Item 1. Business

Overview

Net Power is an energy technology company that has developed a novel power generation system (which we refer to as the “Net Power Cycle”) designed to produce reliable and affordable electricity from natural gas while capturing virtually all atmospheric emissions. Net Power was founded in 2010 and methodically progressed the technology from a theoretical concept to reality with the construction and commissioning of the Company’s demonstration facility in La Porte, Texas (the “Demonstration Plant”). The Net Power Cycle is designed to inherently capture CO 2 while producing virtually no air pollutants such as SOX, NOX, and other particulates. It is configurable to a wide range of local altitude, humidity, and ambient temperatures, all of which can facilitate project siting and operation in a variety of climates. It can operate as a traditional baseload power plant, providing reliable electricity to the grid at capacity factors targeted to be above 90%. It can also complement intermittent renewables, providing clean dispatchable electricity that can be dispatched on demand at the request of power grid operators and according to market needs, while delivering substantial improvements in operability, affordability, and environmental performance as compared to alternative technologies for power generation. It can leverage existing natural gas infrastructure and can avoid issues of generation capacity and grid transmission overbuild created by other technologies, helping to further reduce system-wide decarbonization costs.

The Net Power Cycle is designed to achieve clean, reliable, and affordable electricity generation through Net Power’s patented highly recuperative oxy-combustion process. This process involves the combination of two technologies:

Oxy-combustion, a clean heat generation process in which fuel is mixed with oxygen such that the resulting byproducts from combustion consist of only water and pure CO 2; and

Supercritical CO 2(sCO 2) power cycle, a closed or semi-closed loop process that replaces the air or steam used in most power cycles with recirculating CO 2 at high pressure, producing power by expanding sCO 2 continuously through a turbo expander.

In the Net Power Cycle, CO 2 produced in oxy-combustion is immediately captured in a sCO 2 cycle that produces electricity. As CO 2 is added through oxy-combustion and recirculated, excess captured CO 2 is siphoned from the cycle at high purity for export to permanent storage or utilization.

The Net Power Cycle was first demonstrated at our 50 MWth Demonstration Plant in La Porte, Texas, for which construction commenced in 2016 and testing began in 2018. We conducted three testing campaigns over three years and the facility was ultimately synchronized to the Texas grid in the fall of 2021. Through these tests, we achieved technology validation, reached critical operational milestones, and accumulated over 1,500 hours of total facility runtime. During 2024, we made significant upgrades to the Demonstration Plant in preparation for validation testing of commercial-scale turbo expander components. The first of four planned phases of this equipment validation program commenced in late 2024 and is expected to progress over the next three years.

Net Power’s primary business model is to license its technology to customers to enable them to build, own, and operate facilities that utilize the Net Power Cycle. We plan to offer multiple plant designs, including a large utility-scale plant that can generate up to 300 MW net electric output capacity, as well as a smaller, industrial-scale plant that can generate 25-115 MW net electric output capacity. We are actively advancing the utility-scale program and intend to commence the industrial-scale program in the future. The technology is supported by a portfolio of 485 issued patents (as of December 31, 2024) in-licensed on an exclusive, irrevocable basis (in the applicable field) from 8 Rivers as well as significant know-how and trade secrets generated through experience at the Demonstration Plant and from engineering, design, and development of our first utility-scale plant. Net Power’s first-generation utility-scale design (which we refer to as Gen1U) is expected to be a 550 MWth power plant, targeting a CO 2 capture rate of 97% or greater and net LHV efficiency of up to 50% for later Gen1U units. Given the nascent nature of this technology, early Gen1U deployments are focused on ensuring a safe, clean, and reliable system targeting a net LHV efficiency of approximately 45% after incorporating learnings from operations of our early plants. Net Power intends to incorporate learnings from early deployments to drive improvements in future plants, including increases in net efficiency and reductions in costs to build and operate the plants.

Over the next several years, Net Power plans to conduct additional research and equipment validation testing campaigns at its Demonstration Plant and work to develop its first utility-scale plant (“SN1”). Net Power began purchasing initial long-lead materials for SN1 in 2024 with the intention of locating SN1 in the Permian Basin of West Texas (“Project Permian”). However, after completing the front-end engineering and design (“FEED”) process in December 2024, the initial cost estimates were higher than originally anticipated. In response, during the first quarter of 2025, Net Power commenced a post-FEED optimization and value engineering process. Further long lead equipment releases have been suspended but value engineering and certain development work remain in progress. Provided we are successful in our value engineering process, the project would come online no earlier than 2029.

Net Power intends to deploy its technology in the United States (“U.S.”) and around the world by leveraging experience gained from the Demonstration Plant, and SN1, as well as from the support and expertise of Net Power’s current owners, including OXY, BHES, and Constellation.

Net Power’s potential customers include electric utilities, oil and gas companies, midstream oil and gas companies, technology and data center companies, and industrial facilities, both in domestic and international markets. Net Power has engaged in active dialogue with potential customers in each of these industries. Net Power’s end-markets can be broken down into three general categories: grid power, industrial applications, and data centers. The grid power end-market includes electric utilities and power generation companies that produce and sell power into local and regional power markets. Net Power is designed to generate power continuously (baseload) and as-needed (load-following) in order to complement intermittent renewable power. Potential industrial applications, such as direct air capture facilities, steel facilities, chemical plants, and hydrogen production facilities, include those that have significant 24-hour energy needs and desire to utilize low-emission power, which we believe Net Power’s technology can provide. The technology and data center end-market is one of the fastest growing segments in many of our key target geographies. Historically, data centers have procured their power directly from the grid, but growing grid constraints across many markets plus growing demand, due in part to the proliferation of artificial intelligence applications, have led data center companies to evaluate co-location of data centers with dedicated power generation facilities, similar to the industrial market segment.

Key benefits for customers include the following:

Clean—The Net Power Cycle is expected to result in a life cycle carbon intensity (“CI”) of 40g to 75g CO 2 e/kWh and capture CO 2 at > 97% rate, providing for approximately 85% CO 2 emissions reduction in comparison to conventional combined cycle gas turbine technology. CO 2 is inherently captured at pipeline pressure and ready for transportation. The Net Power Cycle results in de minimis NOX, SOX, and particulate emissions as compared to traditional coal or natural gas fossil fuel generation, which may allow for project siting near population centers. Net Power expects efforts to reduce upstream methane emissions will further reduce the Net Power Cycle CI.

