Item 2. Properties

Our sole exploration and development property is the Whistler Project, located in the Yentna Mining District of Alaska, approximately 170 km northwest of Anchorage.

We also lease and maintain an office at 301 Calista Court, Suite 200, Office 203, Anchorage, Alaska, 99518. We also maintain office space at 1188 West Georgia Street, Suite 1830, Vancouver, British Columbia, Canada, V6E 4A2. We do not currently own any real estate. We believe that we have adequate space for our anticipated needs and that suitable additional space will be available at commercially reasonable prices as needed.

The Whistler Project

The following information is primarily condensed and extracted from the S-K 1300 Report. Readers should refer to the full text of the S-K 1300 Report, attached hereto as Exhibit 96.1, for further information regarding the Whistler Project.

Project Description, Location and Access

The Whistler Project is a gold-copper exploration project located in the Yentna Mining District of Alaska, approximately 170 km (105 miles) northwest of Anchorage.

As of the date hereof, the Whistler Project comprises 377 State of Alaska mining claims covering an aggregate area of approximately 217.5 km 2. The center of the property is located at 152.566° longitude west and 61.983° latitude north. The Whistler Project is located in the drainage of the Skwentna River. Elevation varies from about 400 masl in the valley floors to over 5,000 masl in the highest peaks.

An all-season camp facility exists near the confluence of Portage Creek and the Skwentna River, approximately 15 km southeast of the Rainy Pass Hunting Lodge. The camp is serviced with a 1,000 m gravel airstrip for wheel-based aircraft. The camp is equipped with kitchen and messing facility, ablutions facility, accommodations for up to 24 personnel, a maintenance workshop, water well and potable water filtration system, septic field system, diesel generators, office and core logging and sampling facility and a satellite communications link, tent structures on wooden floors, and several wood-framed buildings.

The following map sets forth the location of the Whistler Project and shows the proposed alignment of the West Susitna Access Road.

Royalties and Encumbrances

We acquired rights to the Whistler Project and certain related assets in August 2015 for a total cost of approximately $1.32 million pursuant to an asset purchase agreement dated July 20, 2015, by and among us, GoldMining, Kiska and Geoinformatics. Pursuant to such agreement, we acquired rights and assumed obligations under several related underlying agreements. The related underlying agreements on the Whistler Project are listed below:

1.2.75% net smelter return (“NSR”) over all 377 claims and extending outside the current claims over an Area of Interest defined by the maximum historical extent of claims held on the Whistler Project to Osisko Mining (USA) Inc. (“OM”) pursuant to an Amended and Restated Net Smelter Returns Royalty Deed dated December 16, 2014, granted by Geoinformatics (as assumed by us on August 5, 2015) in favour of MF2 LLC (as assumed by OM). Gold Royalty U.S. Corp. holds a right to buy down the royalty percentage from 2.75% to 2.0% upon payment to OM of a one-time payment of $5,000,000. The royalty was subsequently assigned to Nevada Select Royalty, Inc. (a subsidiary of Gold Royalty Corp.).
2.2.0% net proceeds royalty interest over an Area of Interest specified by standard township sub-division overlying the Whistler and Raintree West deposits to Sandstorm Gold Ltd. pursuant to an agreement dated October 1, 1999, between us (the ultimate successor-in-interest to Kent Turner, Jr.) and Sandstorm Gold Ltd. (the ultimate successor-in-interest to Cominco American Incorporated).
3.1.0% NSR over the Whistler Project to Gold Royalty U.S. Corp. pursuant to a Net Smelter Returns Royalty Agreement dated January 11, 2021, between us and Gold Royalty U.S. Corp.

History

Mineral exploration in the Whistler area was initiated by Cominco in 1986 and continued through 1989. During this period, the Whistler and the Island Mountain gold-copper porphyry occurrences were discovered and partially tested by drilling. In 1990, Cominco ceased exploration and all cores from the Whistler region were donated to the State of Alaska and the property was allowed to lapse.

