expenditures required for the Corpus Christi Stage 3 Project in order to achieve completion by a certain specified date.

Current wording

In addition, prior to completion of the Corpus Christi Stage 3 Project, CCH is also required to confirm that it has sufficient funds, including senior debt commitments, equity funding and projected contracted cash flows from the fixed price component of its third party SPAs, to meet remaining expenditures required for the Corpus Christi Stage 3 Project in order to achieve completion by a certain specified date.

Previous wording

Our efforts to manage commodity and financial risks through derivative instruments, including our IPM agreements, could adversely affect our earnings reported under GAAP and our liquidity.

Current wording

Our use of derivative instruments, including our IPM agreements, to manage risks could adversely affect our earnings reported under GAAP and our liquidity.

Previous wording

We use derivative instruments to manage commodity, currency and financial market risks. The extent of our derivative position at any given time depends on our assessments of the markets for these commodities and related exposures. We currently account for our derivatives at fair value, with immediate recognition of changes in the fair value in earnings, as described in Note 2—Summary of Significant Accounting Policies of our Notes to Consolidated Financial Statements. Such valuations are primarily valued based on estimated forward commodity prices and are more susceptible to variability particularly when markets are volatile, which could have a significant adverse effect on our earnings reported under GAAP. For example, as described in Results of Operations in Item 7. Management’s Discussion and Analysis of Financial Condition and Results of Operations, our net income for the year ended December 31, 2022 included $5.7 billion of losses resulting from changes in the fair values of our derivatives, of which substantially all of such losses were related to commodity derivative instruments indexed to international LNG prices, mainly our IPM agreements.

Current wording

We use derivative instruments to manage certain risks, including commodity-related price risk. The extent of our derivative position at any given time depends on our assessment of risks and related exposures for these commodities. We currently account for our derivatives at fair value, with immediate recognition of changes in the fair value in earnings, as described in Note 2—Summary of Significant Accounting Policies of our Notes to Consolidated Financial Statements. Such valuations are primarily valued based on estimated forward commodity prices and are more susceptible to variability particularly when markets are volatile, which could have a significant adverse effect on our earnings reported under GAAP. For example, as described in Results of Operations in Item 7. Management’s Discussion and Analysis of Financial Condition and Results of Operations, our net income for the years ended December 31, 2024 and 2023 included $1.3 billion and $8.0 billion of gains, respectively, resulting from changes in the fair values of our derivatives (before tax and the impact of non-controlling interests), substantially all of which were related to commodity derivative instruments indexed to international LNG prices, mainly our IPM agreements.

Previous wording

In addition, our liquidity may be adversely impacted by the cash margin requirements of the commodities exchanges or the failure of a counterparty to perform in accordance with a contract. As of December 31, 2023 and 2022, we had collateral posted with counterparties by us of $18 million and $134 million, respectively, which are included in margin deposits in our Consolidated Balance Sheets.

Current wording

In addition, our liquidity may be adversely impacted by the cash margin requirements of the respective commodity exchanges or over-the-counter arrangements, or the failure of a counterparty to perform in accordance with a contract. As of December 31, 2024 and 2023, we had collateral posted with counterparties by us of $128 million and $18 million, respectively, which are included in margin deposits in our Consolidated Balance Sheets.

Previous wording

Additionally as of December 31, 2023, $2.1 billion of repurchase authority remained under our share repurchase program our Board had authorized. Our share repurchase program does not obligate us to acquire a specific number of shares during any period, and our decision to commence, discontinue or resume repurchases in any period will depend on the same factors that our Board may consider when declaring dividends, among others.

Current wording

Additionally as of December 31, 2024, $3.9 billion of repurchase authority remained under our share repurchase program our Board had authorized, which was increased in June 2024 by $4.0 billion through 2027. Our share repurchase program does not obligate us to acquire a specific number of shares during any period, and our decision to commence, discontinue or resume repurchases in any period will depend on the same factors that our Board may consider when declaring dividends, among others.

