Item 1. Legal Proceedings

On October 20, 2023, Sweet Cut Grow, LLC and Green Ice, LLC (collectively, “Claimant”) a client of the Company with which it had an equipment contract and engineering contract, filed a demand for arbitration asserting claims for breach of contract, breach of warranty, and unjust enrichment, and demand for $1,049,280 in damages, plus interest (“Claims”). The Company continues to deny all the Claims and has asserted a counterclaim. The Company believes Claimant is owed nothing as the Company fulfilled all its obligations under the contracts to Claimant, and further, that the negligence of a third-party supplier is the basis of the Claims. We intend to generally defend the claims on the basis that we promptly addressed all problems, and that any issues with defective HVAC equipment are the responsibility of our third-party equipment manufacturer. The Company’s equipment contract with Claimant requires the parties to arbitrate their disputes under the rules of the American Arbitration Association (“AAA”). The arbitration will be heard in Denver, Colorado in September 2025. The matter is in the discovery phase. The parties will pay their own legal fees and expenses. The Company intends to defend itself vigorously, believing there are no merits to the claims as currently presented.

Given the current uncertainty around estimating the likelihood of success of claims and potential damages, we have not recorded an accrual for any potential loss related to these matters.

On or about April 17, 2024, Optima Consulting Services, LLC (the “Claimant”), a client of the Company with which it had an equipment contract and engineering contract, advised the Company of a potential claim related to work performed by the Company for Claimant and demanded mediation under the parties’ contract. On or about October 28, 2024, Claimant informed the Company it was asserting claims for negligent/defective design and breach of warranty, and alleges its damages exceed $2,000,000 (Claims”). The Company denies all the Claims and that Claimant is entitled to any damages. The Company believes Claimant is owed nothing as the Company fulfilled all its obligations under the contracts to Claimant and performed all work in line with all applicable standards. We intend to generally defend the Claims on the basis that all work was performed pursuant to the contract and any alleged issues that may have occurred were the result of actions by Claimant and/or third parties. If Claimant moves forward with its Claims, the Company’s equipment contract with Claimant requires the parties to arbitrate their dispute with the American Arbitration Association (“AAA”). The arbitration will be heard in Denver, Colorado. The matter is in the preliminary phase. The parties will pay their own legal fees and expenses. The Company intends to defend itself vigorously, believing there are no merits to the Claims as currently presented.

From time to time, we may be a party to certain legal proceedings in the ordinary course of business, including proceedings relating to the enforcement of our rights under contracts with our customers. While the outcome of these legal proceedings cannot be predicted with certainty, we do not expect that these proceedings will have a material effect upon our financial condition or results of operations.

ContentsView on SEC.gov

The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.