In 1999, Kent Turner staked 25 State of Alaska mining claims at Whistler and leased the property to Kennecott. From 2004 through 2006, Kennecott conducted extensive exploration of the Whistler region, including geological mapping, soil, rock and stream sediments sampling, ground Induced Polarization survey, and the evaluation of the Whistler gold-copper occurrence with fifteen core boreholes (7,948 m) and reconnaissance core drilling at other targets in the Whistler region (4,184 m). Over that period Kennecott invested over $6.3 million in exploration.

In June 2007, Geoinformatics announced the conditional acquisition of the Whistler Project as part of a strategic alliance with Kennecott.

From 2007 through 2008, Geoinformatics drilled twelve holes totaling 5,784 m on the Whistler Deposit and six holes totaling 1,841 m on other exploration targets in the Whistler area. Drilling by Geoinformatics on the Whistler Deposit was done to infill the deposit to sections spaced at 75 m and to test for the north and south extensions of the deposit. Exploration drilling by Geoinformatics in the Whistler area targeted geophysical anomalies in the Raintree and Rainmaker areas, using the same basic porphyry exploration model as Kennecott.

In 2009, Kiska was formed by the merger of Geoinformatics and Rimfire Minerals Corporation. In total, Kiska completed 224 line-km of 3D Induced Polarization geophysics, 40 line-km of 2D IP geophysics, 327 line-km of cut-line, geological mapping on the 3D IP grid, detailed mapping of significant Au-Cu prospects, collection of 109 rock samples and 61 soil samples, 8,660 m of diamond drilling from 23 drillholes (all greater than 200 m in total length), petrographic analysis of mineralization at Island Mountain, a preliminary review of metallurgy at the Whistler Resource, and metallurgical testing of mineralization from the Discovery Breccia at Island Mountain. In August of 2010, Kiska delivered a report to Kennecott summarizing the results of the completed Trigger Program. In September of 2010, Kennecott informed Kiska that it would not exercise its back-in right on the Whistler Project and hence retained a 2% NSR on the property.

From this point forward, Kiska continued to drill and explore the Whistler Project for the duration of the 2010 and 2011 field seasons. The majority of this work included shallow grid drilling (25 m to 50 m top of bedrock drilling) in the Whistler area (also referred to as the Whistler Corridor), conventional step-out drilling from prospects in the Whistler area, step-out drilling at the Island Mountain deposit, an airborne EM survey of the Island Mountain area, reconnaissance drilling at Muddy Creek, and minor infill drilling at the Whistler Deposit, followed by the publication of an updated resource estimate.

Commencing 2014, the Alaska State Government has studied a ‘Roads to Resources’ initiative. The Alaska Industrial Development and Export Authority (“AIDEA”) has published several studies since 2014 to assess potential road routes and alternatives, and to assess economic benefits of constructing a public access road from Palmer/Wasilla to the Susitna Mining District in the Alaska Range. On October 27, 2021, AIDEA announced the receipt of $8.5 million in funds for the advancement of predevelopment work for the West Susitna Access Road (“WSAR”) project, which would extend into areas west of Cook Inlet in Southcentral Alaska in the vicinity of the Whistler Project. During 2022 - 2024, AIDEA undertook road engineering investigations to support road design and test alternatives, environmental baseline surveys and archaeological surveys, and stakeholder consultation. In 2023, the Alaska Department of Transportation and Public Facilities (the “DOT”) subsequently announced that it has included the first 25 miles of the proposed WSAR within its State Transportation Infrastructure Plan, and in 2024, the DOT commenced stakeholder engagement ahead of planned project permitting and potential construction commencement in 2025.

Geological Setting, Mineralization and Deposit Types

Geological Setting

The Whistler Project is located in the Alaska Range. The Alaska Range is a continuation of the Pacific Coastal Mountains extending in an arc across the northern Pacific, and represents a long-lived continental arc characterized by multiple magmatic events ranging in age from about 76 Ma to 30 Ma and associated with a wide range of base and precious metals hydrothermal sulphide bearing mineralization. The geology of the Whistler Project is characterized by a thick succession of Cretaceous to early Tertiary (ca. 97 to 65 Ma) volcano-sedimentary rocks intruded by a diverse suite of plutonic rocks of Jurassic to mid-Tertiary age.

