Vistra Corp.
For the period ended Sep 30, 2025. Filed Nov 7, 2025.
View on SEC.govAbout this filing
A company's report for each of its first three quarters. The financial statements are not audited. It shows how the business has moved since the last annual report, and what management says changed.
Sep 30, 2025 · Filed Nov 7, 2025
Extracted filing text, with the paragraph anchors used by the comparison.
See the whole filing, with its images and exhibitsContents
Significant Activities and Events, and Items Influencing Future Performance
On October 22, 2025 (Acquisition Date), pursuant to a purchase and sale agreement dated May 15, 2025, Vistra Operations acquired 100% of the membership interests of subsidiaries of Lotus (the Acquisition). The Acquisition resulted in the addition of seven natural gas generation facilities totaling 2,600 MW in Delaware and Pennsylvania (PJM), Rhode Island (ISO-NE), New York (NYISO), and California (CAISO) further geographically diversifying Vistra's natural gas fleet.
The aggregate purchase price consisted of a base purchase price of $1.9 billion, subject to certain customary adjustments, including the acquired companies' working capital, cash, indebtedness, and certain other adjustments. Vistra Operations funded the Acquisition with a combination of cash and the assumption of the acquired companies' indebtedness, which consisted of a senior secured credit facility, including an existing term loan with approximately $800 million principal outstanding, which reduced the cash consideration payable at closing. Cash consideration payable at closing, excluding adjustments for the acquired companies' working capital, cash, and certain other adjustments, was $1.1 billion. See Note 2 to the Financial Statements for more information concerning the Acquisition.
Comanche Peak Power Purchase Agreement
In September 2025, Vistra entered into a 20-year power purchase agreement (with options to extend for up to an additional 20 years) with a large, investment grade company (the Customer), pursuant to which Vistra has agreed to supply to the Customer 1,200 MW of carbon-free power from the Comanche Peak Nuclear Power Plant. Vistra anticipates power delivery to begin in the fourth quarter of 2027 and ramp to full capacity by 2032.
Capacity Markets — PJM Auction Results
In July 2025, Vistra received its results from PJM's Reliability Pricing Model (RPM) auction results for planning year 2026-2027, and the table below lists clearing price per MW-day and our cleared capacity volumes by zone:
| Clearing Price per MW-day · Total MW Cleared | |||
|---|---|---|---|
| RTO zone | $329.17 | 3,969 | |
| ComEd zone | $329.17 | 2,082 | |
| DEOK zone | $329.17 | 952 | |
| EMAAC zone | $329.17 | 615 | |
| MAAC zone | $329.17 | 445 | |
| ATSI zone | $329.17 | 2,048 | |
| DOM zone | $329.17 | 203 | |
| Total | 10,314 | ||
Nuclear Plant License Renewal
In July 2025, our application for license renewal at our Perry Nuclear Plant was approved by the NRC. The license now extends through 2046.
OBBBA and CAMT
In July 2025, the legislation known as the OBBBA was signed into law and we have accounted for the effects in our consolidated financial statements. Key changes include the immediate expensing of domestic research and development costs, the reinstatement of 100% bonus depreciation, and increases in the limitation of interest deductibility. Certain provisions of the OBBBA will change the timing of cash tax payments in the current fiscal year and future year periods, however the legislation did not have a material impact on our consolidated financial statements. We do not expect Vistra to be subject to the corporate alternative minimum tax (CAMT) in the 2025 tax year as it applies only to corporations with a three-year average annual adjusted financial statement income in excess of $1 billion. We have taken the CAMT and forecasted OBBBA impacts into account when forecasting cash taxes.
Macroeconomic Conditions
Our industry is subject to uncertainties associated with the impact of rapidly evolving technology on U.S. electricity demand, as well as evolving political, regulatory and economic uncertainties.
Electricity Demand
Emerging electricity demand drivers including the rise of large-scale data centers, the electrification of oil field operations, and electric vehicle load building are contributing to a faster-paced load growth in the regions we serve. Our integrated retail electricity and power generation operations allows us to quickly respond to electricity demand changes. We are actively engaged in discussions with various counterparties regarding the potential long-term sale of power from both our operating nuclear and gas facilities as well as facilities in development to support large-scale electricity consumers.
Our business and these types of transactions are subject to inherent risks and uncertainties, including regulatory reviews, necessary approvals, and potential legislative actions. Such factors could affect the timing and feasibility of finalizing any definitive agreements with large scale electricity consumers.
Supply Chain Constraints
Our industry continues to face ongoing supply chain constraints and labor shortages, which have reduced the availability of essential equipment and supplies for constructing new generation facilities, increased lead times for procuring materials and raised labor costs associated with maintaining our natural gas, nuclear, and coal fleet.
We are proactively managing these constraints by continuously re-evaluating the business cases and timing of our planned development projects. This has led to the deferral or abandonment of some planned capital expenditures for our solar and battery projects and could impact the economic feasibility of additional projects in our new generation development pipeline. We are engaging with suppliers to secure key materials needed to maintain our existing generation facilities before future planned outages.