Previous wording

Weather events such as major hurricanes and winter storms have caused interruptions or temporary suspension in construction or operations at our facilities or caused minor damage to our facilities. Our risk of loss related to weather events or other disasters is limited by contractual provisions in our SPAs, which can provide under certain circumstances relief from operational events, and partially mitigated by insurance we maintain. Aggregate direct and indirect losses associated with the aforementioned weather events, net of insurance reimbursements, have not historically been material to our Consolidated Financial Statements, and we believe our insurance coverages maintained, existence of certain protective clauses within our SPAs and other risk management strategies mitigate our exposure to material losses. However, future adverse weather events and collateral effects, or other disasters such as explosions, fires, floods or severe droughts, could cause damage to, or interruption of operations at our terminals or related infrastructure, which could impact our operating results, increase insurance premiums or deductibles paid and delay or increase costs associated with the construction and development of the Liquefaction Projects or our other facilities. Our LNG terminal infrastructure and LNG facilities located in or near Corpus Christi, Texas and Sabine Pass, Louisiana are designed in accordance with requirements of 49 Code of Federal Regulations Part 193, Liquefied Natural Gas Facilities: Federal Safety Standards, and all applicable industry codes and standards.

Current wording

Weather events such as major hurricanes and winter storms have caused interruptions or temporary suspension in construction or operations at our facilities or caused minor damage to our facilities. Our risk of loss related to weather events or other disasters is limited by contractual provisions in our SPAs, which can provide under certain circumstances relief from operational events, and partially mitigated by insurance we maintain. Aggregate direct and indirect losses associated with the aforementioned weather events, net of insurance reimbursements, have not historically been material to our Consolidated Financial Statements, and we believe our insurance coverages maintained, existence of certain protective clauses within our SPAs and other risk management strategies mitigate our exposure to material losses. However, future adverse weather events and collateral effects, or other disasters such as explosions, fires, floods or severe droughts, could cause damage to, or interruption of operations at our terminals or related infrastructure, which could impact our operating results, increase insurance premiums or deductibles paid and delay or increase costs associated with the construction and development of our Liquefaction Projects or our other facilities. Our LNG terminal infrastructure and LNG facilities located in or near Corpus Christi, Texas and Sabine Pass, Louisiana are designed in accordance with requirements of 49 Code of Federal Regulations Part 193, Liquefied Natural Gas Facilities: Federal Safety Standards, and all applicable industry codes and standards.

Previous wording

Under the SPAs with our customers, we are required to make available to them a specified amount of LNG at specified times. The supply of natural gas to our Liquefaction Projects to meet our LNG production requirements timely and at sufficient quantities is critical to our operations and the fulfillment of our customer contracts. However, we may not be able to purchase or receive physical delivery of natural gas as a result of various factors, including non-delivery or untimely delivery by our suppliers, depletion of natural gas reserves within regional basins and disruptions to pipeline operations as described in the risk factor Disruptions to the third party supply of natural gas to our pipelines and facilities could have a material adverse effect on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects. Our risk is in part mitigated by the diversification of our natural gas supply and transportation across suppliers and pipelines, and regionally across basins, and additionally, we have provisions within our supplier contracts that provide certain protections against non-performance. Further, provisions within our SPAs provide certain protection against force majeure events. While historically we have not incurred significant or prolonged disruptions to our natural gas supply that have resulted in a material adverse impact to our operations, due to the criticality of natural gas supply to our production of LNG, our failure to purchase or receive physical delivery of sufficient quantities of natural gas under circumstances where we may not be protected could have a material adverse effect on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.

Current wording

Under the SPAs with our customers, we are required to make available to them a specified amount of LNG at specified times. The supply of natural gas to our Liquefaction Projects to meet our LNG production requirements timely and at sufficient quantities is critical to our operations and the fulfillment of our customer contracts. However, we may not be able to purchase or receive physical delivery of natural gas as a result of various factors, including composition changes in the quality of feed gas received from third parties, non-delivery or untimely delivery by our suppliers, depletion of natural gas reserves within regional basins and disruptions to pipeline operations as described in the risk factor Disruptions to the third party supply of natural gas to our pipelines and facilities could have a material adverse effect on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects. Our risk is in part mitigated by the diversification of our natural gas supply and transportation across suppliers and pipelines, and regionally across basins, and additionally, we have provisions within our supplier contracts that provide certain protections against non-performance. Further, provisions within our SPAs provide certain protection against force majeure events. While historically we have not incurred significant or prolonged disruptions to our natural gas supply that have resulted in a material adverse impact to our operations, due to the criticality of natural gas supply to our production of LNG, our failure to purchase or receive physical delivery of sufficient quantities of natural gas under circumstances where we may not be protected could have a material adverse effect on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.

