Skip to main content

Cheniere Energy Partners LP

For the period ended Dec 31, 2023. Filed Feb 22, 2024.

View on SEC.gov

About this filing

A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.

FY2023 · Filed Feb 22, 2024

CQP$60.22+2.6%Stored close · as of Nov 10, 2026

Extracted filing text, with the paragraph anchors used by the comparison.

See the whole filing, with its images and exhibits
Contents

Liquidity and Capital Resources

The following information describes our ability to generate and obtain adequate amounts of cash to meet our requirements in the short term and the long term. In the short term, we expect to meet our cash requirements using operating cash flows and available liquidity, consisting of cash and cash equivalents, restricted cash and cash equivalents and available commitments under our credit facilities. Additionally, we expect to meet our long term cash requirements by using operating cash flows and other future potential sources of liquidity, which may include debt offerings by us or our subsidiaries and equity offerings by us. The table below provides a summary of our available liquidity (in millions). Future material sources of liquidity are discussed below.

December 31, 2023
Cash and cash equivalents$575
Restricted cash and cash equivalents designated for the Liquefaction Project56
Available commitments under our credit facilities (1):
SPL Revolving Credit Facility720
CQP Revolving Credit Facility1,000
Total available commitments under our credit facilities1,720
Total available liquidity$2,351

(1)Available commitments represent total commitments less loans outstanding and letters of credit issued under each of our credit facilities as of December 31, 2023. See Note 11—Debt of our Notes to Consolidated Financial Statements for additional information on our credit facilities and other debt instruments.

Our liquidity position subsequent to December 31, 2023 will be driven by future sources of liquidity and future cash requirements as further discussed under the caption Future Sources and Uses of Liquidity.

Although our sources and uses of cash are presented below from a consolidated standpoint, we and our subsidiary SPL operate with independent capital structures. Certain restrictions under debt instruments executed by SPL limit its ability to distribute cash, including the following:

SPL is required to deposit all cash received into restricted cash and cash equivalents accounts under certain of their debt agreements. The usage or withdrawal of such cash is restricted to the payment of liabilities related to the Liquefaction Project and other restricted payments. In addition, SPL’s operating costs are managed by subsidiaries of Cheniere under affiliate agreements, which may require SPL to advance cash to the respective affiliates; and

SPL is restricted by affirmative and negative covenants included in certain of its debt agreements in its ability to make certain payments, including distributions, unless specific requirements are satisfied.

Despite the restrictions noted above, we believe that sufficient flexibility exists to enable each independent capital structure to meet its currently anticipated cash requirements. The sources of liquidity at SPL primarily fund the cash requirements of SPL, and any remaining liquidity not subject to restriction, as supplemented by liquidity provided by SPLNG, is available to enable CQP to meet its cash requirements.

Supplemental Guarantor Information

The 2033 CQP Senior Notes are jointly and severally guaranteed by each of our current and future subsidiaries who guarantee the CQP Revolving Credit Facility and the $1.5 billion of 4.500% Senior Notes due 2029, $1.5 billion of 4.000% Senior Notes due 2031 and $1.2 billion of 3.25% Senior Notes due 2032 (together with the 2033 CQP Senior Notes, the“CQP Senior Notes”) are jointly and severally guaranteed by each of our subsidiaries other than SPL and, subject to certain conditions governing its guarantee, Sabine Pass LP (each a“Guarantor” and collectively, the “CQP Guarantors”).

The CQP Guarantors’ guarantees are full and unconditional, subject to certain release provisions including (1) the sale, disposition or transfer (by merger, consolidation or otherwise) of the capital stock or all or substantially all of the assets of the CQP Guarantors, (2) upon the liquidation or dissolution of a Guarantor, (3) following the release of a Guarantor from another guarantee that resulted in the creation of its guarantee of the CQP Senior Notes and (4) upon the legal defeasance or satisfaction and discharge of obligations under the indenture governing the CQP Senior Notes. In the event of a default in payment of the principal or interest by us, whether at maturity of the CQP Senior Notes or by declaration of acceleration, call for redemption or otherwise, legal proceedings may be instituted against the CQP Guarantors to enforce the guarantee.