Reliable—The Net Power Cycle can provide 24/7 baseload power, with a targeted capacity factor above 90%, power ramp rates of 10% to 15% per minute and the ability to turn down the plant net electrical output from 100% to 0% while still operating and synchronized to the grid, allowing for maximum grid support. It can function as a utility-scale large plant or pair as a load-following asset to support variable renewable energy such as wind or solar.

Affordable—Net Power targets a levelized cost of energy in the U.S. that is competitive with alternative low-carbon, dispatchable generation such as advanced nuclear, combined cycle gas turbines with post combustion capture and solar photovoltaic panels (“PVs”) coupled with eight hours or more of battery storage.

Utilizes existing infrastructure—The U.S. alone has approximately three million miles of natural gas pipeline infrastructure, with over 300,000 miles of transmission pipelines. Approximately 50 individual CO 2 pipelines with a combined length of over 4,500 miles exist in the U.S. today. According to the U.S. Energy Information Administration (the “EIA”), there are hundreds of thermal power generation facilities at or nearing their retirement or replacement period through 2050, many of which Net Power believes could serve as potential brownfield site locations for our technology.

Compact footprint—Net Power’s modular design and the inherent energy density of sCO 2 as a working fluid leads to a low surface footprint targeted to be less than 15 acres, equal to 1/100th of the solar PV of a similar electric output. This allows Net Power to serve as a re-powering option for retiring facilities or facilities that cannot secure additional space for capture equipment.

Net Power believes that the Net Power Cycle can serve as a key enabling solution for a low-carbon future, addressing shortfalls inherent to alternative options while contributing to an overall lower system-wide cost of decarbonization. Net Power believes that through its innovative process, it can provide a lower cost of electricity, a reduction of, and in some cases the elimination of, environmental impacts related to thermal power use (air pollution, water use, land use, and deforestation), improve reliability and dispatchability contributing to energy security, as well as an ability to achieve required carbon reduction targets. Net Power believes the build-out of the Net Power Cycle can provide the world with clean, reliable, and affordable energy.

Corporate Strategy

Net Power employs a three-pillar corporate strategy as the foundation to direct our capital allocation and align our decision-making with our long-term vision.

Pillar 1: Develop and prove Net Power’s technology at the utility-scale

Our first priority is to progress our joint development program with Baker Hughes. Together with Baker Hughes, we began the first of four testing campaigns at our Demonstration Plant in 2024 and expect to continue testing over the next 3 years, which is expected to provide invaluable operational data ahead of deploying our first utility-scale plant.

Concurrently, we are evaluating the initial FEED package we received for Project Permian. As we continue the post-FEED optimization process, further long lead equipment releases for Project Permian have been suspended but value engineering and certain development work remain in progress. The ultimate goal for the first utility-scale deployment is to construct and operate with a focus on clean, reliable, and safe operations as we expect it to serve as the launch-point for all future deployments.

Pillar 2: Achieve full commercialization and competitiveness of the technology

In parallel to developing and proving Net Power’s commercial scale technology, we will focus over the next few years on creating a backlog of projects for future deployment. This involves originating projects and developing a standardized multi-unit design to drive cost improvements and gain economies of scale. We believe one of the largest drivers to achieve full commercial adoption will be lowering the capital cost per plant. To reduce capital cost, Net Power plans to standardize the design, supply, and construction of plants into a multi-unit configuration of between two and four Net Power units. We expect standardization and scale efficiencies will be large drivers of future capital expenditure reductions.

Additionally, we intend to build a backlog of hub opportunities through our origination efforts. Origination includes identifying CO 2 sequestration sites, securing surface rights for plant sites, filing applications to connect to the regional grid systems, and forming strategic partnerships with a variety of stakeholders to set up projects for success. With this approach, we believe we can accelerate deployment of Net Power’s technology in the most cost effective and responsible manner for the benefit of our customers, the communities where these plants will be located, and our investors. We expect that originated projects will ultimately be majority owned by customers upon reaching final investment decision (“FID”) and each originated project will pay Net Power license fees and royalties similar to those paid by third-party customers. Our goal is to achieve broad commercial adoption via a robust backlog of multi-plant ‘hub’ deployments.

Pillar 3: Prepare for standard plant mass deployment

Developing a standardized multi-unit design is expected to allow our original equipment manufacturers and EPC partners to enter mass manufacturing mode. Similarly, we expect more work, primarily plant fabrication, will take place in a controlled factory environment, and less plant construction will take place in the field at remote locations. By taking this modularization approach, we expect to have more control over driving down the plant capital cost, reducing project risk, and reducing lead time to build future plants. We have already put strategic supply chain partnerships in place for certain equipment, including our turbomachinery and recuperative heat exchangers, and we expect to continue to do so with other key equipment, services, and technology. We expect to work with these partners to build out the manufacturing capacity needed to support our commercialization.

Government and Regulatory Environment

Grant and Loan Opportunities—The November 2021 Bipartisan Infrastructure Law (“BIL/IIJA”) provided further support to the DOELoan Program Office (“LPO”) Title XVII program to support early commercial facilities across the U.S. More recently, the Inflation Reduction Act (the “IRA”), which was adopted in August 2022, ushered in further support to LPO Title XVII (additional appropriations of $40 billion through 2026), $3.6 billion to cover credit subsidy costs of loans and introduced a new “Energy Infrastructure Reinvestment” fund with $250 billion of new commitment authority to “retool, repower, repurpose, or replace energy infrastructure” with emission control technologies. However, in January 2025, President Trump issued an executive order directing an immediate pause on the disbursement of funds appropriated through the BIL/IIJA and the IRA.

Global funding opportunities, such as the European Union (“EU”) Innovation Fund, the European Commission’s Just Transition Fund, and the United Kingdom (“UK”) Department for Business, Energy & Industrial Strategy (“BEIS”) Net

Zero Innovation Portfolio, offer opportunities in Europe. Other opportunities exist across the world, and we are evaluating these on a case-by-case basis to de-risk and support initial projects.

Tax Credit Opportunities—The IRA provides the 45Q tax credit up to $85 per metric ton of captured CO 2 permanently geologically sequestered, and $60/ton of CO 2 captured and then utilized for enhanced oil recovery (“EOR”) or other uses. A Net Power plant is inherently designed to meet and exceed the CO 2 capture thresholds and minimum capture rate for electric generating units of 75%. To qualify for the 45Q tax credit, eligible facilities like Net Power plants must commence construction by January 1, 2033 and can claim the tax credit for the first 12 years in service.