Russia/Ukraine Conflict
We are closely monitoring developments in the Russia and Ukraine conflict, specifically sanctions (or potential sanctions) against Russian energy exports and Russian nuclear fuel supply and enrichment activities, and actions by Russia to limit energy deliveries, which may further impact commodity prices in Europe and globally. The Prohibiting Russian Uranium Imports Act (PRUI Act), which was signed into law on August 11, 2024, prohibits importation of Russian uranium; however, the Department of Energy can issue waivers (subject to decreasing annual caps) until December 31, 2027 if there is no alternate source of low-enriched uranium available to keep U.S. nuclear reactors operating or is in the national interest. Additionally, passage of the PRUI Act enabled the allocation of $2.72 billion in federal funding to ramp up production of domestic uranium fuel. On November 15, 2024, the Russian Federation temporarily suspended shipments of uranium to the U.S., stating that they would grant future export licenses on a case-by-case basis.
Our 2025 and 2026 refueling plans have not been affected by the Russia and Ukraine conflict, nor have we seen any disruption to the delivery of nuclear fuel impacting our refueling schedules. All nuclear fuel requirements for 2025 and 2026 are either in inventory or are onshore. We work with a diverse set of global nuclear fuel cycle suppliers to procure our nuclear fuel years in advance. We have nuclear fuel contracted to support all our refueling needs through 2030 without any additional Russian deliveries. We continue to take affirmative action by building strategic inventory and deploying mitigating strategies in our procurement portfolio to ensure we can secure the nuclear fuel needed to continue to operate our nuclear facilities through potential Russian supply disruption.
Moss Landing 300 Incident
On January 16, 2025, we detected a fire at our Moss Landing 300 MW energy storage facility at the Moss Landing Power Plant site (the Moss Landing Incident) that resulted in ceasing operations at all facilities at the Moss Landing complex until the fire was contained. No injuries occurred due to the fire or the Company's response. The Moss Landing complex includes two other battery facilities and a gas plant. The gas plant returned to service in February 2025, but the two other battery facilities remain offline as we continue to investigate the cause of the fire. We expect the Moss Landing 350 MW battery to return to service in late 2025 or early 2026. There is less certainty about the return to service regarding the Moss Landing 100 MW battery. We will know more after the investigation of the cause of the Moss Landing Incident is complete. As of September 30, 2025, the net book value of the Moss Landing 100 facility was approximately $165 million.
As a result of the damage caused by the Moss Landing Incident, during the three months ended March 31, 2025, we wrote-off the net book value of Moss Landing 300 of approximately $400 million to depreciation expense and moved the asset to the Asset Closure segment as we have no plans to return the Moss Landing 300 facility to operations (see Notes 6 and 16 to the Financial Statements for additional information).
In July 2025, we entered into an Administrative Settlement Agreement and Order on Consent (ASAOC) with the EPA related to the Moss Landing 300 site. Under the ASAOC, we are required to perform specific battery removal and remediation activities, including battery removal and disposal, building demolition, and air and water monitoring. We estimate the total cost of these activities to be approximately $110 million. We have incurred expenses of approximately $29 million on ASAOC activities through September 30, 2025. As of September 30, 2025, our accrual for estimated future costs for the ASAOC activities is approximately $81 million, of which, $68 million is reflected in other current liabilities and $13 million is reflected in other noncurrent liabilities and deferred credits in the condensed consolidated balance sheets. This estimate assumes the ASAOC activities will be completed by the end of 2026. Aside from battery removal and disposal, our estimate does not reflect costs associated with removal of other hazardous waste that could be identified as the demolition progresses as we are unable to estimate such costs until sampling of waste material is complete. We will account for any adjustments to the accrual as a change in estimate in the period new information becomes available.
Additional impacts from the Moss Landing Incident include loss of revenue from the facilities being offline and may include litigation costs and penalties under contracts. We are currently unable to estimate the full impact the Moss Landing Incident will have on us as our estimate will evolve as demolition progresses. See Note 13 to the Financial Statements for additional information.
We have filed insurance claims against applicable insurance policies with combined business interruption and property loss limits of $500 million, net of deductibles. See Note 1 to the Financial Statements for additional information. Given uncertainty in timing of remaining insurance recoveries and additional expenses that could be incurred related to the fire, we cannot predict the full impact this event will have on our 2025 financial statements.
Martin Lake Unit 1 Incident
On November 27, 2024, we experienced a fire at Unit 1 of our Martin Lake facility in ERCOT (the Martin Lake Incident), an 815 MW unit. We wrote-off the unit's net book value of less than $1 million to depreciation expense in December 2024. We expect the unit to return to service in late 2025 or early 2026. We estimate total cash capital expenditures required to restore the unit to service will be approximately $355 million, of which approximately $155 million in cash capital expenditures were incurred in the nine months ended September 30, 2025.
