Discussion Of Operational Results

The Company owns and operates four past producing gold properties in Nevada, one of the largest gold producing regions in the world. During the year ended December 31, 2024, the Company continued to advance its gold properties which are currently at various stages of redevelopment following successful exploration programs at each of the four properties.

Granite Creek

The Granite Creek property includes the Granite Creek Underground Project, a fully permitted, constructed and operating mine and the Granite Creek open pit oxide deposit adjacent to the underground project, currently in the permitting stage. The Granite Creek Underground Project is the first company asset to be redeveloped and is currently ramping up to full production.

Gold was initially discovered at Granite Creek in the mid to late 1930’s and includes the former Pinson mine. Approximately one million ounces have been produced from the property since that time. The Granite Creek property is comprised of several land parcels which now encompass approximately 4,480 acres, located in the Potosi mining district, approximately 27 miles northeast of Winnemucca, within Humboldt County, Nevada. The seven-square miles of land contain all areas of past gold production and the area of mineral resources (underground and open pit).

Granite Creek · Three months endedDecember 31, · Year endedDecember 31,
Operational Statistics · 2024 · 2023 · 2024 · 2023
Oxide mineralized material minedtonnes21,36920,83962,78948,573
Sulfide mineralized material minedtonnes8,14812,19227,33830,185
Total oxide and sulfide mineralized material minedtonnes29,51733,03190,12778,758
Oxide mineralized material mined gradeg/t13.0210.8811.6012.28
Sulfide mineralized material mined gradeg/t9.778.598.2110.48
Low-grade mineralized material mined1tonnes29,30519,49272,11146,260
Low-grade mineralized material grade1g/t3.083.113.033.06
Waste minedtonnes65,66842,045164,010106,830
Total material minedtonnes124,48994,568326,248231,848
Processed mineralized material2tonnes76,59421,400115,76942,537
Gold ounces sold3oz5,58311,38210,96116,502
Underground mine development (pre-development)ft6919593,7623,194
Exploration drillingft—6,44823,41327,392
Financial Statistics2024202320242023
Mining cost (total mineralized material and waste)$/t99100126124
Processing cost (processed mineralized material)$/t31233351
Site general and administrative (“G&A”) (total mineralized material mined4)$/t21133322
Royalties$000s5934302,507905
Capital expenditure5$000s609181,1383,933
Pre-development expenditures$000s5,0015,49419,57716,712
Exploration expenditures$000s4901,5334,8513,694

1 Low-grade mineralized material extracted as part of the mining process that is below cut-off grade but incrementally economic.

2 Processed mineralized material consists of toll treated material and material placed under leach.

3 Gold ounces sold include attributable gold from mineralized material sales at a payable factor of 58% in 2024 (2023 - 56%).

4 Total mineralized material mined consists of sulfide, oxide, and low-grade mineralized material.

5 Capital expenditure based on accrual basis.

Mining rates and gold extraction for the year 2024 were below the anticipated levels due to an escalation in groundwater ingress into the underground working areas. This development adversely affected productivity and the pace of development. In response to the increased water ingress, the mine expanded pumping capacity, deepened an existing dewatering well, drilled a new dewatering well, and reconfigured the dewatering system to enhance the flow capacity to the water treatment facility. Water levels are dropping throughout the mining area and water ingress rates are anticipated to decrease in the near term. extraction rates are expected to ramp up to steady-state during the second half of 2025. Additional dewatering infrastructure upgrades will be completed in 2025. In early 2025 a predictive groundwater model was completed and the Company is utilizing this study to evaluate future dewatering needs.

The Company continues to encounter elevated levels of oxide mineralized material. A substantial portion of this lower-grade mineralized material has been deemed suitable for processing via heap leach at the Company's Lone Tree heap leach facility. During the quarter, 1,261 ounces were processed and sold from the Lone Tree heap leach facility. Additionally, during the three months ended in December 31, 2024, 30,911 tonnes of sulfide mineralized material were processed under the toll milling agreement. As at December 31, 2024, sulfide mineralized material of approximately 13,000 tonnes were on the stockpile to be processed in 2025.

Capital expenditures for the year were primarily related to mining equipment.

