LAS VEGAS SANDS CORP
For the period ended Dec 31, 2025. Filed Feb 6, 2026.
View on SEC.govAbout this filing
A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.
FY2025 · Filed Feb 6, 2026
Extracted filing text, with the paragraph anchors used by the comparison.
See the whole filing, with its images and exhibitsContents
Development Agreement with Singapore Tourism Board
On August 23, 2006, MBS entered into a development agreement, as amended by a supplementary agreement on December 11, 2009 (the “Development Agreement”), with the STB to design, develop, construct and operate the Marina Bay Sands. The Development Agreement includes a concession for MBS to own and operate a casino within the Integrated Resort. In addition to the casino, the Integrated Resort includes, among other amenities, a hotel, a retail complex, a convention center and meeting room complex, a theater, restaurants and an art/science museum. MBS is one of two companies awarded a concession to operate a casino in Singapore. Only two licensees were granted the right to operate a casino in Singapore during an initial ten-year exclusive period (the “Exclusivity Period”), which expired on February 28, 2017. This Exclusivity Period was subsequently extended to December 31, 2030, when the Second Development Agreement (see below) was entered into. In connection with entering into the Development Agreement, MBS entered into a 60-year lease with the STB for the parcels underlying the project site and entered into an agreement with the Land Transport Authority of Singapore for the provision of necessary infrastructure for rapid transit systems and road works within and/or outside the project site. During the Exclusivity Period, the Company, which is currently the 100% indirect shareholder of MBS, is required to be the single largest entity with direct or indirect controlling interest of at least 20% in MBS, unless otherwise approved by the GRA.
The term of the casino concession provided under the Development Agreement is for 30 years commencing from the date the Development Agreement was entered into, or August 23, 2006. In order to renew the casino concession, MBS must give notice to the STB and other relevant authorities in Singapore at least five years before its expiration in August 2036. The Singapore government may terminate the casino concession prior to its expiration in order to serve the best interests of the public, in which event fair compensation will be paid to MBS.
In April 2019, MBS and the STB entered into the Second Development Agreement pursuant to which MBS has agreed to construct a development on land adjacent to Marina Bay Sands. The Second Development Agreement provides for a total minimum project cost of approximately SGD 4.5 billion (approximately $3.5 billion at exchange rates in effect on December 31, 2025).
The MBS Expansion Project will include a hotel tower with luxury rooms and suites, a rooftop attraction, premium gaming areas, convention and meeting facilities and a state-of-the-art live entertainment arena with approximately 15,000 seats.
In connection with the Second Development Agreement, MBS entered into a lease with the STB for the parcels of land underlying the project (the “Land”). In April 2019 and in connection with the lease, MBS provided various governmental agencies in Singapore the required premiums, deposits, stamp duty, goods and services tax and other fees in an aggregate amount of approximately SGD 1.54 billion (approximately $1.14 billion at exchange rates in effect at the time of the transaction).
In March 2022, MBS entered into a letter agreement with the STB to extend the construction commencement date for the MBS Expansion Project from April 8, 2022 to April 8, 2023. On March 22, 2023, MBS and the STB entered into the Supplemental Agreement, which further extended the construction commencement date to April 8, 2024 and the construction completion date to April 8, 2028, and allowed for changes to the construction and operation plans under the Second Development Agreement.
In January 2025, MBS entered into the Second Supplemental Agreement whereby MBS committed to assume liability for the Additional Land Premium, which includes the Additional Gaming Area and adjustments to the 2019 land premium payment due to consequential changes to the allocations of gross floor area for the MBS Expansion Project. These allocations prescribe and limit the use of the gross floor area for hotel, gaming, retail, food and beverage, MICE and arena at the MBS Expansion Project site. The Second Supplemental Agreement also formalized the dates by which MBS has agreed with the Singapore government to commence and complete construction of the MBS Expansion Project, being July 8, 2025 and July 8, 2029, respectively. Construction works for the project commenced in May 2025, before the requisite commencement date under the Second Supplemental Agreement. While our current estimate is that construction will be complete by June 2030 with an anticipated opening date in January 2031, any extension of the completion date beyond the July 8, 2029 deadline is subject to the approval of the Singapore government.