The rights of holders of the CQP Senior Notes against the CQP Guarantors may be limited under the U.S. Bankruptcy Code or state fraudulent transfer or conveyance law. Each guarantee contains a provision intended to limit the Guarantor’s liability to the maximum amount that it could incur without causing the incurrence of obligations under its guarantee to be a fraudulent conveyance or transfer under U.S. federal or state law. However, there can be no assurance as to what standard a court will apply in making a determination of the maximum liability of the CQP Guarantors. Moreover, this provision may not be effective to protect the guarantee from being voided under fraudulent conveyance laws. There is a possibility that the entire guarantee may be set aside, in which case the entire liability may be extinguished.

The following tables include summarized financial information of CQP (the“Parent Issuer”), and the CQP Guarantors (together with the Parent Issuer, the“Obligor Group”) on a combined basis. Investments in and equity in the earnings of SPL and, subject to certain conditions governing its guarantee, Sabine Pass LP (collectively with SPL, the“Non-Guarantors”), which are not currently members of the Obligor Group, have been excluded. Intercompany balances and transactions between entities in the Obligor Group have been eliminated. Although the creditors of the Obligor Group have no claim against the Non-Guarantors, the Obligor Group may gain access to the assets of the Non-Guarantors upon bankruptcy, liquidation or reorganization of the Non-Guarantors due to its investment in these entities. However, such claims to the assets of the Non-Guarantors would be subordinated to any claims by the Non-Guarantors’ creditors, including trade creditors.

Summarized Balance Sheets (in millions)December 31,
20232022
ASSETS
Current assets
Cash and cash equivalents$575$904
Accounts receivable from Non-Guarantors5555
Other current assets3940
Current assets—affiliate86171
Current assets with Non-Guarantors1—
Total current assets7561,170
Property, plant and equipment, net of accumulated depreciation2,9152,946
Other non-current assets, net110109
Total assets$3,781$4,225
LIABILITIES
Current liabilities
Due to affiliates$121$193
Deferred revenue from Non-Guarantors324
Other current liabilities17795
Other current liabilities from Non-Guarantors—2
Total current liabilities301314
Long-term debt, net of premium, discount and debt issuance costs5,5424,159
Finance lease liabilities1418
Other non-current liabilities6778
Non-current liabilities—affiliate1818
Total liabilities$5,942$4,587
Summarized Statement of Income (in millions)Year Ended December 31, 2023
Revenues$199
Revenues from Non-Guarantors549
Total revenues748
Operating costs and expenses247
Operating costs and expenses—affiliate188
Operating costs and expenses—Non-Guarantors12
Total operating costs and expenses447
Income from operations301
Net income105

Future Sources and Uses of Liquidity

The following discussion of our future sources and uses of liquidity includes estimates that reflect management’s assumptions and currently known market conditions and other factors as of December 31, 2023. Estimates are not guarantees of future performance and actual results may differ materially as a result of a variety of factors described in this annual report on Form 10-K.

Future Sources of Liquidity under Executed SPAs

As described in Items 1. and 2. Business and Prop erties, our long-term customer arrangements form the foundation of our business and provide us with significant, stable, long-term cash flows. Substantially all of our future revenues are contracted under SPAs and because many of these contracts have long-term durations, we are contractually entitled to significant future consideration under these contracts which has not yet been recognized as revenue. This future consideration is, in most cases, not yet legally due to us and was not reflected on our Consolidated Balance Sheets as of December 31, 2023. In addition, a significant portion of this future consideration is subject to variability as discussed more specifically below. We anticipate that this consideration will be available to meet liquidity needs in the future. The following table summarizes our estimate of future material sources of liquidity to be received from executed SPAs as of December 31, 2023 (in billions):

Estimated Revenues Under Executed SPAs by Period (1) (2)
20242025 - 2028ThereafterTotal
LNG revenues (fixed fees)$3.9$14.1$31.0$49.0
LNG revenues (variable fees) (3)5.124.460.189.6
Total$9.0$38.5$91.1$138.6

(1)Agreements in force as of December 31, 2023 that have terms dependent on project milestone dates are based on the estimated dates as of December 31, 2023. The timing of revenue recognition under GAAP may not align with cash receipts, although we do not consider the timing difference to be material. We may enter into contracts to sell LNG that are conditioned upon one or both of the parties achieving certain milestones such as reaching FID on a certain liquefaction Train, obtaining financing or achieving substantial completion of a Train and any related facilities. These contracts are included in the revenues above when the conditions are considered probable of being met.