Previous wording

Our investment decision on the Corpus Christi Stage 3 Project and any potential future expansion of LNG facilities, including the CCL Midscale Trains 8 & 9 Project and the SPL Expansion Project, relies on cost estimates developed initially through front end engineering and design studies. However, due to the size and duration of construction of an LNG facility, the actual construction costs may be significantly higher than our current estimates as a result of many factors, including but not limited to changes in scope, the ability of Bechtel Energy Inc. (“Bechtel”) and our other contractors to execute successfully under their agreements, changes in commodity prices (particularly nickel and steel), escalating labor costs and the potential need for additional funds to be expended to maintain construction schedules or comply with existing or future environmental or other regulations. As construction progresses, we may decide or be forced to submit change orders to our contractor that could result in longer construction periods, higher construction costs or both, including change orders to comply with existing or future environmental or other regulations. Additionally, our SPAs generally provide that the customer may terminate that SPA if the relevant Train does not timely commence commercial operations. As a result, any significant construction delay, whatever the cause, could have a material adverse impact on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.

Current wording

Our investment decision on the Corpus Christi Stage 3 Project and any potential future expansion of LNG facilities, including the CCL Midscale Trains 8 & 9 Project and the SPL Expansion Project, relies on cost estimates developed initially through front end engineering and design studies. However, due to the size and duration of construction of an LNG facility, the actual construction costs may be significantly higher than our current estimates as a result of many factors, including but not limited to changes in scope and the ability of Bechtel Energy Inc. (“Bechtel”) and our other contractors to execute successfully under their agreements. Although our major EPC contracts are fixed price, as construction progresses, we may decide or be forced to submit change orders to our contractor, including change orders to comply with existing or future environmental or other regulations. Any change orders could result in longer construction periods, higher construction costs, including increased commodity prices (particularly nickel and steel) and escalating labor costs, or both. Additionally, our SPAs generally provide that the customer may terminate that SPA if the relevant Train does not timely commence commercial operations. As a result, any significant construction delay, whatever the cause, could have a material adverse impact on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.

Previous wording

Significant increases in the cost of a liquefaction project beyond the amounts that we estimate could impact the commercial viability of the project as well as require us to obtain additional sources of financing to fund our operations until the applicable liquefaction project is fully constructed (which could cause further delays), thereby negatively impacting our business and limiting our growth prospects. While historically we have not experienced cost overruns or construction delays that have had a significant adverse impact on our operations, factors giving rise to such events in the future may be outside of our control and could have a material adverse effect on our current or future business, contracts, financial condition, operating results, cash flow, liquidity and prospects.

Current wording

Significant increases in the cost of a liquefaction project or significant construction delays could impact the commercial viability of the project as well as require us to obtain additional sources of financing to fund our operations until the applicable liquefaction project is fully constructed (which could cause further delays), thereby negatively impacting our business and limiting our growth prospects. While historically we have not experienced cost overruns or construction delays that have had a significant adverse impact on our operations, factors giving rise to such events in the future may be outside of our control and could have a material adverse effect on our current or future business, contracts, financial condition, operating results, cash flow, liquidity and prospects.

Previous wording

We sell a significant amount of our LNG under delivered at terminal (“DAT”) terms requiring delivery to international destinations. To fulfill our transportation requirements under these arrangements, including those under long term SPAs, we depend on the ability to secure chartered vessels often through long term lease arrangements. The construction and delivery of LNG vessels require significant capital and long construction lead times, and we may execute charters several years before the lease arrangements commence.

Current wording

We sell a significant amount of our LNG under DAT terms requiring delivery to international destinations. To fulfill our transportation requirements under these arrangements, including those under long term SPAs, we depend on the ability to secure chartered vessels often through long term lease arrangements. The construction and delivery of LNG vessels require significant capital and long construction lead times, and we may execute charters several years before the lease arrangements commence.

