Skip to main content

Bimergen Energy Corp

For the period ended Jun 30, 2025. Filed Aug 14, 2025.

View on SEC.gov

About this filing

A company's report for each of its first three quarters. The financial statements are not audited. It shows how the business has moved since the last annual report, and what management says changed.

Jun 30, 2025 · Filed Aug 14, 2025

BESS$3.03+14.8%Stored close · as of Nov 6, 2026

Extracted filing text, with the paragraph anchors used by the comparison.

See the whole filing, with its images and exhibits

Notes to Condensed Consolidated Financial Statements

NOTE 1. DESCRIPTION OF BUSINESS AND GOING CONCERN

Bimergen Energy Corporation (the “Company”, “we” or “us”) was incorporated under the laws of Delaware on March 4, 1998. In connection with the Company’s planned expansion of its business following the completion of the acquisition of Bitech Mining Corporation, a Wyoming corporation (“BTM”), it filed a Certificate of Amendment to its Certificate of Incorporation, as amended (the “Certificate of Amendment”) with the Secretary of State of the State of Delaware on April 29, 2022 to change its corporate name to Bitech Technologies Corporation. On January 28, 2025, the Company filed a Certificate of Amendment to its Certificate to Incorporation to: (i) effect a reverse stock split of its common stock, par value $0.001 per share (the “Common Stock”) at a ratio of 1 post-split share for every 140 pre-split shares; and (ii) to change the name of the Company to Bimergen Energy Corporation.

In April 2024, the Company acquired a portfolio of development-stage Battery Energy Storage System (BESS) and solar energy projects from Emergen Energy LLC (“Emergen”). The acquired portfolio includes 23 utility-scale BESS projects with an estimated cumulative storage capacity of 1.965 gigawatts (GW) and 13 utility-scale solar energy projects with an anticipated cumulative generation capacity of 1.640 GW (collectively, the “Development Projects”), subject to completion of development, construction, and interconnection milestones. The Company became the sole project owner upon acquisition.

As of the date of this filing, the Development Projects are in various stages of development and have not yet achieved commercial operation. The Company expects that certain BESS projects may be collocated with solar projects, depending on site configuration and permitting.

Reverse Stock Split

On February 3, 2025, the Company’s shareholders approved and the Company effected a reverse stock split of the shares of common stock at a ratio of 1-for-140 (the “Reverse Stock Split”). The number of authorized shares and par value per share were not adjusted as a result of the Reverse Stock Split. All references to shares, restricted stock awards, and options to purchase common stock, share data, per share data, and related information contained in the financial statements have been retrospectively adjusted to reflect the effect of the Reverse Stock Split for all periods presented.

Going Concern

The Company’s consolidated financial statements are prepared using the generally accepted accounting principles applicable to a going concern, which contemplates the realization of assets and liquidation of liabilities in the normal course of business. However, the Company has incurred substantial recurring losses from continuing operations, negative cash flows from operations, and is dependent on additional financing to fund operations. We incurred a net loss of approximately $1.7 million and $1.1 million for the six months ended June 30, 2025 and 2024. As of June 30, 2025, the Company had cash and cash equivalents of approximately $0.02 million and an accumulated deficit of approximately $6.5 million. These conditions raise substantial doubt about the Company’s ability to continue as a going concern within one year after the date the financial statements are issued. The consolidated financial statements do not include any adjustments relating to the recoverability and classification of recorded asset amounts and classification of liabilities that might be necessary should the Company be unable to continue in existence. The Company will need additional funding to sustain operations, satisfy existing and future obligations and liabilities, and otherwise support the Company’s operations and business activities and working capital needs. Management’s plans include attempting to secure additional required funding through equity or debt financings if available, seeking to enter into one or more strategic agreements regarding, or sales of development rights. There is no assurance that the Company will be successful in obtaining the necessary funding to sustain its operations or meet its business objectives.

NOTE 2. SIGNIFICANT ACCOUNTING POLICIES

Basis of Presentation and Consolidation

The accompanying condensed consolidated financial statements have been prepared in accordance with U.S. generally accepted accounting principles (“U.S. GAAP”) and the requirements of the Securities and Exchange Commission (the “SEC”) for interim reporting. As permitted under those rules, certain footnotes or other financial information that are normally required by U.S. GAAP can be condensed or omitted. These condensed financial statements have been prepared on the same basis as the annual financial statements included in the Annual Report on Form 10-K for the fiscal year ended December 31, 2024, filed with the SEC on May 30, 2025.