(2)LNG revenues (including $1.4 billion and $7.6 billion of fixed fees and variable fees, respectively, from affiliates) exclude revenues from contracts with original expected durations of one year or less. Fixed fees are fees that are due to us regardless of whether a customer exercises, in certain instances, their contractual right to not take delivery of an LNG cargo under the contract. Variable fees are receivable only in connection with LNG cargoes that are delivered.

(3)LNG revenues (variable fees, including affiliate) reflect the assumption that customers elect to take delivery of all cargoes made available under the contract. LNG revenues (variable fees, including affiliate) are based on estimated forward prices and basis spreads as of December 31, 2023. The pricing structure of many of our SPA arrangements with our customers incorporates a variable fee per MMBtu of LNG generally equal to 115% of Henry Hub, which is paid upon delivery, thus limiting our net exposure to future increases in natural gas prices.

Through our SPAs and IPM agreement, we have contracted approximately 85% of the total anticipated production from the Liquefaction Project, with approximately 14 years of weighted average remaining life as of December 31, 2023, excluding volumes that are contractually subject to additional liquefaction capacity beyond what is currently in construction or operation. The majority of the contracted capacity is comprised of fixed-price, long-term SPAs that SPL has executed with third parties to sell LNG from the Liquefaction Project. Under the SPAs, the customers purchase LNG on an FOB basis (delivered to the customer at the Sabine Pass LNG Terminal) generally for a price consisting of a fixed fee per MMBtu of LNG (a portion of which is subject to annual adjustment for inflation) plus a variable fee per MMBtu of LNG generally equal to 115% of Henry Hub. Certain customers may elect to cancel or suspend deliveries of LNG cargoes, with advance notice as governed by each respective SPA, in which case the customers would still be required to pay the fixed fee with respect to the contracted volumes that are not delivered as a result of such cancellation or suspension. The variable fees under our SPAs were generally sized with the intention to cover the costs of gas purchases, transportation and liquefaction fuel consumed to produce the LNG to be sold under each such SPA. In aggregate, the annual fixed fee portion to be paid by the third party SPA customers is approximately $3.4 billion. Our long-term SPA customers consist of creditworthy counterparties, with an average credit rating of A, A2 and A by S&P Global Ratings, Moody’s and Fitch, respectively. A discussion of revenues under our SPAs can be found in Note 13—Revenues of our Notes to Consolidated Financial Statements.

In addition to the third party SPAs discussed above, SPL has executed agreements with Cheniere Marketing under SPAs and letter agreements at a price equal to 115% of Henry Hub plus a fixed fee, except for an SPA associated with an IPM agreement for which pricing is linked to international natural gas prices.

In August 2020, we entered into an arrangement with subsidiaries of Cheniere to provide the ability, in limited circumstances, to potentially fulfill commitments to LNG buyers in the event certain conditions impact operations at either the Sabine Pass or Corpus Christi liquefaction facilities. The purchase price for such cargoes would be (i) 115% of the applicable natural gas feedstock purchase price or (ii) a free-on-board U.S. Gulf Coast LNG market price, whichever is greater.

Additional Future Sources of Liquidity

Regasification Revenues

SPLNG has a long-term, third party TUA with TotalEnergies, under which TotalEnergies is required to pay fixed fees of approximately $125 million annually, whether or not it uses the regasification capacity it has reserved. SPL has a partial TUA assignment agreement with TotalEnergies, whereby SPL gained access to substantially all of TotalEnergies’ capacity and other services provided under TotalEnergies’ TUA with SPLNG. Notwithstanding any arrangements between TotalEnergies and SPL, payments required to be made by TotalEnergies to SPLNG will continue to be made by TotalEnergies to SPLNG in accordance with its TUA and we continue to recognize the payments received from TotalEnergies as revenue. Costs incurred by SPL to TotalEnergies under this partial TUA assignment agreement are recognized in operating and maintenance expense. Full discussion of the partial TUA assignment and SPLNG’s revenues under the TUA agreements can be found in Note 13—Revenues of our Notes to Consolidated Financial Statements.