Previous wording

•disruptions to maritime transportation routes, such as the recent security situation in the Gulf of Aden and congestion at the Panama Canal resulting from decreased water levels caused by prolonged drought conditions; and

Current wording

•disruptions to maritime transportation routes, such as the security situation in the Gulf of Aden and congestion at the Panama Canal; and

Previous wording

•changes in regulatory, tax or other governmental policies regarding imported LNG, natural gas or alternative energy sources, which may reduce the demand for imported LNG and/or natural gas;

Current wording

•changes in regulatory, tax or other governmental policies regarding exported LNG, natural gas or alternative energy sources, which may reduce the demand for exported LNG and/or natural gas;

Previous wording

•adverse relative demand for LNG compared to other markets, which may decrease LNG imports from North America; and

Current wording

•adverse relative demand for LNG compared to other markets, which may decrease LNG exports from North America; and

Previous wording

As described in Market Factors and Competition, it is expected that global demand for natural gas and LNG will continue to increase as nations seek more abundant, reliable and environmentally cleaner fuel alternatives to alternative fossil fuel energy sources such as oil and coal. However, as a result of transitions globally from fossil-based systems of energy production and consumption to renewable energy sources, LNG may face increased competition from alternative, cleaner sources of energy as such alternative sources emerge. Additionally, LNG from the Liquefaction Projects also competes with other sources of LNG, including LNG that is priced to indices other than Henry Hub. Some of these sources of energy may be available at a lower cost than LNG from the Liquefaction Projects in certain markets. The cost of LNG supplies from the United States, including the Liquefaction Projects, may also be impacted by an increase in natural gas prices in the United States.

Current wording

As described in Market Factors and Competition in Items 1. and 2. Business and Properties, it is expected that global demand for natural gas and LNG will continue to increase as nations seek more abundant, reliable and environmentally cleaner fuel alternatives to alternative fossil fuel energy sources such as oil and coal. However, as a result of transitions globally from fossil-based systems of energy production and consumption to renewable energy sources, LNG may face increased competition from alternative, cleaner sources of energy as such alternative sources emerge. Additionally, LNG from the Liquefaction Projects also competes with other sources of LNG, including LNG that is priced to indices other than Henry Hub. Some of these sources of energy may be available at a lower cost than LNG from the Liquefaction Projects in certain markets. The cost of LNG supplies from the United States, including the Liquefaction Projects, may also be impacted by an increase in natural gas prices in the United States.

Previous wording

As described in Market Factors and Competition, we have contracted through our SPAs and IPM agreements approximately 95% of the total anticipated production from the Liquefaction Projects through the mid-2030s, excluding volumes from contracts with terms less than 10 years and volumes that are contractually subject to additional liquefaction capacity beyond what is currently in construction or operation. However, as a result of the factors described above and other factors, the LNG we produce may not remain a long term competitive source of energy internationally, particularly when our existing long term contracts begin to expire. Any significant impediment to the ability to continue to secure long term commercial contracts or deliver LNG from the United States could have a material adverse effect on our customers and on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.

Current wording

As described in General in Items 1. and 2. Business and Properties, we have contracted through our SPAs and IPM agreements approximately 95% of the total anticipated production from the Liquefaction Projects through the mid-2030s, excluding volumes from contracts with terms less than 10 years and volumes that are contractually subject to additional liquefaction capacity beyond what is currently in construction or operation. However, as a result of the factors described above and other factors, the LNG we produce may not remain a long term competitive source of energy internationally, particularly when our existing long term contracts begin to expire. Any significant impediment to the ability to continue to secure long term commercial contracts or deliver LNG from the United States could have a material adverse effect on our customers and on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.

Previous wording

A cyber attack involving our business, operational control systems or related infrastructure, or that of third party pipelines which supply the Liquefaction Facilities, could negatively impact our operations, result in data security breaches, impede the processing of transactions or delay financial or compliance reporting. These impacts could materially and adversely affect our business, contracts, financial condition, operating results, cash flow and liquidity.