We are monitoring the global market for other tax credit or carbon tax opportunities, with the belief that any value ascribed to carbon, whether a credit or tax, benefits our technology over other emitting alternatives.

Net Power Cycle Licenses and Support Services

Beyond our first utility-scale plant, our primary revenue stream is expected to be license and royalty fees paid by the customer for each plant. We expect a customer seeking to deploy a Net Power plant will purchase a license from us to construct, operate, and maintain the plant. We expect that the customer will pay a license deposit before the commencement of FEED, which would be credited toward the license fee, and the remaining license fee would be paid in installments at key milestones leading to a plant’s commercial operations. We also expect that customers will pay an annual royalty fee for the life of the plant. We currently expect each utility-scale license to generate approximately $65 million of value, based on the expected cash flow of future licensing fees over the life of the license using a 10 percent discount rate.

In addition to licenses, we expect to provide customers with a list of pre-qualified EPC companies for the design and construction of the plant. We believe that our pre-qualification of these EPC companies can provide customers with reasonable confidence that the contractors they engage have the requisite skill and expertise to successfully deliver a Net Power plant. Furthermore, this process is designed to ensure that EPC companies comply with our IP protection requirements, licensing business model, and quality control expectations.

We expect to also provide customers with a preferred vendors list and a robust approved list for key equipment suppliers, further ensuring quality control and de-risking the supply chain. Customers developing a Net Power plant are expected to purchase equipment from one of our licensed suppliers.

We intend to provide support to customers throughout the development process. During scoping and early development of potential facility sites, we may conduct feasibility and pre-FEED studies for our customers. When customers are ready to begin FEED processes, we intend to provide a license package with the necessary specifications to pre-qualified EPC companies. We plan to support each customer’s execution of FEED, with the appropriate scope of work being determined on a case-by-case basis. We expect that our support will continue to the commercial operations of each plant and will include support for start-up and commissioning as well as operator training.

Competition

Our competitors are other power generation technologies, including traditional baseload, unabated generation, gas generation with post combustion carbon capture, advanced nuclear, and renewables. We believe our competitive strengths differentiate us from our competition globally, in part because we expect our technology to achieve clean, reliable, and affordable power generation while we expect most of our competitors only achieve two of these three factors.

Traditional Unabated Emission Generation—According to the International Energy Agency (the “IEA”), approximately 70% of global electricity supply in 2023 was comprised of natural gas, coal, oil, and large-scale nuclear. These technologies are highly reliable, cost-effective, and dispatchable. However, with the exception of traditional large-scale nuclear, these resources are carbon-intensive, and we expect them to largely be replaced with lower carbon-intensity generation over time. Traditional natural gas power plants, while delivering lower carbon electricity than other fossil fuel feedstocks, are not viewed as a permanent solution by certain regulators and policymakers in light of concerns related to climate change. Instead, some view conventional natural gas as a bridge fuel until cleaner sources of energy are available. Our technology combines the reliability of natural gas with the decarbonizing capabilities of carbon capture.

Coal-fired and gas-fired generation with Post Combustion Carbon Capture—An alternative solution to reduce CO 2 emissions from coal-fired and natural gas-fired power generation is post-combustion carbon capture (“PCC”). PCC involves capturing CO₂ emissions from the exhaust gases of traditional coal-fired and natural gas-fired power plants after combustion has occurred. This approach is typically achieved using chemical absorption processes, such as amine-based systems, which separate CO₂ from the flue gas before it can be transported and stored. While this technology has the potential to reduce greenhouse gas emissions from conventional coal-fired and natural gas-fired power plants, commercially successful PCC applications have been limited, primarily due to the high upfront cost to build PCC capture facilities and high operating costs to capture the emissions, including the impact of lower overall net electric output of the power plant due to the energy-intensive requirements of the PCC application. A number of companies are attempting to develop more efficient capture technologies that could potentially reduce capital costs, operating costs, and energy intensity of PCC applications. There are several other key differences between Net Power and PCC. First, we expect a Net Power plant will require less land than a traditional power plant equipped with PCC. Second, Net Power’s oxy-combustion process inherently reduces potential NOx and SOx emissions whereas PCC applications are generally not designed to eliminate NOx or SOx emissions. NOx and SOx are designated as criteria air pollutants by the U.S. Environmental Protection Agenda (“EPA”) and facilities that emit certain volumes of these criteria air pollutants may be subject to additional siting, permitting, and reporting requirements. Finally, PCC systems are chemical plant processes and are not amenable to rapid change in operating conditions, thus preventing the power plant into which they are integrated from rapidly ramping in output to support the grid.

Advanced Nuclear—There are several advanced nuclear reactor technologies that are in various stages of development. These technologies are designed to be clean, safe, and highly reliable. However, none of these technologies have yet been licensed for commercial use in the U.S., and many of the technologies have not been demonstrated and generally do not have requisite fuel supply infrastructure in place. Regulatory pathways for permitting and constructing advanced nuclear reactors also entail substantial uncertainties with respect to cost and timing.

Renewables—According to the EIA, approximately 21% of U.S. generation in 2023 was wind, solar, hydropower, and other sources of renewable power generation. Although these sources generate carbon-free power, wind, and solar can be intermittent and non-dispatchable, unless paired with long duration energy storage. Hydropower, while carbon-free, can be seasonal and subject to curtailment and has limited growth in the U.S., where most capable sources have already been developed. Additionally, because wind and solar are highly sensitive to weather, we believe they are too unreliable to support certain end-use cases, including certain applications that require extensive on-site, always-available power. Our technology allows for the reliability and low-cost nature of natural gas to remain intact while reducing carbon emissions arising from natural gas-fired generation of electricity.

Customers

Net Power’s potential customers include electric utilities, oil and gas companies, midstream oil and gas companies, technology and data center companies, and industrial facilities, both in domestic and international markets. Net Power has engaged in active dialogue with potential customers in each of these industries. Net Power's end-markets can be broken down into three general categories: grid power, industrial applications, and data centers. The grid power end-market includes electric utilities and power generation companies that produce and sell power into local and regional power markets. Net Power is designed to generate power continuously (baseload) and as-needed (load-following) in order to complement intermittent renewable power. Potential industrial applications, such as direct air capture facilities, steel facilities, chemical plants, and hydrogen production facilities, include those that have significant 24-hour energy needs and desire to utilize low-emission power, which we believe Net Power’s technology can provide. The technology and data center end-market is one of the fastest growing segments in many of our key target geographies. Historically, data centers have procured their power directly from the grid, but growing grid constraints across many markets plus growing demand, due in part to the proliferation of artificial intelligence applications, data center companies are evaluating co-location of data centers with dedicated power generation facilities, similar to the industrial market segment.

