Item 8. Report of Independent Registered Public Accounting Firm

REPORT OF INDEPENDENT REGISTERED PUBLIC ACCOUNTING FIRM

To the Shareholders and Board of Directors of

Consolidated Water Co. Ltd.

Opinion on the Financial Statements

We have audited the accompanying consolidated balance sheets of Consolidated Water Co. Ltd. (the “Company”) as of December 31, 2023 and 2022, the related consolidated statements of income, stockholders’ equity and cash flows for each of the two years in the period ended December 31, 2023, and the related notes (collectively referred to as the “financial statements”). In our opinion, the financial statements present fairly, in all material respects, the financial position of the Company as of December 31, 2023 and 2022, and the results of its operations and its cash flows for each of the two years in the period ended December 31, 2023, in conformity with accounting principles generally accepted in the United States of America.

Basis for Opinion

These financial statements are the responsibility of the Company's management. Our responsibility is to express an opinion on the Company's financial statements based on our audits. We are a public accounting firm registered with the Public Company Accounting Oversight Board (United States) ("PCAOB") and are required to be independent with respect to the Company in accordance with the U.S. federal securities laws and the applicable rules and regulations of the Securities and Exchange Commission and the PCAOB.

We conducted our audits in accordance with the standards of the PCAOB. Those standards require that we plan and perform the audits to obtain reasonable assurance about whether the financial statements are free of material misstatement, whether due to error or fraud. The Company is not required to have, nor were we engaged to perform, an audit of its internal control over financial reporting. As part of our audits we are required to obtain an understanding of internal control over financial reporting but not for the purpose of expressing an opinion on the effectiveness of the Company's internal control over financial reporting. Accordingly, we express no such opinion.

Our audits included performing procedures to assess the risks of material misstatement of the financial statements, whether due to error or fraud, and performing procedures that respond to those risks. Such procedures included examining, on a test basis, evidence regarding the amounts and disclosures in the financial statements. Our audits also included evaluating the accounting principles used and significant estimates made by management, as well as evaluating the overall presentation of the financial statements. We believe that our audits provide a reasonable basis for our opinion.

Critical Audit Matters

The critical audit matters communicated below are matters arising from the current period audit of the financial statements that were communicated or required to be communicated to the audit committee and that: (1) relate to accounts or disclosures that are material to the financial statements and (2) involved our especially challenging, subjective, or complex judgments. The communication of critical audit matters does not alter in any way our opinion on the financial statements, taken as a whole, and we are not, by communicating the critical audit matters below, providing separate opinions on the critical audit matters or on the accounts or disclosures to which they relate.

Revenue Recognition - Estimated Costs to Complete

As described in Note 2 to the consolidated financial statements, the Company recognizes revenue for its construction and custom/specialized manufacturing contracts over time under the input method using costs incurred to date relative to the total estimated costs at completion to measure progress toward satisfying a contract's performance obligations as such measure best reflects the transfer of control of the promised good to the customer. The cost estimation process for these contracts is based on the knowledge and experience of the Company's project managers, engineers, and financial professionals. Changes in job performance, job conditions and management's assessment of expected variable

consideration are factors that influence estimates of the total contract transaction price, total costs to complete those contracts and the Company's revenue recognition.

We identified the estimated costs to complete on these revenue contracts as a critical audit matter. The determination of the total estimated cost and progress toward completion requires management to make significant estimates and assumptions. Total estimated costs to complete projects include various contracts costs that include labor, materials and subcontractor costs. Due to the extended time it may take to complete many of the Company’s contracts and the scope and nature of the work required to be performed on those contracts, the estimations of total revenue and costs at completion is complicated and subject to many variables and, accordingly, are subject to changes. Changes in these estimates can have a significant impact on the revenue recognized each period. Auditing these estimates involved especially challenging auditor judgment in evaluating the reasonableness of management's assumptions and estimates over the duration of these contracts.

The primary procedures we performed to address this critical audit matter included:

●We obtained an understanding and evaluated the design and implementation of the internal controls over management's process related to estimated costs to complete, including controls over management's review of: (i) the development of project budgets and key cost inputs, (ii) the ongoing assessment and revisions to project budgets, and (iii) the ongoing review of project status, including the nature of activities to complete open projects.
●Evaluating management’s ability to generate reasonable estimated costs to complete through performing a retrospective review of budget to actual variances.
●Assessing the reasonableness of the estimated costs to complete by evaluating the reasonableness of projects budgets and the nature of costs required to complete the project. Evaluation consists of investigating significant differences or unexpected results that take into consideration known changes in client operations, industry, and/or business conditions.
●Assessing the accuracy and the occurrence of the actual cost amount used in the percentage of completion by testing a sample of project costs incurred to date.
●Evaluating the reasonableness of project status by performing site visits and performing inquiries of project managers to assess the nature and costs of activities required to complete the project.
●Assessing the reasonableness of changes in estimated costs to complete by comparing project profitability estimates in the current period to historical estimates and actual performance including during the period under audit and subsequent to the period end and investigating reasons for changes in expected costs and project margins.
​​
/s/ Marcum LLP​
​​
We have served as the Company’s auditor since 2005.​
​​