In the opinion of the Company’s management, the information in these condensed financial statements reflects all adjustments, all of which are of a normal and recurring nature necessary for a fair statement of the financial position and results of operations for the reported interim periods. The Company considers events or transactions that occur after the balance sheet date but before the financial statements are issued to provide additional evidence relative to certain estimates or to identify matters that require additional disclosure. The results of operations for interim periods are not necessarily indicative of results to be expected for the full year or any other interim period.

Any reference in these notes to applicable guidance is meant to refer to the authoritative U.S. GAAP as found in the Accounting Standards Codification (“ASC”) and Accounting Standards Updates (“ASU”) of the Financial Accounting Standards Board (“FASB”).

The unaudited consolidated financial statements represent the consolidation of the accounts of the Company, its subsidiaries. All intercompany accounts and transactions have been eliminated in consolidation.

Use of Estimates

The preparation of financial statements in conformity with GAAP requires management to make estimates and assumptions that affect the reported amounts of assets, liabilities and the disclosure of contingent assets and liabilities at the date of the financial statements and the reported amounts of expenses during the reporting period. On an ongoing basis, the Company evaluates its estimates and assumptions, including those related to variable consideration and stock based compensation. Management bases its estimates on historical experience and on various other assumptions that are believed to be reasonable under the circumstances, the results of which form the basis for making judgments about the carrying values of assets and liabilities and the amount reported as revenue and expenses that are not readily apparent from other sources. Actual results may differ materially from those estimates.

Significant Accounting Policies

There have been no material changes to the accounting policies discussed in Note 2 to the financial statements included in the Company’s Annual Report on Form 10-K for the fiscal year ended December 31, 2024, filed with the SEC on May 30, 2025.

Recent Accounting Pronouncements Not Yet Adopted

In December 2023, the FASB issued ASU 2023-09, Income Taxes (Topic 740): Improvements to Income Tax Disclosures. This ASU requires public entities, on an annual basis, to provide disclosure of specific categories in the rate reconciliation, as well as disclosure of income taxes paid disaggregated by jurisdiction. ASU 2023-09 is effective for fiscal years beginning after December 15, 2024, with early adoption permitted. The amendments in this ASU should be applied prospectively; however, retrospective application is also permitted. The Company is currently evaluating the impact from the adoption of this standard on the Company’s financial statements.

In November 2024, the FASB issued ASU No. 2024-03, Income Statement - Reporting Comprehensive Income - Expense Disaggregation (Subtopic 220-40): Disaggregation of Income Statement Expenses. The amendments in ASU 2024-03 require a public business entity to disclose specific information about certain costs and expenses in the notes to its financial statements for interim and annual reporting periods. The objective of the disclosure requirements is to provide disaggregated information about a public business entity’s expenses to help investors (a) better understand the entity’s performance, (b) better assess the entity’s prospects for future cash flows, and (c) compare an entity’s performance over time and with that of other entities. ASU 2024-03 is effective for fiscal years beginning after December 15, 2026, and for interim periods within fiscal years beginning after December 15, 2027, with early adoption permitted. The Company is currently evaluating the impact of the adoption of this standard on its financial statements.

NOTE 3. STOCKHOLDERS’ EQUITY

The total number of authorized shares of our common stock, par value $0.001 per share, was 1,000,000,000 shares. As of June 30, 2025 and December 31, 2024, there were 3,857,906 and 5,121,384 common shares issued and outstanding, respectively.

The total number of authorized shares of our preferred stock, par value $0.001 per share, was 10,000,000. There wasno preferred stock outstanding as of June 30, 2025 and December 31, 2024.

During the year ended December 31, 2024 the Company sold 64,337 unregistered shares of its Common Stock to eight private investors for an aggregate of $576,000 ($7.00 - $11.20 per share)

The Company issued 18,616 shares of unregistered shares of its Common Stock for services valued at $117,611 for the six months ended June 30, 2025.

NOTE 4. STOCK OPTIONS

As of June 30, 2025 there were 964,286 options outstanding. The Company does not have an adopted option plan and can issue stock options up to the amount of authorized shares that are not issued and outstanding as of June 30, 2025.