Two main intrusive suites are important in the Whistler Project area:

●The Whistler Igneous Suite comprises alkali-calcic basalt-andesite, diorite and monzonite intrusive rocks with an age of approximately 76 Ma with restricted extrusive equivalent. These intrusions are commonly associated with gold-copper porphyry-style mineralization (the “Whistler Deposit”).
●The Composite Suite intrusions vary in composition from peridotite to granite and their ages span from 67 to about 64 Ma. Gold-copper veinlets and pegmatitic occurrences are characteristics of the composite plutons (e.g. the Mt. Estelle prospect, the Muddy Creek prospect).

We acquired the project for its potential to host magmatic hydrothermal gold and copper mineralization. Magmatic hydrothermal deposits represent a wide clan of mineral deposits formed by the circulation of hydrothermal fluids into fractured rocks and associated with the intrusion of magma into the crust.

Mineralization and Deposit Types

The Whistler Deposit and prospects in the Whistler Area (Raintree West, Raintree North and Rainmaker) display a common pattern of alteration, vein paragenesis, and mineralization styles that suggest these spatially separate porphyry centres share a common genetic association. These features are hosted by, and genetically linked to, pulses of diorite porphyry intrusive bodies that are nested in pipe-like centres. Geophysical inversion models of the airborne magnetic data suggest that these pipes represent hypabyssal apophyses (stocks and dykes) emanating from a deep causative batholith. That these porphyry centres are genetically associated is corroborated by common alteration assemblages, vein types, mineralization styles and paragenetic relationships. At the Whistler Deposit, the earliest Diorite Porphyry phase (Main Stage Whistler Diorite Porphyry) is associated with the main stage of gold-copper mineralization, whereas subsequent phases are less mineralized, and thus are either weak metal contributors or diluting bodies.

The Whistler Deposit is hosted within the Whistler Intrusive Suite, a composite of diorite stocks and dykes that divide the suite broadly into an early Main Stage Porphyry (“MSP”), a later Intermineral Porphyry Suite (“IMP”) and a late intrusive phase referred to as the Late-Stage Porphyry (“LSP”). Gold and copper mineralization is characterized by abundant disseminated sulphide and quartz + sulphide vein stockworks (including classic porphyry diagnostic ‘A’, ‘B’, ‘D’, and ‘M’ type veins), and potassic alteration which is variably overprinted by later phyllic alteration. The early-stage MSP suite is most strongly altered, veined and mineralized, with the IMP being less intensely altered and veined but remaining consistently mineralized, and the late or post-mineralization LSP generally containing below cut-off grade or being unmineralized. In addition, a robust core of higher-grade mineralization is recognized within the deposit that correlates with intense alteration and B-veining within MSP and IMP in the eastern part of the intrusive suite.

The High-Grade Core contains inner zones of strong potassic and magnetite alteration (see below), which is dominantly overprinted by pervasive chlorite-sericite alteration and local phyllic alteration. This domain is also defined by the consistent occurrence and highest concentration of M-veins and mineralized quartz veins (A- and B-veins), which generally range in volume from 1 to 5%. Local higher-grade mineralization occurs in zones of high-density quartz vein stockwork (locally >20% quartz vein volume) and quartz + magnetite + chalcopyrite cemented hydrothermal breccias.

Mineralization at Raintree West occurs as two main types: 1) early, porphyry-style gold-copper mineralization hosted by diorite porphyry stocks and consisting of quartz and magnetite stockwork veining, with vein and disseminated chalcopyrite associated with potassic alteration, and 2) later cross-cutting silver-gold-lead-zinc mineralization in quartz-carbonate veins that contain pyrite, sphalerite, galena, and chalcopyrite, with occasional banded epithermal-like textures. The early gold-copper mineralization is best developed within, and controlled by, early diorite porphyry intrusions (akin to MSP at the Whistler Deposit), whereas the later silver-gold-lead-zinc veins surround and locally overprint the porphyry mineralization and are most abundant in the host volcanic rocks in zones of strong to intense phyllic alteration vertically above and adjacent to the diorite porphyries.

