A company's report for each of its first three quarters. The financial statements are not audited. It shows how the business has moved since the last annual report, and what management says changed.

Mar 31, 2024 · Filed May 3, 2024

LNG$277.95-0.6%Stored close · as of Nov 6, 2026
See the whole filing, with its images and exhibits

Notes to Consolidated Financial Statements

NOTE 1—NATURE OF OPERATIONS AND BASIS OF PRESENTATION

We operatetwo natural gas liquefaction and export facilities located in Cameron Parish, Louisiana at Sabine Pass and near Corpus Christi, Texas (respectively, the“Sabine Pass LNG Terminal” and“Corpus Christi LNG Terminal”).

CQP owns the Sabine Pass LNG Terminal, which has natural gas liquefaction facilities consisting ofsix operational Trains, for a total production capacity of approximately 30 mtpa of LNG (the“SPL Project”). The Sabine Pass LNG Terminal also has operational regasification facilities that include five LNG storage tanks, vaporizers andthree marine berths. We also own and operate a 94-mile natural gas supply pipeline that interconnects the Sabine Pass LNG Terminal with several large interstate and intrastate pipelines (the“Creole Trail Pipeline”). As of March 31, 2024, we owned 100% of the general partner interest, a 48.6% limited partner interest and 100% of the incentive distribution rights of CQP.

The Corpus Christi LNG Terminal currently hasthree operational Trains for a total production capacity of approximately 15 mtpa of LNG, three LNG storage tanks andtwo marine berths. Additionally, we are constructing an expansion of the Corpus Christi LNG Terminal (the“Corpus Christi Stage 3 Project”) consisting ofseven midscale Trains with an expected total production capacity of over 10 mtpa of LNG. We also own a 21.5-mile natural gas supply pipeline that interconnects the Corpus Christi LNG Terminal with several large interstate and intrastate natural gas pipelines (the“Corpus Christi Pipeline” and together with the existing assets at the Corpus Christi LNG Terminal and the Corpus Christi Stage 3 Project, the“CCL Project”).

We are pursuing expansion projects to provide additional liquefaction capacity at the SPL Project and the CCL Project (collectively, the“Liquefaction Projects”), and we have commenced commercialization to support the additional liquefaction capacity associated with these potential expansion projects. The development of these sites or other projects, including infrastructure projects in support of natural gas supply and LNG demand, will require, among other things, acceptable commercial and financing arrangements before we make a positive FID.

Basis of Presentation

The accompanying unaudited Consolidated Financial Statements of Cheniere have been prepared in accordance with GAAP for interim financial information and in accordance with Rule 10-01 of Regulation S-X and reflect all normal recurring adjustments which are, in the opinion of management, necessary for a fair statement of the financial results for the interim periods presented. Accordingly, these Consolidated Financial Statements do not include all of the information and footnotes required by GAAP for complete financial statements and should be read in conjunction with the Consolidated Financial Statements and accompanying notes included in ourannual report on Form 10-K for the fiscal year ended December 31, 2023.