Item 1A. Risk Factors
In addition to the other information set forth in this Quarterly Report, including the cautionary statement under the caption “Cautionary Note Regarding Forward-Looking Statements,” Management’s Discussion and Analysis of Financial Condition and Results of Operations, the condensed consolidated financial statements and related notes, and the following additional risk factors, you should carefully consider the risks discussed in “Part I, Item 1A - Risk Factors” in the 2025 Annual Report. There have been no material changes with respect to the risk factors disclosed in our 2025 Annual Report. However, we note that the risks described in this report and in our 2025 Annual Report are not the only risks facing the Corporation, and such additional risks and uncertainties that we currently deem to be immaterial or are unknown to us could negatively impact our business, operations and/or financial results.
Our future contracts with HPC data center customers could subject us to significant liability.
In the ordinary course of business, we have entered into, and aim to continue to enter into, agreements with customers pursuant to which we provide data center space, power, environmental controls, physical security, and connectivity products to our HPC hosting and colocation customers. These contracts typically contain indemnification and liability provisions, in addition to service level commitments, which could potentially impose a significant cost on us in the event of losses arising out of certain breaches of such agreements, services to be provided by us or our subcontractors, or from third-party claims. HPC data center customers increasingly are looking to pass through their regulatory obligations and other liabilities to their outsourced data center providers, and we may not be able to limit our liability or damages in an event of loss suffered by such customers whether as a result of our breach of an agreement or otherwise. If such an event of loss occurred, we could be liable for material monetary damages and could incur significant legal fees in defending against such an action, which could adversely affect our financial condition and results of operations.
We may also develop space specifically for HPC data center customers pursuant to agreements signed prior to beginning or early in the development process. In those cases, if we fail to meet our development obligations under those agreements, these customers may be able to terminate their agreements, and we will be required to find a new customer for this space. In addition, in certain circumstances, we may lease HPC data center facilities prior to their completion. If we fail to complete the facilities in a timely manner, the customer may be entitled to terminate its agreement, seek damages or penalties against us or pursue other remedies and we may be required to find a new customer for the space. If we are not able to complete an HPC data center in a timely manner, if development costs are higher than we currently estimate, our financial condition, results of operations and cash flow could be materially adversely affected.
Additionally, a customer’s decision to lease space and power at our facilities typically involves a significant commitment of resources and due diligence on the part of our customers regarding the adequacy of our facilities. As a result, we may expend significant time and resources in pursuing a particular transaction that may not result in revenue. Economic conditions, including market downturns and the implementation of new tariffs and more restrictive trade regulations, may impact customers’ ability to plan future business activities, which could cause customers to slow spending or delay decision making. Our inability to adequately manage the risks associated with these developments may adversely affect our business, financial condition and results of operations.
Certain of our agreements with HPC data center customers may include restrictions on providing HPC data center services to certain third parties, which could have a material adverse effect on our business, financial condition, and/or results of operations.
Certain of the customer agreements that we may enter into may prohibit us from providing HPC data center services to certain third parties, including competitors of existing HPC data center customers. The existence of such restrictions could hinder our ability to enter into agreements with additional HPC data center customers, which could have a material, adverse effect on our business, financial condition and/or results of operations.