The Island Mountain deposit area is host to several mineralized zones interpreted to represent a cluster of individual porphyry centres within this large intrusive complex. These include the Breccia, Cirque and Howell Zones, and other prospects defined by surface geochemistry and geophysical anomalies that require further field assessment. Exploration activity and the majority of diamond drilling by Kiska have concentrated on mineralization associated within the Breccia Zone on the southwest slope of Island Mountain. There, at least three styles of significant gold and copper mineralization are currently recognized: 1) gold-copper mineralization hosted by K-feldspar altered monzonitic intrusive breccia, 2) gold-copper mineralization hosted by intrusive and hydrothermal breccias associated with strong sodic-calcic alteration, and 3) gold-only mineralization associated with vein and disseminated pyrrhotite.

The Muddy Creek area represents an additional exploration target with the potential to host a bulk tonnage, intrusion-related gold deposit. Gold mineralization at Muddy Creek is hosted throughout the core of the monzonitic plutonic complex and is controlled by northwest-striking and steeply southwest-dipping, mm- to locally cm-wide veinlets of sulphides and quartz, manifest as rusty-weathering sub-parallel fracture sets, commonly spaced a metre or more apart. These veinlets may contain any combination of chalcopyrite, arsenopyrite, pyrite, stibnite, pyrrhotite and native gold, with minor amounts of galena, sphalerite and molybdenite. Moderate sericitic alteration is typically restricted to cm-wide selvages to these veins, whereas the bulk of the interleaving rock is relatively unaltered and unmineralized. The Muddy Creek prospect may share geological similarities with the Korbel deposit owned by Nova Minerals Limited located 12 miles north.

Exploration

We recommenced exploration work at the Whistler Project in 2023. Prior to this, we had not completed field-based exploration work at the Whistler Project since acquiring the Whistler Project in 2015.

Our strategy is to enhance and grow the value of our asset base, with a focus on exploring to grow the in situ mineral deposits, and to advance mining, environmental and heritage studies on the Whistler Project towards delineation of a mining business case, optimizing bulk mineable near surface deposits.

We are fully permitted to undertake our planned exploration activities. On June 30, 2022, we submitted an APMA to the ADNR in order to commence exploration field work activities in 2023. On September 22, 2022, the ADNR approved the Exploration Permit and Reclamation Plan. On July 7, 2023, we received approval for amendments to the APMA, incorporating alterations to our exploration plans, in 2023 and 2024. On August 6, 2024, we received approval for amendments to the APMA, incorporating alterations to our exploration plans for 2024. The Exploration Permit allows us to conduct exploration including drilling, operate and maintain a camp including storage of fuel, and to transport people, equipment and consumables to the Whistler Project. The Company expects to file amendment applications for APMA 2278 annually, as exploration results and strategy evolve, in order to ensure exploration programs are fully authorized. Prior to expiry of AMPA 2278 on December 31, 2026, the Company plans to apply for a new Exploration Permit.

Drilling

A total of 72,480 m of diamond drilling in 261 holes are documented in the Whistler database for drilling on the Whistler Project by Cominco, Kennecott, Geoinformatics, Kiska and us from 1986 to the end of 2023. Of these drillholes 23,334 m in 53 holes have been drilled in the Whistler Deposit area, 5,190 m in 58 holes have been drilled in the Raintree area, and 15,572 m in 40 holes comprise the Island Mountain resource area. There are 29,385 m in 110 holes in areas outside the three aforementioned mineral resource areas.

In 2024, we drilled six diamond core holes for 4,006 m at the Whistler Project, including four drill holes for 2,782 m completed at the Whistler Deposit, and two drill holes for 1,224 m completed at the Raintree Deposit. Subsequently, drilling completed across the project now totals 76,486 m.