Pre-development expenditures are for underground development work, definition drilling and dewatering well costs.

During the fourth quarter, Management began a process to update the technical reports for both the Granite Creek underground and open pit projects which were completed during the first quarter of 2025. An infill drilling program is planned to be completed in 2025 to upgrade resources to a feasibility study level. Permitting activities associated with the Granite Creek open pit expansion are planned to begin in early 2025 with the initial focus on required baseline field studies. Federal National Environmental Policy Act ("NEPA") and State of Nevada permitting is anticipated to take approximately three years.

During the three months ended December 31, 2024, the Company paused its drilling program in favor of developing an underground exploration drift. The development of an exploration drift at Granite Creek Underground commenced in the fourth quarter of 2024. This drift will provide access for infill drilling from underground in the South Pacific Zone.

Ruby Hill

During the 1990’s, an ore body was discovered, which became the Archimedes pit. Later discoveries included the Ruby Deeps sulfide deposit with the most recent discovery of the Hilltop zone. The Ruby Hill property is located within the Battle Mountain-Eureka trend, a northwest-trending geological belt located in north-central Nevada.

Ruby Hill includes the Archimedes Underground Project, the Mineral Point open pit heap leach project, as well as several base metal deposits. The Archimedes Underground Project is expected to be the Company's second underground mine. Mineral Point is a large oxide gold and silver deposit with the potential to become the Company’s largest gold producing asset. Processing infrastructure at Ruby Hill includes a primary crushing plant, grinding mill, leach pad, and carbon-in-column circuit, as well as associated mining infrastructure. Some of the existing facilities are expected to be utilized for Mineral Point, however new crushing, a Merrill Crowe plant and heal leach facilities will be required.

The federal permit has been received from the Bureau of Land Management, with the Nevada state permits expected during the second quarter 2025. The timeframe to first production is approximately 14 months in duration from the commencement of portal blasting which will commence once the state permit is approved. In the meantime, the Company is leaching the historic leach pads, which provides minor amounts of gold extraction.

Permitting for Archimedes underground continued in the fourth quarter of 2024. During the first quarter of 2025 the Company received the record of decision from the BLM for the commencement of the underground portals. Associated state permits are still in process and are expected to be received in the second quarter of 2025. Construction of the surface facilities and associated infrastructure commenced in the fourth quarter of 2024 and will carry into the first half of 2025. Underground construction activities are expected to begin in the third quarter of 2025. The Mineral Point deposit drill program is expected to begin in the third quarter of 2025 to support geotechnical, metallurgical and hydrology studies for baseline data to advance the permitting and technical reports for Mineral Point.

Ruby Hill · Three months endedDecember 31, · Year endedDecember 31,
Operational Statistics · 2024 · 2023 · 2024 · 2023
Gold ounces soldoz1,6111,8623,6186,643
Exploration drillingft—18,8044,03293,488
Financial Statistics2024202320242023
Mining cost$/oz———11
Processing cost (processed oz)$/oz7215831,245809
Site G&A (processed oz)$/oz477296847347
Royalties$000s126106252356
Capital expenditure1$000s289112407142
Pre-development expenditures$000s5572731,1121,269
Exploration expenditures$000s1341,76668415,794

1 Capital expenditure based on accrual basis.

During the three and twelve months ended December 31, 2024, the Company continued to recover ounces from the heap leach pads at Ruby Hill. The volume of ounces sold was lower than the prior year comparable periods due to the continued decline in leachable ounces. The Company will continue to recover ounces from the leach pads at Ruby Hill as long as it is economical to do so.

There was minimal spending on capital expenditures for the three and twelve months. During the fourth quarter, the Company prepared a preliminary economic assessment on the Archimedes Underground Project and Mineral Point open pit project which was finalized in the first quarter of 2025.

Exploration spending for the three and twelve months were related to metallurgical tests and drilling for metallurgical samples on the base metal deposits.

Permitting and technical study advancement of the base metal deposits at Ruby Hill including Hilltop and Blackjack have been suspended for the foreseeable future as the Company focuses on ramping up, permitting and developing the Company's three underground and two open pit oxide gold projects through the balance of the decade. As a result of the adoption of the new gold-focused strategy, the base metal joint venture, which the Company had been advancing previously, has been terminated.