Available Commitments under Credit Facilities

As of December 31, 2023, we had $1.7 billion in available commitments under our credit facilities, as detailed earlier in the table summarizing our available liquidity, subject to compliance with the applicable covenants, to potentially meet liquidity needs. Our credit facilities mature in 2028.

Financially Disciplined Growth

Our significant land position at the Sabine Pass LNG Terminal provides potential development and investment opportunities for further liquefaction capacity expansion at a strategically advantaged location with proximity to pipeline infrastructure and resources. In May 2023, certain subsidiaries of CQP entered the pre-filing review process with the FERC under the NEPA for the SPL Expansion Project. The development of this sites or other projects, including infrastructure projects in support of natural gas supply and LNG demand, will require, among other things, acceptable commercial and financing arrangements before we make a positive FID.

Future Cash Requirements for Operations and Capital Expenditures under Executed Contracts

We are committed to make future cash payments for operations and capital expenditures pursuant to certain of our contracts. The following table summarizes our estimate of material cash requirements for operations related to our core operations under executed contracts as of December 31, 2023 (in billions):

Estimated Payments Due Under Executed Contracts by Period (1)
20242025 - 2028ThereafterTotal
Purchase obligations (2):
Natural gas supply agreements (3)$3.5$10.0$5.2$18.7
Natural gas transportation and storage service agreements (4)0.30.92.33.5
Other purchase obligations (5)0.20.91.12.2
Leases (6)—0.10.10.2
Total$4.0$11.9$8.7$24.6

(1)Agreements in force as of December 31, 2023 that have terms dependent on project milestone dates are based on the estimated dates as of December 31, 2023.

(2)Purchase obligations consist of agreements to purchase goods or services that are enforceable and legally binding that specify fixed or minimum quantities to be purchased. We include contracts for which we have an early termination option if the option is not currently expected to be exercised. We include contracts with unsatisfied contractual conditions if the conditions are currently expected to be met.

(3)Pricing of natural gas supply agreements is based on estimated forward prices and basis spreads as of December 31, 2023. Pricing of our IPM agreements is based on global gas market prices less fixed liquefaction fees and certain costs incurred by us. Includes $0.8 billion under natural gas supply agreements with unsatisfied contractual conditions.

(4)Includes $0.2 billion of purchase obligations to related parties under the natural gas transportation and storage service agreements.

(5)Includes $1.2 billion of purchase obligations to affiliates under services agreements and payments under SPL’s partial TUA assignment agreement with TotalEnergies Gas & Power North America, Inc. (“TotalEnergies”), as discussed in Note 13—Revenues of our Notes to Financial Statements.

(6)Includes payments under operating leases and finance leases. Certain of our leases also contain variable payments, such as inflation, which are not included above unless the contract terms require in-substance fixed payments that are, in effect, unavoidable. Payments during renewal options that are exercisable at our sole discretion are included only to the extent that the option is believed to be reasonably certain to be exercised.

Natural Gas Supply, Transportation and Storage Service Agreements

We have secured natural gas feedstock for the Liquefaction Project through long-term natural gas supply agreements, including an IPM agreement. Under our IPM agreement, we pay for natural gas feedstock based on global gas market prices less fixed liquefaction fees and certain costs incurred by us. While our IPM agreement is not a revenue contract for accounting purposes, the payment structure for the purchase of natural gas under the IPM agreement generates a take-or-pay style fixed liquefaction fee, assuming that LNG produced from the natural gas feedstock is subsequently sold at a price approximating the global gas market price paid for the natural gas feedstock purchase.

As of December 31, 2023, we have secured approximately 77% of the natural gas supply required to support the total forecasted production capacity of the Liquefaction Project during 2024. Natural gas supply secured decreases as a percentage of forecasted production capacity beyond 2024. Natural gas supply is generally secured on an indexed pricing basis plus a fixed fee, with title transfer occurring upon receipt of the commodity. As further described in the LNG Revenues section above, the pricing structure of our SPA arrangements with our customers often incorporates a variable fee per MMBtu of LNG generally equal to 115% of Henry Hub, which is paid upon delivery, thus limiting our net exposure to future increases in natural gas prices. Inclusive of amounts under contracts with unsatisfied contractual conditions that are currently considered probable of being met and exclusive of extension options that were uncertain to be taken as of December 31, 2023, we have secured up to 5,169 TBtu of natural gas feedstock through agreements with remaining fixed terms of up to approximately 14 years. A discussion of our natural gas supply and IPM agreements can be found in Note 8—Derivative Instruments of our Notes to Consolidated Financial Statements.