The Development Agreement contains, among other things, restrictions limiting the use of the leased land to the development and operation of the project, requirements that MBS obtain prior approval from the STB in order to subdivide the hotel and retail components of the project, prohibitions on any such subdivision during the Exclusivity Period and limitations on MBS’ ability to assign the lease or sub-lease any portion of the land during the Exclusivity Period. In addition, the Development Agreement contains events of default, including, among other things, the failure of MBS to perform its obligations under the Development Agreement and events of bankruptcy or dissolution.
Employees whose job duties relate to the operations of the casino are required to be licensed by the relevant authorities in Singapore. MBS also must comply with comprehensive internal control standards or regulations concerning advertising; branch office operations; the location, floor plans and layout of the casino; casino operations including casino-related financial transactions and patron disputes, issuance of credit and collection of debt, relationships with and permitted payments to gaming promoters; security and surveillance; casino access by Singaporeans and non-Singaporeans; compliance functions and the prevention of money laundering; periodic standard and other reports to the GRA; and those relating to social controls including the exclusion of certain persons from the casino.
There is a goods and services tax of 7% imposed on gross gaming revenue, which, effective January 1, 2023, increased to 8%, and, effective January 1, 2024, further increased to 9%. There is also a casino tax imposed on the gross gaming revenue from the casino after reduction for the amount of goods and services tax. With effect from March 1, 2022, the casino tax rates of 5% for premium players and 15% for mass players were increased to 8% and 18% on gross gaming revenue up to SGD 2.4 billion and SGD 3.1 billion (approximately $1.9 billion and $2.4 billion at exchange rates in effect on December 31, 2025), respectively. On gross gaming revenue above the stated thresholds, the new casino tax rates are 12% for premium players and 22% for mass players. The bad debts written off from the extension of credit granted to gaming patrons is not deductible against gross gaming revenue when calculating the casino tax, but is deductible for the purposes of calculating the goods and services tax (subject to the prevailing law).
MBS is permitted to extend casino credit to persons who are not Singapore citizens or permanent residents, but is not permitted to extend casino credit to Singapore citizens or permanent residents except to premium players.
The key constraint imposed on the casino under the Development Agreement is the total size of the gaming area, which must not be more than 15,000 square meters (approximately 161,000 square feet), although the Second Development Agreement provides for an option to purchase additional gaming area as described above and below. The following are not counted towards the gaming area: back of house facilities, reception, restrooms, food and beverage areas, retail shops, stairs, escalators and lift lobbies leading to the gaming area, aesthetic and decorative displays, performance areas and major aisles. Under the Development Agreement, the casino located within Marina Bay Sands could not have more than 2,500 gaming machines (although this restriction has been modified by the Second Development Agreement as described below), but there is no limit on the number of tables for casino games permitted in the casino.
Under the Casino Control Act, as amended (the “Singapore Act”), a casino operator may be subject to a financial penalty, for each ground of disciplinary action which amounts to a serious breach, of a sum not exceeding 10% of the annual gross gaming revenue (as defined in the Singapore Act) of the casino operator for the financial year immediately preceding the date the financial penalty is imposed.
The Singapore Act also requires future applicants and/or renewals for a casino license to be a suitable person to develop, maintain and promote the Integrated Resort as a compelling tourist destination that meets prevailing market demand and industry standards and contributes to the tourism industry in Singapore. The Singapore government has established an evaluation panel that will assess applicants and report to the GRA on this aspect of the casino licensing requirements. Our casino license, which has a three-year term, is set to expire in April 2028.
The Second Development Agreement contains provisions relating to the construction of the MBS Expansion Project and associated deadlines for completion, levels of insurance and limitations on MBS’ ability to assign the lease or sub-let any portion of the Land. In addition, the Second Development Agreement contains events of default, including, among other things, the failure of MBS to perform its obligations under the Second Development Agreement. The Second Development Agreement also contains, among other things, restrictions limiting the use of the Land to the development and operation of the MBS Expansion Project and requirements that MBS obtain the prior approval of the STB in order to subdivide the Land or any building thereon, which approval, if given, will be subject to such terms and conditions as may be determined by the STB.
