Skip to main content

CONSTELLATION ENERGY GENERATION LLC

For the period ended Dec 31, 2025. Filed Feb 24, 2026.

View on SEC.gov

About this filing

A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.

FY2025 · Filed Feb 24, 2026

CEG$276.09+10.5%Stored close · as of Nov 9, 2026

Extracted filing text, with the paragraph anchors used by the comparison.

See the whole filing, with its images and exhibits
Contents

3. Regulatory Matters

  1. Regulatory Matters

The following matters below discuss the status of our material regulatory and legislative proceedings.

New England Regulatory Matters

Mystic Units 8 and 9 Cost of Service Agreement. In December 2018, FERC issued an order accepting a cost of service agreement for Mystic Units 8 and 9 for the period between June 1, 2022 to May 31, 2024. The agreement preserved the two gas-fired electric generating units for the period while allowing the Mystic units to recover their costs of operating, including a substantial portion of the costs associated with the adjacent EMT. Upon the expiration of the agreement on May 31, 2024, the two generating units retired.

The Mystic COS required an annual process whereby we identified and supported our projected costs under the agreement and/or true-up previous projections to the actual costs incurred. Interested parties then had the opportunity to challenge our filings. All proceedings related to the annual files or outstanding matters related to the Mystic COS have been settled and approved by FERC. The settlements did not have a material financial impact on our consolidated financial statements.

Federal Regulatory Matters

One Big Beautiful Bill Act of 2025. In July 2025, the OBBBA was signed into law, which, among other things, permanently extends key provisions of the 2017 Tax Cuts and Jobs Act, including full bonus depreciation and immediate deduction of research and development expenses. In addition, the OBBBA preserves transferability and certain federal tax credits from the IRA, specifically, 45U for existing nuclear plants through 2032 and 45Y for new nuclear projects, including uprates, restarts, and new reactors, through 2035, while enhancing the credit to allow advanced nuclear facilities to qualify for the energy communities bonus adder, subject to eligibility requirements. As it relates to both 45U and 45Y, certain foreign entity of concern rules must be met to qualify for the respective credits. Overall, the OBBBA reinforces the long-term economic viability of our nuclear generation assets. While the provisions of the OBBBA resulted in acceleration of cash benefits of approximately $200 million, the impact of these provisions recognized in the year ended December 31, 2025 was not material to our results of operations.

Note 3 — Regulatory Matters

Operating License Renewals

Conowingo Hydroelectric Project. In 2012, we submitted an application to FERC for a new license for the Conowingo Hydroelectric Project (Conowingo). In connection with our efforts to obtain a water quality certification pursuant to Section 401 of the Clean Water Act (401 Certification) from MDE for Conowingo, we had been working with MDE and other stakeholders to resolve water quality licensing issues, including: (1) water quality, (2) fish habitat, and (3) sediment.

In 2019, we and MDE filed with FERC a Joint Offer of Settlement (Offer of Settlement) that would resolve all outstanding issues relating to the 401 Certification. FERC subsequently issued a new 50-year license for Conowingo, effective March 1, 2021. Several environmental groups appealed FERC’s ruling to the U.S. Court of Appeals for the D.C. Circuit. The court of appeals issued a decision vacating FERC’s decision to grant Conowingo its license renewal and sending the matter back to FERC for further proceedings. Upon issuance of the mandate from the U.S. Court of Appeals for the D.C. Circuit, we began operating under an annual license, which renews automatically, containing the same terms as the license that was in effect prior to the 2021 FERC order. MDE informed us that as a result of the U.S. Court of Appeals decision, MDE would be resuming its administrative reconsideration of the 401 Certification.

In September 2025, we reached a settlement agreement with MDE and the other parties to the MDE reconsideration proceeding, Lower Susquehanna Riverkeeper Association, and Waterkeepers Chesapeake, which resolves all outstanding issues relating to the 401 Certification. As a result, MDE issued a Revised Water Quality Certification, which is needed for FERC to move forward with the issuance of a new 50-year license. The Revised Water Quality Certification and accompanying settlement agreement provide for a modified operational flow regime, funding for water quality and resiliency projects, commitments for trash and debris removal, fish and eel passage improvements, funding for freshwater mussel restoration and control of invasive species like snakeheads and blue catfish, and funds to support additional studies on dredging and related activities. Our commitments under the various provisions of this settlement are not effective unless and until FERC approves and issues the new license. The terms of this settlement have no impact on the prior settlement agreement with the DOI.

The financial impact of this settlement and other commitments related to this renewal are estimated to be $15 million to $20 million per year, on average, recognized over the term of the 50-year renewal, inclusive of capital and operating costs. The actual timing and amount of the majority of these costs are not currently fixed and will vary from year to year throughout the life of the new license. We cannot currently predict when FERC will issue the new license. Depreciation provisions continue to assume operation through 2071 given our expectation that a 50-year license will be issued.

Peach Bottom Units 2 and 3. In March 2020, the NRC approved a second 20-year license renewal for Peach Bottom Units 2 and 3. As a result, Peach Bottom Units 2 and 3 were granted the authority to operate through 2053 and 2054, respectively.

Notwithstanding its 2020 approval, in February 2022, the NRC took action to modify Peach Bottom's subsequently renewed licenses in response to a request for hearing that the NRC had not previously adjudicated. In its February 2022 decision, the NRC reversed itself and concluded that the previous environmental review required by the National Environmental Policy Act (NEPA) for the Peach Bottom subsequently renewed licenses was incomplete because it did not adequately address environmental impacts resulting from renewing the units’ licenses for an additional 20 years. As a result, the NRC undertook a rulemaking to modify its regulations and guidance to specifically address environmental impacts during the period of subsequent license renewal. In addition, the NRC modified the expiration dates for the Peach Bottom licenses from 2053 and 2054 to 2033 and 2034, respectively, pending the completion of the updated NEPA analysis.

In September 2025, the NRC completed its environmental impact review of Peach Bottom Units 2 and 3, restoring the expiration dates of the respective operating licenses to 2053 and 2054, consistent with current accounting estimates utilized for both depreciation and ARO assumed retirement dates.

ContentsView on SEC.gov

The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.