Partnerships

License Agreement with 8 Rivers

On August 7, 2014, we entered into a license agreement with 8 Rivers, pursuant to which 8 Rivers granted us perpetual, irrevocable, and worldwide rights under patents relating to the Net Power Cycle (which was invented by 8 Rivers), for the generation of electricity using CO 2 as the primary working fluid. The license is exclusive in the field of utilizing any carbonaceous gas fuel other than those derived from certain solid fuel sources. 8 Rivers remains an investor in us.

License Agreement and Joint Development Agreement with Baker Hughes

On February 3, 2022, we entered into the Original JDA, which was amended and restated on December 13, 2022. Pursuant to this agreement, NPI is developing sCO 2 turbo expanders for use in facilities implementing the Net Power Cycle. These turbo expanders are intended to be compatible with our existing technology and are highly specialized. We and NPI formed a Joint Design Committee to provide oversight and support for program schedule, equipment design and performance.

NPI will oversee the installation and commissioning of the first industrial scale combustor and turbo expander at the Demonstration Plant during the fourth phase of the testing campaign. A team of NPI specialists will be deployed at the site, offering technical advice and conducting testing and validation processes. We intend to work with NPI to ensure the implementation and integration process occurs according to plan and any required personnel are trained properly.

In connection with the Original JDA, on February 3, 2022, Net Power entered into the BH License Agreement with NPT (the “BH License Agreement”), pursuant to which NPT and its affiliates will have limited exclusivity for manufacturing utility-scale turbo expanders and full exclusivity for industrial-scale units. We will own intellectual property developed by NPI related to the Net Power Cycle, and NPI can only sell the jointly developed turbo expanders to our licensees. We and NPI will market the technology through a Joint Commercial Committee, leveraging Baker Hughes’ global sales channels.

OLCV Net Power, LLC Investment

OXY invested in Net Power in 2019 and provides expertise in the CO 2 value chain and construction of large facilities, like our Demonstration Plant. OXY is expected to play a key role in the development and commercialization of Project Permian should we decide to continue the development of Project Permian as SN1. OXY is the lessor for the site for Project Permian near Midland, Texas.

Intellectual Property

As of December 31, 2024, our technology is supported by a portfolio of 485 issued patents (and 48 pending applications) that extends across more than 30 countries and six continents. These patent rights have been in-licensed from 8 Rivers pursuant to a 2014 license agreement which provides us with exclusive licensing, sublicensing, and commercialization rights for natural gas and certain other fuel sources. Such patents extend through the mid-2030s. Protections are intended to provide coverage for integrated permutations of the patented technology as it expands as a platform and not simply a power generation concept. We also have trade secrets that may provide for an additional scope of protected and licensable rights extending beyond patent lifetimes.

Our intellectual property encompasses rights under patents related to the Net Power Cycle and trade secret information derived from the Demonstration Plant. Our registered trademarks include the Net Power logo and company name. We also have explicit company policy to protect our proprietary data through various classification, handling, and control systems.

Pursuant to the BH License Agreement, NPT, and its affiliates will have limited exclusivity for manufacturing utility-scale turbo expanders and full exclusivity for industrial-scale units. We will own intellectual property developed by NPI related to the Net Power Cycle, and NPI can only sell the jointly developed turbo expanders to our licensees. The Amended and Restated JDA and the BH License Agreement include contractual obligations dictating the use of our intellectual property to preserve its integrity.

Our technology, including its use and incorporation in processes, plants, and components for use, is protected by certain intellectual property and contractual rights in the U.S. and various other countries of the world. We continually review our development efforts to assess the existence and patentability of our intellectual property. Our intellectual property continues to grow and expand, protecting iterative product design and development of our technology.

We rely upon a combination of patents, copyrights, trade secrets, and trademark laws, along with employee and third-party non-disclosure agreements and other contractual restrictions to establish and protect our proprietary rights. Patent protection was obtained shortly after the invention of our technology, providing protection for this one-of-a-kind natural gas cycle from its earliest stages.

Human Capital

As of December 31, 2024, we had 68 full-time employees and six contractors and on-site service employees. Our headquarters are located in Durham, North Carolina. In July 2024, we opened a second corporate office in Houston, Texas to accommodate our growing resource requirements. None of our employees are subject to a collective bargaining agreement. We consider our relationship with our employees to be positive.

Talent Acquisition and Retention

We support business growth by seeking to attract and retain best-in-class talent. We use internal and external resources to recruit highly skilled candidates for open positions. We provide employees with compensation packages that may include various components, such as base salary, annual incentive bonuses, and long-term equity incentive awards. We also offer comprehensive employee benefits, such as life, disability, and health insurance, vision and dental insurance, paid time off, and a 401(k) plan with an employer contribution. It is our intention to be an employer of choice in our industry by providing a market-competitive compensation and benefits package.

Training and Development

We believe in encouraging employees to become lifelong learners by providing ongoing learning and leadership training opportunities. While we strive to provide real-time recognition of employee performance, we have a formal annual review process designed to identify areas where training and development may be necessary or beneficial.

Diversity, Equity, Inclusion & Accessibility

We believe a diverse workforce is critical to our success. Our mission is to value differences in races, ethnicities, religions, nationalities, genders, ages, abilities, and sexual orientations as well as education, skill sets, and experience. We are focused on inclusive hiring practices, fair and equitable treatment, organizational flexibility and training and resources.

Government Regulations

Energy Regulatory Matters

Electric power sales and markets in the U.S. are subject to extensive regulation at both the federal and state levels. Accordingly, Net Power’s Demonstration Plant, which is located within the Electric Reliability Council of Texas (“ERCOT”), and other Net Power plants that Net Power may own in the future located in ERCOT and other jurisdictions within the U.S., are subject to substantial energy regulation and may be adversely affected by legislative or regulatory changes, as well as liability under, or any future ability to comply with, existing or future energy regulations or requirements. Compliance with the requirements under these various regulatory regimes may cause the applicable company to incur significant costs, and failure to comply with such requirements could result in the shutdown of the non-complying facility or the imposition of liens, fines, or civil or criminal liability.