The Second Development Agreement makes provision for certain benefits and entitlements conferred on MBS on specified terms and conditions. Among these, upon the achievement of certain milestones, MBS is entitled to make available an additional 1,000 gaming machines over and above its existing 2,500 gaming machines. On October 7, 2019, MBS was granted entitlement to make available 500 of these additional 1,000 gaming machines. In addition, under the Second Development Agreement, MBS is granted approval for the change of use of the area comprising the whole of the 53rd and 54th floors of Marina Bay Sands’ hotel Tower 2, or such other areas as may be agreed, to be developed and used as part of Marina Bay Sands’ casino; and MBS is granted an option to purchase an additional 2,000 square meters of casino gaming area at a price to be determined by the relevant Singapore government authority upon written request by MBS to exercise the option. As described above, MBS exercised this option in January 2025. In addition, the Second Development Agreement contemplates that for a period of not less than 10 years commencing no sooner than March 1, 2022, the rate of casino tax applicable to MBS will not exceed specified tiered rates; there shall not be more than two casino licenses in force under the Singapore Act at any time prior to January 1, 2031; and for a period of five years from the date of the Second Development Agreement, the entry levy payable by a Singapore citizen or permanent resident for entry into the casino will not exceed SGD 150 for a 24-hour period and SGD 3,000 for a 12-month period. The Second Development Agreement also provides for MBS to be entitled to compensation by the STB for any losses or damages suffered under certain conditions and events related to the above-described benefits and entitlements. The Second Development Agreement further provides that MBS must maintain compliance with the material terms of the Second Development Agreement to obtain the above-described benefits and entitlements.
Doing Business in Macao, Hong Kong and Mainland China
We are a parent company with limited business operations of our own; our main asset is the capital stock of our subsidiaries. A significant portion of our business operations are based in Macao and held by various Macao-incorporated indirect subsidiaries of SCL, our majority-owned subsidiary incorporated in Cayman Islands and listed in Hong Kong (collectively referred to as the “Macao Operations”). We also have subsidiaries incorporated in mainland China and Hong Kong that provide back-office support, such as information technology, accounting, hotel management and marketing services, which complement and support SCL’s main back-office functions in Macao.
We face various legal and operational risks and uncertainties relating to having a majority of our operations based in Macao and held by various Macao-incorporated indirect subsidiaries of SCL. Substantially all of SCL’s assets are located in Macao and substantially all of SCL’s revenue is derived from Macao. Accordingly, our results of operations, financial position and prospects are subject to a significant degree to the economic, political and legal situation in Macao. On December 20, 1999, Macao became a Special Administrative Region of China when China resumed the exercise of sovereignty over Macao. The Basic Law of Macao provides that Macao will be governed under the principle of “one country, two systems” with its own separate government and legislature and that Macao will have a high degree of legislative, judicial and economic autonomy.
We also face risks and uncertainties associated with evolving Chinese laws and regulations, such as those associated with the extent to which the level of Chinese government involvement, control of capital inflows and outflows, control of foreign exchange and allocation of resources currently applicable within mainland China may become applicable to us and other risks and uncertainties as to whether and how Chinese government statements and regulatory developments, such as those relating to data and cyberspace security and anti-monopoly which, where applicable to us, could result in a material change in our operations and/or the value of our securities or could significantly limit or completely hinder our ability to offer or continue to offer securities to investors, cause the value of such securities to significantly decline or be worthless and affect our ability to list securities on a U.S. or other foreign exchange. If, in the future, there were to be a significant change in the manner in which the Chinese government exercises direct or indirect oversight, discretion or control over businesses operated in Macao, mainland China and Hong Kong, including the current interpretation and application of existing Chinese laws and regulations on how the Chinese government exercises direct or indirect oversight, discretion or control over businesses operated in Macao, mainland China and Hong Kong, it could potentially result in our Macao Operations being materially adversely affected and it could potentially adversely affect our results of operations, financial position and cash flows.
