3. Retirement of Generation Facilities

  1. RETIREMENT OF GENERATION FACILITIES

Operational results for plants with defined retirement dates are included in our Sunset segment beginning in the quarter when a retirement plan is announced and moved to the Asset Closure segment at the beginning of the calendar year the retirement is expected to occur.

FacilityLocationISO/RTOFuel TypeNet Generation Capacity (MW)Announced Retirement Date (a)Segment
BaldwinBaldwin, ILMISOCoal1,185By the end of 2025Sunset
Coleto CreekGoliad, TXERCOTCoal650By the end of 2027 (b)Sunset
KincaidKincaid, ILPJMCoal1,108By the end of 2027Sunset
Miami FortNorth Bend, OHPJMCoal1,020By the end of 2027Sunset
NewtonNewton, ILMISO/PJMCoal615By the end of 2027Sunset
EdwardsBartonville, ILMISOCoal585Retired January 1, 2023Asset Closure
JoppaJoppa, ILMISOCoal802Retired September 1, 2022Asset Closure
JoppaJoppa, ILMISONatural Gas221Retired September 1, 2022Asset Closure
ZimmerMoscow, OHPJMCoal1,300Retired June 1, 2022Asset Closure
Total7,486

(a)Generation facilities may retire earlier than announced dates if economic or other conditions dictate.

(b)Following the retirement of Coleto Creek as a coal-fueled plant, the Company intends to repower it as a gas-fueled plant.