State regulators also regulate the rates that retail utilities can charge and the terms under which they serve retail (end-use) electric customers. Certain states also have authority to regulate mergers, acquisitions, financing, and securities issuances. State regulators may also review individual utilities’ electricity supply requirements and have oversight over the ability of traditional regulated utilities to pass through to their ratepayers the costs associated with power purchases from independent generators. Federal regulatory filings and authorizations generally are required for generation projects in the U.S. that sell energy wholesale and are connected to the interstate transmission grid. Furthermore, even when a particular energy business entity is subject to federal energy regulation, state, and local approvals (such as siting and permitting approvals) are often required.

Federal Power Act

The Federal Power Act (the “FPA”) provides the Federal Energy Regulatory Commission (“FERC”) exclusive federal jurisdiction over the sale of electric energy at wholesale (that is, for resale) in interstate commerce and the transmission of electric energy in interstate commerce, including wholesale markets for electric energy, capacity, ancillary services, and transmission services. Section 205 of the FPA gives FERC jurisdiction and authority over, among other things, the rates, charges, and other terms for the sale of electric energy, capacity, and ancillary services at wholesale by public utilities (entities that own or operate projects subject to FERC jurisdiction) and for transmission services. These rates may be based on a cost-of-service approach or may be determined on a market basis through competitive bidding or negotiation. As a result, a public utility must obtain FERC approval of its rates and charges and must make the associated, required filings to maintain the granted authority. To obtain authority to make sales at market-based rates, the public utility must demonstrate to FERC that it does not possess market power, as defined by FERC. Net Power's Demonstration Plant, which is located within ERCOT, is not generally subject to FERC’s rate-regulation authority under Section 205 of the FPA, but any future Net Power facilities located outside of ERCOT may be.

The FPA also provides FERC authority for the regulation of mergers, acquisitions, financings, and securities issuances involving entities subject to its jurisdiction. This jurisdiction may, for certain transactions, extend to entities and assets within ERCOT. Consequently, in certain cases, FERC approval may be required prior to entering into a transaction involving a public utility or for certain holding company transactions involving specified assets.

ISOs and RTOs

Generation projects also may be located in regions in which the bulk power transmission system and associated wholesale markets for electric energy, capacity, and ancillary services are administered by Independent System Operators (“ISOs”) and Regional Transmission Organizations (“RTOs”) that are subject to FERC jurisdiction and operate under FERC jurisdictional tariffs, including open access transmission tariffs, or, in the case of ERCOT, generation, and transmission tariffs and protocols that are regulated by the Public Utility Commission of Texas (“PUCT”). These RTOs and ISOs prescribe rules and protocols for the terms of participation in the wholesale energy and ancillary services markets (and for certain RTOs and ISOs, capacity markets). Many of these entities can impose rules, restrictions, and terms of service that are regulatory in nature and may have a material adverse effect on business. For example, ISOs and RTOs have developed bid-based locational pricing rules for the electric energy markets that they administer. In addition, most ISOs and RTOs have also developed bidding, scheduling, and market behavior rules, both to curb the potential exercise of market power by electricity generating companies and to ensure certain market functions and system reliability. These rules, restrictions, and terms of service could change over time and could materially adversely affect a power plant’s ability to sell, and the price received for, energy, capacity, and ancillary services.

Energy Policy Act of 2005

Net Power and its projects may also be subject to the mandatory reliability standards of the North American Electric Reliability Corporation (the “NERC”). In 2005, the U.S. federal government enacted the Energy Policy Act of 2005, which supplemented the FPA to vest FERC with authority to ensure the reliability of the bulk electric system. Such authority mandated that FERC assume both oversight and enforcement roles. Pursuant to this mandate, FERC certified the NERC as the nation's Electric Reliability Organization (“ERO”) to develop and enforce mandatory reliability standards and requirements to address medium- and long-term reliability concerns. The NERC reliability standards are a series of requirements that relate to maintaining the reliability of the North American bulk electric system and cover a wide variety of topics, including physical security and cyber-security of critical assets, information protocols, frequency and voltage standards, testing, documentation, and outage management. If generation and transmission owners and operators that are part of the bulk electric system fail to comply with these standards, they could be subject to sanctions, including substantial monetary penalties. NERC and FERC also delegate these responsibilities to regional entities, such as Texas Reliability, Inc., which enforce both NERC and regional reliability standards.

Public Utility Holding Company Act of 2005

The Public Utility Holding Company Act of 2005 (“PUHCA”) provides FERC and state regulatory commissions with access to the books and records of public utility holding companies and other companies in public utility holding company systems; it also provides for the review of certain costs. Companies like Net Power that are holding companies under PUHCA solely with respect to one or more Exempt Wholesale Generators (“EWGs”) or Qualifying Facilities (“QFs”) are generally exempt from requirements which give FERC access to books and records.

State Utility Regulation

While federal law provides the utility regulatory framework for our project subsidiaries’ sales of electric energy, capacity, and ancillary services at wholesale in interstate commerce, there are also important areas in which traditional public utilities fall under state jurisdiction. For example, the regulated electric utility buyers of electricity from our projects are generally required to seek state public utility commission approval for the pass-through in retail rates of costs associated with power purchase agreements entered into with a wholesale seller or seek approval for the siting and construction of a new power plant. Certain states also regulate the acquisition, divestiture, and transfer of some wholesale power projects and financing activities by the owners of such projects. In addition, states and other local agencies require a variety of environmental and other permits.

Texas

The Demonstration Plant is located in ERCOT. ERCOT is a largely self-contained market on a standalone grid with only approximately 1,100 MW of transfer capability through direct-current, asynchronous ties with the Southwest Power Pool, and the Comision Federal de Electricidad in Mexico. Therefore, in ERCOT, the wholesale electricity market is, for most purposes, considered to be intrastate commerce, and so its rules, as well as the provision of transmission and distribution service in Texas, generally remain regulated by the PUCT.

