Advanced-Stage Properties – Fenix Project
On December 31, 2020, we announced the results of a feasibility study for the development of our 100%-owned Fenix Project, which includes existing heap leach material at the El Gallo mine and the El Gallo Silver deposit. Key environmental permits for Phase 1 were received in 2019, including the approval for an in-pit tailings storage facility and process plant construction. We are currently awaiting the renewal of key mining permits prior to a construction decision.
The processing plant is expected to employ proven and conventional mineral processing and precious metal recovery technologies. Phase 1 is projected to have a processing rate of 3,400 tons per day.
Tailings generated during operations are expected to be stored in the depleted Samaniego pit at the El Gallo site. This approach provides increased safety by avoiding the construction of embankment structures, focusing solely on the geochemical stability of the dam, rather than its physical stability.