We have granted non-qualified stock options to employees and contractors. All non-qualified options are generally issued with an exercise price no less than the fair value of the common stock on the date of the grant as determined by our Board of Directors. Options typically may be exercised up to ten years following the date of the grant, with vesting schedules determined by us upon grant. Vesting schedules vary by grant, with some fully vesting immediately upon grant to others that ratably vest over a period of time up to five years. Standard vested options may be exercised up to three months following date of termination of the relationship unless alternate terms are specified at grant. The fair values of options are determined using the Black-Scholes option-pricing model. Forfeitures are accounted for as they occur. The estimated fair value of options is recognized as expense on the straight-line basis over the options’ vesting periods. At June 30, 2025, we had approximately $3.9 million unrecognized stock-based compensation related to stock options expected to be recognized over the next 3.3 years on a weighted average.

Stock option transactions during the period ended June 30, 2025 were as follows:

Shares · Weighted- Average Exercise Price · Weighted Average Remaining Contractual Term (in years) · Aggregate Intrinsic Value (in thousands)
Outstanding at December 31, 2024966,072$102.759.0$-
Options Granted--
Options Exercised--
Options Forfeited or Cancelled(1,786)14.70
Options Expired--
Outstanding and Vested or Expected to Vest at June 30, 2025964,286102.918.5-
Options Exercisable at June 30, 2025386,42928.358.1$-

No options were exercised during the period ended June 30, 2025.

We recognized stock compensation of $554,000 and $558,080 related to stock options for the six months ended June 30, 2025 and 2024, respectively, including $289,000 and $64,300 related to stock options for the three months ended June 30, 2025 and 2024, respectively.

NOTE 5. RESTRICTED STOCK AWARDS

Restricted Stock Award transactions during the six months ended June 30, 2025 were as follows:

SharesWeighted- Average Grant Date Fair Value
Unvested at Beginning of Period69,883$34.05
Granted--
Vested(4,285)11.20
Forfeited or Cancelled RSAs--
Unvested at End of Period65,598$35.18

At June 30, 2025, we had approximately $0.1 million unrecognized stock-based compensation related to restricted stock awards. The weighted average non-performance based will be recognized over the next 0.5 years.

There are 65,598 performance RSAs unvested with a weighted average grant date fair value of $2.3 million at June 30, 2025.

We recognized stock compensation of $48,000 and $54,000 related to restricted stock awards for the six months ended June 30, 2025 and 2024, respectively, including $24,000 and $0 related to restricted stock awards for the six months ended June 30, 2025 and 2024, respectively.

NOTE 6. ACQUISITION OF EMERGEN ENERGY LLC

On April 24, 2024 (the “Closing”), Bimergen Energy Corp. (the “Company”) acquired 100 % of the membership interests of Emergen Energy LLC (“Emergen”) pursuant to a Membership Interest Purchase Agreement dated April 14, 2024 (as amended on April 24, 2024, the “MIPA”). At Closing the Company issued 1,587,300 unregistered shares of common stock to C & C Johnson Holdings LLC (an entity controlled by Cole Johnson) with a fair value of $22.2 million (based on the $14.00 closing price on April 24, 2024). Emergen became a wholly-owned subsidiary; Mr. Johnson simultaneously became President of the Company’s BESS and Solar divisions and a director of the Company.

Emergen, formed immediately prior to the transaction, held only early-stage renewable-energy development rights and no liabilities or operating activities. Accordingly, management concluded the transaction is an asset acquisition rather than a business combination.

At acquisition Emergen’s assets consisted of 1.965GW and 3.840GW of BESS and Solar Projects, respectively. Because the projects lacked substantive process or outputs, the Company recorded the entire $22.2 million purchase price as indefinite-lived intangible assets (“Development Projects”) and allocated the $22.2 million purchase price to the BESS and Solar portfolios based on relative fair values determined from project-level discounted-cash-flow models corroborated by observable market pricing for comparable development assets. The Company allocated $20.0 million and 2.2 million to BESS and Solar Projects respectively as of the acquisition date.

The following agreements were entered into on the date of Closing as provided for in the MIPA:

On April 24, 2024 the Company and Emergen entered into a PMSA with Energy Independent Partners LLC (“EIP”), an entity controlled by Cole Johnson, under which EIP provides development, permitting, and financing-support services for each project.