Current wording

A cyber attack involving our business, operational control systems or related infrastructure, or that of third parties with whom we do business, including pipelines which supply our Liquefaction Projects, or an attack on our critical suppliers, could negatively impact our business or operations, result in data security breaches, impede the processing of transactions, delay financial or compliance reporting and potentially harm our reputation.

Previous wording

The pipeline and LNG industries are increasingly dependent on business and operational control technologies to conduct daily operations. We rely on control systems, technologies and networks to run our business and to control and manage our trading, marketing, pipeline, liquefaction and shipping operations. Cyber attacks on businesses have escalated in recent years, including as a result of geopolitical tensions, and use of the internet, cloud services, mobile communication systems and other public networks exposes our business and that of other third parties with whom we do business to potential cyber attacks, including third party pipelines which supply natural gas to our Liquefaction Facilities. For example, in 2021 Colonial Pipeline suffered a ransomware attack that led to the complete shutdown of its pipeline system for six days. Should a multiple of the third party pipelines which supply our Liquefaction Facilities suffer similar concurrent attacks, the Liquefaction Facilities may not be able to obtain sufficient natural gas to operate at full capacity, or at all. A cyber attack involving our business or operational control systems or related infrastructure, or that of third party pipelines with which we do business, could negatively impact our operations, result in data security breaches, impede the processing of transactions, or delay financial or compliance reporting. These impacts could materially and adversely affect our business, contracts, financial condition, operating results, cash flow and liquidity.

Current wording

The pipeline and LNG industries are increasingly dependent on business and operational control technologies to conduct daily operations. We rely on control systems, technologies and networks to run our business and to control and manage our trading, marketing, pipeline, liquefaction and shipping operations. Cyber attacks on businesses have escalated in recent years, including as a result of geopolitical tensions, and use of the internet, cloud services, mobile communication systems and other public networks exposes our business and that of other third parties with whom we do business to potential cyber attacks, including third party pipelines which supply natural gas to our Liquefaction Projects. For example, in 2021 Colonial Pipeline suffered a ransomware attack that led to the complete shutdown of its pipeline system for six days. Should multiple of the third party pipelines which supply our Liquefaction Projects suffer similar concurrent attacks, our Liquefaction Projects may not be able to obtain sufficient natural gas to operate at full capacity, or at all. A cyber attack involving our business or operational control systems or related infrastructure, or that of third parties pipelines with whom we do business, or an attack on our critical suppliers, could negatively impact our business or operations, result in data security breaches, impede the processing of transactions, delay financial or compliance reporting and potentially harm our reputation.

Previous wording

We are dependent upon the available labor pool of skilled employees. We compete with other energy companies and other employers to attract and retain qualified personnel with the technical skills and experience required to construct and operate our facilities and pipelines and to provide our customers with the highest quality service. We are also subject to the Fair Labor Standards Act, which governs such matters as minimum wage, overtime and other working conditions. A shortage in the labor pool of skilled workers, remoteness of our site locations, general inflationary pressures, changes in applicable laws and regulations or labor disputes could make it more difficult for us to attract and retain qualified personnel and could require an increase in the wage and benefits packages that we offer, thereby increasing our operating costs. In addition, we are also subject to increased competition for skilled workers from new entrants to the LNG market. Any increase in our operating costs could materially and adversely affect our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.

Current wording

We are dependent upon the available labor pool of skilled employees. We compete with other energy companies and other employers to attract and retain qualified personnel with the technical skills and experience required to construct and operate our facilities and pipelines and to provide our customers with the highest quality service. In the United States, we are also subject to the Fair Labor Standards Act, which governs such matters as minimum wage, overtime and other working conditions. A shortage in the labor pool of skilled workers, remoteness of our site locations, general inflationary pressures, changes in applicable laws and regulations or labor disputes could make it more difficult for us to attract and retain qualified personnel and could require an increase in the wage and benefits packages that we offer, thereby increasing our operating costs. In addition, we are also subject to increased competition for skilled workers from new entrants to the LNG market. Any increase in our operating costs could materially and adversely affect our business, contracts, financial condition, operating results, cash flow, liquidity and prospects.

