Skip to main content

Greenidge Generation Holdings Inc

For the period ended Dec 31, 2023. Filed Apr 10, 2024.

View on SEC.gov

About this filing

A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.

FY2023 · Filed Apr 10, 2024

VIP$1.02+5.9%Stored close · as of Nov 9, 2026

Extracted filing text, with the paragraph anchors used by the comparison.

See the whole filing, with its images and exhibits
Contents

Item 2. Properties

We own the approximately 106 MW nameplate natural gas power generation facility used by our Cryptocurrency Datacenter and Power Generation Segment, which is located on our 162-acre property in the Town of Torrey, New York. Our Town of Torrey mining operations take place at this facility. This property is subject to a lease/leaseback relationship with the Yates County Industrial Development Agency. In consideration for certain incentives provided by the Yates County Industrial Development Agency, we are committed to certain investment and job creation obligations, all of which have been fulfilled. The primary obligations are the continuation of employment, including the Yates County Industrial Development Agency as an additional insured on various insurance policies and the completion of annual reporting forms. The payment in lieu of taxes agreement executed by the Yates County Industrial Development Agency and us provides predictability with respect to the increase in the annual real property tax burden on the power plant.

We also own an additional 143 acres of land located in the Town of Torrey, New York. Approximately 29 acres are occupied by a landfill used to dispose of coal ash by the power plant’s former owners.

We own the 4.6-mile-long natural gas pipeline that runs from our power plant facility, to the connector pipeline in Milo, Yates County, New York. We also hold a series of easements and right of way agreements with landowners through whose land the pipeline runs.

On November 9, 2023, we closed the sale of the South Carolina Facility to complete the deleveraging transaction with NYDIG. We are evaluating future uses of the remaining real estate assets in South Carolina, which include approximately 153 acres of land and the original building, which was classified as construction in process and was not used in cryptocurrency mining.

On March 6, 2024, we agreed to purchase a parcel of land containing approximately 12 acres located in Columbus, Mississippi, including over 73,000 square feet of industrial warehouse space. This property will provide us with access to 32.5 MW in additional power capacity and we intend to deploy 7 MW of miners on the Columbus Property in the second quarter of 2024. We expect the transaction to close in April 2024 and intend to deploy 7 MW of miners on the property in the second quarter of 2024. We have also deployed additional miners in conjunction with a 7.5 MW mining capacity lease in North Dakota, which has a term of five years and provides us with energy to power mining at a cost of $58.50/MWh.

We lease office space in Fairfield, Connecticut.