Cove Project

Modern exploration for copper and gold in the McCoy Mining District started in the 1960s. The Cove Project is a high-grade underground development project and is expected to be the Company's third underground mine. It covers 30,923 acres and is located 32 miles south of the town of Battle Mountain, in the Fish Creek Mountains of Lander County, Nevada, and lies within the McCoy Mining District. The Cove Project is, for the most part, on land controlled by the U.S. Department of Interior, Bureau of Land Management ("BLM") and patented mining claims and consists of 1,535 100%-owned unpatented claims and twelve leased patented claims.

The draft plan of operations has been submitted to the BLM and the baseline permitting work is largely in the process of being finalized. In 2024, the Company focused on updating their existing permits related to water pollution control and land reclamation to ensure compliance with environmental regulations and maintaining operational standards. Additionally, a new air quality operating permit application will be submitted to the regulatory agency. This new permit is essential for regulating and controlling the emissions and pollutants released into the air by the site, thereby ensuring that the operations meet air quality standards set by regulatory authorities. Management is targeting the submittal of an Environmental Impact Statement in mid-2025, which will be required primarily due to the significant project disturbance acres and impact on water. The preparation and submission of these permitting documents are anticipated to be a key priority in the first half of 2025.

Cove · Three months endedDecember 31, · Year endedDecember 31,
Operational Statistics · 2024 · 2023 · 2024 · 2023
Exploration drillingft26,53313,10278,77661,150
Financial Statistics2024202320242023
Pre-development expenditures$000s4442,4432,9916,470
Exploration expenditures$000s2,8541,3938,99413,137

Parallel to the permitting process, an infill drill program is nearing completion to expand mineral resources as well as engineering work to complete a feasibility study expected in 2025. Underground delineation drilling continued during the fourth quarter on the Helen the CSD and Gap deposits with two core rigs, completing 26,533 feet of core drilled bringing total drilling over the course of the infill campaign to approximately 78,776 feet. A further 15,000 feet of drilling is planned into the first quarter of 2025 to complete the program. The 2024/2025 drill program will be included in a planned updated feasibility study.

Lone Tree Project

The Lone Tree project is a historic producing mine that completed mining operations in 2006. The development project is located within the Battle Mountain-Eureka Trend, midway between the Company's Granite Creek property and Cove underground project. The property consists of the past-producing Lone Tree mine and processing facility, as well as the nearby Buffalo Mountain deposit and the Brooks open pit mine, which is currently on care and maintenance. Processing infrastructure at Lone Tree includes an autoclave, carbon-in-leach mill, flotation mill, heap leach facility, assay lab and gold refinery, tailings dam, waste dumps and several buildings, including a warehouse, maintenance shop and administration building. The Company anticipates these facilities will support the development of all its mining projects.

The focus at Lone Tree is a feasibility study to evaluate the refurbishment of the autoclave facility with the intention of processing sulfide ore from the three underground mines (Granite Creek, Archimedes and Cove) in support of the Company's regional hub-and-spoke mining and processing strategy. Management continues to review the value engineering studies in preparation for the feasibility study which is expected to be completed in the third quarter of 2025.

The Lone Tree open pit is expected to remain in inventory into the 2030’s as the Company focuses ramp up, permitting and development of its three underground mines and two open pit oxide mines.

At the Company's Lone Tree property, the continued leaching of the historic leach pad is producing a reasonable amount of gold. The Company plans to continue to recover ounces from the Lone Tree leach pads as long as it is economical to do so.

Lone Tree · Three months endedDecember 31, · Year endedDecember 31,
Operational Statistics · 2024 · 2023 · 2024 · 2023
Gold ounces soldoz1,8591,0876,9486,225
Financial Statistics2024202320242023
Processing cost (processed oz)$/oz5041,134663875
Site G&A (processed oz)$/oz118211189231
Capital expenditure1$000s18426776213,162

1 Capital expenditure based on accrual basis.

Capital expenditures for the three and twelve months were related to general infrastructure in sustaining the operations and activities at Lone Tree. Spending in 2023 was related to the technical work on the refurbishment of the autoclave processing plant.