Sampling, Analysis and Data Verification

There is no available documentation about sampling and analysis by Cominco. Previous operators Kennecott, Geoinformatics, and Kiska used industry standard practices to collect, handle and assay soil, rock and core samples collected during the period 2004-2011. These procedures are documented in detailed reports describing pertinent aspects of the exploration data collection and management.

All assay samples were assayed at either the Alaska Assay Laboratory (2004 and 2009) in Fairbanks, Alaska, or the accredited laboratory of ALS Minerals (formerly ALS-Chemex), a division of ALS Limited, a global company that provides testing, inspection and certification services, in Vancouver, British Columbia for all other years. Sample preparation was accomplished in Alaska, either at the Alaska Assay Lab or ALS-Minerals preparation lab in Anchorage, Alaska. Samples were assayed for gold by fire assay and a suite of elements including silver and copper by aqua regia or multi-acid digestion and inductively coupled plasma atomic emission spectroscopy. Operators Kennecott, Geoinformatics, and Kiska used industry standard quality control practices during exploration at Whistler. The S-K 1300 Technical Report discloses that analysis of the QA/QC data indicates the assay data is of sufficient quantity and quality for resource estimation.

Sue Bird, P.Eng., of MMTS, visited the Whistler Project site on September 14, 2022, and again on August 6, 2024. No observations contradicting previously published information were made. In the opinion of the QP, sampling preparation, analysis, and security by previous operators are consistent with industry standard practices. Review and analysis of the assay database and QA/QC data shows the assay database is of sufficient quality for resource estimation.

Mineral Processing and Metallurgical Testing

Metallurgical testing had been carried out in three phases starting with the 2004/2005 preliminary testing in Salt Lake City under the general supervision of Kennecott and culminating in the two phases under Kiska conducted at G&T Laboratories in Kamloops during 2010 to 2012.

Whistler Deposit preliminary metallurgical testwork included gravity concentration or flotation to recover the copper and gold. From the metallurgical testwork results and subsequent analysis it appears that the Whistler Deposit is metallurgically amenable to a conventional flotation route to produce saleable high quality copper concentrates with gold credits, despite the low head grade, and that the levels of recovery and upgrade for both copper and gold are relatively insensitive to feed grade. We believe that there are no processing factors or deleterious elements that could have a significant effect on potential economic extraction.

The preliminary testing indicated that the Island Mountain material tested is amenable to copper recovery by flotation and that the gold is relatively free milling. The results indicate that in the range of 90% of the potential gold may be recoverable by either whole ore leaching or a combination of flotation and leaching of the tailings.

Further flotation work is expected to improve both potential copper and gold recoveries to concentrate.

For both deposits further metallurgical development and assessment work is required to develop the best flowsheet with respect to capital and operating costs, metal recoveries and overall economics.

As of the date hereof, no metallurgical testing has been carried out on rocks from the Raintree West Deposit, however, given the similarities in geological setting, host rock, mineralization and alteration between Raintree West and the Whistler Deposits, we have assumed that metallurgical processes and metal recoveries determined for the Whistler Deposit are a reasonable approximation for the Raintree West Deposit at this time.

Metal recoveries reported for the Whistler Project resource estimate include 83% for copper, 70% for gold and 65% for silver with silver grades below 10 g/t and 0% for silver grades above 10 g/t.

Mineral Resource Estimates

The following table sets forth the Mineral Resource estimate detailed in the S-K 1300 Technical Report, with an effective date of September 12, 2024.