As advised by our PRC legal advisers, Haiwen & Partners, our Macao Operations are currently not required to obtain any permission or approval from the China Securities Regulatory Commission (“CSRC”), Cyberspace Administration of China (“CAC”) or any other mainland Chinese governmental authority to issue securities to foreign investors, other than those related to its two subsidiaries incorporated in mainland China that only provide back-office support. We have received all requisite permissions and approvals for the back-office supporting functions located in mainland China, primarily being the standard business licenses issued by the relevant authorities in mainland China, and we have never been denied such permissions and approvals. If we do not receive or maintain such permissions or approvals in relation to such back-office support functions, we do not expect there will be any material adverse impact on our business, financial condition and results of operations. In the event that we have inadvertently concluded that such permissions or approvals are not required for our Macao Operations or if, in the future, applicable laws, regulations or interpretations were to change and require us to obtain such permissions or approvals, the failure to obtain such permissions or approvals could potentially result in penalties and other regulatory actions against us and may materially and adversely affect our business and results of operations.
See “Item 1A. — Risk Factors —Risks Related to Doing Business in China” for more detailed information.
Transfers of Cash to and from Our Non-U.S. Subsidiaries
We are primarily dependent upon our properties in Macao and Singapore. We are a parent company with limited business operations of our own; our main asset is the capital stock of our subsidiaries. We conduct most of our business operations through our direct and indirect subsidiaries. Accordingly, our primary sources of cash are royalties, dividends and distributions derived from the earnings and cash flow generated by our operating properties.
Subject to applicable law, our future dividend payments will be made at the discretion of our Board of Directors, taking into account various factors such as our future operations and earnings, capital requirements and surplus, general financial condition, contractual restrictions and other factors. There can be no assurance that dividends will be paid in any particular amount, if at all, for any given period.
The ability of subsidiaries to make distributions to us depends on the earnings and cash flow generated from operations and various other factors, including dividend requirements to third-party public stockholders in the case of funds being repatriated from SCL, compliance with certain local statutes, the laws and regulations currently and in the future applicable to our subsidiaries and restrictions in connection with their contractual arrangements. For example, our revenues in Macao are denominated in patacas, the legal currency of Macao, and in Hong Kong dollars. The Macao pataca is pegged to the Hong Kong dollar and, in many cases, is used interchangeably with the Hong Kong dollar in Macao. The Hong Kong dollar is pegged to the U.S. dollar. The mainland Chinese government imposes controls on the convertibility of the Renminbi into foreign currencies and, in certain cases, the remittance of currency out of China by our subsidiaries incorporated in mainland China. While currently there are no foreign exchange or capital control restrictions applicable to intercompany transactions between us and our Macao and Hong Kong subsidiaries, we cannot assure you that this will continue to be the case in the future and that our ability to convert large amounts of patacas into U.S. dollars over a relatively short period will not be limited. If, in the future, new foreign exchange or capital control restrictions were to be imposed, or existing foreign exchange or capital control restrictions were to be modified, and become applicable to us, such restrictions could potentially reduce the amounts that we would be able to receive from our Macao, Hong Kong and mainland China subsidiaries.
In addition, our SCL and Singapore credit facility agreements, under certain circumstances, may limit or prohibit certain payments of dividends or other distributions to us. We expect future debt instruments issued by our subsidiaries may contain similar restrictions.
Our non-U.S. subsidiaries, including those located in Singapore, Macao, Hong Kong and mainland China, held unrestricted cash and cash equivalents of $2.45 billion and restricted cash of $125 million as of December 31, 2025, of which approximately $2.07 billion is available to be repatriated, either in the form of dividends or via intercompany loans or advances, to the U.S., subject to the abovementioned restrictions. We do not expect withholding taxes or other foreign income taxes to apply should these earnings be distributed in the form of dividends or otherwise.
Cash may be transferred between and among the Company and its subsidiaries through capital contributions, intercompany loans or advances, dividends, royalties and transfers of cash and other assets. The total net transfers to the Company from SCL were $1.56 billion, $111 million and $100 million and from Marina Bay Sands were $1.56 billion, $1.08 billion and $937 million for the years ended December 31, 2025, 2024 and 2023, respectively.
Net transfers from SCL’s subsidiaries to SCL were $1.66 billion, $963 million and $1.86 billion for the years ended December 31, 2025, 2024 and 2023, respectively. During the years ended December 31, 2025, 2024 and 2023, SCL made interest payments to the holders of the SCL senior notes in the amount of $288 million, $319 million and $346 million, respectively. During the years ended December 31, 2025 and 2024, SCL redeemed $1.63 billion and repurchased $175 million, respectively, of the outstanding principal amount of the SCL senior notes.
The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.