We expect to recover a majority of the expenditures associated with the Martin Lake Incident through property damage insurance and to receive additional business interruption proceeds. See Note 1 to the Financial Statements for additional information. Given uncertainty in timing of remaining insurance recoveries, we cannot predict the full impacts this event will have on our 2025 financial statements.
Acquisition of Noncontrolling Interest
On September 18, 2024 (the UPA Transaction Date), Vistra Operations and Vistra Vision Holdings I LLC, an indirect subsidiary of Vistra Operations (Vistra Vision Holdings), entered into separate Unit Purchase Agreements (as amended, the UPAs) with each of Nuveen Asset Management, LLC (Nuveen) and Avenue Capital Management II, L.P. (Avenue), pursuant to which Vistra Vision Holdings agreed to purchase each of Nuveen's and Avenue's combined 15% noncontrolling interest in Vistra Vision for approximately $3.2 billion in cash (collectively, the Transaction). The Transaction closed on December 31, 2024 and Vistra Vision Holdings now owns 100% of the equity interests in Vistra Vision. See Notes 2 and 9 to the Financial Statements for additional information.
Planned Gas-Fueled Dispatchable Power in ERCOT
In May 2024, we announced our intention to add up to 2,000 MW of dispatchable, natural gas-fueled electricity capacity in west, central, and north Texas consisting of the following projects:
Building up to 860 MW of advanced simple-cycle peaking plants to be located in west Texas to support the increasing power needs of the region, including the state's oil and gas industry.
Repowering the coal-fueled Coleto Creek Power Plant near Goliad, Texas, set to retire in 2027 to comply with EPA rules, as a natural-gas fueled plant with up to 600 MW of capacity.
Completing upgrades at existing natural gas-fueled plants that will add more than 500 MW of summer capacity and 100 MW of winter capacity.
In July 2024, we filed applications with the PUCT under the Texas Energy Fund loan program seeking financing for the 860 MW of new advanced simple-cycle peaking plants referenced above. Both projects were selected for due diligence as part of the Texas Energy Fund loan program, which is ongoing. An invitation to due diligence does not mean an applicant is awarded a loan.
In September 2025, we announced we will move forward with construction of the 860 MW peaking plants discussed above. Early development work is underway, and we anticipate the units will be online in 2028.
Merger with Energy Harbor
On March 1, 2024 (Merger Date), pursuant to a transaction agreement dated March 6, 2023, (i) Vistra Operations transferred certain of its subsidiary entities into Vistra Vision, (ii) Black Pen Inc., a wholly owned subsidiary of Vistra, merged with and into Energy Harbor, (iii) Energy Harbor became a wholly owned subsidiary of Vistra Vision, and (iv) affiliates of Nuveen and Avenue exchanged a portion of the Energy Harbor shares held by Nuveen and Avenue for a 15% equity interest of Vistra Vision (collectively, Energy Harbor Merger). The Energy Harbor Merger combined Energy Harbor's and Vistra's nuclear and retail businesses and certain Vistra Zero renewables and energy storage facilities to provide diversification and scale across multiple carbon-free technologies (dispatchable and renewables/storage) and the retail business. The cash consideration for Energy Harbor Merger was funded by Vistra Operations using a combination of cash on hand and borrowings under the Commodity-Linked Facility, the Receivables Facility, and the Repurchase Facility. See Note 2 to the Financial Statements for additional information.
Inflation Reduction Act of 2022 (IRA)
In August 2022, the U.S. enacted the IRA, which, among other things, implements substantial new and modified energy tax credits, including recognizing the value of existing carbon-free nuclear power by providing for a nuclear PTC, a solar PTC, new technology-neutral ITCs and PTCs that apply to various different clean energy technologies and a first-time stand-alone battery storage investment tax credit. The IRA also implements a 15% corporate alternative minimum tax (CAMT) on book income of certain large corporations, and a 1% excise tax on net stock repurchases. The section 45U nuclear PTC is available to existing nuclear facilities from 2024 through 2032 and provides a federal tax credit of up to $15 per MWh, subject to phase out when annual gross receipts are between $25.00 per MWh and $43.75 per MWh and $26.00 per MWh and $44.75 per MWh for 2024 and 2025, respectively (each subject to annual inflation adjustments). The Company accounts for transferable ITCs and PTCs we expect to receive by analogy to the grant model within International Accounting Standards 20, Accounting for Government Grants and Disclosures of Government Assistance. As discussed in Note 1 to the Financial Statements in our 2024 Form 10-K, we recognized transferable nuclear PTC revenues of $545 million in the year ended December 31, 2024. As discussed in Note 4 to the Financial Statements, we recognized transferable nuclear PTC revenues of $145 million in each of the three and nine months ended September 30, 2025. U.S. Treasury regulations are expected to further define the scope of the legislation in many important respects, including interpretive guidance on the definition of gross receipts for the nuclear PTC. Any interpretive guidance on the definition of gross receipts that differs from the interpretation used in our estimates could result in a material change to PTC revenues recorded in 2024 and 2025 and would be reflected as a change in estimate in the period in which the guidance is received
The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.