The PUCT, with the help of ERCOT, regulates competitive market participants, including power generation companies (i.e., owners and operators of power plants that make sales into the wholesale electricity and ancillary services markets in ERCOT) and power marketers (i.e., entities that do not own power plants but make sales of electricity at wholesale). Such regulation includes oversight of operations (including imposing real-time telemetry and dispatch requirements, monitoring for market power abuses, and requiring emergency operations planning and weather preparedness), registration, reporting, and record-keeping requirements. The PUCT and ERCOT do not directly regulate wholesale or retail prices, except to monitor for potential market power abuses and anti-competitive behavior. The PUCT has authority to investigate and impose fines for violations of its enabling statute, the Public Utility Regulatory Act (Tex. Util. Code §§ 11.001-66.016), its rules (set out in Chapter 25 of Title 16 of the Texas Administrative Code), and of the ERCOT Protocols or other binding documents. Fines can be up to $25,000 per violation per day for most violations and up to $1,000,000 per violation per day for specific violations relating to weather-preparedness requirements.

Power generation companies also must seek pre-approval from the PUCT for proposed mergers, acquisitions, or other affiliations with other power generation companies in certain circumstances, pursuant to the Public Utilities Regulatory Act § 39.158.

The structure of the energy industry and its regulation in the U.S. is currently, and may continue to be, subject to change. We expect the laws and regulation applicable to our business and the energy industry generally to be in a state of transition for the foreseeable future. Changes in such laws and regulations could have a material adverse effect on our business, financial condition, and results of operations.

Environmental Matters

Power plant operations are required to comply with various environmental, health, and safety (“EHS”) laws and regulations. For Net Power plants in which we have an ownership interest, these existing and future laws and regulations may affect existing and new projects, require us to obtain and maintain permits and approvals, undergo environmental review processes, and implement EHS programs and procedures to monitor and control risks associated with the siting, construction, operation, and decommissioning of regulated or permitted energy assets, all of which involve a significant investment of time and resources.

We also incur costs in the ordinary course of business to comply with these laws, regulations, and permit requirements. EHS laws and regulations frequently change, and may become more stringent or subject to more stringent interpretation or enforcement over time. Such changes in EHS laws and regulations, or the interpretation or enforcement thereof, could require us to incur materially higher costs, or cause a costly interruption of operations due to delays in obtaining new or amended permits.

The failure of our project operations to comply with EHS laws and regulations, as well as permit requirements, may result in administrative, civil, and criminal penalties, imposition of investigatory, cleanup, and site restoration costs and liens, denial or revocation of permits or other authorizations, and issuance of injunctions to limit, suspend, or cease operations.

In addition, claims by third parties for damages to persons or property, or for injunctive relief, have been brought in the past against owners and operators of projects similar to the projects we will own and operate, as a result of alleged EHS effects associated with such projects, and we expect such claims may be brought against us in the future.

Environmental Regulation

To construct and operate our projects, we are required to obtain from federal, state, and local governmental authorities a range of environmental permits and other approvals, including those described below. In addition to being subject to these regulatory requirements, we or similar projects have experienced and/or may experience significant opposition from third parties during the permit application process or in subsequent permit appeal proceedings.

Clean Water Act. In some cases, our projects may be located near wetlands and we will be required to obtain permits under the federal Clean Water Act from the U.S. Army Corps of Engineers (the “Army Corps”) for the discharge of dredged or fill material into waters of the U.S., including wetlands and streams. The Army Corps may also require us to mitigate any loss of wetland functions and values that accompanies our activities. In addition, we are required to obtain permits under the federal Clean Water Act for water discharges, such as storm water runoff associated with construction activities, and to follow a variety of best management practices to ensure that water quality is protected and effects are minimized.

Bureau of Land Management (“BLM”) Right-of-Way Grants. Our projects may be located, or partially located, on lands administered by the BLM. Therefore, we may be required to obtain and maintain BLM right-of-way grants for access to, or operations on, such lands. Obtaining and maintaining a grant requires that the project conduct environmental reviews (discussed below) and implement a plan of development and demonstrate compliance with the plan to protect the environment, including potentially expensive measures to protect biological, archaeological, and cultural resources encountered on the grant.

Environmental Reviews. Our projects may be subject to federal, state, or local environmental reviews, including under the federal National Environmental Policy Act (“NEPA”), which requires federal agencies to evaluate the environmental effects of all major federal actions affecting the quality of the human environment. The granting of a land lease, a right-of-way grant, a federal permit, or similar authorization for a major pre-construction project, or the interconnection of a significant private project into a federal project, generally is considered a major federal action that requires review under NEPA. As part of the NEPA review, the federal agency considers a broad array of environmental effects, including effects on air quality, water quality, wildlife, historical and archaeological resources, geology, socioeconomics, aesthetics, and alternatives to the project. The NEPA review process, especially if it involves preparing a full Environmental Impact Statement, can be time-consuming and expensive. A federal agency may decide to deny a permit based on its environmental review under NEPA, though in most cases a project would be redesigned to reduce effects or we would agree to provide some form of mitigation to offset effects before a denial is issued. Such measures are often implemented to occur during the operational phase and may compromise or even require temporary cessation of operations under certain conditions such as seasonal migrations. As noted above and discussed more fully below, our projects may be subject to similar environmental review requirements at the state and local level in jurisdictions with NEPA equivalents.

Threatened, Endangered and Protected Species. Federal agencies considering the permit applications for our projects are required to consult with the U.S. Fish and Wildlife Service (the “USFWS”) to consider the effect on potentially affected endangered and threatened species and their habitats under the federal Endangered Species Act and related statutes, which prohibit and impose stringent penalties for harming endangered or threatened species and their habitats. We may also be required to obtain permits from the USFWS and state agencies authorizing the incidental take of certain protected species. There is also increasing interest in nature-related matters beyond protected species, such as general biodiversity, which may similarly require us or our customers to incur costs or take other measures that may adversely impact our business or operations.

Historic Preservation. State and federal agencies may be required to consider a project’s effect on historical or archaeological and cultural resources under the federal National Historic Preservation Act or similar state laws and may require us to conduct archaeological surveys or take other measures to protect such resources. Among other things, the National Historic Preservation Act requires federal agencies to evaluate the effect of all federally funded or permitted projects on historic properties (buildings, archaeological sites, etc.) through a process known as Section 106 review. Ongoing monitoring, mitigation activities, or financial compensation may be required as a condition of conducting project operations.

Clean Air Act. Certain project operations may be subject to federal, state, or local permit requirements under the Clean Air Act, which regulates the emission of air pollutants, including greenhouse gases. Federal and state regulators have developed, and continue to develop, stringent regulations governing emissions of air pollutants at specified sources. New facilities may be required to obtain permits before work can begin, and modified and existing facilities may be required to obtain additional permits.

