Notes to Consolidated Financial Statements
NOTE 1—NATURE OF OPERATIONS AND BASIS OF PRESENTATION
We own a natural gas liquefaction and export facility located in Cameron Parish, Louisiana at Sabine Pass (the“Sabine Pass LNG Terminal”), which has natural gas liquefaction facilities with total production capacity of over 30 mtpa of LNG (the“Liquefaction Project”) as of September 30, 2026. The Sabine Pass LNG Terminal also hasfive LNG storage tanks, vaporizers andthree marine berths. We also own and operate a 94-mile natural gas supply pipeline that interconnects the Sabine Pass LNG Terminal with several large interstate and intrastate pipelines (the“Creole Trail Pipeline”).
We are developing a two-phased expansion project adjacent to the Liquefaction Project to provide additional liquefaction capacity, inclusive ofthree liquefaction trains and supporting infrastructure, with an expected total peak production capacity of up to approximately 20 mtpa of LNG, inclusive of estimated debottlenecking opportunities (the“SPL Expansion Project”), and we are commercializing to support the additional liquefaction capacity associated with this potential expansion project. In May 2026, SPL Stage V entered into a lump sum, turnkey EPC contract with Bechtel Energy, Inc. for the first phase of the SPL Expansion Project and has commenced early engineering and procurement pursuant to the limited notices to proceed issued. The development of this project or other projects, including infrastructure projects in support of natural gas supply and LNG demand, will require, among other things, regulatory approvals and acceptable commercial and financing arrangements before the Board of Directors of our general partner makes a positive FID.
We donot have employees and thus we and our subsidiaries have various services agreements with affiliates of Cheniere in the ordinary course of business, including services required to construct, operate and maintain the Liquefaction Project, and administrative services. See Note 10—Related Party Transactions for additional details of the activity under these services agreements during the three and nine months ended September 30, 2026.
As of September 30, 2026, Cheniere owned 48.6% of our limited partner interest in the form of 239.9 million of our common units. Cheniere also owns 100% of our general partner interest and our incentive distribution rights (“IDRs”).
Basis of Presentation
The accompanying unaudited Consolidated Financial Statements of CQP have been prepared in accordance with GAAP for interim financial information and in accordance with Rule 10-01 of Regulation S-X and reflect all normal recurring adjustments, which are, in the opinion of management, necessary for a fair statement of the financial results for the interim periods presented. Accordingly, these Consolidated Financial Statements do not include all of the information and footnotes required by GAAP for complete financial statements and should be read in conjunction with the Consolidated Financial Statements and accompanying notes included in ourannual report on Form 10-K for the fiscal year ended December 31, 2025.