Item 1A. Risk Factors
There have been no material changes to the Company’s “Risk Factors” previously disclosed in Part I, Item 1A of our Annual Report
on Form 10-K for the year ended December 31, 2025, except as provided below.
We have limited historical experience as an operator of development programs.
We have initiated an operated development program which will require us to devote additional financial, technical and operational
resources to drilling and completion activities. Development activities generally require us to commit capital substantially in advance
of realizing production and cash flows, which may increase the variability of returns compared to our historical acquisition strategy.
Although we have drilled wells in various basins in the past and we have highly skilled personnel with significant drilling and
completion experience through prior acquisitions, including our Chief Operating Officer, who previously oversaw the drilling program
at Maverick Natural Resources, our historical business model has primarily focused on the acquisition, optimization and operation of
existing producing assets.
Success in development programs depends upon effective well planning, capital allocation, execution of drilling and completion
operations, reservoir evaluation, leasing, permitting, and project management. Executing these operations will require us to engage
and rely upon drilling contractors, completion crews and other oilfield services providers, whose availability, performance and pricing
are outside our control. Our development activities may not achieve expected results, and our returns could be adversely affected if
development costs increase, reserve estimates are revised downward, or wells fail to perform as anticipated. In addition, we cannot
provide assurance that unproved property acquired by us will be profitably developed, that wells drilled in connection with our
development activities will be productive, or that we will recover all or any portion of our investment in such unproved property or
wells.
Our development activities are subject to risks and uncertainties that are not present, or are present to a lesser degree, in our
existing producing asset base.
Historically, a substantial portion of our business has consisted of acquiring and operating existing producing assets. As we increase
our investment in drilling and development activities, we are exposed to additional risks, including:
dry holes, or wells that are productive but do not produce sufficient volumes to recover drilling and completion and operating
costs, or to achieve targeted returns;
drilling or completion delays, or the curtailment or cancellation of planned activity;
cost overruns and increases in drilling and completion costs;
shortages of or delays in obtaining qualified personnel or equipment, including rigs, pressure pumping crews, tubulars, sand,
water, chemicals and other equipment or critical services;
unexpected geological conditions;
drilling hazards and mechanical failures;
well control incidents, blowouts, fires and environmental events;
leasing or title problems;
delays in obtaining permits and regulatory approvals, and environmental, health and safety requirements applicable to drilling
and completion operations;
adverse weather and surface access constraints;
inability to secure or dispose of water used in drilling and completion operations; and
| Table of Contents | Form 10-Q | Diversified Energy Company |
|---|
insufficient takeaway, gathering or processing capacity.
Any of these events may result in increases in costs, delays in production, lower-than-expected recoveries, impairment of capital
invested in development projects and reduced returns.
Estimates of reserves, drilling inventory and future development opportunities are inherently uncertain and may prove to be
inaccurate.
The identification of drilling locations and estimates of reserves, estimated ultimate recovery, production profiles and future economic
returns depend upon complex geological, geophysical, engineering and economic analyses. These analyses require assumptions
regarding reservoir characteristics, hydrocarbon recovery, well performance, commodity prices, capital costs and operating expenses.
In evaluating undeveloped acreage, we may rely on seismic data, well logs, core information, production data from offset operators,
geologic models, type curves and other technical information. The interpretation of such information is inherently uncertain.
Actual drilling results may differ materially from our expectations. Wells that we believe are commercially attractive based on seismic
interpretation or geologic analysis may fail to achieve anticipated production rates, recoveries or economic returns. New information
obtained through drilling and production activities may require us to revise reserve estimates, development plans, drilling inventories
and expected future cash flows.
Because drilling and completion occurs over an extended period, the economics of our development activities are subject to changes in
commodity prices between the time we commit capital and the time any resulting production is sold. If we are unable to execute
drilling and completion programs successfully, such failure could materially and adversely affect our business, results of operations,
and financial condition.