Previous wording

Outbreaks of infectious diseases, such as COVID-19, at one or more of our facilities could adversely affect our operations.

Current wording

Outbreaks of infectious diseases, such as COVID-19, at one or more of our facilities could adversely affect our operations or business.

Previous wording

Our facilities at the Sabine Pass LNG Terminal and Corpus Christi LNG Terminal are critical infrastructure and continued to operate during the COVID-19 pandemic through our implementation of workplace controls and pandemic risk reduction measures. While the COVID-19 pandemic, including subsequent variants, had no adverse impact on our on-going operations, the risk of future variants and other infectious diseases is unknown. While we believe we can continue to mitigate any significant adverse impact to our employees and operations at our critical facilities related to the virus in its current form, the outbreak of a more potent variant or another infectious disease in the future at one or more of our facilities could adversely affect our operations.

Current wording

Our facilities at the Sabine Pass LNG Terminal and Corpus Christi LNG Terminal are critical infrastructure and continued to operate during the COVID-19 pandemic through our implementation of workplace controls and pandemic risk reduction measures. While the COVID-19 pandemic, including subsequent variants, had no adverse impact on our on-going operations, the risk of future variants and other infectious diseases is unknown and the outbreak of a more potent variant or another infectious disease in the future at one or more of our facilities could adversely affect our operations or business.

Previous wording

The design, construction and operation of interstate natural gas pipelines, LNG terminals, including the Liquefaction Projects, the CCL Midscale Trains 8 & 9 Project, the SPL Expansion Project and other facilities, as well as the import and export of LNG and the purchase and transportation of natural gas, are highly regulated activities. Approvals of the FERC and DOE under Section 3 and Section 7 of the NGA, as well as several other material governmental and regulatory approvals and permits, including several under the CAA and the CWA, are required in order to construct and operate an LNG facility and an interstate natural gas pipeline and export LNG.

Current wording

The design, construction and operation of interstate natural gas pipelines, LNG terminals, including the Liquefaction Projects, CCL Midscale Trains 8 & 9 Project, the SPL Expansion Project and other facilities, as well as the import and export of LNG and the purchase and transportation of natural gas, are highly regulated activities. Approvals of the FERC and DOE under Section 3 and Section 7 of the NGA, as well as several other material governmental and regulatory approvals and permits, including several under the CAA and the CWA, are required in order to construct and operate an LNG facility and an interstate natural gas pipeline and export LNG.

Previous wording

To date, the FERC has issued orders under Section 3 of the NGA authorizing the siting, construction and operation of the six Trains and related facilities of the SPL Project, the three Trains and related facilities of the CCL Project and the seven midscale Trains and related facilities for the Corpus Christi Stage 3 Project, as well as orders under Section 7 of the NGA authorizing the construction and operation of the Creole Trail Pipeline and the Corpus Christi Pipeline. In May 2023, certain subsidiaries of CQP entered the pre-filing review process with the FERC under the NEPA for the SPL Expansion Project and in March 2023, certain of our subsidiaries submitted an application with the FERC under the NGA for the CCL Midscale Trains 8 & 9 Project. To date, the DOE has also issued orders under Section 4 of the NGA authorizing SPL, CCL and the Corpus Christi Stage 3 Project to export domestically produced LNG. In January 2024, the Biden Administration announced a temporary pause on pending decisions on exports of LNG to non-FTA countries until the DOE can update the underlying analyses for authorizations. We do not believe such a pause will have a material adverse effect on our business, contracts, financial condition, operating results, cash flow, or liquidity. The CCL Midscale Trains 8 & 9 Project is currently our only project pending non-FTA export approval with the DOE, although such approval is first subject to the receipt of regulatory permit approval from the FERC, responsive to our formal application in March 2023. We would anticipate seeking non-FTA export authorization from the DOE on the SPL Expansion Project in the future, having entered the pre-filing review process with the FERC in May 2023. Additionally, we hold certificates under Section 7(c) of the NGA that grant us land use rights relating to the situation of our pipelines on land owned by third parties. If we were to lose these rights or be required to relocate our pipelines, our business could be materially and adversely affected.

