6. Property, Plant, and Equipment

  1. PROPERTY, PLANT, AND EQUIPMENT

Our property, plant, and equipment consist of our power generation assets, related mining assets, land, information systems hardware, capitalized corporate office lease space, and other leasehold improvements. Land and construction work in progress are not depreciated.

June 30,2025December 31,2024
(in millions)
Power generation and structures$22,298$22,783
Office and other equipment173160
Land614603
Construction work in progress (a)1,5571,060
Finance lease right-of-use assets186186
Nuclear fuel2,0061,843
Property, plant and equipment — gross26,83426,635
Less accumulated depreciation(8,541)(8,020)
Less finance lease right-of-use assets accumulated amortization(37)(33)
Less accumulated amortization on nuclear fuel(520)(409)
Property, plant and equipment — net$17,736$18,173

(a)In the second quarter of 2025, we recognized impairments of $68 million related to development projects we have no plans to complete.

Depreciation and amortization of property, plant, and equipment (including the classification in the condensed consolidated statements of operations) consisted of the following:

Property, Plant, and Equipment · Condensed Consolidated Statements of Operations · Three Months Ended June 30, · Six Months Ended June 30,
2025 · 2024 · 2025 · 2024
(in millions)
Power generation and structures and office and other equipmentDepreciation and amortization$497$389$976$754
Finance lease right-of-use assetsDepreciation and amortization2244
Nuclear fuelFuel, purchased power costs, and delivery fees12297237146
Total property, plant, and equipment expense$621$488$1,217$904

Retirement of Generation Facilities

Below are our facilities that are retired or have an announced retirement date. Operating results for generation facilities with defined retirement dates are included in our Asset Closure segment in the calendar year the retirement occurs or is expected to occur. The Moss Landing 300 facility was transferred to the Asset Closure segment during the first quarter of 2025 as we do not plan to return the asset to operations. See Note 1 for additional information.

FacilityLocationISO/RTOFuel TypeNet Capacity (MW)Expected or Actual Retirement Date (a)Segment
BaldwinBaldwin, ILMISOCoal1,185By the end of 2027East
Coleto CreekGoliad, TXERCOTCoal650By the end of 2027Texas
KincaidKincaid, ILPJMCoal1,108By the end of 2027East
Miami FortNorth Bend, OHPJMCoal1,020By the middle of 2028East
NewtonNewton, ILMISOCoal615By the end of 2027East
EdwardsBartonville, ILMISOCoal585Retired January 1, 2023Asset Closure
Total5,163

(a)Expected retirement dates may change if economic or other conditions dictate.

The Company intends to repower Coleto Creek as a gas-fueled facility upon its retirement as a coal-fueled facility. We are currently evaluating the feasibility of converting the other coal-fueled facilities with expected retirement dates in 2027 and 2028 to gas-fueled facilities.