Climate Change. Climate change continues to attract considerable public and scientific attention. As a result, numerous proposals have been made and may continue to be made at the international, national, regional, and state levels of government to monitor and limit emissions of greenhouse gases, with the reduction of greenhouse gases from the energy sector being a key focus. In November 2021, the $1 trillion legislative infrastructure package, or BIA/IIJA, was signed into law and included climate-focused spending initiatives targeted at climate resilience, enhanced response and preparation for extreme weather events, and clean energy and transportation investments. The IRA also provided significant funding and incentives for research and development of low-carbon energy production methods, carbon capture, and other programs directed at addressing climate change. However, in January 2025, President Trump issued an executive order directing an immediate pause on the disbursement of funds appropriated through the BIA/IIJA and the IRA. Further, under the Biden Administration, the U.S. rejoined the Paris Agreement treaty on climate change (the “Paris Agreement”), made a commitment under the Paris Agreement to cut U.S. greenhouse gas emissions by 50-52% from 2005 levels by 2030, and participated in the Global Methane Pledge, a pact that aims to reduce global methane emissions at least 30% below 2020 levels by 2030. At the 27th Conference of the Parties, the U.S. agreed, in conjunction with the

European Union and a number of other partner countries, to develop standards for monitoring and reporting methane emissions to help create a market for low methane-intensity natural gas. At the 28th Conference of the Parties, member countries agreed to the first “global stocktake,” which calls on countries to contribute to global efforts, including a tripling of renewable energy capacity and doubling energy efficiency improvements by 2030, accelerating efforts towards the phase-down of unabated coal power, phasing out inefficient fossil fuel subsidies, and transitioning away from fossil fuels in energy systems. Most recently, at the 29th Conference of the Parties, 159 countries met and, among other things, agreed on rules to operationalize international carbon markets under Article 6 of the Paris Agreement. However, in January 2025, President Trump issued executive orders directing the immediate notice to the United Nations of the United States’ withdrawal from the Paris Agreement and all other agreements made under the United Nations Framework Convention on Climate Change. At the same time, many state and local leaders have intensified or stated their intent to intensify efforts to support international climate commitments and treaties, in addition to considering or enacting laws requiring the disclosure of climate-related information and developing programs that are aimed at reducing greenhouse gas emissions by means of cap and trade programs, carbon taxes or encouraging the use of renewable energy or alternative low-carbon fuels. We are committed to a clean energy future and we believe our business is well-positioned to benefit from growing regulatory and policy support for decarbonization. However, the adoption and implementation of any international, federal, or state legislation, regulations or other regulatory initiatives that requires reporting of greenhouse gases or otherwise restricts emissions of greenhouse gases from our equipment and operations could require us to incur increased operating costs. In addition, increasing concentrations of greenhouse gases in the Earth's atmosphere may produce climate changes that have significant physical effects, such as increased frequency and severity of storms, floods, droughts, and other extreme climatic events. If any such effects were to occur, they could have an adverse effect on the construction and operation of our projects.

Underground Injection and Carbon Sequestration. In certain cases, we may be responsible for the underground injection of CO 2 for long-term carbon sequestration. Such injection is regulated by the federal Safe Drinking Water Act and similar state laws, which ensure the quality of the nation’s public drinking water through adoption of drinking water standards and the regulation of underground injection of fluids to protect drinking water sources. Such injection may require us to secure permits for the injection activity, which may be costly, time-consuming, and subject to opposition by third parties. Additionally, for long-term carbon sequestration, we will need to control the underground pore-space where carbon is to be stored, which will require legally securing the necessary real property rights for such storage. In some states and other jurisdictions, the legal requirements for pore-space ownership are unsettled and evolving, and there may be conflicts between mineral owners and landowners as to who has the right to use pore-space. If one of our projects is proposed in a jurisdiction with unsettled law, that could have an adverse effect on our ability to operate the project or to properly sequester carbon and may give rise to future liability regarding the sequestered carbon.

Health and Safety. We are subject to the requirements of the federal Occupational Safety and Health Act (“OSHA”) and comparable state statutes. These laws and the implementing regulations strictly govern the protection of the health and safety of employees in the workplace. The OSHA hazard communication standard, the EPA community right-to-know regulations under Title III of the Comprehensive Environmental Response, Compensation and Liability Act, and similar state statutes require that we organize and/or disclose information about hazardous materials used or produced in the construction, operation, and maintenance of our projects.

Local Regulations. Our project operations are subject to local environmental and land use requirements, including county and municipal land use, zoning, building, water use, and transportation requirements. Permitting at the local municipal or county level often consists of obtaining a special use or conditional use permit under a land use ordinance or code, or, in some cases, rezoning in connection with the project. Obtaining or maintaining a permit often requires us to demonstrate that the project will conform to development standards specified under the ordinance so that the project is compatible with existing land uses and protects natural and human environments. Local or state regulatory agencies may require modeling, testing, and, where applicable, ongoing mitigation of sound levels, radar, and other microwave interference, or shadow flicker in connection with the permitting and approval process. Local or state agencies also may require decommissioning plans and the establishment of financial assurance mechanisms for carrying out the decommissioning plan.

Other State and Local Programs. In addition to the federal requirements discussed above, our current projects, and any future projects, are subject to a variety of state environmental review and permitting requirements. Many states where our projects are or may be located have laws that require state agencies to evaluate a broad array of environmental effects before granting state permits. The state environmental review process often resembles the federal NEPA process and may be more stringent than the federal review. Our projects also often require state law-based permits in addition to federal permits. State agencies evaluate similar issues as federal agencies, including a project’s effect on wildlife, historic sites, aesthetics, wetlands and water resources, agricultural operations, and scenic areas. States may impose different or additional monitoring or mitigation requirements than federal agencies.

Additional approvals may also be required for specific aspects of a project, such as a stream or wetland crossing, effects to designated significant wildlife habitats, storm water management, and highway department authorizations for oversize loads and state road closings during construction. Permitting requirements related to transmission lines may be required in certain cases.

Finally, to the extent a project is located on Native American lands, such projects may be subject to a variety of environmental permitting and review requirements that are similar to, and potentially more stringent than, those arising under equivalent federal, state, and local laws, including those relating to the protection of cultural, historic, and religious resources.