To ensure that we are able to transport natural gas feedstock to the Sabine Pass LNG Terminal, we have entered into firm pipeline transportation and other agreements to secure firm pipeline transportation capacity from third party interstate and intrastate pipeline companies. We have also entered into firm storage services agreements with third parties to assist in managing variability in natural gas needs for the Liquefaction Project.

Capital Expenditures

Although we do not currently have any material capital expenditures under executed contracts, we expect to incur ongoing capital expenditures to maintain our facilities and other assets, as well as to optimize our existing assets and purchase new assets that are intended to grow our productive capacity. See Financially Disciplined Growth section for further discussion.

Leases

We have entered into leases for the use of tug vessels and land sites. A discussion of our lease obligations can be found in Note 12—Leases of our Notes to Consolidated Financial Statements.

Additional Future Cash Requirements for Operations and Capital Expenditures

Operational Services

We rely on our general partner to manage all aspects of the development, construction, operation and maintenance of the Sabine Pass LNG Terminal and to conduct our business. Because our general partner has no employees, it relies on subsidiaries of Cheniere to provide the personnel necessary to allow it to meet its management obligations to us, SPLNG, SPL and CTPL. As of December 31, 2023, Cheniere and its subsidiaries had 1,605 full-time employees, including 501 employees who directly supported the Sabine Pass LNG Terminal operations. See Note 14—Related Party Transactions of our Notes to Consolidated Financial Statements for a discussion of the services agreements pursuant to which general and administrative services are provided to us, SPLNG, SPL and CTPL.

Financially Disciplined Growth

Our significant land position at the Sabine Pass LNG Terminal provides potential development and investment opportunities for further liquefaction capacity expansion at strategically advantaged locations with proximity to pipeline infrastructure and resources. In May 2023, certain of our subsidiaries entered the pre-filing review process with the FERC under the NEPA for the SPL Expansion Project, and in April 2023, one of our subsidiaries executed a contract with Bechtel Energy Inc. to provide the front end engineering and design work on the project. We expect that the SPL Expansion Project and any further expansion at the Sabine Pass LNG Terminal would increase cash requirements to support expanded operations, although expansion may be designed to leverage shared infrastructure to reduce the incremental costs of any potential expansion.

Future Cash Requirements for Financing under Executed Contracts

We are committed to make future cash payments for financing pursuant to certain of our contracts. The following table summarizes our estimate of material cash requirements for financing under executed contracts as of December 31, 2023 (in billions):

Estimated Payments Due Under Executed Contracts by Period (1)
20242025 - 2028ThereafterTotal
Debt$0.3$6.7$9.0$16.0
Interest payments0.92.21.24.3
Total$1.2$8.9$10.2$20.3

(1)Debt and interest payments are based on the total debt balance, scheduled contractual maturities and fixed or estimated forward interest rates in effect at December 31, 2023. Debt and interest payments do not contemplate repurchases, repayments and retirements that we may make prior to contractual maturity.

Debt

As of December 31, 2023, our debt complex was comprised of senior notes with an aggregate outstanding principal balance of $16.0 billion and credit facilities with no outstanding loan balances. As of December 31, 2023, we and SPL were in compliance with all covenants related to their respective debt agreements. Further discussion of our debt obligations, including the restrictions imposed by these arrangements, can be found in Note 11—Debt of our Notes to Consolidated Financial Statements.

Interest

As of December 31, 2023, our senior notes had a weighted average contractual interest rate of 4.83%. Borrowings under our credit facilities are indexed to SOFR. Undrawn commitments under our credit facilities are subject to commitment fees ranging from 0.075% to 0.300%, subject to change based on the applicable entity’s credit rating. Issued letters of credit under our credit facilities are subject to letter of credit fees ranging from 1.00% to 2.00%, subject to change based on the applicable entity’s credit rating. We had $280 million aggregate amount of issued letters of credit under our credit facilities as of December 31, 2023.