On April 24, 2025 the parties executed Amendment No. 2 to the PMSA, stated to be effective June 28, 2024 and governed by Delaware law. Amendment 2 superseded Amendment 1 and eliminated the former Initial-Fee and RTB-Fee construct, replacing it with a single “Development-Fee” model that is payable only when a project secures third-party, project-specific financing. The principal commercial terms now in effect are:

●BESS projects. For each battery-storage project, the Company will owe EIP a development fee of $0.035 per watt once that specific project secures third-party debt and/or equity financing sufficient to fund the fee. Based on the current BESS portfolio capacity (approximately 1.965 GW), the aggregate exposure, if every project achieves financing, would be about $69 million.
●Solar projects. For each solar-power project, the same rate—$0.035 per watt—applies, again only after project-specific financing is in place. Given the remaining solar capacity in the Emergen portfolio (roughly 1.640 GW), the maximum potential fees total approximately $57 million.
●Other renewable projects. For any future development projects that are neither BESS nor solar, the fee is the greater of (i) 50 percent of gross margin or (ii) $0.02 per watt, payable once the project reaches ready-to-build (RTB) status. Because the Company has no such projects in its pipeline today, no aggregate cap is presently estimable.

Based on portfolio capacities; actual fees depend on future financings and may not be incurred.

●Sale-of-Project Clause – If a project is sold, EIP is entitled to the greater of unpaid Development Fees or 62.5 % of net sale proceeds.
●Acceleration Clause – 62.5 % of unpaid fees accelerate within 90 days of (i) a change in control of the Company or (ii) removal of Mr. Johnson from his role.
●Termination & Indemnification – The PMSA may be terminated by mutual consent or for cause; customary indemnities apply.

Because payment is contingent on future project-financing milestones, no PMSA liabilities have been recognized as of June 30, 2025.

NOTE 7. SOLAR PROJECTS SALE

On May 30, 2024, Emergen Energy LLC (“Emergen”) entered into a Project Sale Agreement (“PSA”) with Bridgelink Development, LLC (“Bridgelink”) covering 2.425 GW of green-field solar projects (the “Greenfield Projects”). Bridgelink simultaneously resold the projects to an unrelated third-party purchaser (“Purchaser”).

Total consideration payable to Emergen is $19.4 million, comprising:

●a non-refundable deposit of $0.9 million received in June 2024; and
●$18.5 million in milestone payments—$5,000 per MW upon securing necessary land rights and $3,000 per MW upon the project reaching ready-to-build (“RTB”) status. There is no specified timetable for milestone achievement.

The deposit is recorded as contract liability (deferred revenue). Revenue (and related cost) will be recognized at a point in time when the relevant milestones are achieved by the purchaser, which management expects within twelve months of year-end. No milestone revenue was recognized in 2024 because the required conditions were not met.

Under the Project Management Services Agreement (“PMSA”), Emergen remits 62.5 % of amounts received to Energy Independent Partners LLC (“EIP”), an entity controlled by Cole Johnson, and retains 37.5 %. Accordingly, $0.25 million of the June 2024 deposit was paid to EIP and the remaining $0.4 million remains deferred and recorded as accounts payable and accrued liabilities – related parties. Additional EIP payments will be recorded only when Bridgelink remits milestone proceeds. Bridgelink may return a project, without refund, only if no milestone payment has yet been made and the return occurs within seven years of the PSA’s effective date. A December 31, 2024 amendment clarified that all funds paid to Emergen are non-refundable and limited the return option as noted above; all other material terms remain unchanged.

NOTE 8. RELATED PARTY TRANSACTIONS

All transactions described in Notes to the Financial Statements 6 and 7 were transacted with a now related party, Cole Johnson, President and Director, as of the April 24, 2024 acquisition of Emergen Energy, LLC. All negotiations related to these transactions were prior to Cole Johnson being a related party to Bimergen.

During the six months ended June 30, 2025 the Company issued seven unsecured promissory notes, aggregating $415,300, to EIP, an entity controlled by president and director Cole Johnson. The notes were executed per the schedule below:

Promissory Notes Executed:

March 3, 2025$60,000
March 28, 2025$75,000
April 22, 2025$25,000
April 30, 2025$75,000
May 30, 2025$77,300
June 9, 2025$28,000
June 30, 2025$50,000
$415,300

The notes bear simple interest at 9.5 percent per annum, mature on December 31, 2025, are pre-payable without penalty, and were used to fund working-capital for operating expenses. Accrued interest at June 30, 2025 was approximately $4,600.

NOTE 9 SEGMENT INFORMATION

The Company operates and manages its business asone reportable operating segment. The Company’s CODM, the Chief Executive Officer, reviews internal financial information presented and decides how to allocate resources based on net income (loss). Net income (loss) is used for evaluating financial performance.