Current wording

To date, the FERC has issued orders under Section 3 of the NGA authorizing the siting, construction and operation of the six Trains and related facilities of the SPL Project, the three Trains and related facilities of the CCL Project and the seven midscale Trains and related facilities for the Corpus Christi Stage 3 Project, as well as orders under Section 7 of the NGA authorizing the construction and operation of the Creole Trail Pipeline and the Corpus Christi Pipeline. In February 2024, certain of our subsidiaries submitted an application to the FERC under the NGA for authorization to site, construct and operate the SPL Expansion Project. In March 2023, certain of our subsidiaries submitted an application with the FERC under the NGA for the CCL Midscale Trains 8 & 9 Project, for which a positive Environmental Assessment from the FERC was received in June 2024. To date, the DOE has also issued orders under Section 4 of the NGA authorizing SPL, CCL and the Corpus Christi Stage 3 Project to export domestically produced LNG. We currently have the SPL Expansion Project and the CCL Midscale Trains 8 & 9 Project pending non-FTA export approval with the DOE. However, approval is first subject to the receipt of regulatory permit approval from the FERC, responsive to our formal applications. Additionally, we hold certificates under Section 7(c) of the NGA that grant us land use rights relating to the situation of our pipelines on land owned by third parties. If we were to lose these rights or be required to relocate our pipelines, our business could be materially and adversely affected.

Previous wording

Our business is and will be subject to extensive federal, state and local laws, rules and regulations applicable to our construction and operation activities relating to, among other things, air quality, water quality, waste management, natural resources and health and safety. Many of these laws and regulations, such as the CAA, the Oil Pollution Act, the CWA and the RCRA, and analogous state laws and regulations, restrict or prohibit the types, quantities and concentration of substances that can be released into the environment in connection with the construction and operation of our facilities, and require us to maintain permits and provide governmental authorities with access to our facilities for inspection and reports related to our compliance. In addition, certain laws and regulations authorize regulators having jurisdiction over the construction and operation of our LNG terminals, docks and pipelines, including FERC, PHMSA, EPA and the United States Coast Guard, to issue regulatory enforcement actions, which may restrict or limit operations or increase compliance or operating costs. Violation of these laws and regulations could lead to substantial liabilities, compliance orders, fines and penalties, difficulty obtaining and maintaining permits from regulatory agencies or increased capital expenditures that could have a material adverse effect on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects. Federal and state laws impose liability, without regard to fault or the lawfulness of the original conduct, for the release of certain types or quantities of hazardous substances into the environment. As the owner and operator of our facilities, we could be liable for the costs of cleaning up hazardous substances released into the environment at or from our facilities and for resulting damage to natural resources.

Current wording

Our business is and will be subject to extensive federal, state and local laws, rules and regulations applicable to our construction and operation activities relating to, among other things, air quality, water quality, waste management, natural resources and health and safety. Many of these laws and regulations, such as the CAA, the Oil Pollution Act, the CWA and the RCRA, and analogous state laws and regulations, restrict or prohibit the types, quantities and concentration of substances that can be released into the environment in connection with the construction and operation of our facilities, and require us to maintain permits and provide governmental authorities with access to our facilities for inspection and reports related to our compliance. In addition, certain laws and regulations authorize regulators having jurisdiction over the construction and operation of our LNG terminals, marine berths and pipelines, including FERC, PHMSA, EPA and the United States Coast Guard, to issue regulatory enforcement actions, which may restrict or limit operations or increase compliance or operating costs. Violation of these laws and regulations could lead to substantial liabilities, compliance orders, fines and penalties, difficulty obtaining and maintaining permits from regulatory agencies or increased capital expenditures that could have a material adverse effect on our business, contracts, financial condition, operating results, cash flow, liquidity and prospects. Federal and state laws impose liability, without regard to fault or the lawfulness of the original conduct, for the release of certain types or quantities of hazardous substances into the environment. As the owner and operator of our facilities, we could be liable for the costs of cleaning up hazardous substances released into the environment at or from our facilities and for resulting damage to natural resources.