Cut-off Value · ROM Tonnage · In situ Grades · In situ Metal
ClassDeposit(US$/t)(ktonnes)NSR (US$/t)AuEqv (g/t)Au (g/t)Cu (%)Ag (g/t)AuEqv (koz)Au (koz)Cu (mlbs)Ag (koz)
IndicatedWhistler Pit10282,20522.840.680.410.161.896,2013,72499917,166
Raintree Pit108,90521.080.630.460.084.81180131161,378
Indicated Open Pitvaries291,41022.790.680.410.161.986,3813,8551,01518,544
Raintree UG253,06434.411.030.790.134.49101789443
Total Indicatedvaries294,47422.910.680.420.162.016,4823,9331,02418,987
InferredWhistler Pit1018,22421.010.630.400.131.75368233541,025
Island Mountain Pit10124,52918.210.540.450.051.022,1801,8171394,084
Raintree Pit1015,05623.120.690.550.064.36335267212,112
Inferred Open Pitvaries157,80919.000.570.450.061.422,8832,3172147,221
Raintree UG2540,43232.810.980.760.123.311,2759941034,300
Total Inferredvaries198,24121.820.650.520.071.814,1583,31131711,521

Notes to Table 1:

(1)The Mineral Resource estimate for the Whistler, Island Mountain, and the upper portions of the Raintree West deposits have been confined by an open pit with “reasonable prospects of economic extraction” using the following assumptions:
●Metal prices of US$1,850/oz Au, US$4.00/lb Cu and US$23/oz Ag;
●Payable metal of 95% payable for Au and Ag, and 96.5% payable for Cu;
●Refining costs for Au of US$8.00/oz, for Ag of US$0.60/oz and for Cu of US$0.05/lb;
●Offsite costs for Au of US$77.50/wmt, for Ag of US$3.50/wmt and for Cu of US$55.00/wmt;
●Royalty of 3% NSR;
●Pit slopes are 50 degrees;
●Mining cost of US$2.25/t for waste and mineralized material; and
●Processing, general and administrative costs of US$7.90/t.
(2)The lower portion of the Raintree West Deposit has been constrained by a mineable shape with “reasonable prospects of eventual economic extraction” using a US$25.00/t cut-off.
(3)Metallurgical recoveries are: 70% for Au, 83% for Cu, and 65% Ag for Ag grades below 10g/t. The Ag recovery is 0% for values above 10g/t for all deposits.
(4)The NSR equations are: below 10g/t Ag: NSR (US$/t)=(100%-3%)((Au70%US$54.646/t) + (Cu83%US$3.7022204.62 + Ag65%US$0.664)), and above 10g/t Ag: NSR (US$/t)=(100%-3%)((Au70%US$56.646g/t) + (Cu83%US$3.7022204.62))
(5)The Au Equivalent equations are: below 10g/t Ag: AuEq=Au + Cu1.771 +0.0113Ag, and above 10g/t Ag: AuEq=Au + Cu1.771
(6)The specific gravity for each deposit and domain ranges from 2.76 to 2.91 for Island Mountain, 2.60 to 2.72 for Whistler with an average value of 2.80 for Raintree West.
(7)The SEC definitions for Mineral Resources in S-K 1300 were used for Mineral Resource classification which are consistent with Canadian Institute of Mining, Metallurgy and Petroleum (CIM) Definition Standards for Mineral Resources and Mineral Reserves (CIM (2014) definitions).
(8)Numbers may not add due to rounding.

Fiscal Year Ended 2024 Updates

At the start of the 2024 summer field season, we recommenced the drilling program at the Whistler Project. Our initially planned exploration programs over the 2023 and 2024 field seasons consisted of up to 10,000 m of core drilling, which is reduced from the initial target of 15,000 m drilling, in order to allow us to determine actual costs of drilling while we re-established field operations. We intend to complete the balance of the 10,000 m drilling in 2025.

Additional surface exploration includes geological mapping, soil geochemical sampling, geophysical data reprocessing, geological data processing and interpretation. In addition, supporting work includes collection of mine planning and mineral processing information including metallurgical, geotechnical and hydrogeological data. Environmental baseline data collection, as well as archaeological and heritage land use studies were initiated in 2023, with additional baseline survey and archaeological surveys conducted in 2024. We have also engaged in stakeholder consultation with respect to both the present and ongoing exploration activity and the potential for future mine development of the Whistler Project.

On August 21, 2023, we announced the commencement of a confirmatory drill program (the “Drilling Program”). The Drilling Program is intended to advance the underlying geologic model to support an updated Mineral Resource estimate for the Whistler Project in preparation for a potential preliminary economic assessment. During the 2023 field season, four diamond core drill holes were completed for a total of 2,234 m at the Whistler Project.