Significant segment expenses include salaries and payroll, legal fees, stock based compensation, audit costs, contract services, rent, and other administrative expenses. The measurement of segment assets is reported on the consolidated balance sheets as total assets. The following table presents the significant segment expenses and other segment items regularly reviewed by our CODM.

For the Three Months Ended June 30, 2025For the Three Months Ended June 30, 2024For the Six Months Ended June 30, 2025For the Six Months Ended June 30, 2024
Revenues · $ · - · $ · - · $ · - · $ · -
Cost of Goods Sold----
Gross Profit----
Operating Expenses
Salaries and Payroll Expenses182,00065,500360,000114,000
Legal Fees10,483101,71313,749203,961
Stock-based compensation289,000493,780602,000588,080
Investors Relations5,22724,268125,37824,686
Audit Costs131,2509,750169,25027,500
Contract Services143,61583,171293,12083,171
Rent4,8244,4739,7899,143
Other operating expenses49,67040,24599,82086,194
Total Operating Expenses816,069822,9001,673,1061,136,735
Loss (Income) from Operations(816,069)(822,900)(1,673,106)(1,136,735)
Interest Income and Other (Expenses), net(5,340)-(5,947)328
Net loss before Income Tax$(821,409)$(822,900)$(1,679,053)$(1,136,407)

NOTE 10 COMMITMENTS AND CONTINGENCIES

The Company is subject to various claims, legal actions, and regulatory proceedings arising in the ordinary course of business. In the opinion of management, after consultation with legal counsel, the ultimate resolution of these matters is not expected to have a material adverse effect on the Company’s financial position, results of operations, or cash flows.

Joint-Venture Agreement with RelyEZ Energy Group

On April 20, 2025, the Company’s wholly-owned subsidiary, Emergen Energy, LLC, executed a definitive agreement with RelyEZ Energy Group to form a joint venture to develop, construct and operate up to 2 GW of utility-scale battery-energy-storage projects (2- to 4-hour BESS) in the United States through 2027.

Ownership and economics. Until project refinancing, each project SPV will be owned 80 percent by RelyEZ and 20 percent by Emergen. After refinancing, the Company may repurchase RelyEZ’s interest at cost plus a 12 percent annual return.

Capital commitments. RelyEZ has committed up to $50 million, including an initial $10 million funding within ten days of closing. Emergen will contribute up to $12.5 million on a 20 percent pro-rata basis after RelyEZ’s first $10 million is funded. Because the closing conditions (including RelyEZ’s initial funding) had not been satisfied as of June 30, 2025, the Company had no present funding obligation and no liability recorded in these financial statements. This mezzanine capital will be used to advance long-lead items and qualifying the BESS projects for permanent debt financing.

Status of accounting evaluation. The agreement had not closed as of June 30, 2025; therefore no assets, liabilities, revenues or expenses related to the joint venture are reflected in the accompanying financial statements. Management will assess variable-interest-entity (VIE) status and consolidation under ASC 810 when the venture is legally formed and capitalized.

NOTE 11. SUBSEQUENT EVENTS

Subsequent to June 30, 2025 the Company has issued three additional unsecured promissory notes to EIP under terms substantially identical to those described in Note 8, totaling $175,000 of principal.

Joint-Venture Agreement with RelyEZ Energy Group

On August 11, 2025, RelyEZ completed the funding as required by the definitive agreement to the Joint Venture which satisfies the closing conditions of the definitive agreement.

Joint-Venture Agreement Letter of Agreement with Cox Energy Group

On August 11, 2025, the Company’s wholly-owned subsidiary, Emergen Energy, LLC, executed a letter of agreement (LOA) with Cox Energy Group (operating from Madrid, Spain) to form a joint venture to develop, construct and operate up to 1 GW of utility-scale battery-energy-storage projects in the United States to reach ready-to-build status during calendar years 2025 and 2026.

Ownership and economics. Until project refinancing, it is anticipated that each project entity will be owned 75 percent by Cox and 25 percent by Emergen. After refinancing, it is expected that Cox will maintain at least 51% equity ownership.

Capital commitments. Cox has agreed to an initial capital commitment of $10 million to fund pre-construction and early-stage construction activities. The Cox JV agreement allows for a total of up to $200 million of equity financing if the parties mutually agree on project-acceptance terms. This capital will serve as the equity component (typically 10 - 20%) required for permanent debt financing.

ContentsView on SEC.gov

The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.