Management, Disposal, and Remediation of Hazardous Substances

Real property that we own or lease for our projects may be subject to federal, state, and local requirements regarding the storage, use, transportation, and disposal of petroleum products and toxic or hazardous substances, including spill prevention, control, and counter-measure requirements. Project properties and materials stored or disposed thereon may be subject to the federal Resource Conservation and Recovery Act, the Toxic Substances Control Act, the Comprehensive Environmental Response, Compensation, and Liability Act, and analogous state laws. If our owned or leased properties are contaminated, whether during or prior to our ownership or operation, we could be responsible for the costs of investigation and cleanup and for any related liabilities, including claims for damage to property, persons, or natural resources. That responsibility may arise even if we were not at fault and did not cause or were not aware of the contamination. In addition, the waste we generate is at times sent to third-party disposal facilities. If those facilities become contaminated, we and any other persons who arranged for the disposal or treatment of hazardous substances at those sites may be jointly and severally responsible for the costs of investigation and remediation as well as for any claims for damage to third parties, their property, or natural resources. We may incur significant costs in the future if we become responsible for the investigation or remediation of hazardous substances at our owned or leased properties or at third-party disposal facilities.

Government Incentives

U.S. federal, state, and local governments and utilities have established various incentives to support the development of emissions reductions technologies. Set forth below is a summary of various programs and incentives that we expect will apply to our business.

The global regulatory landscape surrounding carbon capture, utilization and sequestration (“CCUS”) has considerably improved in recent years. In the U.S., the passage of the BIL/IIJA in November 2021 and the IRA in August 2022 introduced and bolstered government incentives for emissions reduction technologies such as the Net Power Cycle. However, in January 2025, President Trump issued an executive order directing an immediate pause on the disbursement of funds appropriated through the BIL/IIJA and the IRA. In addition, the IRA may be subject to amendment or repeal through Congressional budget reconciliation. The full impact of these actions and next steps remains uncertain at this time.

Tax Credits

45Q Tax Credit. The 45Q federal tax credit, first enacted in 2008 as a part of the Energy Improvement and Extension Act, provides an incentive to capture CO 2. This credit initially provided $20/metric ton for carbon sequestration and $10/metric ton for EOR. Following the passage of the IRA in August 2022, these tax credits increased for both permanent geological carbon sequestration and EOR to up to $85/metric ton and $60/metric ton, respectively. These tax credits can be monetized through a fully refundable direct payment or transferred to a third-party in exchange for cash payment. The deadline to commence construction is January 1, 2033 to qualify for the tax credit, and eligible facilities like Net Power plants can claim the tax credit for up to 12 years. In July 2024, the Internal Revenue Service (the “IRS”) within the U.S. Department of Treasury issued additional guidance to further implement the 45Q tax credit.

Grants and Government Funding

U.S. Department of Energy. The DOE oversees U.S. national energy policy, funds large infrastructure projects, and administers research funding across the industry. In fiscal year 2024, the DOE had a total budget of approximately $50 billion, with $17 billion dedicated to energy programs. Within energy programs, the budget of Fossil Energy and Carbon Management was approximately $865 million, and includes specific allocations to carbon capture, utilization, and storage and power systems. DOE's fiscal year 2025 budget is still pending final congressional action, but has been so far maintained at 2023 levels through continuing resolutions.

Other Government Funding. Multiple pools of government capital are potentially available to aid in de-risk financing for early movers using our technology. The EU Innovation Fund, European Commission Transition Fund, Invest EU fund, and Catalyst EU programs all offer incentivized opportunities. Additionally, the UK BEIS Net Zero Portfolio and the Industrial Strategy Challenge Fund also offer potential financial support.

Regulatory Standards

Air Pollution Control. Under the U.S. Clean Air Act, the EPA maintains standards for the regulation of criteria pollutants and greenhouse gas emissions from existing and planned power plants to protect air quality and address climate change, respectively. Criteria air pollutants include ground level ozone, particulate matter, carbon monoxide, lead, sulfur dioxide, and nitrogen dioxide.

In addition, Sections 111(b) and (d) of the Clean Air Act require the EPA to regulate the emission of greenhouse gases from industrial sectors, including the power generation sector, which entails establishing standards based on the “best system of emission reduction” for such facilities. In May 2024, the EPA published final rules for carbon emission limits and guidelines for existing coal-fired power plants and new, modified and coal- and natural gas-fired power plants. The rules purport to reflect the best system of emissions reduction and use of technology-based improvements, including carbon capture and sequestration and low-greenhouse gas hydrogen. A coalition of 25 states, energy companies, utilities and fossil fuel industry groups immediately challenged the rules in federal court. In October 2024, the U.S. Supreme Court denied a request to stay the rule for new gas-fired and existing coal-fired power plants while the litigation continues. In early January 2025, the EPA provided notice of final action denying or partially denying two petitions for reconsideration of the rule. On January 15, 2025, several utilities sent a letter to the new EPA Administrator, urging either an administrative stay of the rule or a limited rulemaking to ease compliance deadlines while the EPA develops a broader rulemaking to rescind the requirements. Additionally, in January 2025, President Trump issued an executive order directing the heads of all federal agencies to identify and begin the processes to suspend, revise or rescind all agency actions that are unduly burdensome on the identification, development or use of domestic energy resources. Consequently, future implementation and enforcement of this rule remains uncertain at this time.

Regarding requirements both for the control of criteria air pollutants and greenhouse gas emissions, we believe the Net Power Cycle offers customers a distinct advantage over competitors because of the low level of pollutants that result from the operation of the Net Power Cycle relative to conventional gas-fired electricity generation and the reuse and capture of carbon dioxide inherent to the design of the Net Power Cycle.

Available Information

Our website address is www.netpower.com. We use our website as a routine channel for distribution of information that may be material to investors, including news releases, financial information, presentations and corporate governance information. Information contained or connected to our website is not incorporated by reference in this Annual Report on Form 10-K unless expressly noted. Our Annual Reports on Form 10-K, Quarterly Reports on Form 10-Q, Current Reports on Form 8-K and any amendments to those reports filed or furnished pursuant to Section 13(a) or 15(d) of the Securities Exchange Act of 1934 (the “Exchange Act”) are available on our website, free of charge, as soon as reasonably practicable after we electronically file such materials with, or furnish them to, the SEC. Additionally, the SEC maintains a website that contains reports, proxy and information statements, and other information regarding issuers that file electronically with the SEC, including us, at www.sec.gov.

ContentsView on SEC.gov

The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.