Previous wording

The EPA has finalized or proposed multiple GHG regulations that impact our assets and supply chain. On December 2, 2023, the EPA issued final rules to reduce methane and VOC emissions from new, existing and modified emission sources in the oil and gas sector. These regulations will require monitoring of methane and VOC emissions at our compressor stations. Further, the IRA includes a charge on methane emissions above certain emissions thresholds employing empirical emissions data that will apply to our facilities beginning in calendar year 2024. In January 2024, the EPA issued a proposed rule to impose and collect methane emissions charges authorized under the IRA. In addition, other international, federal and state initiatives may be considered in the future to address GHG emissions through treaty commitments, direct regulation, market-based regulations such as a GHG emissions tax or cap-and-trade programs or clean energy or performance-based standards. Such initiatives could affect the demand for or cost of natural gas, which we consume at our terminals, or could increase compliance costs for our operations.

Current wording

The EPA has finalized or proposed multiple GHG regulations that impact our assets and supply chain. On December 2, 2023, the EPA issued final rules to reduce methane and VOC emissions from new, existing and modified emission sources in the oil and gas sector. These regulations require monitoring of methane and VOC emissions at our compressor stations. Further, the IRA includes a charge on methane emissions above certain emissions thresholds employing empirical emissions data that applied to our facilities beginning in calendar year 2024. On November 12, 2024, the EPA finalized a rule to impose and collect methane emissions charges authorized under the IRA. In addition, other international, federal and state initiatives may be considered in the future to address GHG emissions through treaty commitments, direct regulation, market-based regulations such as a GHG emissions tax or cap-and-trade programs or clean energy or performance-based standards. Such initiatives could affect the demand for or cost of natural gas, which we consume at our terminals, or could increase compliance costs for our operations.

Previous wording

On February 28, 2022, the EPA removed a stay of formaldehyde standards in the NESHAP Subpart YYYY for stationary combustion turbines located at major sources of HAP emissions. Owners and operators of lean remix gas-fired turbines and diffusion flame gas-fired turbines at major sources of HAP that were installed after January 14, 2003 were required to comply with NESHAP Subpart YYYY by March 9, 2022 and demonstrate initial compliance with those requirements by September 5, 2022. We do not believe that our operations, or the construction and operations of our liquefaction facilities, will be materially and adversely affected by such regulatory actions.

Current wording

In 2022, the EPA removed a stay of formaldehyde standards in the NESHAP Subpart YYYY for stationary combustion turbines located at major sources of HAP emissions. Owners and operators of lean remix gas-fired turbines and diffusion flame gas-fired turbines at major sources of HAP that were installed after January 14, 2003 were required to comply with NESHAP Subpart YYYY beginning in 2022.

Previous wording

We are subject to various types of tax arising from normal business operations in the jurisdictions in which we operate and transact. Any changes to local, domestic or international tax laws and regulations, or their interpretation and application, including the Organization for Economic Cooperation and Development’s (the“OECD”) adopted model rules for a 15% global minimum tax (commonly referred to as Pillar Two), could affect our tax obligations, profitability and cash flows in the future. In addition, tax rates in the various jurisdictions in which we operate may change significantly due to political or economic factors beyond our control. We continuously monitor and assess proposed tax legislation that could negatively impact our business.

Current wording

We are subject to various types of tax arising from normal business operations in the jurisdictions in which we operate and transact. Any changes to local, domestic or international tax laws and regulations, or their interpretation and application, including those related to tariffs and duties, could affect our obligations, profitability and cash flows in the future. In addition, tax rates in the various jurisdictions in which we operate may change significantly due to political or economic factors beyond our control. We continuously monitor and assess proposed tax legislation that could negatively impact our business.

Previous wording

CAMT issued by the U.S. Department of Treasury and the Internal Revenue Service in the future could potentially affect both the timing and amount of our CAMT cash tax payments.

Current wording

We became subject to the 15% CAMT in 2024. On September 12, 2024, the U.S. Department of Treasury and the Internal Revenue Service (the“IRS”) released proposed regulations relating to the application and implementation of the CAMT. The proposed regulations address a wide range of topics relating to the operation of CAMT; however, significant uncertainty continues to exist regarding many of the operative implementing provisions and regulatory guidance related to the CAMT issued in the future could affect both the timing and amount of our CAMT liability.