On June 27, 2024, we announced the recommencement of the Drilling Program for the 2024 field season. During 2024 we completed six diamond core holes for 4,006 m, bringing the total drill production meterage for 2023 and 2024 to 6,240 m. During 2024, four drill holes for 2,782 m were completed at the Whistler Deposit, and two drill holes for 1,224 m were completed at the Raintree Deposit located approximately one km east of the Whistler Deposit.

The HQ and NQ diamond drill core from the Drilling Program were logged and sampled at the Whistler field camp facility, supervised by qualified geologists (P.Geo. designation) from our lead exploration consultant, Equity Exploration Ltd., and supervised by our QPs, Tim Smith (MSc., P.Geo.). Samples were collected from NQ/HQ diameter core by sawing the drill core in half, with one-half sent to Bureau Veritas Commodities Canada Ltd. (“BV”) in Fairbanks, Alaska, for sample preparation, then to BV’s analytical laboratory in Vancouver, Canada for assaying, and the other half of the core is retained at the site for future reference. Sample lengths downhole were generally 2.0 m, except where samples were taken to honor geological contacts.

BV is a certified commercial laboratory and is independent of us. We have implemented a quality assurance and quality control program for the sampling and analysis of drill core samples, including duplicates, mineralized standards and blank samples for each batch of core samples. The gold analyses were completed by lead collection fire assay fusion with AAS finish (FA430 method) on 30 grams test weight. Copper, silver and other base metals assays (total suite of 45 elements) were assayed by 4-acid digestion and ICP-MS analysis (MA200 method) on 0.25 grams test weight.

The following table sets out the assay intercepts reported from the Drilling Program.

Hole NumberInterval From (m)Interval To (m)Core Length (m)Gold Grade (g/t)Copper Grade (%)Silver Grade (g/t)AuEq (g/t)*Lead Grade (%)Zinc Grade (%)
WH23-03-EXT0.41717.00716.590.680.151.400.93--
Including7.00659.46652.460.730.161.501.00--
Including131.00307.00176.001.240.191.661.55--
And373.50423.0049.500.920.101.821.10--
And441.00457.0016.001.030.201.641.36--
And480.00501.0021.000.800.352.111.37--
And523.00539.0016.000.830.301.141.31--
And575.00632.0057.001.070.171.181.36--
WH23-03-EXT698.03717.0018.970.520.111.020.70--
WH24-01107.00109.002.000.45-8.600.580.613.07
WH24-01147.00151.004.000.28-7.100.420.441.20
WH24-01159.00161.002.000.64-4.500.720.291.59
WH24-01249.00266.0017.000.330.0741.970.450.330.75
Including249.00253.004.000.780.22171.551.121.192.53
WH24-01280.60300.0019.400.31-1.810.380.120.40
Including284.00286.002.001.23-4.701.320.371.27
WH24-01311.00372.3861.380.360.094.430.530.140.39
Including321.00362.0041.000.410.115.430.610.150.49
WH24-02227.00500.96273.960.480.120.860.71--
Including291.00444.00153.000.650.140.740.90--
Including291.00411.00120.000.720.160.831.00--
Including297.00337.0040.000.820.251.131.28--
And357.00377.0020.000.960.160.931.26--
WH24-0340.0052.7412.741.300.352.371.96--
385.08525.00139.920.210.140.970.47--
Including401.00429.0028.000.410.241.740.85--
643.00679.0036.000.080.121.080.29--
731.00767.0036.000.200.111.230.40--
868.00917.0049.000.180.051.900.28--
WH24-0491.00682.00591.000.370.151.480.66--
Including224.00682.00458.000.460.161.660.75--
Including260.00308.0048.000.610.342.191.23--
And406.00456.0050.000.730.131.500.98--
WH24-05306.00325.0019.000.790.0317.700.870.731.72
489.00508.5019.500.330.027.760.410.511.20
603.50773.00169.500.770.0415.380.860.400.86
Including635.00773.00138.000.890.0517.570.990.440.95
Including635.00661.0026.001.360.0615.381.480.691.61
And681.00715.0034.001.490.0819.951.650.811.35
Including699.00715.0016.002.900.1438.593.161.472.38
And755.00773.0018.001.700.1366.331.930.621.84
Including763.00773.0010.002.820.22113.743.211.003.00