Additional Future Cash Requirements for Financing

CQP Distribution

Our partnership agreement requires that, within 45 days after the end of each quarter, we distribute all of our available cash, which, as defined in our partnership agreement, consists of cash on hand at the end of a quarter less the amount of any reserves established by our general partner. All distributions paid to date have been made from accumulated operating surplus.

Capital Allocation Plan

In September 2022, the board of directors of Cheniere approved a revised long-term capital allocation plan, which may involve the repayment, redemption or repurchase, on the open market or otherwise, of debt, including senior notes of CQP and SPL.

Sources and Uses of Cash

The following table summarizes the sources and uses of our cash, cash equivalents and restricted cash and cash equivalents (in millions). The table presents capital expenditures on a cash basis; therefore, these amounts differ from the amounts of capital expenditures, including accruals, which are referred to elsewhere in this report. Additional discussion of these items follows the table.

Year Ended December 31,
20232022
Net cash provided by operating activities$3,109$4,149
Net cash used in investing activities(227)(451)
Net cash used in financing activities(3,247)(3,676)
Net increase (decrease) in cash, cash equivalents and restricted cash and cash equivalents$(365)$22

Operating Cash Flows

The $1.0 billion decrease between the periods was primarily related to lower cash receipts from the sale of LNG cargoes from lower pricing per MMBtu, as a result of decreased Henry Hub pricing, and regasification fees. The decrease was partially offset by lower cash outflows for natural gas feedstock, mostly due to lower U.S. natural gas prices.

Investing Cash Flows

Cash outflows for property, plant and equipment during the year ended December 31, 2023 were primarily related to optimization and other site improvement projects. Cash outflows for property, plant and equipment during the year ended December 31, 2022 were primarily related to the construction costs for Train 6 of the Liquefaction Project, which achieved substantial completion on February 4, 2022.

Financing Cash Flows

The following table summarizes our financing activities (in millions):

Year Ended December 31,
20232022
Proceeds from issuances of debt$1,397$559
Redemptions and repayments of debt(1,700)(1,560)
Distributions(2,907)(2,635)
Other(37)(40)
Net cash used in financing activities$(3,247)$(3,676)

Debt Activity

During the year ended December 31, 2023, we issued an aggregate principal amount of $1.4 billion of 2033 CQP Senior Notes, the proceeds of which were used, together with cash on hand, to redeem $1.4 billion of the 2024 SPL Senior Notes. Additionally, during the year ended December 31, 2023, SPL purchased $200 million of the 2024 SPL Senior Notes in the open market and redeemed an additional $100 million of the 2024 SPL Senior Notes, which leaves only $300 million to be repaid for debt maturing in 2024.

Cash Distributions to Unitholders

Our partnership agreement requires that, within 45 days after the end of each quarter, we distribute all of our available cash (as defined in our partnership agreement). Our available cash is our cash on hand at the end of a quarter less the amount of any reserves established by our general partner. All distributions paid to date have been made from accumulated operating surplus.

The following provides a summary of distributions paid by us during the years ended December 31, 2023 and 2022:

Total Distribution (in millions)
Date PaidPeriod Covered by DistributionDistribution Per Common UnitCommon UnitsGeneral Partner UnitsIncentive Distribution Rights
November 14, 2023July 1 - September 30, 2023$1.030$499$14$201
August 14, 2023April 1 - June 30, 20231.03049914201
May 15, 2023January 1 - March 31, 20231.03049914201
February 14, 2023October 1 - December 31, 20221.07051815220
November 14, 2022July 1 - September 30, 2022$1.070$518$15$220
August 12, 2022April 1 - June 30, 20221.06051315215
May 13, 2022January 1 - March 31, 20221.05050815210
February 14, 2022October 1 - December 31, 20210.700339847

In addition, Tug Services distributed $13 million and $12 million during the years ended December 31, 2023 and 2022, respectively, to Cheniere Terminals in accordance with their terminal marine service agreement, which is recognized as part of the distributions to the holder of our general partner interest.

On January 26, 2024, with respect to the fourth quarter of 2023, we declared a cash distribution of $1.035 per common unit to unitholders of record as of February 7, 2024 and the related general partner distribution that was paid on February 14, 2024. These distributions consist of a base amount of $0.775 per unit and a variable amount of $0.260 per unit.