Notes:

WH23-03-EXT drilled down-plunge to test the deeper extents of mineralization within the Whistler Deposit eastern high-grade core, therefore the mineralized intervals reported are not representative of true width. The mineralized intercepts within WH24-01 are estimated to be approximately two-thirds of true width. WH24-02 and WH24-03 drilled oblique to dip and strike to test the vertical profile of mineralization, therefore the mineralized intervals reported are not representative of true width. WH24-04 tested obliquely across strike and to depth to test the vertical profile of mineralization, thus the mineralized intervals reported are estimated to be approximately half to two-thirds of true width. WH24-05 tested obliquely across strike and dip, thus mineralized intervals reported are estimated to be approximately two-thirds of true width.

Specifically, for drilling reported prior to the 2024 Mineral Resource estimate update (WH23-03-EXT and WH24-01): below 10g/t Ag: AuEq=Au + Cu1.5733 +0.0108Ag, and above 10g/t Ag: AuEq=Au + Cu1.5733. For drilling reported subsequent to the 2024 Mineral Resource estimate update (WH24-02, -03, -04 & -05): below 10g/t Ag: AuEq=Au + (Cu%1.771) + (Ag0.0113), and above 10g/t Ag: AuEq=Au + (Cu%*1.771). AuEq calculations do not include Pb and Zn as it is unknown whether these metals can be recovered.

The following table sets out the drill locations and depths for the Drilling Program:

Hole NumberEasting Meters (UTM Zone 18)Northing Meters (UTM Zone 18)Elevation (masl)Depth (m)Azimuth (Degrees)Dip (Degrees)Status
WH23-01518,7826,871,260886.0467.87140.80-49.0All assays received
WH23-02518,7796,871,253886.0605.64229.20-60.1All assays received
WH23-03-EXT518,7766,871,253886.0874.50189.20-82.9All assays received
WH23-04520,1936,869,142352.0560.83134.80-78.0All assays received
WH24-01520,4946,871,260497.0445.7714.63-46.9All assays received
WH24-02518,4526,871,362849.0716.30135.43-75.2All assays received
WH24-03518,7466,871,335859.0961.9309.69-80.1All assays received
WH24-04518,6806,871,248876.0832.20185.85-78.0All assays received
WH24-05520,4956,871,258497.0777.85184.37-55.3All assays received

The following map sets forth the location of the Whistler Deposit drilling with gold and copper histograms plotted (left and right respectively; see legend). Drill traces for the 2023 and 2024 drill holes are shown in bold (with prefix “WH23” and “WH24”) and gold and copper assay histograms are highlighted. Drilling is overlain on a geological interpretation of the host diorite porphyry (cut at 200 m below surface) to illustrate the overall geometry of mineralized porphyry phases (pale purple) and non-mineralized LSP phases (darker purple).

We are working to delineate the geometry, extents and continuity of the MSP and IMP suites, which serves to focus drilling on opportunities to expand mineralization where the potentially mineralized porphyry phases remain under-explored. In addition, the technical team has identified the presence of a robust core of higher-grade mineralization within the Whistler Deposit that correlates with intense alteration and veining within the MSP in the eastern part of the deposit, and in 2024 we interpreted and confirmed via drilling the presence of a high grade core in the western part of the Whistler Deposit. Optimizing the geological model to improve confidence in the delineation of the MSP and IMP is a key focus of the Drilling Program as it will improve confidence in distribution and continuity of mineralization, and in particular higher-grade zones within the Whistler Deposit.

We plan to recommence the remainder of the previously announced approximate 10,000 m drilling program at the Whistler Project at the start of the 2025 summer field season.